CONSERVATION OF OLD FREE MASONS LODGE /
ESTABLISHMENT OF WILD LIFE MUSEUMKARACHI 35.291 (M)
-
8/8/2019 Free Mason Lodge Karachi
2/74
2
-
8/8/2019 Free Mason Lodge Karachi
3/74
CONSERVATION OF OLD FREE MASONS LODGE /
ESTABLISHMENT OF WILD LIFE MUSEUM KARACHI
-
8/8/2019 Free Mason Lodge Karachi
4/74
4
MAIN BUILDING VIEWS BEFORE
CONSERVATION PROCESS
-
8/8/2019 Free Mason Lodge Karachi
5/74
5
-
8/8/2019 Free Mason Lodge Karachi
6/74
6
-
8/8/2019 Free Mason Lodge Karachi
7/74
AA Issued on 11th-March,08
(a) Special project management/consultant arrangement got approved
(b) Project management awarded
(c) Tenders Invited
CONSERVATION OF OLD FREE MASONS
LODGE / ESTABLISHMENT OF WILD LIFE
MUSEUM KARACHI
-
8/8/2019 Free Mason Lodge Karachi
8/74
Conservation issues
Many rooms & hall are still in wild lifes Department
possession, causing hindrance in the process of
conservation of the building
Encroached Party adjacent to the protected
monument
Extension of landscaping zone in the eastern-
southern area
Major Issues
-
8/8/2019 Free Mason Lodge Karachi
9/74
-
8/8/2019 Free Mason Lodge Karachi
10/74
adjacent to the protected monument
Extension of landscaping zone in theeastern-southern area
-
8/8/2019 Free Mason Lodge Karachi
11/74
REMOVAL OF NEW ADDITIONS BY WILD LIFEDEPARTMENT
Masonry WallsServant Quarters Wash Rooms Marble & Mosaic Tiles
RCC ceilings Replacement of GrillsElectrification, Plumbers & Sewerage Work Wash Rooms, Servant QuartersNewly concrete Structure
-
8/8/2019 Free Mason Lodge Karachi
12/74
12
-
8/8/2019 Free Mason Lodge Karachi
13/74
13
Existing Ground Floor
Existing First Floor
-
8/8/2019 Free Mason Lodge Karachi
14/74
14
EXISTINGELEVATIONS
-
8/8/2019 Free Mason Lodge Karachi
15/74
15
-
8/8/2019 Free Mason Lodge Karachi
16/74
16
-
8/8/2019 Free Mason Lodge Karachi
17/74
17roposed Site Plan
-
8/8/2019 Free Mason Lodge Karachi
18/74
18
Proposed Ground Plan
-
8/8/2019 Free Mason Lodge Karachi
19/74
19
Proposed First Floor
-
8/8/2019 Free Mason Lodge Karachi
20/74
20
Proposed First Floor(Flooring)
-
8/8/2019 Free Mason Lodge Karachi
21/74
-
8/8/2019 Free Mason Lodge Karachi
22/74
22
Proposed Section 1
-
8/8/2019 Free Mason Lodge Karachi
23/74
23
Proposed Section 2
-
8/8/2019 Free Mason Lodge Karachi
24/74
24
Cafeteria, Lecture Hall ,Rest Rooms
-
8/8/2019 Free Mason Lodge Karachi
25/74
REMOVAL OF OLD MORTAR & CEMENT & LIME PLASTER
STONE WORK
PLUMBING WORK
CONTROLLING OF DAMPNESS RISING
ALTERATION OF ARCHES
REMOVAL OF ADDITIONAL ROOMS
WOOD WORK TREATMENT
ADDITIONS OF MISSING ELEMENTS
Work Plan for Entire Building
-
8/8/2019 Free Mason Lodge Karachi
26/74
26
ISSUES: LAYERS OF
PLASTER
Wrong Application of Multilayers of Plaster is done withthe passage of time
-
8/8/2019 Free Mason Lodge Karachi
27/74
27
ISSUE: PILASTER REMOVING
-
8/8/2019 Free Mason Lodge Karachi
28/74
28
REMOVING OF INNER LIBARAYS
PILASTER
The inner cemented pilasterlayer is removed from thelibrary later lime pilaster wouldbe applied
-
8/8/2019 Free Mason Lodge Karachi
29/74
29
LIME PILASTER
Aggregates of lime pilaster which areusing are
1. Lime2. Jute3. Sand
4. Water
After mixing of aggregates an initiallayer of pilaster around 1.5 inch
thick is applied on the wall of rareside of library after one week
another layer of pilaster will beapplied
-
8/8/2019 Free Mason Lodge Karachi
30/74
APPLYING NEW LIME PILASTER
-
8/8/2019 Free Mason Lodge Karachi
31/74
31
ISSUE: TRACES of RISING DAMPNESS
DRAIN FOR CONTROLLING A drain was excavated to control rising
-
8/8/2019 Free Mason Lodge Karachi
32/74
32
DRAIN FOR CONTROLLING
RISING DAMP
A drain was excavated to control risingdampness in parallel with the foundationof the building
-
8/8/2019 Free Mason Lodge Karachi
33/74
33
REMOVAL OF WOODEN PARTITION
BEFORE AFTER
-
8/8/2019 Free Mason Lodge Karachi
34/74
34
REMOVAL OF CORRUGATED GI SHEETAdditional roof of GI sheets at verandah or passages are removed
and it will serve as open to sky which was its original form
AFTER BEFORE
f f
-
8/8/2019 Free Mason Lodge Karachi
35/74
35
Removal of improper Installation of Air Conditioning Units:
Outdoor units are removed
which are placed in thewindows and proper space isdefined for outlet units
-
8/8/2019 Free Mason Lodge Karachi
36/74
REMOVAL OF WASH ROOM AREA
Removal of newly addition washroomWould be removed to get the originalityOf the building
REMOVAL OF CEMENT PLASTER FROM ROOF
-
8/8/2019 Free Mason Lodge Karachi
37/74
37
REMOVAL OF CEMENT PLASTER FROM ROOF
A layer of cement pilaster
around 2 inches thick isremoved from the top of theroof of library
AFTER BEFORE
-
8/8/2019 Free Mason Lodge Karachi
38/74
38
REMOVING OF EXISTING
ECLECTIC CHANNELING
WIRING
Removing of existingeclecticchanneling wiring is
happening from the libraryas the wires are damage andnew installation will be doneof electric wiring
-
8/8/2019 Free Mason Lodge Karachi
39/74
39
UNWANTED VEGETATIONS CUTTING
-
8/8/2019 Free Mason Lodge Karachi
40/74
BEFORE
-
8/8/2019 Free Mason Lodge Karachi
41/74
AFTER UNWANTED VEGETATIONS CUTTING
REPLACING PLINTHS STONE
-
8/8/2019 Free Mason Lodge Karachi
42/74
REPLACING PLINTHS STONE
During Working Before
-
8/8/2019 Free Mason Lodge Karachi
43/74
REPLACING PLINTHS STONE
-
8/8/2019 Free Mason Lodge Karachi
44/74
-
8/8/2019 Free Mason Lodge Karachi
45/74
The newly stone is manually chiseledand then applied at the plinth of thebuilding
MANUAL CHIESELING OF DRESSED STONE
-
8/8/2019 Free Mason Lodge Karachi
46/74
46
STONE CHISLING
Stone of exterior faade is chiseled from the entire building And limepointing is done on overall faade
AFTER BEFORE
MORTAR POINTING
-
8/8/2019 Free Mason Lodge Karachi
47/74
47
MORTAR POINTINGThree types of Sampling of grouting is donebetween the stone block1. Flash2. Recessed
3. EjectedOne of it will be applied on the walls wherever
necessary
Causes to the erosion ofmortar joint is presence ofsalt, crystallization, scouringaction of winds; anddisintegrating effect ofplants growing on a wall andwater penetration leading tothe concentration ofmoisture and dampness.
POINTING OF STONE MASONRY
-
8/8/2019 Free Mason Lodge Karachi
48/74
48
POINTING OF STONE MASONRY
Due to later intervention alayer of cement pilasterwhich was used earlier is
removed now
Now the pointing betweenstone would be used
-
8/8/2019 Free Mason Lodge Karachi
49/74
-
8/8/2019 Free Mason Lodge Karachi
50/74
DURING WORKING
-
8/8/2019 Free Mason Lodge Karachi
51/74
AFTER BEFORE
-
8/8/2019 Free Mason Lodge Karachi
52/74
-
8/8/2019 Free Mason Lodge Karachi
53/74
STONE CHIESELING AT FACADE
AFTER BEFORE
-
8/8/2019 Free Mason Lodge Karachi
54/74
STONE CHIESELING AT FACADE
AFTER BEFORE
-
8/8/2019 Free Mason Lodge Karachi
55/74
NEW FLOOR IS INSTALL
New floor is laying of same pattern
of original one which was usedearlier having same color andcomposition
Before After
-
8/8/2019 Free Mason Lodge Karachi
56/74
57
FLOORING
BEFOREAFTER
TERMITE ATTACKS WOOD:
-
8/8/2019 Free Mason Lodge Karachi
57/74
58
Insect or termite attack is a majorproblem in wild life building it happensin a damp and digestible timber. It
causes soften a timber and formfurther cracksit is dangerous to leave the timberwhich may insects or termite holebecause they may soften the timberand form further cracks.
The decayed timber is removed andnew frames were fixed with anti termitesolution
NEW FRAMES OF DOORS & WINDOWS
-
8/8/2019 Free Mason Lodge Karachi
58/74
59
NEW FRAMES OF DOORS & WINDOW S
Some of the frames are badlyabused with serious damagedon surfaces and deteriorated;
leading to further structuralproblem and unsafe tooccupants the main cause to thedeterioration are insects andtermite attacks and unqualifiedhuman intervention
New frames for doors &windows are fixing at groundand first floor
NEW PANELS AND FRAMES FOR WINDOWS
-
8/8/2019 Free Mason Lodge Karachi
59/74
NEW PANELS AND FRAMES FOR WINDOWS
New panels and frames for windows
Are making at the site of samereplicasOf original one
-
8/8/2019 Free Mason Lodge Karachi
60/74
NEW POLISHED DOORS
New doors are fixed and polished at
Sindh Wild Life
PARAPET AT FIRST FLOOR
-
8/8/2019 Free Mason Lodge Karachi
61/74
62
Existing parapet would be
removed and new parapetwould be built with samedesign and pattern
DURING WORKING
BEFORE
PARAPET AT FIRST FLOOR
-
8/8/2019 Free Mason Lodge Karachi
62/74
63AFTER BEFORE
WATER OUTLET PIPE
-
8/8/2019 Free Mason Lodge Karachi
63/74
WATER OUTLET PIPE
USED AT THE PARAPET
A water outlet pipe for drainage isusedFixed at the parapet wall
Removing of inner library's pilaster
-
8/8/2019 Free Mason Lodge Karachi
64/74
65
The inner cemented pilasterlayer is removed from thelibrary later lime pilaster
would be applied
BEFORE
DURING WORKING
Removing of inner library's pilaster
-
8/8/2019 Free Mason Lodge Karachi
65/74
66
The inner cemented pilaster layer is removedfrom the library later lime pilaster would beapplied
AFTER BEFORE
-
8/8/2019 Free Mason Lodge Karachi
66/74
-
8/8/2019 Free Mason Lodge Karachi
67/74
-
8/8/2019 Free Mason Lodge Karachi
68/74
CENTRAL HALL OPENING ON TOP OF
DOOR
wooden Framing is done on top of archopenings of display hall
Before After
-
8/8/2019 Free Mason Lodge Karachi
69/74
RE-CREATION OF MISSINGARCHITECTURAL FEATURES
-
8/8/2019 Free Mason Lodge Karachi
70/74
RE STRENGTHING OF CENTRAL STAIRCASE
-
8/8/2019 Free Mason Lodge Karachi
71/74
RE-STRENGTHING OF CENTRAL STAIRCASE
Temporary support for centralstaircase
Is provided as the staircase is leaningalong one side
BEFORE AFTER
-
8/8/2019 Free Mason Lodge Karachi
72/74
CLEANING OF PLAQUE
-
8/8/2019 Free Mason Lodge Karachi
73/74
AFTER BEFORE
-
8/8/2019 Free Mason Lodge Karachi
74/74
THANK YOU
For More detail please Visit:www.sindh.gov.pk/dpt/Antiquities/index.htmOr contact atDepartment of Antiquities
Room no:712 New sindh secretariate building, karachi.
http://www.sindh.gov.pk/dpt/Antiquities/index.htmhttp://www.sindh.gov.pk/dpt/Antiquities/index.htm