Florida Gas TransmissionMainline Hydrostatic Test
From the Golden Glades Interchange to the interchange of NW 122nd Street
with the Palmetto Expressway Miami-Dade County
![Page 2: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/2.jpg)
2
Who is Florida Gas Transmission (FGT)?
Why is FGT testing?What is the test exactly?When will the test occur?Where will the test take place?How will the test be conducted?How will the test affect me?
Today’s Outline
![Page 3: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/3.jpg)
3
Natural gas transmission company operating a 5,000 mile pipeline system along the Gulf
Provide all of the natural gas for power generation in Miami-Dade County
18” diameter Mainline serving South FloridaCustomers include:
Electric utility companies Local distributors Industrial clients
Florida Gas Transmission Company
![Page 4: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/4.jpg)
4
The U.S. Department of Transportation regulates all interstate pipelines
Testing is federally mandatedBest practice to confirm the safety
and reliability of the pipeline Safety is our #1 priority Ensure continued superb customer
service
Need for the Test
![Page 5: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/5.jpg)
5
Hydrostatic Test Remove the natural gas from the line• Controlled release vents harmlessly into
atmosphere• Service is maintained on another system
Test the integrity of the pipeline by filling the line with water• Put the water under pressure for a fixed
period of time
Nature of the Test
![Page 6: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/6.jpg)
6
Hydrotesting the 18” Mainline systemStandard, common pipeline test
procedureRecent, successful 18” Mainline tests
were completed in: Saint Lucie Palm Beach
Last Miami-Dade test done April 2011
Background
Martin Broward
![Page 7: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/7.jpg)
7
Public Awareness Campaign
Project Process
Begin Project
Obtain Permits
Prepare System for
TestingConduct
HydrotestEnd Project
![Page 8: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/8.jpg)
8
TASK DATECommunity Awareness November 2013 – May 2014
Permit Applications November 2013 – February 2014System Preparation January 2014 – February 2014
Test Preparation February 2014 – March 2014Conduct Hydrotest 16 April 2014
Test window is set: Early morning Wednesday 16 April 2014
Coordinated with FP&L and regulators
Project Schedule
![Page 9: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/9.jpg)
9
Total Project Length = 10.2 miles Begin: Golden Glades Interchange End: NW 122nd Street
Generally, along the Palmetto ExpresswayWithin the limits of:
City of Miami Gardens Town of Miami Lakes City of Hialeah Unincorporated Miami-Dade County
Project Location
![Page 10: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/10.jpg)
10
Project Location (con’t)
Project Limit
Project Limit
N
![Page 11: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/11.jpg)
11
Remove natural gas from the 18” Mainline Completed the week before the hydrotest
Fill the line with waterPressurize the system
Normal operating pressure is 722 PSI Test pressure is up to 1,444 PSI• Relatively short duration (approx. 30 minutes)
Reduce to intermediate pressure at 1,108 PSI•Maintain for 8 hours
How the Test is Performed
![Page 12: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/12.jpg)
12
De-pressurize the lineDrain the water from the systemIf any integrity issues are found:
They are corrected as soon as possible The hydrotest is performed again• Any re-testing must be performed within the
prescribed test window timeframeResume normal natural gas service
How the Test is Performed (con’t)
![Page 13: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/13.jpg)
13
Safety is our #1 priorityPerformed extensive test
preparations, including an inspection of the entire system
Any pipe anomalies will be repaired in advance of conducting the hydrotest
For the duration of the high pressure test, as a safety consideration, we plan to isolate sections of the pipeline route from people and traffic
Safety During the Test
![Page 14: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/14.jpg)
14
Advance Preparations Make all key stakeholders aware• Adjacent property owners• Emergency service providers•General driving public
Announcements• Flyers, newspaper, FL511, website, etc.
Dynamic message signs• 2 weeks in advance
Conducting the Test
![Page 15: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/15.jpg)
15
Night of the Test Begin at midnight Close ramps/roads/lanes with barricades Law enforcement support Confirm all-clear along the 10.2-mile
corridor Conduct hydrotest Reopen roadways at approximately 4:00
AM
Conducting the Test (Con’t)
![Page 16: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/16.jpg)
16
General Utility Permit from the Florida Department of Transportation is in process
Officers will be stationed at ramp and road closures and at detours
Traffic will be detoured from: Turnpike I-95 Palmetto Expressway
Traffic Control During the Test
![Page 17: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/17.jpg)
17
Project Location – District 1
![Page 18: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/18.jpg)
18
Project Location – District 13
![Page 19: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/19.jpg)
19
Project Location – District 12
![Page 20: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/20.jpg)
20
Please visit our website:www.fgthydrotest.comOr contact FGT:
Mr. Terry Coleman2405 Lucien Way, Suite 200
Maitland, FL 32751Toll Free – 844.FGT.INFO
(844.348.4636)Office – 407.838.7054Fax – 407.838.7052
Email – [email protected]
For More Information
![Page 21: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/21.jpg)
21
FGT 18” Mainline Hydrotest Summary
Federal mandate Testing with water Test window is set for
Wednesday 16 April 2013
Midnight – 4:00 AM 10.2 mile section of
pipe Detours for Turnpike,
I-95, Palmetto Expressway
Law enforcement support
Project Limit
Project Limit
N
![Page 22: Florida Gas Transmission Mainline Hydrostatic Test](https://reader035.vdocuments.us/reader035/viewer/2022062323/56816294550346895dd3074a/html5/thumbnails/22.jpg)
Thank You
22