Earned Value Measurement in MS Project
Jeff Smoot
1
![Page 2: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/2.jpg)
EVM in MS Project
Earned Value Management (EVM): A management methodology for integrating scope, schedule, and resources, and for objectively measuring project performance (earned value) and comparing it to the actual cost of work performed (actual cost)
– PMI PMBOK, 4th Edition, pg. 433
2
![Page 3: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/3.jpg)
EVM in MS Project
3
• How do we go from this….
Source: EMEN5030 10/24/05 Lecture, Bob Kois
![Page 4: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/4.jpg)
EVM in MS Project
4
• To this….
![Page 5: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/5.jpg)
EVM in MS Project
• Steps to view Earned Value in MS Project– Set Baseline– Set Status Date– Preconfigured Tables – Generate Earned Value Over Time Report
5
Assuming all work packages, resources, and resource usage has been input into MS Project
![Page 6: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/6.jpg)
Set Baseline
• MS Project uses the Baseline as the basis for the Planned Value (PV) calculation
• In the Project View, Set a Baseline for the project.
6
![Page 7: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/7.jpg)
Set Baseline
7
• Planned Value (PV) for TrackMyFitness Project
![Page 8: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/8.jpg)
Set Status Date
• A snapshot in time of current project performance.• In MS Project, set the status date to the desired date to
review project progress.
8
Due to nature of Earned Value Calculation, the status date will affect displayed data
![Page 9: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/9.jpg)
Preconfigured Tables
• MS Project has 3 preconfigured views for reviewing Earned Value in table format.– Earned Value
• PV (BCWS), EV (BCWP), AC (ACWP), SV, CV, EAC, BAC, VAC
– Earned Value Cost Indicators• CV%, CPI, TCIP
– Earned Value Schedule Indicators • SV%, SPI
9
Each individual table can be further customized.
![Page 10: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/10.jpg)
Earned Value Table
10
![Page 11: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/11.jpg)
Generate EV Over Time Report
• MS Project has a preconfigured Earned Value Over Time Report.• In the Project View, select Visual Reports, then Earned Value Over Time
Report from the pop-up
11
![Page 12: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/12.jpg)
Pivot Table
12
In addition to EV, PV, AC the pivot table allows you to view multiple other project metrics
![Page 13: EVM in MS Project](https://reader033.vdocuments.us/reader033/viewer/2022061204/547f171eb4af9f80678b4589/html5/thumbnails/13.jpg)
EV Over Time Report
13
An easy graphical summary of project status