Download - EVM for CNGS
CNGS Review15 July 2003
M. Meddahi 1
EVM for CNGS
• Definitions
• Pre-requisites
• Application to CNGS
CNGS Review15 July 2003
M. Meddahi 2
Definitions
EVM: Earned Value Management-> Measure amount of work performed-> Estimate total costs and duration
PVPlanned Value
EVEarned Value
ACActual Cost
Schedule Variance
SV = EV-PV
Cost VarianceCV = EV-AC
BCBudget at complete
CNGS Review15 July 2003
M. Meddahi 3
time
Money
PV
Today
AC
EV
Cost variance
Schedule variance
CNGS Review15 July 2003
M. Meddahi 4
EVM at CERN
- EVM for LHC- Much work done for implementing EVM for LHC- CNGS decided to also apply this management tool- Autumn 2002 started to implement EVM for CNGS
CNGS Review15 July 2003
M. Meddahi 5
Pre-requisites
Work BreakdownStructure
ProjectProgressTracking
Data collectionfrom project
engineers
CNGS Review15 July 2003
M. Meddahi 6
Work Breakdown Structure
CNGS Review15 July 2003
M. Meddahi 7
WBS layers
CNGS Review15 July 2003
M. Meddahi 8
Data collection
CNGS Review15 July 2003
M. Meddahi 9
PPT: Project progress tracking
• EVM project baseline frozen 9 May 2003
• 1st phase of utilisation and learning for the users:Project engineers are getting used to the system and the reporting.Analysing the results obtained from the EVM tools and proposing correcting actions.
CNGS Review15 July 2003
M. Meddahi 10
CNGS Review15 July 2003
M. Meddahi 11
Status of Work Units
CNGS Review15 July 2003
M. Meddahi 12
Work unit reporting
CNGS Review15 July 2003
M. Meddahi 13
Staff plan
CNGS Review15 July 2003
M. Meddahi 14
Planned cash Flow
CNGS Review15 July 2003
M. Meddahi 15
EVM summaries: an example
Proton Beam dump
WindowsShieldingHelium tubes
Target station
ShutterHadron Stop
CNGS Review15 July 2003
M. Meddahi 16
Summary
Organised the CNGS tasks in a Work Breakdown Structure
Defined the Work Units required to complete the project(313 Work Units for CNGS)
EVM CNGS baseline frozen on 9 May 2003
Earned Value Management applied to CNGS- Work is in progress- Monitoring of the project’s progress started (one report per month requested)