Earthwork includes: 1. Excavation 2. Grading: Moving earth to change
elevation 3. Temporary shoring 4. Back fill or fill: Adding earth to
raise grade 5. Compaction: Increasing density 6. Disposal
![Page 3: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/3.jpg)
TazriAziz
A. Job conditionsMaterial typeWater level and moisture contentJob sizeLength of haulHaul road condition (accessibility and
load restrictions)
![Page 4: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/4.jpg)
TazriAziz
B. Management conditionsEquipment conditions and
maintenance practicesSkills of work force and managementPlanning, supervision and
coordination of work.
![Page 5: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/5.jpg)
TazriAziz
J ob Conditions** Excellent Good Fair Poor
Excellent 0.84 0.81 0.76 0.70
Good 0.78 0.75 0.71 0.65
Fair 0.72 0.69 0.65 0.60
Poor 0.63 0.61 0.57 0.52
Management Conditions*
![Page 6: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/6.jpg)
TazriAziz
Meter cube m3 (bank, loose, or
compacted)
Bank (BCY): Materials in its natural state before disturbance (in-place, in-situ)
Loose (LCY): Material that has been compacted or disturbed or loaded
Compacted (CCY): Material after compaction
![Page 7: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/7.jpg)
TazriAziz
1.0
1.25
0.90
1.0 METER CUBE IN NATURAL CONDITION (IN-PLACE YARD)
1.25 METER CUBE AFTER DIGGING (LOOSE YARDS)
0.90 METER CUBE AFTER COMPACTED (COMPACTED YARDS)
In place CompactedLoose
![Page 8: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/8.jpg)
TazriAziz
Bank: VB
Bank Meter Cube (BMC)Density B Lb /BMC
Loose: VL
Loose Meter Cube (LMC)Density L Lb/LMC
Compacted: Vc
Compacted Meter Cube (CMC)Density C LB/CMC
![Page 9: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/9.jpg)
TazriAziz
Swell:A soil increase in volume when it is excavated.
Swell (%) = ( - 1) x 100
Load factor =
Bank Volume = Loose volume x Load factor
Loose densityBank density
Bank densityLoose density
![Page 10: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/10.jpg)
TazriAziz
Shrinkage:
A soil decreases in volume when it is compacted
Shrinkage (%) = (1 - ) x 100
Shrinkage factor = 1 - Shrinkage
Compacted volume
= Bank volume x Shrinkage factor
Bank densityCompacted density
![Page 11: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/11.jpg)
TazriAziz
Material
Loose
(kg/m3)
Bank
(kg/m3)Swell (%)
Load Factor
Clay, dry 1,604 2,024 26 0.79Clay, wet 2,062 2,731 32 0.76Clay and gravel, dry 1,833 2,139 17 0.85Clay and gravel, wet 1,986 2,368 17 0.85Earth, dry 1,693 2,177 29 0.78Earth, moist 1,841 2,353 28 0.78Earth, wet 2,101 2,582 23 0.81Gravel, wet 2,123 2,398 13 0.88Gravel, dry 2,360 2,765 17 0.85Sand, dry 1,986 2,230 12 0.89Sand, wet 2,368 2,689 13 0.88Sand and gravel, dry 2,215 2,483 12 0.89Sand and gravel, wet 2,597 2,865 10 0.91
Exact values will vary with grain size, moisture content, compaction, etc. Test to determine exact values for specific soils.
![Page 12: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/12.jpg)
TazriAziz
Initial
Soil Type Soil Condition Bank Loose CompactedClay Bank 1.00 1.27 0.90
Loose 0.79 1.00 0.71Compacted 1.11 1.41 1.00
Common earth Bank 1.00 1.25 0.90Loose 0.80 1.00 0.72Compacted 1.11 1.39 1.00
Rock (blasted) Bank 1.00 1.50 1.30Loose 0.67 1.00 0.87Compacted 0.77 1.15 1.00
Sand Bank 1.00 1.12 0.95Loose 0.89 1.00 0.85Compacted 1.05 1.18 1.00
Convrted to:
![Page 13: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/13.jpg)
TazriAziz
Angle of Repose2’-0”or more
![Page 14: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/14.jpg)
TazriAziz
For Sloping Sides of Excavation
OriginalGround Line
Solid
Rock
, Sla
te o
r C
em
ente
d S
and a
nd G
ravel
(90
Deg.)
Com
pact
ed A
ngul
ar G
rave
ls
1/2:
1 (6
3 D
eg.)
Reco
mm
ende
d Sl
ope
for A
vera
ge S
oils
1:1
(45
Deg.)
Compacted Sharp
Sand
1 1/2 :1 (3
3 Deg.)
Well Rounded Loose Sand
2:1 (26 Deg.)
![Page 15: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/15.jpg)
TazriAziz
1. End Area Method
2. Contour Line/ Grid Method
![Page 16: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/16.jpg)
TazriAziz
Used in sites where length is much greater than width
![Page 17: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/17.jpg)
TazriAziz
1. End Area Method
a.Take cross-sections at regular intervals, typically, 10m intervals.
b.Calculate the cross-section end areas
c.The volume of earthwork between sections is obtained by taking the average of the end areas at each station in square meter.
![Page 18: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/18.jpg)
TazriAziz
Fill
Cut
80
82
84
86
88
80
84
86
88
82
78
A’ B’ C’ D’ E’ F’
A B C D E F10 10 10 10 10
50m
30
m
![Page 19: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/19.jpg)
TazriAziz
80
78
76
82
80
78
84
82
80
86
84
88
86
90
88
78.5
80.3
82.3
84.2
86.2
88.2
Sec. A’- A
Sec. B’- B
Sec. C’- C
Sec. D’- D
Sec. E’- E
Sec. F’- F
Pro
ject
Cro
ss S
ect
ion
s
![Page 20: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/20.jpg)
TazriAziz
80
79
78
77
76
79.5
78.5
76.7
Section A’- A
Area = = 173.7193 x 1.8
2
Area = = 53.5107 x 1.0
2
![Page 21: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/21.jpg)
TazriAziz
82
81
80
79
78
81.8
80.3
76.7
Section B’- B
Area = = 189.0210 x 1.8
2
Area = = 67.590 x 1.5
2
![Page 22: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/22.jpg)
TazriAziz
Section Emb (CCY) Exc. (BCY) Exc. x B/C(CCY)
Net Exc.(CCY)
Cum Exc(CCY)
A-B 672 224 254 - 418 - 418B-C 567 441 499 - 68 - 486C-D 215 791 896 681 195D-E 0 1031 1167 1167 1362E-F 0 1222 1384 1384 2746
![Page 23: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/23.jpg)
TazriAziz
Used for parking lots and site “leveling”
Grid size from 10mx10m to 50mx50m
the greater the terrain variance the smaller the grid
![Page 24: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/24.jpg)
TazriAziz
Step l
Determine by visual study of the site drawing if the net total will be an import (more fill required than cut) an export (less fill required than cut) or a blend (cut and fill about equal)
Step 2Determine the pattern of calculation points or grid size.
Step 3 Determine elevations at each calculation location, the corners of each grid.
Step 4 Calculate the cubic yards of cut or fill required in each grid cell.
Step 5Add the individual Grid Cell quantities together to arrive at the total cut, total fill volume and the import or volume export yardage required for the job.
![Page 25: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/25.jpg)
TazriAziz
A B C D E F87.6 88.6 89.4 90.4 91.6 93.2
G H J K L M87.4 88.2 89.5 90.6 91.6 92.7
N O P Q R S87.2 87.7 89.0 90.4 91.3 92.0
87.6 88.5 89.3 90.3 91.5 95.0
94.3
93.5
93.1
A B C D E F G60m
88’ 89’ 90’ 91’ 92’ 93’ 94’
No ScaleNotes:1. Bring the entire site to elevation 90.2. All grids are 10m x 10m = 100 sq m3. Present contours
![Page 26: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/26.jpg)
TazriAziz
PurposeGrade the entire site to grade 90’
Quick and DirtyAssume one gridExisting 90.50Proposed 90.00Cut 0.50
Total Cost = = 1.851m310 x 10 x 0.5027
10m
10
m
NeedFill
Need
Cut
90'
90' 91'
90.5'
![Page 27: Estimating Earthwork - kontrak prosedur 2](https://reader036.vdocuments.us/reader036/viewer/2022081413/5477a3c4b4af9fd57e8b466e/html5/thumbnails/27.jpg)
TazriAziz
Average elevation
=
= 88.08change = 90-88.08
= 1.92m3
If we choose the grid size to be 10mx10m
87.6+88.5+87.6+88.64
87.6
88.6
87.687.6