Download - Epc project execution orientation course
![Page 1: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/1.jpg)
HERVE BARON
© 2015 – Hervé Baron
The execution of a Complex Project… a guided tour
![Page 2: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/2.jpg)
HERVE BARON
© 2015 – Hervé Baron
The actors
Impossible d’afficher l’image.
The COMPANY
“Client” The EPC Contractor
The suppliers
The sub-contractors
![Page 3: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/3.jpg)
HERVE BARON
© 2015 – Hervé Baron
Conceptual evaluation + Pre-Project
By COMPANY
Basic Engineering By ENGINEERING
Project Execution by EPC CONTRACTOR
Sanction Sanction
The phases
![Page 4: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/4.jpg)
HERVE BARON
© 2015 – Hervé Baron
Design Procurement Manufacturing Shipping
Installation Construction & erection Inspection & tests Hand-over
![Page 5: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/5.jpg)
HERVE BARON
© 2015 – Hervé Baron
The multiple sides of a Project
Hum
an Resources M
anagement
Project Control
PROJECT
![Page 6: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/6.jpg)
HERVE BARON
© 2015 – Hervé Baron
Engineering Sub-Contractor (India) Detail Engineering (part)
Shipyard (Korea) Hull Engineering & Fabrication
Shipyards (Singapore & Malaysia) Topsides Fabrication & Integration
Home office (Paris) •Project management •Detail Engineering (part) •Procurement
Satellite office Detail Engineering (part)
Fabrication yard (Nigeria): Fabrication (part)
Offshore (Nigeria): Installation, commissioning, start-up
The multiple sites of a Project
![Page 7: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/7.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering Procurement Construction
![Page 8: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/8.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering Procurement Construction
![Page 9: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/9.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process facilities:
Feedstock and products flow
Feedstock composition
Battery limit conditions
Equipment Spare
Performance:
Products specifications
Energy efficiency, emissions
Utilities:
Electric power supply
Other utilities
Systems:
Process control
Fire/gas alarm
Public address, LAN, PABX
Infrastructure:
Administrative and technical buildings
Control room
Access road
Site fencing, gates, check point
Design criteria:
% of over design
Environment data:
Min/max temperature
Rain/snow fall
Wind
Geological conditions
Applicable codes and standards:
International standards
Local rules
0 5
10 15 20 25 30 35 40 45 50
-85 -80 -75 -70 -65 -60 -55
Pre
ssu
re (
ba
r)
The facilities design basis
![Page 10: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/10.jpg)
HERVE BARON
© 2015 – Hervé Baron
Engineering Documents for Purchase:
bill of quantity & specification
Documents for Construction:
Construction drawings & specifications
Design basis:
- Functional requirements
- Client specifications
- Design codes
Engineering in the Project
![Page 11: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/11.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering
Instruments& Control
Layout & Piping Process Electrical Equipment Civil Safety
Procurement Construction
![Page 12: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/12.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering
Instruments& Control
Layout & Piping Process Electrical Equipment Civil Safety
Procurement Construction
![Page 13: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/13.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process simulations
![Page 14: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/14.jpg)
HERVE BARON
© 2015 – Hervé Baron
Heat & Material balance
Thermodynamic calculations
Process Flow Diagram (PFD)
![Page 15: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/15.jpg)
HERVE BARON
© 2015 – Hervé Baron
Equipment list
![Page 16: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/16.jpg)
HERVE BARON
© 2015 – Hervé Baron
Equipment duty
![Page 17: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/17.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process data sheet
![Page 18: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/18.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process Flow Diagram (PFD)
![Page 19: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/19.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping & Instrumentation Diagram (P&ID)
![Page 20: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/20.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping & Instrumentation Diagram (P&ID)
![Page 21: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/21.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process control
![Page 22: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/22.jpg)
HERVE BARON
© 2015 – Hervé Baron
Emergency shut down
![Page 23: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/23.jpg)
HERVE BARON
© 2015 – Hervé Baron
Emergency relief
![Page 24: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/24.jpg)
HERVE BARON
© 2015 – Hervé Baron
Operating manual
![Page 25: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/25.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering
Instruments& Control
Layout & Piping Process Electrical Equipment Civil Safety
Procurement Construction
![Page 26: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/26.jpg)
HERVE BARON
© 2015 – Hervé Baron
Rotating machinery
![Page 27: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/27.jpg)
HERVE BARON
© 2015 – Hervé Baron
Pressure vessels
![Page 28: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/28.jpg)
HERVE BARON
© 2015 – Hervé Baron
Heat exchangers
![Page 29: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/29.jpg)
HERVE BARON
© 2015 – Hervé Baron
Packages,
Fired Equipment
![Page 30: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/30.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process data sheet
Mechanical data sheet
![Page 31: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/31.jpg)
HERVE BARON
© 2015 – Hervé Baron
Material Requisition
![Page 32: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/32.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 33: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/33.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering
Instruments& Control
Layout & Piping Process Electrical Equipment Civil Safety
Procurement Construction
![Page 34: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/34.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 35: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/35.jpg)
HERVE BARON
© 2015 – Hervé Baron
Fire fighting
![Page 36: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/36.jpg)
HERVE BARON
© 2015 – Hervé Baron
Passive fire protection
![Page 37: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/37.jpg)
HERVE BARON
© 2015 – Hervé Baron
Fire & Gas detection layout
![Page 38: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/38.jpg)
HERVE BARON
© 2015 – Hervé Baron
Environmental Impact Assessment
![Page 39: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/39.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering
Instruments& Control
Layout & Piping Process Electrical Equipment Civil Safety
Procurement Construction
![Page 40: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/40.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 41: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/41.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 42: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/42.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 43: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/43.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 44: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/44.jpg)
HERVE BARON
© 2015 – Hervé Baron
Equipment supporting structures
![Page 45: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/45.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping supporting structures (pipe-racks)
![Page 46: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/46.jpg)
HERVE BARON
© 2015 – Hervé Baron
Structural design
![Page 47: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/47.jpg)
HERVE BARON
© 2015 – Hervé Baron
Structural design
![Page 48: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/48.jpg)
HERVE BARON
© 2015 – Hervé Baron
Structural drawings
![Page 49: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/49.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 50: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/50.jpg)
HERVE BARON
© 2015 – Hervé Baron
Architectural drawings
Equipment layout drawing
![Page 51: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/51.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 52: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/52.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering
Instruments& Control
Layout & Piping Process Electrical Equipment Civil Safety
Procurement Construction
![Page 53: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/53.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 54: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/54.jpg)
HERVE BARON
© 2015 – Hervé Baron
Layout/
principles
![Page 55: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/55.jpg)
HERVE BARON
© 2015 – Hervé Baron
Layout/consideration for all networks
![Page 56: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/56.jpg)
HERVE BARON
© 2015 – Hervé Baron
General Plot Plan
![Page 57: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/57.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping Layout drawing
![Page 58: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/58.jpg)
HERVE BARON
© 2015 – Hervé Baron
3D modelling
![Page 59: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/59.jpg)
HERVE BARON
© 2015 – Hervé Baron
3D model review
3D model clash check
![Page 60: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/60.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 61: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/61.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping Design
Design code for Process plants: ASME B31.3
)(
PY 2SWED * Pt+
=
P design pressure D (outside) diameter S stress value for material as per table in ASME B31.3 W weld joint reduction factor – for long term strength of weld at elevated temperature E quality factor, from table in ASME B31.3 (1 for seamless, 0.85 for ER welded pipe, etc.) Y coefficient from table in ASME B31.3 (from 0.4 to 0.7 depending on material and temperature)
To the above calculated thickness shall be added: - The corrosion allowance, e.g., 3 mm - The manufacturing tolerance: 12.5%
![Page 62: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/62.jpg)
HERVE BARON
© 2015 – Hervé Baron
Thickness (mm) Number of passes
![Page 63: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/63.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 64: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/64.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 65: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/65.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 66: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/66.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 67: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/67.jpg)
HERVE BARON
© 2015 – Hervé Baron
Isometric drawing
![Page 68: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/68.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping Pre-fabrication
![Page 69: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/69.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping General Arrangement drawing
![Page 70: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/70.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 71: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/71.jpg)
HERVE BARON
© 2015 – Hervé Baron
Standard Pipe Support drawings
![Page 72: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/72.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 73: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/73.jpg)
HERVE BARON
© 2015 – Hervé Baron
Material Selection
![Page 74: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/74.jpg)
HERVE BARON
© 2015 – Hervé Baron
Material Specification
![Page 75: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/75.jpg)
HERVE BARON
© 2015 – Hervé Baron
Material Specification
![Page 76: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/76.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering
Instruments& Control
Layout & Piping Process Electrical Equipment Civil Safety
Procurement Construction
![Page 77: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/77.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 78: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/78.jpg)
HERVE BARON
© 2015 – Hervé Baron
Instrument data sheet
![Page 79: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/79.jpg)
HERVE BARON
© 2015 – Hervé Baron Process Control System
![Page 80: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/80.jpg)
HERVE BARON
© 2015 – Hervé Baron
System architecture drawing
![Page 81: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/81.jpg)
HERVE BARON
© 2015 – Hervé Baron
Mechanical Equipment Control
![Page 82: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/82.jpg)
HERVE BARON
© 2015 – Hervé Baron
PT JB
Process line
Marshalling
cabinet
Controller
cabinet
Instrument room Control room
VDU
CPU
LAN Secondary cable
Multi cable
The instrumentation hardware
![Page 83: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/83.jpg)
HERVE BARON
© 2015 – Hervé Baron
Building detail drawing/Telecom and PAGA layout
![Page 84: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/84.jpg)
HERVE BARON
© 2015 – Hervé Baron
Cable routing drawings
Cable list
![Page 85: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/85.jpg)
HERVE BARON
© 2015 – Hervé Baron Cable routing inside technical rooms
![Page 86: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/86.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering
Instruments& Control
Layout & Piping Process Electrical Equipment Civil Safety
Procurement Construction
![Page 87: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/87.jpg)
HERVE BARON
© 2015 – Hervé Baron
Electrical consumers list
![Page 88: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/88.jpg)
HERVE BARON
© 2015 – Hervé Baron
Electrical Load Summary
![Page 89: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/89.jpg)
HERVE BARON
© 2015 – Hervé Baron
Electrical distribution
![Page 90: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/90.jpg)
HERVE BARON
© 2015 – Hervé Baron
General One Line Diagram
![Page 91: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/91.jpg)
HERVE BARON
© 2015 – Hervé Baron
Generators
Switchgear
Transformer
Equipment
specification
![Page 92: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/92.jpg)
HERVE BARON
© 2015 – Hervé Baron
Electrical equipment layout
![Page 93: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/93.jpg)
HERVE BARON
© 2015 – Hervé Baron
Electrical Control System
![Page 94: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/94.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process design
PFDs
H&M balance
![Page 95: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/95.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process design
PFDs
H&M balance
Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.
Process data sheet
Equipment specification
![Page 96: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/96.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process design
PFDs
H&M balance
P&IDs
![Page 97: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/97.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process design
PFDs
H&M balance
Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.
P&IDs
Piping
Instrumentation
Layout
Civil
Electrical
Process data sheet
Equipment specification
Vendor drawings
![Page 98: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/98.jpg)
HERVE BARON
© 2015 – Hervé Baron
Engineering work sequence
Extract from the book: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015, page 209
![Page 99: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/99.jpg)
HERVE BARON
© 2015 – Hervé Baron
Typical 3 year EPC Project Engineering schedule
PR = Process, EQ = Equipment, PL = Plant Layout, PI = Piping, I&C = Instrumentation & Control, EL = ELectrcial, HSE = Safety & Environment, CIV = Civil
Extract from the book: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015, page 211
![Page 100: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/100.jpg)
HERVE BARON
© 2015 – Hervé Baron
Process design
PFDs
H&M balance
Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.
P&IDs
Piping
Instrumentation
Layout
Civil
Electrical
Process data sheet
Equipment specification
Vendor drawings
![Page 101: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/101.jpg)
HERVE BARON
© 2015 – Hervé Baron
Vendor Instrumentation &
Control
Electrical
Layout
Civil
Piping Process
![Page 102: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/102.jpg)
HERVE BARON
© 2015 – Hervé Baron
Vendor Instrumentation
& Control
Electrical
Layout
Civil
P&ID
Functional analysis
C&E
Terminals dwgs
Power consumption
General Arrangement
Foundation drawing and loads, including auxiliaries!
Piping Purchaser Mechanical connection list and dwg
Process
Utility consumption
Battery limit conditions
Engineering / Vendor interfaces
![Page 103: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/103.jpg)
HERVE BARON
© 2015 – Hervé Baron
A unique synthesis for the busy Project professional 270 pages 300 illustrations
Interested and wanting to know more on Engineering?
![Page 104: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/104.jpg)
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Order direct from the publisher:
http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html
![Page 105: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/105.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering Procurement Construction
![Page 106: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/106.jpg)
HERVE BARON
© 2015 – Hervé Baron
Procurement
![Page 107: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/107.jpg)
HERVE BARON
© 2015 – Hervé Baron
Inquiry (Call for Tender)
Short listing
Bid analysis
Clarifications
Negotiations
Purchase Order
Expediting
Inspection
Delivery
Warranty Period
Procurement / Steps
![Page 108: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/108.jpg)
HERVE BARON
© 2015 – Hervé Baron
Procurement / Supplier selection criteria
Technical Compliance
Price
Qualification of supplier
Schedule
Load of workshop
References
References with final Client
Financial situation
Annual turn-over
Internal feed-back
![Page 109: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/109.jpg)
HERVE BARON
© 2015 – Hervé Baron
Procurement
![Page 110: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/110.jpg)
HERVE BARON
© 2015 – Hervé Baron
Expediting
![Page 111: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/111.jpg)
HERVE BARON
© 2015 – Hervé Baron
Expediting
![Page 112: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/112.jpg)
HERVE BARON
© 2015 – Hervé Baron
Inspection
![Page 113: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/113.jpg)
HERVE BARON
© 2015 – Hervé Baron
Inspection
![Page 114: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/114.jpg)
HERVE BARON
© 2015 – Hervé Baron
Shipping
![Page 115: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/115.jpg)
HERVE BARON
© 2015 – Hervé Baron
Shipping
![Page 116: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/116.jpg)
HERVE BARON
© 2015 – Hervé Baron
Shipping
![Page 117: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/117.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project
Engineering Procurement Construction
![Page 118: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/118.jpg)
HERVE BARON
© 2015 – Hervé Baron
Earthworks
![Page 119: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/119.jpg)
HERVE BARON
© 2015 – Hervé Baron
Pipeline
![Page 120: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/120.jpg)
HERVE BARON
© 2015 – Hervé Baron
Pipeline
![Page 121: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/121.jpg)
HERVE BARON
© 2015 – Hervé Baron
Roads
![Page 122: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/122.jpg)
HERVE BARON
© 2015 – Hervé Baron
Buildings
![Page 123: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/123.jpg)
HERVE BARON
© 2015 – Hervé Baron
Admixtures
Sand
Aggregate
Cement
Civil Works
![Page 124: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/124.jpg)
HERVE BARON
© 2015 – Hervé Baron
Civil Works
![Page 125: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/125.jpg)
HERVE BARON
© 2015 – Hervé Baron
Civil Works
![Page 126: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/126.jpg)
HERVE BARON
© 2015 – Hervé Baron
Civil Works
![Page 127: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/127.jpg)
HERVE BARON
© 2015 – Hervé Baron
Civil Works
![Page 128: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/128.jpg)
HERVE BARON
© 2015 – Hervé Baron
Civil Works
![Page 129: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/129.jpg)
HERVE BARON
© 2015 – Hervé Baron
Pre-fabrication
![Page 130: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/130.jpg)
HERVE BARON
© 2015 – Hervé Baron
Erection
![Page 131: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/131.jpg)
HERVE BARON
© 2015 – Hervé Baron
Underground networks
![Page 132: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/132.jpg)
HERVE BARON
© 2015 – Hervé Baron
Plant erection
![Page 133: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/133.jpg)
HERVE BARON
© 2015 – Hervé Baron
Steel structure erection
![Page 134: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/134.jpg)
HERVE BARON
© 2015 – Hervé Baron
Equipment installation
![Page 135: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/135.jpg)
HERVE BARON
© 2015 – Hervé Baron
Equipment installation
![Page 136: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/136.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping Pre-fabrication
![Page 137: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/137.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping erection
![Page 138: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/138.jpg)
HERVE BARON
© 2015 – Hervé Baron
Piping erection
![Page 139: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/139.jpg)
HERVE BARON
© 2015 – Hervé Baron
Field Instrumentation Installation
![Page 140: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/140.jpg)
HERVE BARON
© 2015 – Hervé Baron
Electrical equipment connection
![Page 141: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/141.jpg)
HERVE BARON
© 2015 – Hervé Baron
Cable pulling
![Page 142: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/142.jpg)
HERVE BARON
© 2015 – Hervé Baron
Arrangement of Technical rooms
![Page 143: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/143.jpg)
HERVE BARON
© 2015 – Hervé Baron
Cable connections
![Page 144: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/144.jpg)
HERVE BARON
© 2015 – Hervé Baron
Other Systems Field Equipment Installation
![Page 145: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/145.jpg)
HERVE BARON
© 2015 – Hervé Baron
Control room consoles installation
![Page 146: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/146.jpg)
HERVE BARON
© 2015 – Hervé Baron
Testing
![Page 147: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/147.jpg)
HERVE BARON
© 2015 – Hervé Baron
Sub-System
Junction Box
Instrument Loop
Instrument Cable
Mech Equip
Document Folder
Handover System
Elect Equip Circuit
Instrument Tag
Commissioning
![Page 148: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/148.jpg)
HERVE BARON
© 2015 – Hervé Baron
The multiple sides of a Project
Hum
an Resources M
anagement
Project Control
PROJECT
![Page 149: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/149.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project Organisation
Project Manager
Engineering Manager
Project Engineers
Discipline Engineers
Process
Civil
Instrumentation
Electrical
Equipment
Procurement Manager
Purchasers Expediters Inspectors
Site Manager
Construction Manager
Construction Superintendent
Construction supervisor
Construction superintendent
Construction supervisor
Project Control Manager
Contract Manager
Scheduling Manager Cost Control
![Page 150: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/150.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project procedures
![Page 151: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/151.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project temporary facilities
![Page 152: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/152.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project temporary facilities
![Page 153: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/153.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project temporary facilities
![Page 154: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/154.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project temporary facilities
![Page 155: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/155.jpg)
HERVE BARON
© 2015 – Hervé Baron
Project temporary facilities
![Page 156: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/156.jpg)
HERVE BARON
© 2015 – Hervé Baron
Construction Procedures
![Page 157: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/157.jpg)
HERVE BARON
© 2015 – Hervé Baron
![Page 158: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/158.jpg)
HERVE BARON
© 2015 – Hervé Baron
Quality Control
![Page 159: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/159.jpg)
HERVE BARON
© 2015 – Hervé Baron
Slump
Sampling Temperature
Quality Control
![Page 160: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/160.jpg)
HERVE BARON
© 2015 – Hervé Baron
Quality Control
![Page 161: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/161.jpg)
HERVE BARON
© 2015 – Hervé Baron
Cost Control
![Page 162: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/162.jpg)
HERVE BARON
© 2015 – Hervé Baron
Insurance
![Page 163: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/163.jpg)
HERVE BARON
© 2015 – Hervé Baron
Contracts
P.O.
Sub
P.O.
P.O.
Main Contract
Purchase Orders
Sub-Contracts
EPC
Sub
![Page 164: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/164.jpg)
HERVE BARON
© 2015 – Hervé Baron
Contracts
Main Contract
EPC
Terms and Conditions
Price
Schedule
Performance guarantees
Technical basis
Specifications, codes & stds
![Page 165: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/165.jpg)
HERVE BARON
© 2015 – Hervé Baron
Contracts
E P C
![Page 166: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/166.jpg)
HERVE BARON
© 2015 – Hervé Baron
Contracts
∑ + x%
![Page 167: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/167.jpg)
HERVE BARON
© 2015 – Hervé Baron
Construction contracts
Civil
![Page 168: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/168.jpg)
HERVE BARON
© 2015 – Hervé Baron
Construction contracts
Mechanical
![Page 169: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/169.jpg)
HERVE BARON
© 2015 – Hervé Baron
Construction contracts
E&I
![Page 170: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/170.jpg)
HERVE BARON
© 2015 – Hervé Baron
Construction contracts
General Contractor
![Page 171: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/171.jpg)
HERVE BARON
© 2015 – Hervé Baron
Contracts Terms and Conditions
Main Contract
EPC
Obligations of the 2 parties
Limit of liability
Penalties in case of bad performance
Conflict resolution
![Page 172: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/172.jpg)
HERVE BARON
© 2015 – Hervé Baron
Quality Assurance (QA)
![Page 173: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/173.jpg)
HERVE BARON
© 2015 – Hervé Baron
Quality Assurance (QA)
![Page 174: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/174.jpg)
HERVE BARON
© 2015 – Hervé Baron
Quality Assurance (QA)
![Page 175: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/175.jpg)
HERVE BARON
© 2015 – Hervé Baron
Quality Assurance (QA)
![Page 176: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/176.jpg)
HERVE BARON
© 2015 – Hervé Baron
Discipline code
A Instrumentation & Control
C Civil engineering
E Electrical
G Project general documents
J Mechanical
K Safety
M Piping & Layout
P Processes
S Steel Structures
V Vessels – Heat exchangers
W Materials – Welding
Document code
1 Installation drawings
2 Detail drawings
3 Diagrams
4 Lists – Bill of Quantities
5 Isometrics
6 Calculation notes
7 Specifications
8 Data sheets
9 Requisitions
Document Control
![Page 177: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/177.jpg)
HERVE BARON
© 2015 – Hervé Baron
Document Control
![Page 178: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/178.jpg)
HERVE BARON
© 2015 – Hervé Baron
Document Control
Engineering
Documents submitted to client
Client
Approval/
Comments
Vendors
Documents submission Comments
![Page 179: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/179.jpg)
HERVE BARON
© 2015 – Hervé Baron
Intranet / Internet
Intranet / Internet
Breakdown structures
Projects
Interfaces
Reports
Satellite Engineering
Center
Center 1 Sr. Mgmt Center 2 Sr.
Mgmt
Construction Site
Electronic Document Management System
Engineering documents
Vendor documents
Correspondence etc.
Electronic Document Management System
![Page 180: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/180.jpg)
HERVE BARON
© 2015 – Hervé Baron
Interface Management
![Page 181: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/181.jpg)
HERVE BARON
© 2015 – Hervé Baron
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36PLANT START-UPPIPING PRE-FABRICATION & INSTALLATION X X X X X X X X X XPIPING MATERIAL & DRAWINGS AT SITEPIPING MATERIAL MANUFACTURING & SHIPPING X X X X X XPURCHASE OF PIPING MATERIALTECHNICAL & COMMERCIAL CLARIFICATIONS X XCALL FOR TENDER FOR PIPING MATERIALPREPARE PIPING MATERIAL TAKE-OFF XPIPING ROUTING STUDIES X X XPIPING & INSTRUMENTATION DIAGRAMS (PIDs)
PROJECT SCHEDULEMONTH
1
1
2 3
3
4 5
2
4 5
5
Scheduling
![Page 182: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/182.jpg)
HERVE BARON
© 2015 – Hervé Baron
Critical path of an Oil & Gas Project
Extract from the book: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015, page 225
![Page 183: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/183.jpg)
HERVE BARON
© 2015 – Hervé Baron
Progress Monitoring
How would you measure progress?
![Page 184: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/184.jpg)
HERVE BARON
© 2015 – Hervé Baron
Progress Monitoring
![Page 185: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/185.jpg)
HERVE BARON
© 2015 – Hervé Baron
Progress Monitoring
![Page 186: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/186.jpg)
HERVE BARON
© 2015 – Hervé Baron
Progress Monitoring
![Page 187: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/187.jpg)
HERVE BARON
© 2015 – Hervé Baron
15 years ago: 2D
Today: 3D
Tomorrow: 3D & data
IT
![Page 188: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/188.jpg)
HERVE BARON
© 2015 – Hervé Baron
IT
![Page 189: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/189.jpg)
HERVE BARON
© 2015 – Hervé Baron
Safety
![Page 190: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/190.jpg)
HERVE BARON
© 2015 – Hervé Baron
Safety
Guard Rail System with ToeBoards
Cross Bracing
Planking
Runner
Bearer
Longitudinal Brace
Post
Sill
![Page 191: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/191.jpg)
HERVE BARON
© 2015 – Hervé Baron
Safety
![Page 192: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/192.jpg)
HERVE BARON
© 2015 – Hervé Baron
Human resources / career path
3-5 yrs
5 yrs
Graduate Engineer, 25 years old
5-7 yrs
40-45 yrs old Project Manager
Engineering Manager/ Deputy Project Manager
Project Engineer
Process Engineer
Note: the career pattern shown here is a very fast track one to the PM position... One would enjoy oneself just as well taking more time!
![Page 193: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/193.jpg)
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Do you want to know more... Much more?
![Page 194: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/194.jpg)
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
![Page 195: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/195.jpg)
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
Discipline presentation: activities and deliverables
![Page 196: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/196.jpg)
© 2015 – Hervé Baron
HERVE BARON
The work of each
Engineering discipline is described
![Page 197: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/197.jpg)
© 2015 – Hervé Baron
HERVE BARON
Design activities are explained, e.g., Plant
Equipment layout
![Page 198: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/198.jpg)
© 2015 – Hervé Baron
HERVE BARON
Complex activities, such as
QRA, are explained through a practical
example.
![Page 199: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/199.jpg)
© 2015 – Hervé Baron
HERVE BARON
A sample of all common Engineering documents is
included
![Page 200: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/200.jpg)
© 2015 – Hervé Baron
HERVE BARON
Difference between
Engineering and Shop drawings
![Page 201: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/201.jpg)
© 2015 – Hervé Baron
HERVE BARON
Understand the main
technical aspects, e.g., DCS vs ESD
![Page 202: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/202.jpg)
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
The overall process
![Page 203: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/203.jpg)
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
![Page 204: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/204.jpg)
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
![Page 205: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/205.jpg)
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
![Page 206: Epc project execution orientation course](https://reader034.vdocuments.us/reader034/viewer/2022052307/55498025b4c90554648b48b3/html5/thumbnails/206.jpg)
© 2015 – Hervé Baron