Download - Economics
![Page 1: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/1.jpg)
Economics
Section 2Dr.Hoda’s part
Sheet of: Total Capital Investment
Eng. Reda Zein
![Page 2: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/2.jpg)
I S THERE IS ANY PROBLEM IN PREVIOUS SECTION?
![Page 3: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/3.jpg)
TCI is the money utilized in a project to make a profit. TCI =Fixed capital investment (FCI) + Working capital
investment (WCI). FCI is the sum of money paid to build up a plant and make
ready for start up. WCI is the additional sum of money required to start and
operate the plant to the point when income is earned (1-3 months).
Total capital investment (TCI)
![Page 4: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/4.jpg)
- Coulson method:
WCI=5-30% FCI Typically 15%FCI
Beters method:
WCI=15-20%TCI Typically 15%TCI
Working Capital Investment (WCI)
![Page 5: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/5.jpg)
- Coulson method: Works with factors
FCI=Physical plant cost (PPC) + In direct plant
cost (IPC)
IPC=Design and Engineering + Contractor’s
fee +Contingency
Fixed Capital Investment (WCI)
![Page 6: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/6.jpg)
- Beters method: Works with percentages
FCI=Direct plant cost (DPC) + (IPC) +
Contractor’s fee +Contingency.IPC=Design and Engineering only
Fixed Capital Investment (WCI)
![Page 7: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/7.jpg)
Items of PPC Fluid Solid-Fluid
Solid
Equipment Say= A A AInstallation 0.4A 0.5APiping 0.7A 0.2AInstrumentation 0.2A 0.1AElectrical 0.1A 0.1ABuildings 0.15A 0.05AStorages 0.15A 0.2AUtilities 0.5A 0.25ASite development 0.1A 0.1AAuxiliary Buildings
0.15A 0.15A
PPC 3.45A 2.65A
Coulson:
Design and Engineering
0.3 PPC 0.2 PPC
Contractor’s fee 0.05 PPC 0.05 PPCContingency 0.1 PPC 0.1 PPCIPC 0.45 PPC 0.35 PPC
![Page 8: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/8.jpg)
Items of PPC Fluid Solid-Fluid
Solid
Equipment Say= A A AInstallation 45%A 47%APiping 66%A 16%AInstrumentation 18%A 9%AElectrical 10%A 10%ABuildings 18%A 25%ASite development 10%A 10%ALand 6%A 6%AUtility 70%A 40%ADPC 343%A 263%A
Beters:
Design and Engineering (IPC)
33% DPC
Contractor’s fee 5-7% (DPC+IPC)Contingency 10% (DPC+IPC)
Note: Buildings here means all buildings in factory so it includes auxiliary buildings, storages and building of equipment
![Page 9: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/9.jpg)
Let’s begin our sheet
![Page 10: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/10.jpg)
1) Prepare a study estimate of the fixed capital investment for a process plant handling fluids with a high degree of automatic controls knowing that the purchased equipment cost is $ 100,000 (Ans.=$ 500,250)
![Page 11: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/11.jpg)
3) The total capital investment for a chemical plant is $ 1 million and the working is $100,000. If the plant can produce an a average of 8000 kg of final product per day during a 365-day year, what selling price in dollars per kg of product would be necessary to give a turn over ratio of 1?
(Ans. =$ 0.3082/kg)
![Page 12: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/12.jpg)
4) The purchased equipment cost for a plant which produces pentaerythritol (solid-fluid processing plant) is $ 300,000. The plant is to be an addition to an existing plant. The contractor’s fee will be 7% of the direct plant cost. All other values are close to the average values found for typical chemical plants. On the basis of this information, estimate the following: (a) The total direct plant cost.(b) The fixed capital investment.(c) The total capital investment.(Ans.:a)$657,000, b)$ 1,007,181 c) $1,184,919)
![Page 13: Economics](https://reader035.vdocuments.us/reader035/viewer/2022062305/56815b21550346895dc8de4e/html5/thumbnails/13.jpg)
Any questions?