KONKAN GYANPEETH
COLLEGE OF ENGINEERING, KARJAT
CERTIFICATE
This is to certify that the Mr. KAUSTUBH VINAY KOKANE has successfully
carried out the project entitled IMPLEMENTATION OF PRODUCTIVITY
MEASUREMENT SYSTEM IN FABRICATION DEPARTMENT during semester VII
in partial fulfillment of Bachelor of Engineering in Production Engineering degree
awarded by the Mumbai University in the academic year 2011-2012.
Prof. V. K. Gajare Mr. Vasuki P. H. Mr. S. S. Agarkar
(College Guide) (HOD, Fabrication-19) (Company Guide &
GM- Manufacturing)
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
3/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
4/74
4
SYNOPSIS
NAME OF COLLEGE : Konkan Gyanpeeth College of Engineering,
Karjat
CLASS : B.E. (PRODUCTION)
SEMESTER : VII (REVISED)
ACADEMIC YEAR : 2011-2012
PROJECT TITLE : DESIGN & IMPLEMENTATION OF
PRODUCTIVITY MEASUREMENT SYSTEM IN
FABRICATION DEPARTMENT
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
5/74
5
ACKNOWLEDGEMENT
On successful completion of my 7th semester in-plant training at Godrej & Boyce
Mfg. Co. Ltd., I take this opportunity to convey my profound gratitude to all concerned
people who have helped me.
It is only befitting, that I first thank our college management and respected Principal
Mr. M. B. Lele, our H.O.D. Mr. A. G. Nagpure, Training & Placement in-charge Mr. S. R.
Shastri & my project guide Mr. V. K. Gajare for arranging this in-plant training.
I thank Mr. Uday Deshmane (Training & placement officer, Godrej) for giving me an
opportunity to work in the PES division at Godrej Vikhroli establishment.
I am indebted to my company guide Mr. S. S. Agarkar, Mr. Vasuki P. H. and Mr. S.
B. Nuchu for their valuable guidance and support throughout my training period. I would
also like to express my heartfelt gratitude to Mr.Biswadeep S Biswas, Mr. Amit R. Panchal,
Mr. Navaj A. Sattar, Mr. Alam Khan and Mr. Prashant Warudkar for their full
encouragement & guidance throughout my training period.
It would be inequitable if I disregard the co-operation of Quality Assurance, Design,
M.P.C., Machine Shop, Maintenance, Paint Shop and Assembly departments for showing me
how teamwork is done in our PES plant.
Finally, though not the last, I would like to thank all the workmen for their constant
co-operation, support and generous information regarding all the operations that are carried
out at shop floor-level. They were a source of real-life knowledge for me, which I couldn't
have grasped from any textbook.
KAUSTUBH V. KOKANE
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
6/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
7/74
7
INDEX
CHAPTER
NO.DESCRIPTION
PAGE
NO.
1 Company Profile 8-12
2 Introduction to PES Division 13-20
3 Introduction to Fabrication Department 21-24
PROJECT
DESIGN & IMPLEMENTATION OF PRODUCTIVITY
MEASUREMENT SYSTEM IN FABRICATION
DEPARTMENT
25
4
Literature Survey
26-31
5.1 Definitions of Productivity
5.2 Partial Productivity
5.3 Welding Productivity
5.4 Factors Affecting Welding Productivity
5.5 Difficulties in Measuring Productivity
5
Workstation Productivity Measurement
32-416.1 Productivity Analysis of Workstations
6.4 Workstation-wise Analysis & Justification
6
Productivity Measurement by VA-NVA Analysis
42-54
7.1 VA-NVA Analysis
7.2 Standardisation of VA-NVA Activities
7.3 Time Study7.4 Job-specific VA NVA Analysis by Time Study
7.6 Summary Analysis
7.7 Important Improvements
7
Loss Analysis
55-608.1 Sixteen Major Losses
8.2 Job-specific Loss Analysis
8
Calandria Stage I Welding Productivity Measurement
61-70
9.1 Methodology
9.2 Test to Determine Weld Deposition
9.3 Welder Efficiency & Productivity
9.4 Parameter Monitoring
9.5 Theoretical vs. Actual Parameter Comparison9.6 Consistency Trend Analysis
ASSIGN-
MENT
DESIGN & IMPLEMENTATION OF WATER COOLING
ARRANGEMENT FOR CALANDRIA STAGE I NOZZLES71-74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
8/74
8
COMPANY PROFILE
Godrej Industrial Township- Pirojshanagar, Vikhroli
From high tech engineering solutions to daily-use products like locks, Godrej has touched lives
of millions of Indians since it was found in 1897 by an ambitious visionary, Mr. Ardeshir Burjojee
Godrej. After 115 years, Godrej has turned into a conglomerate worth US$ 2.6 billion spreading its arms
globally.
Recent change in brand identity further helped grow the brand. Enriching the Quality of
Life..Everyday, Everywhere is the mission of Godrej group, which signifies the involvement and
importance of Godrej products in Indian peoples lives.
Today Godrej employee over 15,000 people and has grown into one of the most trusted brands in
Indian industry with far reaching service and distribution network. The companys corporate head officeand a huge industrial township is located at Pirojshanagar, Vikhroli, The brainchild of Ardeshir Godrej
has turned into a pioneer for Indian private industries. As it strides ahead confidently, it gives direction to
others.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
9/74
9
VIKHROLI ESTABLISHMENT-
After acquiring vast land of 3200 acres in Vikhroli in 1948, Godrej group has developed it
seamlessly turning it into a benchmark company campus.
Godrej & Boyce is truly a multi-faceted private enterprise housing the following manufacturing
plants in its Vikhroli campus.
PLANT DIVISION & PRODUCTS/SERVICES
1 Steel & Other products manufacturing plant-
-Architectural fabrications, ERW Tubes, feeder of cut steel to other plants.
2,3,5 Godrej Appliances
-Production of Refrigerators, Washing Machines, Microwaves, DVD players
and Air Conditioners
4 Office Equipment Division, Furniture Manufacturing Division
- Production of Office Furniture, Seating and Desk Systems, Computer Furniture
and Home Furniture, Home Storewels, Filing Cabinets and Filing Systems,
Sliding/Tambour Door Units, Personal/Industrial Lockers, Customized storage
Systems, Roll-formed Slides and Components for Furniture
7,8 Tool Room Division
- Production of Precision Tooling (Press Tools / Plastic Injection Moulds / Vacuum
Forming Moulds / Pressure Die-Casting Dies), Special Purpose Machines, High
Precision Components / Equipment for Engineering and allied industries, Sheet
Metal Working
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
10/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
11/74
11
Godrej & Boyce Group Structure
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
12/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
13/74
13
MAJOR PROJECTS UNDERTAKEN AT PES, PL-19
F/M Bridge & Carriage-
Bridge & Carriage Assembly
Project overview-
This assembly acts as the drive mechanism for TAPP and KAPP nuclear power plants operated
by NPCIL. These mechanisms are used in Level 1 safety area of reactor to raise and lower the shut off
rods in reaction chamber.
Important characteristics-
Material SA 515
Size- 9600 x 1100 x 12500 (height) mm
Weight- 70 tons
300 components per assembly
Flatness requirement of 50 microns over 1600 x 8000 mm surface
Challenging task of alignment 10 meter long columns
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
14/74
14
Wind Turbine Parts for Enercon India Ltd-
Enercon project components
Project overview-
Enercon India is aiming to create a nation-wide network of wind-energy operated power plants.
These windmills are located in deep seas or on land where average wind speed is high.
The three components of a windmills manufactured at Godrej PES are extremely vital to itsfunction.
Important Characteristics-
3 Components of CS of 4m diameter, each weighing about 3 tons
Fabrication of a combination of prismatic and cylindrical sections to accuracies of +/- 1mm over
4m length
Fabrication of equipment i.e. prone to heavy distortion during welding
Special fixtures- pneumatic and mechanical fixtures to avoid distortion
Extensive use of automatic welding processes- FCAW and SAW
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
15/74
15
Calandria-
Position 1 Position 2
Project overview-
Calandria is the heart of a nuclear reactor. It is the chamber which holds the radioactive fuel rods
when nuclear fission is occurring. Fuel handling mechanism is also commissioned along with Calandria
to handle new or spent fuel rods.
This particular unit of Calandria is being manufactured for the NPCIL-operated Kota Atomic
Power Plant (KAPP), Rajasthan.
Important characteristics-
Requires a separate enclosure for fabrication to avoid contamination and any contact with CS
material
Total 122 nozzles to be welded in 5 stages.
Automation of plasma cutting process to achieve maximum accuracy Involves GTAW welding in 6G position
Transportation to site (KAPP, Rajasthan) by road is a challenging task.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
16/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
17/74
17
Departments in PES
PERSONNEL:Personnel department is the HR-arm of PES division. It handles all manpower related issues and
handles all contractors on behalf of the manufacturing units. Plant Manager and Time Keeper are the two
persons representing Personnel department in every plant.
Apart from all HR related activities, the personnel department also handles the attendance related
issues of all employees, workmen, trainees and apprentices.
MARKETING:
Marketing department is one of the most important departments involved in the cycle of a
product. Even though it is not directly involved in manufacturing activities in any way, it is the reasonwhy manufacturing units receive the order in the first place.
Marketing department seeks orders from suitable sectors by participating in bids from different
companies. Further, important strategic decisions like choosing the most appropriate project to bid for are
all taken by marketing department after consulting with respective manufacturing departments.
DESIGN:
At Godrej, stress is on using internal drawings for uniformity and ease of understanding. This is
where the Design department plays its role. A team of experienced designers with individual CAD
stations works closely with customers to understand their requirements and make uniform-standard
drawings available for manufacturing.
The team uses the most advanced software in the industry including Inventor, AutoCAD and
Ansys. 3D models of intricate components are also made available for precise manufacturing.
PLANNING:
Planning department is the think-tank behind all routing, sourcing and logistics activities. All
important activities from deciding the raw material supplier to transporting medium are done by planning
department. Project planner decides the sequences of operations and supplies job cards along with
project drawings to the respective manufacturing teams.
Planning department employees are involved in the manufacturing cycle of all projects right
through marketing activities to final dispatch of the manufactured job.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
18/74
18
MANUFACTURING:
FABRICATION:
After receiving raw material from Material Preparation Cell (M.P.C.), Fabrication department
and its 130-strong force of experienced workmen consisting of welders, grinders and fitters that
team up to carry out actual value-added manufacturing activities.
Welding methods used in Fabrication department include FCAW, SMAW, GTAW and SAW.
Welding automation is also encouraged by fabrication supervisors wherever possible, as it reduces
the cycle time considerably and improves the quality of weld produced. Special enclosure is also
available in Plant-19 for SS fabrication when contact with CS material is to be avoided.
MACHINE SHOP:
After being released by Fabrication department, Machine Shop takes over the job and precision
machining is carried out with state-of-art machines. AC enclosure is also available for precisionmachining of small components. CNC machining with up to 1 micron accuracy can be achieved at
PES Machine Shop.
ASSEMBLY:
Assembly department takes over the job in final stages of its manufacturing cycle at Godrej PES
division. Plant-19 houses a shot blasting booth and two paint booths which are operated by
Assembly department. Highly precise assemblies are made with help of special fixtures and an
experienced & skilled workforce.
Currently, a 2.5m deep crater is being dug in Plant-19 for the final assembly of Bridge &
Carriage job before dispatch.
QUALITY ASSURANCE & INSPECTION:
Although the QA department doesnt carry out any manufacturing activities, it ensures that the
job stays within required tolerance limits and accuracy expectations are met at all times. Engineers are
trained in different NDT techniques such as LPT, UT, MPI and RT.
MAINTENANCE:
This department takes care of all the machines in the plant. It looks after the daily maintenance
like checking the lubrication etc. It also undertakes preventive maintenance foe increasing the efficiency
of the plant.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
19/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
20/74
20
INTRODUCTION OF FABRICATION DEPARTMENT
PES division is housed in both Plant-9 and Plant-19 with two separate fabrication shops. Carbon
Steel jobs weighing more than 20 tons are fabricated in Plant-19 and smaller jobs where higher degree of
precision is required are fabricated in Plant-9. There is a separate enclosure for stainless shell fabrication
in Plant-19, where currently Calandria is housed.
Three main pillars of fabrication department are as follows-
1) Training-Comprehensive training is given to all staff and workmen in order to provide them with
operational knowledge related to their work. Different types of trainings provided to workers are as
follows-
i.Apprentice Training-Learning apprentices undergo trade-based training in order to provide them with in-depth
knowledge of their respective trades and different operations related to their trades.
ii.Trade Training-
Periodic trade training is provided to all workmen to further improve their knowledge and
share any new developments related to their trades. Also, in case any new machines are
commissioned in Plant-19, Fabrication, all respective operators are provided extensive training
on the functions of machine.
iii. Safety Training-Regular safety training and meetings are held in order to discuss the ways of improving
safety scenario on shop floor and safe practices of operation.
iv. Multi-skilling-It is a creative new initiative undertaken by PES where workers are trained in trades other
than their own. The main purpose of such training is to reduce the overall cycle time and labor
cost.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
21/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
22/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
23/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
24/74
24
Project
DESIGN & IMPLEMENTATION OF
PRODUCTIVITY MEASUREMENT SYSTEM
IN
FABRICATION DEPARTMENT
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
25/74
25
LITERATURE SURVEY-
DEFINITIONS OF PRODUCTIVITY-
It is difficult to define productivity in standard terms as the phenomenon varies with change in
field of use. For example, the productivity norm used in manufacturing industry can not be used in
construction industry. Thus, it is very important to focus on the factors that are quantifiable and can yield
an interpretable and clear picture of the productivity scenario.
Productivity signifies the measurement of how well an individual entity uses its resources to
produce outputs from inputs. But, selection of factors to be measured is tricky. In general, productivity
can be defined as 'rate of output'. Input and output may vary but at the end, productivity is always a 'rate'
(ratio) of output and input quantities.
The above definition can also be stated as a measure of efficiency of production.
Productivity= Output Quantity
Input Quantity
When the work being done is not exactly quantifiable, it is difficult to measure its productivity in
statistical terms as there is no empirical formula which can help us measure working productivity.
In practice, quantitative and qualitative changes take place when relative quantities and relativeprices of different input and output factors alter. In order to accentuate qualitative changes in output and
input, the formula of total productivity shall be written as follows
Productivity= Output quality and quantity
Input quality and quantity
In manufacturing industry though, the work done on shop floor is in quantifiable terms. Accurate
monitoring of different parameters related to any processes in the shop will help us get a clear picture of
productivity scenario. But, the same is not true for purely manual processes (e. g. SMAW welding).
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
26/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
27/74
27
WELDING PRODUCTIVITY-
Benchmarks for welding productivity are not yet implemented properly in any frontline Indian
manufacturing company. Benchmarks for welding productivity may differ from company to company
based on availability of skilled workforce and hence, it is very difficult to compare the productivitystandards of two organisations. On the other hand, the same productivity measurement systems are
considerably clearer in the western countries like the U.S.
According to a survey by the Department of Commerce, U.S., leading industries use the
following eight general welding productivity measures-
1) Welding speed- (e.g. mm length welded per period of time)
2) Welding process output (e.g. Joint completed per period of time)
3) Welding deposition rate (e.g. kgs of weld metal deposited per period of time)
4) Welding machine arc time (% of time welding machine is in operation)
5) Welded product output- Standardized product- (e.g. welded components completed per period of
time)
6) Welded product output- Customized product- (e.g. tons of steel joined per period of time)
7) Welding defect rate (e.g. defects per 100 welds completed)
8) Performance versus time standard (e.g. percentage of production completed within specified time
standard)
Use of multiple productivity measurement standards is recommended as gives more precise estimate
of welder productivity.
At PES, Plant-19, we use the following productivity measures-
1)
Welding speed2) Welding deposition rate
3) Welding defect rate (defects in terms of % weld length)
4) Performance versus time standard
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
28/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
29/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
30/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
31/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
32/74
32
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
33/74
33
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
34/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
35/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
36/74
36
IDLE TIME ANALYSIS-64% idle time recorded was further sorted by its root causes-
1) No job
2) No manpower (No workers)
3) Waiting for instructions4) Machine breakdown
5) Start-up losses
6) Miscellaneous Losses
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
37/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
38/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
39/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
40/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
41/74
41
STANDARDISATION OF VA-NVA ACTIVITIES-
Before carrying out a detailed analysis regarding VA-NVA activities in fabrication shop, it was
important that standardisation of different VA and NVA activities be done. i.e. activities involved in theshop must be categorized in the following three criteria-
1) Value-Adding Activity
2) Non-Value Adding Necessary Activity
3) Non-Value Adding Removable Activity
For a week, I gathered information about various activities carried out at Fabrication shop in
PES, Plant-19. Then by analyzing their importance and contribution towards project completion, these
activities were further differentiated between Value Adding and Non-Value Adding activities.
The below chart was taken as standard for any further analysis regarding VA-NVA activities.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
42/74
42
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
43/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
44/74
44
TIME STUDY METHODOLOGY-
1) The observer first takes some preliminary observations of the work (a pilot study) to be studied in
order to identify suitable elements which can be clearly recognized on subsequent occasions and areconvenient for measurement.
2) Further studies are then undertaken during which the operator times (records) the duration of the
activities performed during the manufacturing process.
3) For the purpose of recording, the activities are broken up into small divisions known as elements
which are then timed using a stop watch or other timing device. One of the main reasons for studying
the activity in the form of elements, rather than the activity a whole is to exactly pinpoint the weak
link in manufacturing sequence. By altering some activities, cycle time can be reduced considerably.
4) Number of cycles that should be observed depends on the nature of the work and also on the level of
accuracy of observations desired. The accuracy of readings will improve with successive
observations. There is no empirical formula to determine the number of observations to be taken for
getting accurate results.
VIDEO ANALYSIS METHODOLOGY-
1) All important activities defined in the micro process plan were recorded by video shooting them.
2) All the videos were then viewed in a production meeting held by PES Manufacturing divisional
heads and respective supervisors.
3) Any changes required in operational procedure were discussed and standardized. The same
modifications in operating procedure are then conveyed to respective workers and implemented
with immediate effect.
STOPWATCH MONITORING METHODOLOGY-
1) As activities related to fabrication are usually ongoing for hours, it was impractical to evaluate
each and every second's work. Hence, time study was done in minutes and its details are shown
on page 46.
2) Actual recorded time was then compared with theoretical time in micro process plan and
bottleneck activities are identified and efforts are taken to decrease their cycle time.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
45/74
45
JOB-SPECIFIC VA-NVA ANALYSIS BY TIME STUDY-
In Fabrication shop of PES, Plant 19, projects are divided among workstations and job is moved
from one workstation to another as it progresses.Supporting Structure is one of the four key components of ReGen PowerTech project, the other
three being Rotor, Brake Disc and Reinforcing Cap. The windmill project was completed within my
tenure at Godrej & Boyce Mfg. Co. Ltd. Supporting Structure occupies SS1, SS2, Plummer Block, SS3,
SS4. While Supporting Structure was in Fabrication shop, detailed VA-NVA analysis was done.
SS job ready for machining
Completed SS ready for dispatch
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
46/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
47/74
47
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
48/74
48
EXPECTED VS. ACTUAL CYCLE TIME-
Process planning department is responsible for providing job cards stating detailed sequence of
operations to be carried out in order to complete a project. The project manager is then supposed to chalkout a micro process plan with expected cycle time and manpower requirement which may need certain
revisions as the project progresses.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
49/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
50/74
50
IMPORTANT IMPROVEMENTS SUGGESTED AFTER SS PRODUCTIVITY
ANALYSIS-
1) While preheating long seams, workmen should provide a metal lid long enough to cover the
whole WEP region so that maximum efficiency of preheating can be achieved.
#2 long seam welding
2) Magnetic rotary table should be provided for quicker pan/fin setup & welding.
3) Tolerance on #2 & #4 parts should be reduced in order to eliminate or reduce grinding that needs
to be done while setup.
#4 setup
4) Two teams could be deployed for fin and pan setup and tack-welding so that total cycle time for
the activity can be reduced considerably.
5) Dimension of gussets needs to be controlled more precisely. Heavy grinding effort is required for
each gusset setup. Several tryouts may be required in some cases.
6) Welding automation is the key to productivity. BhaGo automated FCAW welding technique
should be deployed as much as possible with long seams of supporting structure. Currently,
hardly any welding automation is used for supporting structure.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
51/74
51
7) Workers have difficulty while positioning all eight spacers correctly. This is caused by
deterioration of top and bottom surfaces of the spacers.
Supporting Structure main fixture design drawing
8) Pan locking fixture design needs to be revised to reduce the amount of efforts required for
carrying out setup of each pan. This can be done by reducing the number of bolts that must be
screwed simultaneously in order to get the pan in correct position for tacking. Currently, there
are nine bolts which must be screwed one by one which is very time consuming and laborious
process.
Pan Locking Fixture
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
52/74
52
LOSS ANALYSYS-
SIXTEEN MAJOR LOSSES-
(1) Seven major losses that impede equipment efficiency-i. Failure losses-
Loss due to breakdown of machines is categorized under failure losses. Detailed
breakdown analysis of all machines will suffice the purpose of analyzing failure losses.
Machine breakdown time is found out using the TPM records. Losses data filled by
the operator at the end of shift is collected daily and at the end of month, collective
breakdown data is calculated and analyzed.
ii. Setup/adjustment losses-When any welding machine is set up at the start of shift, setup activities like earthing
clamping and cleaning are to be done. Any intermediate stops during welding for
current/voltage adjustments are also categorized under setup/adjustment losses.In case of semi-automatic FCAW welding, BhaGo machine is used extensively in
Fabrication shop. Setup & adjustment time for BhaGo machine is the highest among all
welding machines.
iii. Tool change losses-Time required for changing the tool of any particular machine is considered as tool
change loss. Changing wire spool of FCAW welding machine or replacing grinding wheel
of grinding machine are categorized under tool change losses.
iv. Start-up losses-Time required for getting back to work after scheduled suspension, lunch break or
shift change is said to be start-up loss. Generally, start-up losses do not affect theproductivity to such an extent that they can be considered as hindrance. Daily pep talks and
filling up of CLIT checklist usually constitute of start-up losses.
v. Minor stoppage/idling losses-Loss occurring due to minor breakdown of a machine or temporary functional
stoppage is also important.
vi. Speed losses-The difference between the design speed of a machine and actual operating speed
directly affects the cycle time of a process, accounting for speed loss. Similarly, we can
also apply this concept to fabrication processes where micro process plan is made by
experienced shop supervisor and the actual processes take longer than the estimated time inprocess plan.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
53/74
53
vii.Defect/rework losses-It is the most important loss occurring in fabrication department, which must be
avoided as far as possible. Defect and rework are NVA-Removable acts and material and
labor cost is added to process expenses.
LPT Defect Data
(2) Losses that can impede equipment operating rate-i. Shutdown losses-
Production time lost due to machine being shut down for some reason is categorized
under shutdown losses. Improper implementation of time reduction study, critical path and
logical cycle-setting are main reasons for shutdown losses.
(3) Five major losses that can impede human work efficiency-i. Management losses-Loss occurring due to improper management or resources, manpower, proceedings
waiting for raw materials, workmen waiting for instructions and rework are categorized
under management losses.
Management losses must be avoided at all costs. To ensure this, loss data for major
projects is maintained independently and presented to the Manufacturing Head during
project review meetings.
ii. Motion losses-Unnecessary movement of resources and materials, improper implementation of line
flow are said to be motion losses.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
54/74
54
iii. Line organisation losses-Losses occurring due to improper manpower planning and management on line are
said to be line organisation losses.
iv. Losses resulting from failure to automate-These are losses due to non-implementation of automated systems like auto-CO2
welding although they could be implemented to reduce cycle time and improve overall
process efficiency.
v. Measuring and adjustment losses-Man-hours lost due to inspection and measurement activities by QA personnel are
counted under measurement & adjustment losses. This loss accounts for quality defects
and rework.
(4) Three major losses that can impede effective use of production resourcesi. Yield losses-
Losses occurring due to wastage of raw material are said to be yield losses.
ii. Energy losses-Inefficient management of energy resources like electricity, compressed air, PNG and
water lead to energy losses. These losses should be minimized in order to improve overall
process efficiency.
iii. Die, jig, and tool losses-Expenses required for upkeep and maintenance of dies, jigs and other tools are also
considered as losses. Preventive maintenance and careful use should minimize this loss.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
55/74
55
JOB SPECIFIC LOSS ANALYSIS-
After completion of ReGen order, fabrication shop had workload of only two major projects-
Bridge & Carriage and Calandria. Detailed Losses analysis was done for the period to know more aboutwhat are the causes of any losses or delays hampering the jobs progress.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
56/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
57/74
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
58/74
58
TEST TO DETERMINE WELD DEPOSITION OF E308L ELECTRODES-
There was no established benchmark for weld deposition of E308 electrodes (SS to SS). Only
available benchmark was for CS material (E-7018)
Hence, a detailed test was conducted to set a standard for all future analysis of weld deposition
for SS to SS weld joints.
TEST PROCEDURE-
1) Three E308L electrodes of diameters 3.15mm, 4mm and 5mm respectively were also weighed in the same way.
End-to-end length was also measured using a tape.
2) An experienced welder was asked to burn the rods one by one on three different plates. Current setting was
noted from the SMAW machines display and arcing time was measured accurately using a stopwatch.
3) After completing each run, slag was removed using chipping hammer and plates were cleaned by wire brushing
& again weighed using an accurate digital scale.
4) Length and weight of all three stubs were also noted.
5) Weight of weld material deposited and weight of electrode consumed were calculated from the readings.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
59/74
59
WELDER EFFICIENCY & PRODUCTIVITY IN CALANDRIA STAGE I NOZZLE
WELDING-
WELDER EFFICIENCY-
With the detailed analysis of Calandria stage I welding, we can estimate the welder efficiency in
terms of the percentage of actual weld deposition over theoretical weld deposition.
It is not desirable to have any positive deviation from the theoretical weld deposition for any
nozzle as all welding-related factors are already considered by the weld estimator. It is essential to make
sure that minimum required weld deposition is always assured.
Prerequisites for calculating weld deposition-
No. of electrodes consumed & their diameters
Standard deposition of electrodes of different diameters
Diameter of
electrode
(mm)
Weight
deposition
(gm)
3.15 20
4 30
5 50
WELDER PRODUCTIVITY-
Similarly, we can also estimate the productivity by analyzing the actual time required for nozzle
welding. Its percentage over theoretical time required gives us an estimate of productivity of welders.
Any negative deviation is appreciated as it means that welding of a particular nozzle was welded
before its expected completion.
COMPARING PARAMETERS (weld deposition & welding time)-
Actual in terms of % theoretical = Actual value
Theoretical value
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
60/74
60
PARAMETER MONITORING-
1) Quality control and traceability are two most important aims of implementing such productivity
measurement norm with Calandria stage I nozzle welding.2) When welding of a particular nozzle is completed, final weld LPT of inner and outer side of shell
is taken to check if there are any repairs in the weld. Most probably causes of repairs revealed in
LPT include slag, lack of fusion, undercut and pinholes. Corrective action has to be taken to
rectify the defect and it is considered as rework loss which accounts for wastage of both
manpower and time.
3) In order to trace the source of defect, grinding is done and the spot is then filled up and re-
offered for LPT. Ultrasonic Testing (UT) of SS material is not possible; hence it is not an option.
4) The ultimate test for completed weld joint is Radiography Testing (RT); in which the weld joint
is exposed to a radioactive source such as Iridium or Cobalt isotope. The projection is then
captured on a film which is examined to find out minute defects which cannot be detected in
other tests.
5) If any defect indications are found, subsequent repair-welding is done followed by re-RT.
6) Repair welding and subsequent grinding is extremely expensive in terms of time and material
costs; which is why welding parameters are monitored carefully.
7) After knowing the depth of defect, we can come to know which welder was responsible for that
particular pass/layer from the depth chart of the respective nozzle.
8) Comparing actual weld deposition with the deposition expected as per the weld estimator is
another major reason behind maintaining the records. If the actual deposition is higher than the
expected deposition, it can be concluded that welders are not using their electrodes properly and
training is required to educate them.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
61/74
61
ACTUAL CALANDRIA STAGE I NOZZLE WELDING OBSERVATIONS-
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
62/74
62
THEORETICAL VS. ACTUAL PARAMETERS COMPARISON-
Criteria Theoretical Actual
Total Weld Deposition (kg) 119.14 120.95
Total Welding Time (hours) 259 296.75
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
63/74
63
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
64/74
64
ANALYSIS OF CONSISTENCY TREND IN WELDER PRODUCTIVITY-
During welder productivity monitoring, consistency in just as important as productivity itself is.
It represents the ability of a welder to repeat his performance. The welder who is capable of
producing quality output with high productivity consistently is considered as the most valuable
resource.
A highly productive welder may not always be consistent. For example, consider 3 kg as the
benchmark deposition level for a shift for SMAW welding. Now, if a worker deposits nearly 7 kg
in an eight hours shift for two days and does below-par work for rest of the week, his overall
productivity for the week would still be par. But, he wouldn't be as consistent as required, which
is equally important.
A productivity consistency analysis was done on the same lines for Calandria Stage Inozzle welding.
Benchmark weld deposition for SMAW welding in Fabrication shop is 2.7 kg/shift. (as per IMS
manual, Fabrication-19)
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
65/74
65
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
66/74
66
From the analysis, it was found that Anand was the most consistent and productive welder of all
and Nandesh was the poorest performer. The outcome was such even though Nandesh's total weld
deposition was the highest of all, and nearly twice that of Anand.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
67/74
67
ASSIGNMENT 1
DESIGN & IMPLEMENTATION OF WATER COOLING
ARRANGEMENT FOR CALANDRIA STAGE I NOZZLESOut of total 122 nozzles, a total of 22 radial were to be welded during stage I. Nozzles of four
different sizes were to be welded. Hence, cooling arrangements were supposed to be different for all four
sizes.
Basically, external and internal water cooling systems were to be designed separately for each
nozzle.
NEED OF WATER COOLING-
As RM for Calandria Main Shell is stainless steel, it is necessary to maintain the heat input
during welding below 2.0 kJ/mm. It is important to maintain the interpass temperature of 240
C.
Laser Gun being used to measure weld joint temperature after completing a pass
Air cooling will not suffice the purpose of maintaining the required temperature, as the amount
of heat generated during welding is much more than what can be air cooled. Water cooling provides
better rate of cooling which is essential in case of Calandria main shell.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
68/74
68
PRIMARY DESIGN IDEA-
For external cooling, a hollow tube of about 16 mm diameter is taken and then bent to circular
shape by hammering. Small holes of 2-3mm diameters are drilled by pneumatic drilling machine at about100mm pitch. It was reduced to 50mm to effect better cooling.
Visualisation of external water cooling system
An internal cooling system was also designed which consisted of a wooden plug with Morse
taper of about 2. After conducting trials of external cooling using circular tube with holes on its
periphery, it was observed that the temperature of welding zone was well below the interpass
temperature. Hence, it was decided that internal cooling was not required, although it would have
certainly helped in further reducing the temperature of the nozzle side of the weld region. The thickness
of shell was more than that of nozzles, which resulted in lesser heat input in the nozzle region, which
supported the shelving of internal cooling system implementation.
Recirculation of water was the most important part of the system, which meant that de-
mineralized (DM) water would need to be stored in a tank only once a day. DM water would be changed
daily in order to maintain the cleanliness of the tank and the job.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
69/74
69
COMPONENTS REQUIRED FOR EXTERNAL COOLING SYSTEM-
DM WATER-
De-mineralized water is used in water cooling system to prevent any corrosion andcontamination issues that may arise when water comes in contact with the shell.
DM Water Storage Tank
WATER TANK-
A medium-size water tub was identified and used a tank for storing the DM water.
Water Tank
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
70/74
70
WATER PIPE-
A flexible pipe of sufficient diameter was used to carry the water pumped by the motor from the
water tank to the circular tube.
Water Pipe
MOTOR (1/8 hp capacity)-
An electric motor of 1/8 hp capacity was deployed for the purpose of pumping water from the
water tank to the lower surface of nozzle through the water pipe and tube arrangement.
1/8 hp motor
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
71/74
71
T OR L JOINT-
A joint was used to route the water coming from the water tank through the pipe and circulate it
through circular tube.
T Joint L Joint
CIRCULAR RING-
A circular ring of M.S. with holes drilled on its periphery was used to shower water on the shell
and nozzle OD surface with enough pressure.
(a) (b) (c)
(a) Two separate rings
(b) Close-up of rings showing holes drilled on the top side at about 30mm pitch
(c) Two rings joined with a T-joint and a hollow rubber tube
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
72/74
72
CLITS-
Small SS clits were used to hold the circular tube in proper position with respect to the shell O.D.
by tack welding.
Clit used to hold the circular ring in position
HOLDING AREA-
The holding area was made of four SS sheets, used as walls, attached to the base by using tack
welding (TIG) and Epoxy sealant like M-sealant. The SS sheets were inclined before being tack welded
in order to capture more water falling down from the shell.
Holding Area
WATER RECOVERY SYSTEM-
A small SS plate was bent in a way to act as an open pipe, facilitating the recovery of warm
water falling down from the weld zone, after cooling it. The recovery system was designed to send the
water from the holding area back to the water tank for recirculation. The open-pipe arrangement was
used particularly when the capacity of holding area was less to facilitate speedy water recovery.
As an option to SS plate, a water pipe was also used sometimes to send spent water back to the
water tank.
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
73/74
73
IMPROVEMENTS IN THE WATER COOLING SYSTEM-
6) COMMON BASE PLATE-After analyzing loss data for Calandria, it was observed that high setup loss was taking its toll on
the workstation productivity. After pondering on the issue, it was decided that a common base plate
would be used as a base for I-series nozzle welding.
INITIAL SCENARIO-
Holding area for each nozzle was separate. Even if two or more separate nozzles in the same line
were to be welded, as many number of water holding arrangements were made. Setup & tack
welding of SS plates to the base was a very time consuming activity and further water proofing the
whole arrangement needed a lot of time as it could not be used before the curing time of the epoxy
sealant is passed.
IMPROVED SCENARIO-
After using common base plate and SS plates (walls) for water holding area, the setup losses
were considerably reduced as was observed by the Calandria loss data for the period of I-series
nozzle welding.
A bent SS plate was used as an open pipe for transferring spent water from the holding area to
water tank for the purpose of re-circulation.
Common Base Plate
-
7/22/2019 Design & Implementation of Productivity Measurement System in Fabrication Department
74/74
7) USE OF L JOINTS-INITIAL SCENARIO-
T-joints (1 input, 2 outputs) were used at the junction of water pipe and circular tube. It was
observed that the pressure of water jet was not enough when using T-joints as two water streams
separated by the T-junction would collide with each other at the opposite end on the periphery of
the circular tube, resulting in loss of overall pressure of water.
IMPROVED SCENARIO-
By using an L joint (1 input, 1 output), only single water stream would be generated and thus the
arrangement would avert the collision of water streams, as observed with T-joint. This improved the
pressure with which water comes out of the holes drilled.
The end result of the improvement was improved cooling efficiency of water and overall better
cooling rate.
IMPLEMENTATION & WORKING-
DM water is taken in water tank and PVC pipes arranged in the following manner-
1)Water Tank Motor T or L Joint
2)Water Recovery System Water Tank
Water is pumped to the circular ring with pressure enough to spray water on the OD side of the
weld joint.
After taking away heat from the weld joint, warm water falls in the water recollection area which
then flows back to the water tank to complete the cycle.
Warm water falling from the weld joint surface is cooled in the recollection system as the area is
open to air and its cooling is accelerated when it flows down from the water recollection area to
the water tank through a PVC pipe.