Download - Delay Analysis
DELAYS &
DELAY ANALYSIS
• Change happens…
• Events occur that require a Contractor’s planned intent for
executing the works to be changed.
• Delays:
• Delay to progress.
• Delay to completion.
DELAYS AND DELAYING EVENTS
• Step 1: (Analysis of Facts)
• Identify that an event has occurred.
• Step 2: (Analysis of Facts)
• Show that the event affects progress of the works.
• Step 3: (Delay Analysis)
• Demonstrate that this delay to progress causes a delay to completion.
CAUSATION
• Planned programme:
• Accepted programme update
TIME EFFECT OF AN EVENT - PLAN
• Condition 1:
• The event causes no delay to progress and no delay to completion.
TIME EFFECT OF AN EVENT - 1
Planned Completion
• Condition 2:
• The event causes a delay to progress but no delay to completion.
TIME EFFECT OF AN EVENT - 2
Planned Completion
• Condition 3:
• The event causes a delay to progress and a delay to completion.
TIME EFFECT OF AN EVENT - 3
Planned Completion 1
Planned Completion 2
• Impact of different types of delay event.
• Impact of prospective and retrospective perspectives on the
calculation of delay to completion.
• Principles of Delay Analysis
INTRODUCTION TO DELAY ANALYSIS
COMPONENTS
• Programme
• Events
• Progress Records/As-built
• Contract requirements
• Other supporting evidence
• Seek agreement • What does the contract say?
– Likely or Actual delay to completion – Method Specified
• What is to be proved? – EOT or compensation or both
• What materials are available? – Availability and Integrity of an As-Planned
Programme , progress and/or As-Built Data; • Limitations on budget and time? • Complexity of Works in question • Proportionality
– Small disputes do not justify expensive and time consuming analyses
CHOOSING A METHOD
CONTRACT TERMS
- "If the Contractor is or is likely to be unavoidably delayed in achieving a completion obligation or milestone ... either prospectively or retrospectively the time ... shall be extended“
- "... an extension of time ... shall be subject to the requirement that ... the event was the operative cause of the delay suffered ...“
• Likely to cause delay?
• Likely to cause or has caused delay?
• Has caused delay?
• To what?
• In relation to what?
WHAT IS TO BE PROVED
• The prospective likely effect on the completion date for the purposes of an interim EOT
• A retrospective actual effect on completion for the purpose of an EOT
• A contemporaneous or retrospective actual effect on progress for the purposes of compensation for disruption
• A retrospective actual effect on the contractor’s overheads for the purpose of prolongation
Retrospectively create a CPM programme
CPM ? As-Planned
Impacted
Programme available?
As built records available?
Updated with progress ?
Recovery or acceleration ?
As-Planned –v-
As-Built
Retrospectively create a
simulated as-built CPM
programme
As-Built But-For
Time-Impact
Illustrates the effect of an Event on the chosen
programme
Measures the effect of an Event on completion in the sequence of construction finally followed
Measures the effect of an event on completion by tracing the critical
path through change in intent
Measures the difference between planned and
actual activity durations
MATERIALS AVAILABLE
PROPORTIONALITY
• Quick, cheap and tend to be rough
–As-planned v as-built
–As-planned impacted
• Time consuming, costly and tend to be thorough
–As-built But-for
–Time impact
• Disregard labels, identify what is done.
• AACE International Recommended Practice No. 29R-03
METHOD
AACEI RP 29R-03: FORENSIC SCHEDULE ANALYSIS
Table 1 – Nomenclature Correspondence (page 11)
ADVANTAGES & DISADVANTAGES
NOT PREFERENCE … OR PREJUDICE!
• AACE International Recommended Practice No. 29R-03 Section 3
• OBSERVATIONAL
• STATIC LOGIC • GROSS1: As-Planned vs As-Built
• PERIODIC2: As-Planned vs As-Built (‘in windows’)
• DYNAMIC LOGIC • CONTEMPORANEOUS UPDATES: As-Planned vs As-Built in windows
• RE-CONSTRUCTED UPDATES: As-Planned vs As-Built in windows
• MODELLED
• ADDITIVE • SINGLE BASE: Impacted As-Planned
• MULTIPLE BASE: Time Impact Analysis / Snapshot
• SUBTRACTIVE • SINGLE SIMULATION As-Built But For / Collapsed As-Built
• MULTI SIMULATION As-Built But For
METHOD IMPLEMENTATION
PROSPECTIVE V RETROSPECTIVE (WHEN?)
• Prospective:
–During currency of project
–Per SCL Protocol
–Contract requirement (e.g. NEC)
–Avoid disputes
• Retrospective:
–During currency of project (after the event)
–Claim preparation
–Dispute resolution (expert analysis)
PROSPECTIVE V RETROSPECTIVE (HOW?)
• Prospective:
–Forward looking e.g. As-planned impacted, Time Impact
• Retrospective:
–Backward looking (e.g. Collapsed as-built, as-planned v as-
built)
AS-PLANNED V AS-BUILT
• Many variances of the type
–May have a Critical Path network as the as-planned programme;
–May have a reconstructed programme as a baseline
–May be carried out in “windows” or “time slices”
• Simply compares;
–Planned programme and as-built programme
–Difference = delay & relief from LADs ( EOT)
• Often amounts to a “total time claim”
• METHOD:
• Prepare an As-Built schedule with same activities as the As-Planned schedule.
• Identify the sequence of activities on the As-Built schedule which control the overall project duration – the Controlling Path.
• Identify critical delay by comparing the duration, sequence and timing of the controlling activities of the As-Planned and As-Built schedules.
• Research evidence to identify causes of the identified critical delays.
AS-PLANNED V AS-BUILT
AS-PLANNED V AS-BUILT
1. identify a secondary effect
2. Infer a primary cause
3. argue that the tertiary effect has resulted from
the primary cause
DELAY
Planned bars
As built bars
AS-PLANNED V AS-BUILT
Advantages • Cheap and quick to carry out
• Useful review of delays and possible merits of allegations
• Can be an acceptable proof where the effect is indisputably on the Critical Path, eg; • at the start of the job
• at the end of the job
• total suspension of the work
Limitations • Only retrospective
• Easily manipulated to suit the preferred case
• Cannot deal effectively with concurrent causes of delay
• Does not calculate the effect of a cause but asserts the cause of the effect
• Not related to the critical path
• Does not take account of acceleration or re-sequencing
AS-PLANNED IMPACTED
• Based on the planned programme
• METHOD:
1.Identify the planned programme/ baseline
2.Establish excusable event based on planned intent
3.Model the event in planning software;
4.Add the event to the programme & recalculate the completion date
5.Compare revised end date to original end date.
6.Claim relief for the shift in timing on the programme
7.Repeat for next event
AS-PLANNED IMPACTED
Contractual Completion Critical Date
foundations
structure
roof & cladding
inspections
1. Start with planned programme
AS-PLANNED IMPACTED
Unforeseen ground
Contractual Completion Critical Date
foundations
structure
roof & cladding
inspections
Period of Delay
2. Identify a causal event
AS-PLANNED IMPACTED
Contractual Completion
Date
Inferred delay to progress
foundations
structure
roof & cladding
inspections
Revised Completion
Date
3. Calculate effect
Causes secondary effect – a delay to progress
Causes tertiary effect – an impact on the planned completion date
Unforeseen ground
Primary cause
IMPACTED AS-PLANNED
Advantages
• Fairly quick and easy to carry out
• Easily understood
• It can be used where as-built information is limited/ does not exist
• Can be suitable method of proof if:
• Project is of simple character
• The planned programme was realistic and achievable
• The critical path remains largely unchanged except for the effect of events
Limitations
• Ignores the as built history of the works
• Cannot deal with concurrency
• Ignores the effect of any change in sequence or acceleration
• Takes no account of:
• Progress
• Resources
• Changing logic
• METHOD:
• Remove delays from as-built schedule to ascertain when the project would have been completed “but for” these delays. • “Gross” method – remove all at once;
• “Stepped” method – remove delays in reverse chronological order.
• Also known as “Collapsed As-Built”.
• Performed after the works are completed using as built programme as baseline
• Evaluates effect of Events on the basis of the sequence of work that was actually followed
• Analyses the earliest completion date but-for identified delaying events
AS-BUILT BUT FOR
• Step 1: Creation of baseline
1. Create/assess as built programme
2. Identify variances between planned & actual performance & infer cause for each
3. Produce simulated as built programme
– Wind back the data-date
– Remove the “fixed” dates
– Substitute with planned dates and a logic network
• Logic can be based on updated progressed programmes produced during works
AS-BUILT BUT-FOR
AS-BUILT BUT-FOR
• Step 2:
–Remove delay events from simulated as-built programme
–Remove delaying activities in reverse chronological order & recalculate completion date
Unforeseen ground
Actual Completion
Date
foundations
structure
roof & cladding
inspections
1. identify secondary effect on progress
2. infer a primary cause
Original duration
AS-BUILT BUT-FOR
Unforeseen ground
Actual Completion
Date
foundations
structure
roof & cladding
inspections
3. Convert to critical path program
AS-BUILT BUT-FOR
Unforeseen ground
Reduced to zero days
Earliest Completion
Date
foundations
structure
roof & cladding
inspections
4. Subtract identified
effect
Secondary effect - delay to progress
Causes tertiary effect - delay to completion
AS-BUILT BUT-FOR
AS-BUILT BUT FOR
Strengths
• Factually based on actual built times - Easily understood
• Can be used where there is no effective planned programme
• Demonstrates cause and effect of actual timing of event, in sequence in which work was actually built
• Can be used to demonstrate both
• Excusable delay
• Compensable delay ie loss and expense was suffered • Takes account of concurrency
Limitations
• Complicated • Requires accurate and complete as-built data • Requires logic reconstruction - Inferred logic may be challenged • Subjective?
• Takes no account of the planned intent
• Does not identify the effect of events on the contractors intention at the time
• Cannot deal with re-sequencing or acceleration measures
• METHOD:
• Research details of claimed event causing delay;
• Model the event in planning software;
• Link event into updated schedule;
• Recalculate the critical path & Completion date.
• Compare revised end date to updated dated schedule end date;
• Repeat for all events in chronological order.
TIME IMPACT ANALYSIS
• Analysis of the effects of delays – over the life of a project, – sequentially, – In light of the Contractor’s progress & future
intentions
• Update Contractor’s current planned programme to period before the Event.
• Add Event to programme & calculate effect upon the planned programme
TIME IMPACT ANALYSIS
Preparation:
– Identify events & create ‘Fragnet’ for each event.
– List Events chronologically
– Identify planned programme current at time of Event current programme
– Check programme reasonable & fit for use as a base-line
– Re-create or review as-built programme.
– Assess progress information.
TIME IMPACT ANALYSIS
As-planned programme
Contractual Completion Critical Date
foundations
structure
roof & cladding
inspections
TIME IMPACT ANALYSIS
Updated programme
Contractual Completion Critical Date
foundations
structure
roof & cladding
inspections
Updated data date
Revised Completion Critical Date after
Update
Slow progress
Progress to activity
TIME IMPACT ANALYSIS
Culpable delay to completion
Contractual Completion Critical Date
foundations
structure
roof & cladding
inspections
Event
Unforeseen ground
Revised Completion Critical Date
after Update
Updated data date
Updated programme
TIME IMPACT ANALYSIS
Progress to activity
Period of event delay to progress
Culpable delay to completion
Impacted programme
Contractual Completion Critical Date
Foundations completed to update date
structure
roof & cladding
inspections
Revised Completion Critical Date
after Event
Remainder of foundations
Updated data date
Unforeseen ground
TIME IMPACT ANALYSIS
Progress to activity
Period of event delay to progress
Culpable delay to completion
Period of event delay to completion
Event
TIME IMPACT ANALYSIS
• Advantages – Cause and Effect – Takes account of Progress/Resource/Logic – Is the most accurate because it uses all planned, progress and as-built information – Takes account of inadequate progress – Takes account of changes in methodology and re-sequencing – Can be used to resolve concurrent delay – Takes account of acceleration – Can deal with multiple Key Dates & Milestones
• Limitations:
– Requires high quality information – Can be time consuming and expensive – Produces a high volume of output – Complicated (and therefore slow) – Prospective results can be inaccurate – Difficult to communicate (Skanska v Egger [2004])
SMOKE AND MIRRORS
• Smoke and mirrors - analysis that is not what it is described to be by its originator
• Found in discrepancy between description of methodology and that actually adopted
SMOKE AND MIRRORS
• As-planned v As-built generally understood
• API & ABBF methodologies often understood
• Few really understand Time impact analysis
• “Windows”, “time impact” “time slice” and “snapshot” often used indiscriminately