Council subdivision Requirements

Council Receives Permit Sec 32A

Must notify Vic Urban within 7 days (if within area)(i) Receipt of application & Date (ii) If Subdivision previous 3 years

AND(b) Provide copy of planning permit for subdivision

DC or IRC not payable

Levy Not PaidMust not issue compliance certificate

Issue compliance certificate

DC or IRC payable

Paid or agreement

Page 2: Council subdivision Requirements

Relevant Building Surveyor

RBS Receives application for permit

Sec 18A

Must notify Vic urban in writing of (if within area)(i) The application (ii) The cost Sec 201(iii) Any refusal 201 (cost)(iv) Any BAB decision (cost)Provide copy of planning permit

DC or IRC not payable

Levy Not Paid - Must issue refusal

Issue compliance certificate

DC or IRC payable

Paid or agreement

Page 3: Council subdivision Requirements

Council Requirements Sec 32

Council Receives Building permit

Sec 32A

Must notify Vic Urban within 14 days in writinga) Name of applicant b) Address of propertyc) Nature of worksd) Cost of works (201)e) Permit info previous three years

AND(b) Provide copy of any relevant planning permit for Building and works or subdivision

Property in project area Property not in project areaNo action required