HOLIDAY INN NAGPUR
SITE OFFICES - COMPARATIVE STATEMENT
S. No. Description UnitQTY ANANYA ENTERPRISES AER PREFAB TECHNOLOGIES
Rate Amount Rate Amount
OFFICE BLOCK
1.1 Sq. Ft 1,430 410 586,300 243 346,775
1 included included
2 included included
3 Aluminum windows as per specification included included
4 Door will provided with aluminum section included included
5 included included
6 included included
7 Sq. Ft. 1,200 60 72,000 75 90,000
8 Sq. Ft. 1,200 38 45,600 68 81,600
Office block porta cabin size 20’x60’ totalarea 1200 sq ft carpet area & 1430 plinth &roof covered area with following items
Installation of 50mm Aerocon Panels as per thedrawing, design, etc. using floorchannel(14x50/75x25) and ceilingchannel(38x50/75x38) made out of G.I sheet of 1mm thick, duly fastened to the floor with drilling,necessary screws, plugs, etc. at 50mm from eachend and intermediate at 600mmc/c. Joining thepanels with sodium silicate(neutral grade) & flyash(from thermal power plant) at the rate of 1:2and facing sheet joint using synthetic acrylic puttyof "Acroplast" make or equivalent including .
Roofing with M/S pipe( 48x48mm medium )frame & G I colour coated profile sheet0.5mmthick roof sheet with all fixing J hook or drilllbolt.
Painting with oil bound with base putty worksat inner wall & outer wall will eb painting withtexture paint
Plumbing & bathroom toilet & pantry fittingwith pipe lines ( all pipe will provided with PPR( prince ) & fitting provided hindustan &hinway
False ceiling with 600mmx600mm water proof A C or calcium scilicet sheet tiles with GIpowder coated grid frame
Electrical Wiring with switch socket & wiringA_C points power point MCB box ETC. ( WiringKalinga , swithch socket make-Anchor , & MCBmake-Havells
8/7/2019 Copy of SiteOffComp
http://slidepdf.com/reader/full/copy-of-siteoffcomp 2/8
S. No. Description UnitQTY ANANYA ENTERPRISES AER PREFAB TECHNOLOGIES
Rate Amount Rate Amount
9 Sq. Ft. 1,522 60 91,320 78 118,716
10 Sq. Ft. 300 45 13,500 65 19,500
11 Sq. Ft. 1,430 95 135,850 135 193,050
12 False ceiling light 600 x600 Nos. 24 3,650 87,600 2,950 70,800
13 Ceiling round light 6” with CFL tube Nos. 20 850 17,000 840 16,800
Sub Total 1,049,170 937,241
SECURITY GUARD HUT
2.1 Nos. 1 82,000 82,000 47,250 47,250
1 included included
2 included included
3 Aluminum windows as per specification included included
4Door will provided with aluminum section
included included
5 included included
6 included included
7 Sq. Ft. 80 - - - -
Flooring with 600mmx600mm vitrified floortiles with fixing materialWith scatting 4” up ot wall height Make-Kajariya , Somany , etc.
Toilet & pantry wall tiles 200x300 with fixingmaterial. Make-Kajaria , Somany , etc.
Plinth the plinth will make with brick & PCC
work as per drawing.(a) Plinth will be made with use class 2ndbrick(b) PCC 1:2:4: 100mm(c) Mud filling under floor(d) Plaster work(e) Excavation in loose soil(f) Floor finishes 25mm IP.
Complete civil work for plinth as perdrawing attach
NOTE: (a ) outer wiring & water pipe linecharge extra(b ) S T 10.30% ( 30% of total value )( c) Vat 12.5% ( 70% of total value )
Security hut porta cabin size 8’x10’ totalarea 80 sq ft carpet area & 90 sq ft plinth &roof covered area with following items
Installation of 50mm Aerocon Panels as per the
drawing, design, etc. using floorchannel(14x50/75x25) and ceilingchannel(38x50/75x38) made out of G.I sheet of 1mm thick, duly fastened to the floor with drilling,necessary screws, plugs, etc. at 50mm from eachend and intermediate at 600mmc/c. Joining thepanels with sodium silicate(neutral grade) & flyash(from thermal power plant) at the rate of 1:2and facing sheet joint using synthetic acrylic puttyof "Acroplast" make or equivalent including .
Roofing with M/S pipe( 48x48mm medium )frame & G I colour coated profile sheet0.5mmthick roof sheet with all fixing J hook or drilllbolt.
Painting with oil bound with base putty worksat inner wall & outer wall will eb painting withtexture paint
Plumbing & bathroom toilet & pantry fittingwith pipe lines ( all pipe will provided with PPR( prince ) & fitting provided hindustan &hinway
Electrical Wiring with switch socket & wiringA_C points power point MCB box ETC. ( WiringKalinga , swithch socket make-Anchor , & MCBmake-Havells
8/7/2019 Copy of SiteOffComp
http://slidepdf.com/reader/full/copy-of-siteoffcomp 3/8
S. No. Description UnitQTY ANANYA ENTERPRISES AER PREFAB TECHNOLOGIES
Rate Amount Rate Amount
8 Sq. Ft. 90 - - 155 13,950
9 Ceiling round light 6” with CFL tube Nos. 3 - - 500 1,500
Sub Total 82,000 62,700
Total (1+2) 1,131,170 999,941
MOCK UP ROOMS
3.1 Sq. Ft. 1,080 275 297,000 236 254,340
1 included included
2 included included
3
Painting with oil bound with base putty works
included included
4 Sq. Ft. 1,080 95 102,600 135 145,800
Sub Total 399,600 400,140
GRAND TOTAL (1+2+3) 1,530,770 1,400,081
COMPLETION TIME 60 DAYS 45 DAYS
NOTE: M/S Ananya has confirmed to discount the difference amount.
Plinth the plinth will make with brick & PCCwork as per drawing.(a) Plinth will be made with use class 2ndbrick(b) PCC 1:2:4: 100mm(c) Mud filling under floor(d) Plaster work(e) Excavation in loose soil(f) Floor finishes 25mm IP.
Complete civil work for plinth as per
drawing attach
NOTE: (a ) outer wiring & water pipe linecharge extra(b ) S T 10.30% ( 30% of total value )( c) Vat 12.5% ( 70% of total value )
Mock-up Room porta cabin size 14’x67’ totalarea 938 sq ft carpet area & 1080 plinth &roof covered area with following items
Installation of 50mm Aerocon Panels as per thedrawing, design, etc. using floorchannel(14x50/75x25) and ceilingchannel(38x50/75x38) made out of G.I sheet of 1mm thick, duly fastened to the floor with drilling,necessary screws, plugs, etc. at 50mm from eachend and intermediate at 600mmc/c. Joining thepanels with sodium silicate(neutral grade) & flyash(from thermal power plant) at the rate of 1:2and facing sheet joint using synthetic acrylic puttyof "Acroplast" make or equivalent including .
Roofing with M/S pipe frame & G I 0.5mmthick roof sheet with all fixing J hook or drilllbolt .
Plinth the plinth will make with brick & PCCwork as per drawing.(a) Plinth will be made with use class 2ndbrick(b) PCC 1:2:4: 100mm(c) Mud filling under floor(d) Plaster work
(e) Excavation in loose soil(f) Floor finishes 25mm IP.
Complete civil work for plinth as perdrawing attach
NOTE: (a ) outer wiring & water pipe linecharge extra(b ) S T 10.30% ( 30% of total value )( c) Vat 12.5% ( 70% of total value )
8/7/2019 Copy of SiteOffComp
http://slidepdf.com/reader/full/copy-of-siteoffcomp 4/8
S. No. Description UnitQTY ANANYA ENTERPRISES AER PREFAB TECHNOLOGIES
Rate Amount Rate Amount
M/S Ananya has confirmed the specifications & brands/makes of material which are acceptable.
8/7/2019 Copy of SiteOffComp
http://slidepdf.com/reader/full/copy-of-siteoffcomp 5/8
Feb.24, 2011
REMARKS
Ananya & AER: 50 mmth Aerocon Panel & 0.5mm 25x50x25 floorchannel
Ananya: 'Mahavir'section; AER: 'Jindal'section
Ananya: 45 mm flushdoor with aeroconprofile door frame'Mahavir' aluminiumsection 2.1 mm th;AER: 40x50x33 mmsection aluminiumdoor 2mm th 'Jindal'
section, 50% NovaPan & 50% 6 mm StGobain Glass
Ananya:Berger/Nerolac,internal 3 coat &textured external 2coat; AER:Berger/Asian, internal2 coat & external 2
coat cement paint;
Ananya:Hindware/parryware;AER: parryware withJaguar fitting
Ananya: Korean e-board tile with GIpowder coated grid;
Ananya: 'Kalinga'wires, 'Anchor'sockets, 'Havell' MCB;
AER: 'Havell' wires,'Anchor' sockets
8/7/2019 Copy of SiteOffComp
http://slidepdf.com/reader/full/copy-of-siteoffcomp 6/8
REMARKS
Ananya: 'Kajaria'vitrified tile; AER:'Kajaria'/'NavinMarbito' vitrified tile
8/7/2019 Copy of SiteOffComp
http://slidepdf.com/reader/full/copy-of-siteoffcomp 7/8
REMARKS
AER: confirmedinclusion on phone dt24/2/11