Chronological progress of the construction phase:
March 2015 - May 2015 - Completion Report
Installation of silt fence & trees protection
Trees Removal
Removal of top soil to prepare the foundation
Excavation & materials removal
Retaining walls excavation & backfill
Backfilling and compaction
Fire fighting pond
Water storm drainage
June 2015 - Dec 2015 - Completion Report
100% of the perimeter of the concrete walls for first level
100% of walls foaming of lower level concrete
Elevator Pit is complete
CONSTRUCTION IS CURRENTLY ON HOLD DUE TO WINTER AND WILL RESUME BACK IN SPRING 2016
![Page 3: Chronological progress of the construction phasewimnet.ca/wp-content/uploads/2016/09/masjid-construction-update-slideshow.pdfChronological progress of the construction phase: March](https://reader030.vdocuments.us/reader030/viewer/2022040215/5eca414ace74ca60fc41d2d7/html5/thumbnails/3.jpg)
The actual spent as of
Dec 2015 towards the
construction of
Masjid Noor-UL-Haram
is $2.1M which is part
of the $13.5M of the
total cost of project
for phase 1
![Page 4: Chronological progress of the construction phasewimnet.ca/wp-content/uploads/2016/09/masjid-construction-update-slideshow.pdfChronological progress of the construction phase: March](https://reader030.vdocuments.us/reader030/viewer/2022040215/5eca414ace74ca60fc41d2d7/html5/thumbnails/4.jpg)
![Page 5: Chronological progress of the construction phasewimnet.ca/wp-content/uploads/2016/09/masjid-construction-update-slideshow.pdfChronological progress of the construction phase: March](https://reader030.vdocuments.us/reader030/viewer/2022040215/5eca414ace74ca60fc41d2d7/html5/thumbnails/5.jpg)
![Page 6: Chronological progress of the construction phasewimnet.ca/wp-content/uploads/2016/09/masjid-construction-update-slideshow.pdfChronological progress of the construction phase: March](https://reader030.vdocuments.us/reader030/viewer/2022040215/5eca414ace74ca60fc41d2d7/html5/thumbnails/6.jpg)
![Page 7: Chronological progress of the construction phasewimnet.ca/wp-content/uploads/2016/09/masjid-construction-update-slideshow.pdfChronological progress of the construction phase: March](https://reader030.vdocuments.us/reader030/viewer/2022040215/5eca414ace74ca60fc41d2d7/html5/thumbnails/7.jpg)
![Page 8: Chronological progress of the construction phasewimnet.ca/wp-content/uploads/2016/09/masjid-construction-update-slideshow.pdfChronological progress of the construction phase: March](https://reader030.vdocuments.us/reader030/viewer/2022040215/5eca414ace74ca60fc41d2d7/html5/thumbnails/8.jpg)
![Page 9: Chronological progress of the construction phasewimnet.ca/wp-content/uploads/2016/09/masjid-construction-update-slideshow.pdfChronological progress of the construction phase: March](https://reader030.vdocuments.us/reader030/viewer/2022040215/5eca414ace74ca60fc41d2d7/html5/thumbnails/9.jpg)