Chico Urban Area Nitrate Compliance Program
Project Area 2S Neighborhood Meeting April 23, 2014
![Page 2: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/2.jpg)
WELCOME
Scott Gruendl, Mayor City of Chico
![Page 3: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/3.jpg)
Agenda • Nitrate Compliance Program Information • Construction Update • Benefits of Connection • Sewer Fees & Application Process • How to Connect to Sewer • Available Assistance • Questions
![Page 4: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/4.jpg)
NITRATE COMPLIANCE PROGRAM
Casey Hatcher Program Development Manager Butte County Administration
![Page 5: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/5.jpg)
Nitrate Compliance Program • 1990 Regional Water Quality Control Board
adopts Prohibition Order No. 90-126 – Prohibits installation of new septic systems after July
1990. – Eliminates existing septic systems on lots of less than 1
acre by July 1995. – City and County agreed to review Prohibition Order and
develop responses and propose alternatives to the State.
![Page 6: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/6.jpg)
Nitrate Compliance Program • 2000 Nitrate Compliance Plan Adopted
– Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory Committee.
– Plan stated 7,800 dwelling units to be connected to City sewer.
– Today that number is closer to 5,600.
![Page 7: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/7.jpg)
Nitrate Compliance Program • 2008 State Revolving Loan Fund
– City and County create mechanism for property owners to more cost effectively comply with Prohibition Order.
– City and County worked together to secure financing for the public improvements.
• Sewer main • Sewer laterals to the edge of the property line
![Page 8: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/8.jpg)
Nitrate Compliance Program • 2010 First Phase - Complete
– Project Area 1N – Esplanade, Lassen, Cohasset
• 2012 Second Phase – Complete – Project Area 1S - Humboldt, Chapman, Mulberry, Pomona
• 2013 Third Phase – Complete – Project Area 2N – Connors White, El Paso, Pillsbury
• 2014 Fourth Phase – Two Units Complete – Chico Vecino
![Page 9: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/9.jpg)
Stakeholder Relationships
![Page 10: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/10.jpg)
CONSTRUCTION UPDATE PROJECT AREA 2S CHICO VECINO NEIGHBORHOOD
Tamara Miller, P.E. MPM Engineering
![Page 11: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/11.jpg)
Project Overview • Sewer Mains
– The pipes in front of your property • Laterals
– The pipe between the main and your house • Sewer Trunk Lines
– The large pipes that carry sewage to the Plant • Water Pollution Control Plant
– Located about 8 miles southwest of Chico
![Page 12: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/12.jpg)
Project Area 2S (first phase)
![Page 13: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/13.jpg)
What Was Included • Sewer mains • Sewer laterals within public right-of-way • Manholes • Repair of trench including replacement of
curb, gutter and sidewalks to match pre-existing conditions
![Page 14: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/14.jpg)
What Was Not Included • Storm drains and drainage systems • Road improvements
– Only repair of backfill trench • New curb, gutter & sidewalks
– Only repair to match pre-existing conditions • Installation of sewer laterals on private property or
septic tank decommissioning – This is “on-site” work, responsibility of property owner
![Page 15: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/15.jpg)
14
Stakeholder Relationships
![Page 16: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/16.jpg)
Construction Process • Lions, Tigers, and Bears Oh My!
or • Laterals, Trenches, and Manholes, Oh My!
![Page 17: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/17.jpg)
Step 1 in Construction: Potholing
![Page 18: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/18.jpg)
Step 2 in Construction: Trenching
![Page 19: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/19.jpg)
Step 2 in Construction: Manhole
![Page 20: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/20.jpg)
Step 3 in Construction: Install Pipe
![Page 21: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/21.jpg)
Step 4 in Construction: Cold-Patch
![Page 22: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/22.jpg)
Step 5 in Construction: Install Laterals
![Page 23: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/23.jpg)
Step 5 in Construction: Install Laterals
![Page 24: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/24.jpg)
Step 5 in Construction: Install Laterals
![Page 25: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/25.jpg)
Step 5 in Construction: Install Laterals
![Page 26: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/26.jpg)
Step 6 in Construction: Test
![Page 27: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/27.jpg)
Step 7 in Construction: Hot Mix Paving
![Page 28: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/28.jpg)
Step 7 in Construction: Hot Mix Paving
![Page 29: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/29.jpg)
Step 8 in Construction: Manholes to grade
![Page 30: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/30.jpg)
Step 9 in Construction: Striping corrected
![Page 31: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/31.jpg)
And of course… there’s conflict
![Page 32: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/32.jpg)
And of course… there’s conflict
![Page 33: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/33.jpg)
And of course … there is ongoing clean up
![Page 34: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/34.jpg)
Unit 1 Contractor: Visinoni Brothers Construction Began: September 3, 2013 Construction Ends: May 2014 Working Days: ~145 Sewer: ft. 10,177 Laterals: 165 Manholes: ~ 37
![Page 35: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/35.jpg)
Unit 2 Contractor: Visinoni Brothers Construction Began: August 28, 2013 Construction Ends: May 2014 Working Days: ~145 Sewer: ft. 8,780 Laterals: 183 Manholes: ~ 23
![Page 36: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/36.jpg)
SEWER FEES & APPLICATION PROCESS
Matt Thompson Senior Civil Engineer City of Chico Building & Development Services Department
![Page 37: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/37.jpg)
Typical Sewer Fees
Lateral $29.81/ft. Main Line $47.80/ft. WPCP $2,251/unit Trunk Line $1,693/unit
Project Area 2S Fees
Lateral $0/ft. Main Line $0/ft. WPCP $0/unit Trunk Line $1,693/unit
Approximate Fee Savings for Property Owners within Nitrate Compliance Program Boundaries:
$5,600
![Page 38: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/38.jpg)
Sewer Application Process • Submit a Sewer Application
– Application is only one page – Application fee is $100.00
• You will receive a letter from the City indicating connection fees and the steps to sewer connection.
![Page 39: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/39.jpg)
Payment of Sewer Fees • Pay at issuance of Plumbing Permit, or • In-lieu payment
– In-lieu process allows fee to be paid over ten year period. – Application for in-lieu is $364. (fee can be financed) – A recent title report or lot book guarantee is required. Title
companies do charge for these documents.
![Page 40: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/40.jpg)
COUNCIL WILL VOTE SOMETIME IN THE NEXT COUPLE MONTHS. THE INCREASE WILL GO INTO EFFECT 12O DAYS LATER.
Proposed Fee Increases
39
Fee Title Current Fee
Actual Full Cost
First Year Second Year
Third Year (90%)
Sewer App (City)
$100
$276.49
$174.42
$211.63
$248.84
Sewer App (County)
$100
$310.56
$189.80
$234.70
$279.59
Assessment
in Lieu
$364
$972.56
$619.56
$747.48
$875.30
![Page 41: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/41.jpg)
Permits Required Permit Issuing Agency Fee
Plumbing Permit City of Chico $137
Septic Abandonment Butte County $117
![Page 42: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/42.jpg)
HOW TO CONNECT TO SEWER
Tamara Miller, P.E. MPM Engineering
![Page 43: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/43.jpg)
How to Connect to Sewer After application is completed, the steps for sewer connection include: • Plumbing Permit • Hire a Contractor
– Do I hire a contractor? • Locate Lateral
![Page 44: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/44.jpg)
How to Connect to Sewer Steps to sewer connection continued: • Dig a trench • Place a pipe and connect • Inspection • Fill in the trench • Empty and crack septic tank • Final approval
![Page 45: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/45.jpg)
How to Connect to Sewer
![Page 46: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/46.jpg)
How to Connect to Sewer • How much time will the construction take?
– Estimated time is 2 days. • What are the costs?
– Estimated cost for improvements, permits and fees is $5,000 to $6,000.
![Page 47: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/47.jpg)
BENEFITS OF CONNECTION
Casey Hatcher Program Development Manager Butte County Administration
![Page 48: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/48.jpg)
Benefits of Connection • Provides a means for property owners to
comply with Prohibition Order. • Reduces septic tank maintenance issues and
costs. • Increases re-sale value of the home. • Ability to construct decks, pools, paving, etc. • Ability to install garbage disposal.
![Page 49: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/49.jpg)
Benefits of Connection • Ability to cooperate with your neighbors to
hire a single contractor which could lower construction costs and save time.
• Current fee savings for properties identified by the Nitrate Plan of approximately $5,600.
• Through sewer connections in Project Area 2S (first phase), approximately 1.1 tons of nitrate load will be eliminated.
![Page 50: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/50.jpg)
AVAILABLE ASSISTANCE
![Page 51: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/51.jpg)
Available Assistance • Reduction in Fees
– Current fee savings approximately $5,600 • Fees – Assessment in-Lieu
– Contact City of Chico 530-879-6950
![Page 52: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/52.jpg)
Available Assistance • City of Chico Housing Rehabilitation
Nitrate Compliance Program – Grant provided to qualifying low-moderate income
property owners where costs are less than $10,000. – Home must be owner-occupied – Eligible improvements:
• Application, permit, and connection fees • Sewer lateral construction (including abandonment of septic)
• Call 879-6300 to be added to the interest list after July 1, 2014
51
![Page 53: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/53.jpg)
Available Resources • Citizens Guide to Sewer Connection • Biannual Newsletters • www.NitrateCompliance.org • www.TinyUrl.com/ButteCertifiedPumpers
![Page 54: Chico Urban Area Nitrate Compliance Program · 4/23/2014 · – Plan included proposed solutions to nitrate problem as proposed by a technical team and Citizen’s Nitrate Advisory](https://reader034.vdocuments.us/reader034/viewer/2022050305/5f6d73fdde58015de752b6e0/html5/thumbnails/54.jpg)
City of Chico Contacts
Casey Hatcher Program Development Manager
Butte County Administration (530) 538-6182
Jennifer Macarthy Economic and Community
Development Manager Butte County Administration
(530) 538-2554 [email protected]
Butte County Contacts
Kristen McKillop Program Development Manager
Butte County Environmental Health (530) 538-7283
Ruben Martinez Public Works Director
City of Chico (530) 879.6901
Matt Thompson Senior Civil Engineer
City of Chico (530) 879-6959
Tamara Miller, P.E. MPM Engineering (530) 892-1795
MPM Engineering Contact