Centinela Valley Union High Centinela Valley Union High School District
Measure CV Program Update
June 10, 2013
1
Site Construction Progress Site Updates
� Hawthorne High School
� Lawndale High School
� Leuzinger High School
TELACU Construction Management2
Hawthorne High School Community Oversight Committee Status Report June 2013Community Oversight Committee Status Report June 2013
TELACU Construction Management
05, 2013
3
Hawthorne High School Building A & B – Rendering of Counseling and Student Services & Media CenterBuilding A & B – Rendering of Counseling and Student Services & Media Center
Building BBuilding A Building BBuilding A
TELACU Construction Management4
Hawthorne High SchoolBuilding A – Counseling & Student ServicesBuilding A – Counseling & Student Services
The Counseling & Student Services building is on schedule for a summer completion. Since our last update interior dry wall are installed, exterior storefront windows and doors are up, and plastering is completed. Interior and exterior painting, and hard lid ceilings are proceeding.
05, 2013
TELACU Construction Management
completed. Interior and exterior painting, and hard lid ceilings are proceeding.
5
Hawthorne High SchoolBuilding B – Media CenterBuilding B – Media Center
The Media Center structural steel is erected. The roof metal decking and all underground utilities are laid out.
05, 2013
TELACU Construction Management
underground utilities are laid out.
6
Hawthorne High SchoolBuilding C – Sciences BuildingBuilding C – Sciences Building
• 10 Biology Classrooms
• 3 Chemistry Labs
• 1 Physics Classroom• 1 Physics Classroom
• Workrooms
Rendered view from the corner of El Segundo and Inglewood intersection
TELACU Construction Management7
Hawthorne High SchoolScience BuildingScience Building
The Science Building has structural steel erected, all metal decking and underground utilities laid out, grade beams poured. Currently, we are installing rebar on the 2nd floor.
05, 2013
TELACU Construction Management
utilities laid out, grade beams poured. Currently, we are installing rebar on the 2nd floor. Sewer and storm drain piping are currently being laid out around the exterior perimeter.
8
Lawndale High School Site AerialCommunity Oversight Committee Status Report June 2013Community Oversight Committee Status Report June 2013
COSTCO STRIP/ PARKING SOMMERVILLE/ COSTCO STRIP/ PARKING SOMMERVILLE/ UTILITIES
OUTDOOR QUAD
STUDENT STUDENT SERVICES BUILDING
TELACU Construction Management9
Lawndale High School Student Services Building – Rendering of the front of building & Ariel ViewStudent Services Building – Rendering of the front of building & Ariel View
Construction for the Phase 1 Student ServicesBuilding started in October 2012. The BuildingBuilding started in October 2012. The Buildingalong with the Outdoor Quad area will becomplete by August 2014. Building will beready for the 2014-15 school year.
The building will have Administration, Libraryand Campus Security spaces including 43teaching stations which include standardclassrooms, science laboratories, AVIDClassrooms, Digital and media arts.
TELACU Construction Management
Classrooms, Digital and media arts.
10
Lawndale High School Student Services Building – Costco Strip/ ParkingStudent Services Building – Costco Strip/ Parking
The storm water drain and french drain in the Costco strip was completed. The parking area was asphalted strip was completed. The parking area was asphalted and handed over to the District mid-April. Landscaping and fencing will be completed towards the end of the project.
TELACU Construction Management11
Lawndale High School Student Services Building – Structural Steel ErectionStudent Services Building – Structural Steel Erection
The entire Structural Steel for the project was erected in 32 days. The steel erection crew did an erected in 32 days. The steel erection crew did an expert job in accelerating the schedule with zero safety incidents.
TELACU Construction Management12
Lawndale High School Student Services Building – Metal Decking InstallationStudent Services Building – Metal Decking Installation
Placement of metal decking followed closely behind the steel and metal decking on the roof level is the steel and metal decking on the roof level is ongoing. Stair 1 and 2 are being installed right now with Stair # 3 and 4 in fabrication.
TELACU Construction Management13
Lawndale High School Student Services Building – MEP Rough inStudent Services Building – MEP Rough in
MEP rough-in has been ongoing. A portion of the slab on grade was poured. We will be pouring slab on grade was poured. We will be pouring concrete slabs every two weeks so metal stud framing can follow right after.
TELACU Construction Management14
Leuzinger High School Community Oversight Committee Status Report June 2013Community Oversight Committee Status Report June 2013
TELACU Construction Management15
Leuzinger High School Phase IISegment A – 2 Story Classroom & Dining FacilitySegment A – 2 Story Classroom & Dining Facility
North building, Segment A, structural steel erection structural steel erection complete.
First floor metal stud framing and ductwork framing and ductwork installation ongoing.
Second floor concrete pour complete.complete.
Roof metal decking and drain layout complete.
West stairs delivered, erection to commence.
TELACU Construction Management16
Leuzinger High School Phase IISegment B – 2 Story Classroom & Dining FacilitySegment B – 2 Story Classroom & Dining Facility
Middle building, Segment B, structural steel erection/welding structural steel erection/welding ongoing.
Metal decking placement ongoing, preparing for concrete pour.preparing for concrete pour.
TELACU Construction Management17
Leuzinger High School Phase IISegment C – 2 Story Classroom & Dining FacilitySegment C – 2 Story Classroom & Dining Facility
South building, Segment C, South building, Segment C, first floor concrete slab on grade complete.
Stairwell footings excavated. Stairwell footings excavated. Rebar installation complete.
Structural steel erection forthcoming.forthcoming.