Health and Safety Executive
Health and Safety Executive
CDM 2015 & information
a view from HSE
Louise Brearey
Head of Operations
HSE London & South-East
![Page 2: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/2.jpg)
Review of CDM 2007
• Key points from research– aims of CDM 2007 largely met, but– 3 concerns:
• application and interpretation• coordination not working• Had not tackled bureaucracy
– ACoP – how effective?
![Page 3: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/3.jpg)
![Page 4: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/4.jpg)
Main proposed changes to CDM on which we are consulting
• Simplification of the Regulations
• Applies to projects for domestic clients (Implements the TMCS directive)
• Strengthens role of the client
• Removes corporate competence requirements & concentrate on site competence
• Removal of CDM Coorinator role
• Makes designers responsible for coordination in the pre-construction phase
• Removal of ACOP (replace with HSE & industry guidance)
• Change to thresholds for notification (500 person days or 30 days with 20 contractors)
![Page 5: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/5.jpg)
Our message remains the same:
•The right information
•To the right people
•At the right timeAND
Tackling bureaucracy
![Page 6: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/6.jpg)
Golden Rule
EFFORT ≈ RISK (UNFAMILIARITY)
![Page 7: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/7.jpg)
The right information
What information does CDM require (& IS LIKELY TO CONTINUE TO)?
1. Preconstruction information
2. Information about the design that others need to manage risks
3. Information needed to produce the construction phase plan plan
4. Information for the health and safety file
![Page 8: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/8.jpg)
But there are other H&S information requirements:
Risk assessments (method statements),
H&S policies,
COSHH data / assessments/asbestos survey
Training records
Inspections
Lifting plans
Transport management / logistics
Fire / emergency / evacuation
![Page 9: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/9.jpg)
Preconstruction
• “The site contains no unusual hazards that would be unfamiliar to a competent contractor” – a reasonable concept?
![Page 10: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/10.jpg)
Providing design information
• Designers need to provide information about aspects of the design….– not likely to be obvious to a competent contractor– unusual– likely to be difficult to manageIf in doubt, ask those who will use the
information
![Page 11: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/11.jpg)
![Page 12: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/12.jpg)
BIM
![Page 13: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/13.jpg)
Construction phase plan
• A manual?
• “How health and safety will be managed on this site”
• Live document not shelf dweller
• More than somewhere to file generic risk assessments
• How will I monitor? What are the KPIs?
• Appendix 2 of current ACoP
![Page 14: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/14.jpg)
Health & Safety File
• Description: What will future designers / construction or demolition contractors need to know to MANAGE THE RISKS?
• What goes in?
• What stays out!
• Relevant
• Anticipate what users will need?
![Page 15: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/15.jpg)
Golden Rule
EFFORT ≈ RISK (UNFAMILIARITY)
![Page 16: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/16.jpg)
![Page 17: CDM 2015 & information a view from HSE](https://reader035.vdocuments.us/reader035/viewer/2022062309/56813514550346895d9c6919/html5/thumbnails/17.jpg)
Summary
• Aim is to manage and control the risks
• Paperwork is of value if it contributes to this aim
• Remember the user and purpose of the paperwork
• CDM Revision an opportunity for change