Transcript
Page 1: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Adelaide

Metropolitan Rail

Upgrade

Sevan Simonian CEng MICE

Project Manager

Page 2: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

A critical part of the SA

Government’s $2B

investment in public

transport infrastructure.

› Design and construction

of rail network

› Belair, Noarlunga and

Gawler Lines

› 6 D&C Contracts in total

› 1 ECI Contract - Facilitate

Adelaide Metropolitan

Rail Upgrade

Page 3: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Why Upgrade?

Page 4: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

The Challenges

4

› Highly Compressed Programme – No compromise on

Quality, maintain budget

› Geographic diversity/Community

› Safety and Rail Safety

› Environment

› Interfaces

› Community

4

• Securing Best for Project

Designers & Constructors

• Competing with other large

Projects

•Maintaining Key Personnel for

the life of the Project

Key Points:

Page 5: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Proximity to ARTC

5 5

Page 6: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Delivery Models – Pre-ECI

Three D&C Projects

› Belair Line

› 19 Track km

› March – August 2009

› 3 Station Upgrades

› Noarlunga Line Stage 1

› 2.4km – 2 Weekend Occupations

› Nov/Dec 2009

› Gawler Line Stage 1 & 3

› 24 Track km

› May – September 2010

› 6 Station upgrades

6 6

Page 7: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Delivery Models – ECI

Three D&C Projects

› Noarlunga Line Stage 2 & 2A

› 32 Track km

› February – July 2011

› Gawler Stage 4

› 54km Track km

› September 2011 – March 2012

› Noarlunga Stage 3 & Ade Yard

› 26 Track km

› January – June 2013

› New Station - Wayville

› Nairne Junction Upgrade

7 7

Page 8: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

ECI

› RAMP evolves with the Designs

› Agree Rates and Construction Methodologies

› Agree Risk Sharing

› Independent Estimator engaged from the start

› At 70% design gate, package is converted into lump sum price (AS4300)

› Work packages and concurrent design development and implementation

phases, with subsequent learning implemented in following packages assisting

in early transition

8 8

Page 9: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

ECI - Value for Money

› NPV Calculations (Whole of Life)

› Value Engineering

› Innovations

› Risk Assignment and management

› Transition to D&C as early as 30% Design =

Program Savings (Brown Field)

› Operational balance between maintaining

PTSOM Operations with Construction Costs

9 9

Page 10: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Design Strategies

10

› Niche Design Resources, Management,

Review and Verification

› Early 3D Rail Track modelling of the

Alignment Enabled Construction planning

and Interface with other Disciplines

10

• Early Establishment of 3D

Spatial Test Alignment

• Coordinated Input from other

projects in Design

•Designers regularly on track

walks throughout design

Key Points:

Page 11: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Design Strategies – Innovation Recognition

Salisbury Crossover SB3

Moved 400m towards Platform

Allows for Rationalization of the Alignment to

Increase Speed to 100km/hr

Page 12: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Design Delivered as a 3D model

Top ballast

Bottom Ballast

Formation

150mm Capping

Page 13: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Design Challenges of the Existing Alignment

13 13

Page 14: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

14

Earthworks

Page 15: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

15

Earthworks

› Critical to establish ground preparation

› Geotech engineer design signed off

› Formation treatment must be set and established

› Do not deviate

Page 16: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

16

Drainage

› Definitive solutions

Page 17: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

17

Track Construction – Point of difference

Page 18: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

18

Resurfacing

Page 19: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

19

Adelaide Yard – Nairne Junction

Page 20: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

20

Planning Considerations

› Client Risks/Expectations

› Programme

› Public Perception

› Risk Mitigation

› Meticulous Planning – fatigue, heat, resources

› UNIMAT

› Mission Command – Empower Engineers & Supervisors

Page 21: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Project Summary

Over 1,000,000

Man hours

150 project

workers a day

Over 3,000

workers

inducted

725,000 tonnes

of new ballast /

560,000 tonnes

of spent ballast

removed +

recycled

90km of new rail

installed and

240km of rail

remediated

36 road level

crossings +

48 pedestrian

crossings

upgraded

240,000 concrete

sleepers installed

4,600 welds

removed and

remediated

Removed

1500 short

rails and joints

Zero LTIs

Page 22: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

22

Community

› Close to schools, kindergartens, businesses & residents

› Eleven local councils involved throughout works

› Site improvements for future use by councils

› John Holland donation to Elizabeth Special School – Gardening Programme

› Local employment and industry participation > 75% from SA

Page 23: CASE STUDY: Update on Adelaide’s Metropolitan rail upgrade

Questions


Top Related