Case Studies and Benchmarking: Canadian DER Integration Projects
Tarek EL-Fouly, PhD
Workshop: Smart Grid Demo Project ReviewsDecember 10, 2010
2
Outline
Introduction
Modeling, Simulation and Benchmark Case Studies
Demonstrations and Field Tests Case Studies
Smart Grid Demonstration Projects
3
Introduction
Modeling, Simulation and Benchmark Case Studies
Demonstrations and Field Tests Case Studies
Smart Grid Demonstration Projects
4Statistical Source: North American Electric Reliability Council (NERC)Map Source: Global Energy Network Institute (GENI)
Provincial Electricity Generation Mix
5
CanmetENERGY, NRCan
National energy laboratories within the department of Natural Resources Canada
CanmetENERGY manages science and technology programs and services and support the development of energy policies, codes and regulations.
Canadian leader in clean energy research and technology development - 3 energy research centres : Ottawa, Devon and Varennes. Over 450 scientists, engineers and technicians.
Located in Varennes, QC about 26 km from downtown Montreal.
Web link: http://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/eng/index.html
CanmetENERGYVarennes, Québec,
Canada
6
Program Objectives and Key Activities
Smart Grid R&D objective: To support national S&T efforts that will contribute to the modernization of the electricity grid network,enhance the benefits of renewable and clean distributed energy resources, increase diversity and reliability of supply, and facilitate recovery after disruptions.
Key activities:
Modeling, Simulation and Benchmark Case Studies
Technology Assessment and Demonstrations
Standards, Codes and Regulatory Support
National and International Collaboration
7
Introduction
Modeling, Simulation and Benchmark Case Studies
Demonstrations and Field Tests Case Studies
Smart Grid Demonstration Projects
8
Automatic Fault Location Detection on Rural Feeders with DGs
Locating faults on the distribution system is important to:
repair the faulted section and restore service as fast as possible in the case of permanent faults.
identify incipient problems and monitor equipment that may have been damaged during transient fault events.
Automatic fault location detection approaches:Using the voltage and current measured at the substation to estimate the impedance to the fault.
Using the voltage measured at the substation, in addition to voltages obtained from advanced meter infrastructure (AMI).
L1
L11
L12
L13
I1
Zf
V1
Approach using measurements at the substation
Approach using the voltage measurements from the substation and from AMI
L1
L11
L12
L13
V1
Zf
VL1
VL2
VL3
9
Automatic Fault Location Detection on Rural Feeders with DGs (Cont.)
This study considers the impact of DGs on the performance of an automatic fault location approach using the voltage and current measured at the substation.
In general, when the DG is upstream of the fault section, the performance will be degraded, with the impact being more severe for synchronous machine based DG.
L1
9.7 km
C
69 kV260 MVAX/R = 1.6
25/69 kV2- 6 MVA
Substation
L2
4.6 km
L4
2.8 km
L5
16.7 km
L6
4.6 km
L7
10.6 km
L8
6.8 km
L9
5.0 km
L10
14.2 km
BA
EFGHI
J
SB
SDSFSG SI
SJ
SE
L3
2.5 km
D
Hydro DGs scenariosHydro DGs scenariosHydro DGs scenarios
0
2
4
6
8
10
12
14
B C D E F G H I
Fault Location
% e
rror
Wind_AWind_CWind_GNo-DG
0
5
10
15
20
25
B C D E F G H I
Fault Location
% e
rror
Hydro_AHydro_CHydro_GHydro_JNo-DG
Canadian rural feeder
Automatic Fault Location Detection Algorithm
10
Impact of High PV Penetration on Voltage Profiles in Residential Neighborhoods
Canadian overhead residential feeder Benchmark
X 9 X 9 X 9 X 9
X 9 X 9 X 9
A
C
X 9 X 9 X 9
X 9 X 9 X 9
X 9
X 9
X 9 X 9 X 9
X 9 X 9 X 9
X 9
X 9
B
20 m
20 m
20 m
20 m
20 m
20 m
20 m
20 m
20 m
Substation
250 m 250 m 250 m 250 m
A B
C
0 AWG ASC
3 MVA PF 0.90
3 MVA PF 0.90
2 MVA PF 0.95
2 MVA PF 0.95
2 MVA PF 0.95
Sub-Network A
0 AWG ASC
1/0 AWG, Aluminum, XLPE
4/0 AWG, Aluminum, XLPE
75 kVA14.4 kV/120 V/240 V
94 MVA120 kV/25 kV
60 MVA PF 0.95
3 MVA PF 0.9 3 MVA PF 0.92 MVA PF 0.9
2 MVA PF 0.9
2 MVA PF 0.9
216 PV Houses
PSCAD model
A model using PSCAD/EMTDC has been developed for a Canadian overhead residential feeder benchmark.
Various case studies have been investigated: Average loadLight loadFeeder length (impedance)Feeder configurationLV transformer impedance
11
Impact of High PV Penetration on Voltage Profiles in Residential Neighborhoods (Cont.)
Voltage profile in the sub-network A (LV) consideringaverage feeder load level
Feeder length and transformer impedance play important roles in determining the voltage rise level for residential feeders with high PV penetration levels (up to 75 % LV transformer capacity).
An average PV penetration level of around 2.5 kW per household on a typical distribution grid would not cause the voltage to exceed the normal standard voltage threshold value.
Improvements on the LV network efficiency, by reducing transformers and feeder impedances, would reduce the voltage rise
0.98
0.99
1.00
1.01
1.02
1.03
1.04
1.05
1.06
1.07
1.08
-6.25 -5 -3.75 -2.5 -1.25 0 1.25 2.5 3.75 5 6.25Power per Household [kW]
Vol
tage
[pu]
0m
20 m
40 m
60 m
80 m
100 m
CAN3-C235-83 (NR)
CAN3-C235-83 (ER)
0.98
0.99
1.00
1.01
1.02
1.03
1.04
1.05
1.06
1.07
1.08
-6.25 -5 -3.75 -2.5 -1.25 0 1.25 2.5 3.75 5 6.25Power per Household [kW]
Vol
tage
[pu]
0m
20 m
40 m
60 m
80 m
100 m
CAN3-C235-83 (NR)
CAN3-C235-83 (ER)
0
0.5
1
1.5
2
2.5
3
3.5
0.25 RTb 0.5 RTb 0.75 RTb RTb 1.25 RTb 1.5 RTb
Transformer Impedance
Max
. PV
Pen
etra
tion
(kW
/ ho
use)
x
0
0.5
1
1.5
2
2.5
3
0.75 Zb Zb 1.25 Zb 1.5 Zb 2 Zb
Feeder Impedance
Max
. PV
Pen
etra
tion
(kW
/ ho
use)
X
PV penetration levels for different absolute values of the feeder impedances
Drop Lines: Rb = 0.55 Ω/km and Lb = 0.29 mH/kmPole-Pole Lines: Rb = 0.27 Ω/km and Lb = 0.24 mH/km
PV penetration levels for different LV transformer impedances
R1b = 0.06 puR2b = R3b = 0.012 pu
Voltage profile in the sub-network A (LV) consideringlight feeder load level
12 MATLAB&SIMULINK model
F1-165 Recloser
F-183 Recloser
F1-46 Recloser
Voltage Regulator
F-293 Recloser
Substation
(280 amps)
(100 amps)
(100 amps)
(50 amps)
Feeder under investigation (CYMDIST View)
Feeder Protection Systems for Multiple Generation Sites on
the Same FeederData from two actual Canadian feeders are used in the analysis.Four types of faults have been investigated:
3-phase faultsL-L faultsL-G faultsHigh impedance L-G faults System has been analyzed at various
operating conditions/configurations:DG size, location and technologyPeak and minimum loadDifferent load modelTransformer impedance
13
At peak load, all fault types will be detected by the line and/or the DG protection and/or the substation breaker.In some cases, DGs protection will not detect the fault but as soon as the line protection and/or the substation breaker protection trips, the DGsprotection will detect the fault.
Feeder Protection (Cont.)
Report on the findings with conclusions and recommendations will be produced
ONLY 3-phase and L-L faults have been detected
All fault types have been detected
All fault types have not been detected
ONLY L-L fault has been detected
All fault types have been detected
All fault types have not been detected
ONLY L-L fault has been detected
Substation
High impedance L-G fault has not been detected
All fault types have been detected
High impedance L-G fault has not been detected
14
In collaboration with the University of Toronto
A detailed set of studies and results was presented to determine the effect of distributed storage on the Electric Distribution System with emphasis on the depth of penetration of distributed generation units.
4 types of feeders inspired from Toronto Hydro network were used as a benchmark using CYMDIST software.
All load/DG scenarios are simulated with and without distributed storage (DS) units in service.
Impact of Integration of Storage on Distribution Systems
15
Impact of Integration of Storage on Distribution Systems (Cont.)
Three different options for DS capacity are considered:A DS without power and storage capacity constraints,A DS is a typical 1 MW NaS battery with 7.2 MWh storage capacity and 100% DOD; and,A DS is a typical 1 MW NaS battery with 7.2 MWh storage capacity and 90% DOD.
16
Introduction
Modeling, Simulation and Benchmark Case Studies
Demonstrations and Field Tests Case Studies
Smart Grid Demonstration Projects
17
Band Office
Resident
Smart Remote Microgrid
66 residences and 18 buildings Hartley Bay, BC - first smart grid of its kind in North America.
“Rural electricity cooperative” - saving remain in the communityFirst year research results 2010 – Modify transformer loading;
Monitoring 3 diesel generators; research “dispatch strategy” with DR; 2010-11 - Research on demand responsive load and validate
optimal smart grid operation; Knowledge base will improve our understanding of cost-benefit of advanced metering infrastructureTarget fuel cost reduction: $50,000-100,000 per yearOptimal smart microgrid performance tool
Project contact: Tarek El-Fouly
Photos: Pulse Energy
18
AMI infrastructure – pay-as-you go meterResearch on medium penetration Solar PV, whereby the PV
generation exceeded the loadAlternative system design and grid topology optionsResearch combination with diesel gensets and low-load
operation with PVThree measures in the Nemiah grid • Introducing 6 distributed rooftop PV - 27kW, • Replacing a 95 kW genset by a 30 kW genset, • Reducing commercial loads on weekday evenings and
weekends by introducing a contactor to switch these off.- Validation of fuel saving with 25% reduction in diesel fuel compared to baseline- Local employment $ and rural electricity cooperative $
PV-Microgrid Nemiah, BC
5900
11130
9000
PV Commercial load control 30 kW genset
Fuel savings (in litres) from each of the three measures .
General Diagram of the mini-grid.
25kVA
250kVA
Day
/Nig
ht S
witc
h
120/240V Daytime Commercial Bus
120/240V Critical Commercial Loads Bus
14,400V Distribution Grid600V Generation Bus
Serv
ice
Entra
nce
Serv
ice
Entra
nce
kWh$
Pay as you go Meter kWh$
Pay as you go Meter
House with PV House without PV
120/
240V
120/
240V
Source: Dave Turcotte, Sophie Pelland
Residential area blueCommercial area pink
19
Test Line Single Line Diagram
Relays’ Operating Time
0.192.71
0.27 1.73
0
5
10
15
20
25
30
35
40
45
RO
CO
F/V
S
UV
_1
OV
_1
UF_
1
OF_
1
UV
_2
OV
_2
UF_
2
OF_
2
Relays
Det
ectio
n tim
e (s
)
0% mismatch resistive 12.5 % mimatch resistive 9.1 % mimatch resistive 0% mismatch light resistive load11.1% mimatch light resistive load 4.4 mimatch resistive-inductive4.4 mimatch resistive-Capacitive 10.6% mimatch resitive-non-unity generation
Commercial Relays Field Tests for Passive Anti-Islanding
Protection
A combination of ROCOF and VS schemes could detect islanding of a synchronous DGs for power mismatches above 10%.
Synchronous based DGs3 commercial (off-the-shelf) protection relays.In collaboration with Hydro Quebec Research Centre (IREQ)
20
Voltage Regulator Testing with Distributed Generation
In collaboration with Hydro Quebec Research Centre (IREQ).Test Line to be modeled using EMTP-RV to validate the field test results. Results will be analyzed and presented in a paper.
Copper Power System Voltage Regulator
IREQ 25 kV Test Line
Test Line Single Line Diagram
21
Introduction
Modeling, Simulation and Benchmark Case Studies
Demonstrations and Field Tests Case Studies
Smart Grid Demonstration Projects
22
New Brunswick Power Corporation
• Project will install monitoring and control systems in 750 buildings in PEI, NB and NS. Load control will be driven by availability of regional wind power
• 4 utilities involved• $32M project
Hydro-Québec-Institut de recherche
• Development of a smart zone in Boucherville including PHEV charging infrastructure
• $20M project
Power Measurement Ltd• Load curtailment and peak
shaving in large commercial buildings
• Partners include Brookfield Properties, ENMAX
• $10M project
BC Hydro• Installation of two 1MW storage
systems at two locations to support remote and weak grid systems
• $13.4M project
CanmetENERGY provides technical and administration support for
Clean Energy Fund (CEF) demonstration projects
Total $75.4 Million (4 projects)
23
CEF Fund: The Atlantic Power Shift Project
A $32 million 4 year project led by NB Power and involving NS Power, St John Energy and Maritime Electric.
Objective is to demonstrate smart grid technologies to use responsive demand to balance wind generation with at least 750 buildings involved.
CanmetENERGY can provide technical support by providing knowledge on:
Demand response in commercial building
Building to grid models
Communications options for demand response
The Maritimes:World class wind regime but limited grid balancing resources. Current generation is mainly fossil fuel based.
24
This project demonstrates the integration of energy storage as amechanism for mitigating risk of exceeding capacity at near-peak capacity substations.This type of solution has the ability to be used in other remotecommunities where the grid reliability is low and the cost of the transmission line upgrade is uneconomical.Solution to near-capacity substation at Golden
Proposed use of 2 x 1 MW battery storage (at Golden and Field) to bridge capacity gap prior to transmission upgrade (peak shaving)
Solution to poor reliability indices for FieldProposed use of 1 MW battery storage at Field and demand response to provide back-up energy source (islanding)
Use knowledge for future initiativesDefer capacity (transmission or generation) in other locationsSupport for intermittent generation from renewable sourcesEnergy management of distributed energy resourcesAlternative energy source to diesel generation as back-up
CEF Fund: BC Hydro Energy Storage and Demand Response for
Near-Capacity Substation
Source: BC Hydro
Source: BC Hydro
25
C. Abbey, F. Katiraei, C. Brothers, L. Dignard-Bailey, and G. Joos, “Integration of Distributed Generation and Wind Energy in Canada”, Proceedings of the IEEE-Power Engineering Society General Meeting and Conference, Montréal Canada, June 18-22, 2006.T.H.M. EL-Fouly and C. Abbey, “On the Compatibility of Fault Location Approaches and Distributed Generation”Proceedings of the Joint CIGRE PES Integration of Wide-Scale Renewable Resources into the Power Delivery System Symposium, Calgary, Alberta, Canada. (July 29 - 31, 2009) .R. Tonkoski, D. Turcotte and T.H.M. EL-Fouly, “Impact of High PV Penetration on Voltage Profiles in ResidentialNeighbourhoods” to be published Reza Iravani, Milan Graovac and Xiaolin Wang, “Integration of Storage in Electrical Distribution Systems and its Impact on the Depth of Penetration of DG”, CanmetENERGY, Natural Resources Canada, technical report, CETCNumber 2009-174 / 2009-10-21. http://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/eng/renewables/integration_der/publications.html?2009-174S. Pelland, D. Turcotte, G. Colgate and A. Swingler. “Nemiah Valley Photovoltaic-Diesel Mini-Grid: System Performance and Fuel Savings Based on one Year of Monitored Data”, to be published.T.H.M. EL-Fouly and C. Abbey, “Commercial Relays Field Tests for Passive Anti-Islanding Protection Schemes of Synchronous Generator Based DGs”, CIGRE Canada Conference on Power Systems, Toronto, Canada. (October 4 –6, 2009) Smart Grid Demonstration projects, http://www.nrcan.gc.ca/eneene/science/renren-eng.phpH. Whittaker and J. Peralta, “Microgrid R&D at BC Hydro: Golden Energy Storage Project”, 6th international symposium on microgrids, Vancouver, BC, Canada, July 21, 2010. http://der.lbl.gov/presentations/microgrid-rd-bc-hydro-golden-energy-storage-projectSmart Grid Group Publications, CanmetENERGY, Natural Resources Canada, http://canmetenergy-canmetenergie.nrcan-rncan.gc.ca/eng/publications.html
References
26
Questions
Natural Resources Canada, CanmetENERGY1615, Lionel-Boulet, Varennes, Quebec
http://canmetenergy.nrcan.gc.ca/eng/renewables/integration_der.html
CanmetENERGY research centre in Varennes (Quebec)
Further information:[email protected] / (450) 652-6410