COST ESTIMATION“Good cooking takes time.
If you are made to wait, it is to serve you better, and to please you.”
Menu of restaurant Antoine, New Orleans.
(Quoted in the mythical man-month by Brooks)
![Page 2: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/2.jpg)
2
OBJECTIVES
Project Cost Management Process Cost Estimating Cost Budgeting Cost Control is not covered – See Earned
Value for that.
Reference for seminar: MBA Fundamentals by Kanabar & Warburton, 2008 (Kaplan Publishing).
![Page 3: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/3.jpg)
3
BIG DIG
Order of Magnitude Estimate $2.8 Billion.
Final Costs $14 Billion +
WHY?
![Page 4: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/4.jpg)
4
PROCESS
Estimate Costs
Determine Budget
Control Cost
Planning
Planning
Control
![Page 5: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/5.jpg)
5
ESTIMATE COSTS: WHAT ARE THE OUTPUTS?
Activity Cost Estimates
Basis of Estimates
Project Document Updates
Estimate Costs
![Page 6: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/6.jpg)
6
COST ESTIMATING VS. PRICING
Cost estimating and Pricing:Cost estimating: how much will it cost the
performing organization to provide the product or service involved?
Pricing: how much will the performing organization charge for the product or service? This is a business decision and will consider profit
Our focus is on cost estimating.
![Page 7: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/7.jpg)
7
WHY ARE SO MANY COST ESTIMATES WRONG? We need to define the work first and then
estimate the work. Generally we are asked to estimate and then
define the work. The cart is before the horse!
![Page 8: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/8.jpg)
8
MANY OTHER REASONS Failure to assess and mitigate risks Risk Quantification is not done. Contingency Budget is not included. Poor change control: Not saying ‘No’ to
requests for changes. (or no Process exists) Poor quality—work has to be redone Poor communication channels New technology.
From your experience give us one reason.
![Page 9: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/9.jpg)
9
TYPES OF ESTIMATES & ACCURACY
As project unfolds we gather more data about the project and the accuracy improves
Time
ProjectCompletion
Est
ima
te
Early/Order of Magnitude
Approximate/Budget Estimate
DefinitiveEstimate
+75
-25 -10
+25
-5
+10
![Page 10: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/10.jpg)
10
ACCURACY
• Most difficult to estimate as very little project info is available
Estimate Accuracy
Order of Magnitude (Early)
-25%+75%
Budget Estimate
-10%+25
Definitive Estimate
-5%10%
• Used to finalize the Request for Authorization (RFA), and establish commitment
• Development stage estimate. Needed to predict revised project completion date
![Page 11: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/11.jpg)
11
Top Down • analogous method• parametric method• experience based.
Bottom-Up
• Add up WBS tasks.• Detailed estimating.• More definitive estimate.
Focus on individual project process.
Focus on overall development process.
Generic Approach
Task Based Approach
APPROACHES TO ESTIMATING
![Page 12: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/12.jpg)
12
POOR PROJECT MANAGEMENT (1 OF 2)
Inexperienced project managers can mess up projects.
To compress duration it is logical to add more resources. But this might create a problem.
The extra human communications required to add another member to a programming team takes away valuable time from other resources.
![Page 13: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/13.jpg)
13
POOR PROJECT MANAGEMENT (2 OF 2)
Brook's law "Adding manpower to a late software project makes it later." By Fred Brooks, author of "The Mythical Man-Month."
![Page 14: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/14.jpg)
Resources
Mo
nth
s
More resources should decrease duration. BUT if additional co-ordination is required for each task then the Effort increases even more.
Communication Effort = n(n-1)/2Number of people = 3.
3(3-1)/2 = 3 * 2/2 = 3Number of people = 4
4(4-1)/2 = 4 * 3/ 2 = 6
Impact of Communication, etc.
IMPACT OF COMMUNICATIONS
![Page 15: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/15.jpg)
15
ESTIMATING TECHNIQUES
DetailedWBS)
Experience(focus on
Delphi)
Projective & Parametric
![Page 16: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/16.jpg)
16
DELPHI
Provides a formal structured approach for the exchange of “opinions”.
Can be used when no historical data exists. Useful when installing a new product methodology making a significant change to an existing one. implementing a unique product/project
Based on the theory that Group opinions are fairly reliable. Extreme views get annulled. Informal one-on-one conversations are
susceptible to bias & intimidation.
![Page 17: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/17.jpg)
17
DELPHI GROUP
Delphi Monitor
Group should consist of experts on thetopic under discussion. Can include: marketing people, vendors, customers
Should consist of ten people at least.
All communications is done in writing.
Experience: Delphi
![Page 18: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/18.jpg)
18
PROCESS
1. The Delphi group is given the program’s specifications, and an estimation form.
2. They meet to discuss project goals, assumptions, and estimation issues.
3. They then each anonymously list project tasks and estimate size.
4. The estimates are given to the Delphi monitor who tabulates the results and returns them to the experts.
5. Only each expert’s personal estimate is identified on the form. All others are anonymous.
6. The experts meet to discuss the results. They each review the tasks they have defined/estimated.
7. The cycle continues until the estimates converge. (Go back to step 3.)
![Page 19: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/19.jpg)
19
DELPHI TEMPLATE
Project: ______________Estimator:_____________Date:____________Here is the range of estimates from Round: __
0 10025 50 75
x x xy m x
x = EstimatesY = Your estimateM = Median
Please enter your estimate for round : _____Your rationale for the estimate:_____________________________________
_____________________________________
![Page 20: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/20.jpg)
20
PERT METHOD Find the Pessimistic (P), Optimistic (O) and Likely
estimate (L).
Mean = ----------------------6
P + 4 L + O
Maximum - MinimumStandard Deviation= -----------------------------
6
Estimate = Mean +/- 1 SD
For 95% confidence use 2 SD.
For 99% confidence use 3 SD.68% confidence (1 SD)
![Page 21: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/21.jpg)
21
COMBINING DELPHI WITH PERT
While both the methods are independent methods it is possible to combine the two methods.
Procedure: Use Delphi.
Consider the lowest estimate as O Consider the highest estimate as P Consider the median as L
Calculate the Pert Mean Calculate the Standard Deviation.
Add 1, 2 or 3 SD to the Pert Mean
![Page 22: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/22.jpg)
22
PARAMETRIC MODELS
Good tool for early estimating.
Most, if not all, cost models use predictors.A predictor has correlation with later results.
Effort = K * Predictor
House Cost per sq... foot = $100/sq... foot.
Purchase cost of a 2500 sq.. foot house:
= $2500 * 100
= $ 250,000.
![Page 23: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/23.jpg)
23
SOFTWARE PARAMETRIC MODEL
Cocomo Function Point 4GT
![Page 24: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/24.jpg)
24
USING LIFE CYCLE EFFORT DISTRIBUTION TO ESTIMATE IF YOU HAVE METRICS DATA
Initiation & Requirements 8% 80 PD
Functional Design 15% 150 PD
Detail Design 15% 150 PD
Coding (plus unit test) 30% 300 PD
System Testing 13% 130 PD
Acceptance Testing 10% 100 PD
Implementation 7% 70 PD
Wrap-Up 2% 20 PD
Total Effort Estimate: _ 100%___1000 PD__
Historic Ratio
Estimated Project effort is 1000 Person-DaysOne can estimate the project effort if the effort associated with coding is known
![Page 25: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/25.jpg)
25
ESTIMATING RESOURCES – TOP DOWN Calculating Team Size (FTE Person)
Square Root of Effort
Square Root of 40 person-months = 6.5 people
* Barry Boehm – Cocomo Model
![Page 26: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/26.jpg)
26
YOU CAN CALCULATE DURATION Calculating Duration (months)
Person-Months = ----------------------- Persons
40 person-months = --------------------------- 6.5 person(s)
= 6.4 months
![Page 27: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/27.jpg)
27
BOTTOM UP ESTIMATING
Requires construction of WBS. Should be more accurate But not necessarily always. If you miss out
the broader picture you will miss some detailed estimates.
Case Study: Site Analysis and Excavation costs ignored.
![Page 28: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/28.jpg)
28
WBS OUTLINE ROLL UP
![Page 29: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/29.jpg)
29
PERT TOOL BAR
![Page 30: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/30.jpg)
30
PERT
![Page 31: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/31.jpg)
31
NEXT DETERMINE BUDGET: WHAT ARE THE OUTPUTS?
Cost Performance Baseline
Project Funding Documents
Project Document Updates
Estimate Costs
Allocate the overall cost estimates to individual activities or work packages to establish a cost baseline for measuring project performance.
![Page 32: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/32.jpg)
32
CORE CONCEPT
Effort, Duration, and Cost Effort: The number of labor units required to complete an activity Availability: Time a staff person is able to
work Productivity: The relative measure of work in
a time unit Duration = ( Effort / Productivity ) /
Availability Cost = ( Effort / Productivity ) x Unit Cost
Duration = Work_Hours / Work
![Page 33: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/33.jpg)
33
COST BUDGETING PROCESS
1. Cost estimates2. WBS3. Project
schedule4. Cost
management plan
1. Cost budgeting tools and techniques
1. Cost baseline2. Project Funding
Requirements3. Document
Updates
Inputs Tools Outputs
![Page 34: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/34.jpg)
34
CONSIDER DIRECT AND INDIRECT COSTS
Direct costs: Costs incurred for a specific project
Salaries of project staff Equipment bought specifically for the project Indirect costs: Costs span over multiple
projects (“overhead”) Quality assurance department Rooms, electricity, heating
![Page 35: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/35.jpg)
35
COST DISTRIBUTION MODEL- WELLMAN’S DATA FOR IT PROJECTS
Assessment RequirementsDefinition
Software Tools H/W Facilities Design
12%$12,000
8%$8000
10%$10,000
2%$2000
20%$20,000
Development Implementation Training ProjectManagement
Operational SW
20%$20,000
10%$10,000
3%$3000
5%$5000
10%$10,000
Total Cost of the Project = $100,000
![Page 36: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/36.jpg)
36
COSTS TO CONSIDER Labor: Wages paid to all staff. Overhead: Cost of payroll taxes and fringe benefits.
Usually % of Labor Materials: Items used in the project.
cement, lumber, paint Supplies: Cost of tools, office supplies, equipment.
Should be prorated if expected life is beyond the project. General & Administrative: Cost of management & support services
such as: purchasing, accounting, secretarial usually % of project cost.
Equipment Rental: computers, printers compressors, cranes, trucks
Profit Reward for successfully completing the project Calculated as % of project cost.
![Page 37: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/37.jpg)
37
COST BUDGETING COST CONTROL
Cost baseline will be used to measure and monitor cost performance of the project – see Earned Value Slides
Expected Cash Flow
Cost Baseline
Cumulative Values
![Page 38: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/38.jpg)
38
CONTROL COSTS PROCESS Monitor Cost Performance Understand variances from plan Ensure all changes are recorded and agreed
upon Prevent unauthorized changes from being
included in cost baseline Inform stakeholders of authorized changes
![Page 39: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/39.jpg)
39
FINAL THOUGHTS
Accuracy can be achieved if you have historical data.
Introduce an estimating Framework such as what is shown here.
![Page 40: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/40.jpg)
40
FINAL THOUGHTS
Project Costs: Are incurred while the project is being fulfilled.
Life Cycle Costs: Includes the costs after project completion.
There may be temptation to lower project costs at the expense of long term costs. Life Cycle Costing gives the PM a way to consider costs outside of the scope of project fulfillment.
You need to know concepts such as: sunk costs, present value, IRR, Net Present Value, Benefit Cost Ratio.
![Page 41: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/41.jpg)
41
KEY POINTS TO REMEMBER You must get the team members to provide
estimates where possible. When doing bottom-up estimating, use the
rule of “one to two people for one to two weeks.” You can calculate the duration by dividing the total effort by the number of resources.
You can calculate the duration by dividing the total effort by the number of resources.
You can calculate the effort by multiplying the duration with the number of resources.
![Page 42: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/42.jpg)
42
KEY POINTS TO REMEMBER For many types of projects it is preferable to
estimate in days and not hours as people are not productive 8 hours every day.
You should always communicate the type of estimate to the stakeholder—the type of estimate is “order of magnitude”, “budget estimate” and “definitive estimate”. During the initiation phase you only have order of magnitude estimates.
You must consider more than one estimating tool or technique when developing estimates.
![Page 43: C OST E STIMATION “Good cooking takes time. If you are made to wait, it is to serve you better, and to please you.” Menu of restaurant Antoine, New Orleans](https://reader036.vdocuments.us/reader036/viewer/2022062407/56649d965503460f94a7e88a/html5/thumbnails/43.jpg)
43
KEY POINTS TO REMEMBER Reliable budget estimates are arrived only
after creating a work-break-down structure. You must combine both the top-down and
bottom-up estimating techniques for good budget estimates.
Once you’ve completed cost estimation you do cost budgeting.
Cost Control follows Cost Budgeting. This process involves reviewing project progress reports and comparing the results against the cost baseline and determining if management action must be taken.