Download - Bulding 245 schedule update
Bulding 245 schedule update
LIU Booster Meeting 30-01-2014Fulvio Boattini
TE-EPC
TE EPC
Building 245 position
TE-EPC - Fulvio Boattini 2
TE EPC
b245
30/01/2014
physics LS1 physics LS2 physics
2012 2013 2014 2015 2016 2017 2018 2019
May 2016Building ReadyNo ressources
Services Integration(EL, CV,..)
GS/SE studies and procurement
Building construction
October 2013March 2014 March 2015
FC
April 2017Start
Commissioning on dummy load
TE EPC
MPSB Time Schedule
Switching cabinets and cabling installation
30/01/2014 TE-EPC - Fulvio Boattini 3
TE-EPC - Fulvio Boattini 4
TE EPCBuilding 245: electrical power needs
Power needs have been collected and EN/EL worked out a power network layout
30/01/2014
EN/EL needs detailed power departures from TE/EPC and EN/CV
TE-EPC - Fulvio Boattini 5
TE EPCBuilding 245: electrical power needs
EN/EL prepared the first schematic of the LV network is now available.
Transformers:18k/0.4kV 2MVA; 800kVA
Switching cabinets
An UPS
30/01/2014
Building 245: cooling pipes
TE-EPC - Fulvio Boattini 6
TE EPC
EN/CV proposed a path for the pipeworks
• 2 DN200 + 2DN100 pipes for PSB magnets cooling (from b245 to b361)
• 2 DN100 pipes for chilled water (from b361 to b245)
• 2 DN100 pipes for TT2 cooling (from b245 to b289)
30/01/2014
Building 245: power cables
TE-EPC - Fulvio Boattini 7
TE EPC
BATIMENT 361 ETAGE 1 BATIMENT 271 ETAGE R
1-205
1-018
TP9
R-401
R-411
R-402
R-403
R-404
R-405
R-201
12.6 M2
CONTROL ELEMENTS
POWER ELEMENTS
CROWBAR
SWITCHBOARD
C: C11,12,13, C17,18,20
A: C9+C10+C14+C19+Control CablesB: C5÷C8+C15,16,21,22+Control Cables
D: C1÷C4
Cont
rol C
able
s
E: Dummy Load connection (from b367)
ME25
TE/EPC presented power cables paths
No spare magnets are needed anymore inside b245 as POPS spare magnets will be used for commissioning
18kV cables still to be added
EN/EL-TE/EPC shall verify the routing in a cad model
30/01/2014
Building 245 layout
TE-EPC - Fulvio Boattini 8
TE EPC
30/01/2014
Building 245 layout
TE-EPC - Fulvio Boattini 9
TE EPC
30/01/2014
Building 245 layout (b271 side)
30/01/2014 TE-EPC - Fulvio Boattini 10
TE EPC
Building 245 layout (Isolde side)
TE-EPC - Fulvio Boattini 11
TE EPC
30/01/2014
Building 245 layout
TE-EPC - Fulvio Boattini 12
TE EPC
30/01/2014
Building 245 layout
TE-EPC - Fulvio Boattini 13
TE EPC
30/01/2014
Building 245 layout
TE-EPC - Fulvio Boattini 14
TE EPC
30/01/2014
Building 245 layout
TE-EPC - Fulvio Boattini 15
TE EPC
30/01/2014
TE EPC
MPSB Time Schedule
INTEGRATION PROJECT OPEN POINTS:• EN/CV needs to work more on layout design of the cooling part• EN/EL TE/EPC need to find a solution for the EN/EL cabinets layout.
EN/EL is starting to test two solutions on the 3D model but more detailed input from EN/CV is needed.
• Cost estimation needs to be provided by all services of the building
INTEGRATION PROJECT CRITICAL POINTS:• EN/CV announced Glen will have no time for completing the design the
cooling components. Michel will replace him during his absence, but in the whole process we take more than one month of delay.
30/01/2014 TE-EPC - Fulvio Boattini 16
TE-EPC - Fulvio Boattini 17
THANKS FOR THE ATTENTION
QUESTIONS?
Bulding 245 schedule update
TE EPC
30/01/2014
TE EPC
Building 245 layout
30/01/2014 TE-EPC - Fulvio Boattini 18
EN/EL proposal for Electrical Room