Building Program Update
February 5th, 2019
Joe Romenick
Catawba Ridge High School
• Opens - August 2019
• Substantial Completion Date – April 23rd, 2019
• Barring any additional weather delays.
• This does not mean building is ready to occupy with full staff.
• Key personnel can occupy.
• Furniture, furnishings & equipment can be installed.
• Furniture Delivery and Install – April 23rd thru May 14th, 2019
• Staff can move in once Certificate of Occupancy (CO) is received from SC Office of School Facilities. Scheduled for Mid-May 2019.
CRHS – on Parkway
CRHS – Hallway w/ Terrazzo
CRHS – Science Classroom
CRHS – Main Street
CRHS – Main Gym
CRHS – Auditorium
CRHS – Commons
CRHS – 3rd Floor Hallway
CRHS – Courtyard / Media Center
CRHS – Spring Athletics
CRHS – Track & Stadium
Aquatics Center
• On schedule to open to public sometime in October 2019
• Substantial Completion Date – September 30th, 2019
• Barring any additional weather delays.
• This does not mean building is ready to occupy with full staff.
• Key personnel can occupy.
• Furniture, furnishings & equipment can be installed
• Furniture, furnishings and equipment installed September 30th thru October 7th, 2019
• Staff can move in once Certificate of Occupancy (CO) is received from SC Office of School Facilities. Scheduled for Early October 2019.
AQUATICS CENTER – First Wall Panel
AQUATICS CENTER – Building Site
AQUATICS CENTER – Parking Lot Area
Elementary # 11 – Parkway
• Opens - August 2020
• Substantial Completion Date – June 1st, 2020
• Barring any additional weather delays.
• This date has already been pushed out 2 weeks because of weather.
• Furniture Delivery and Install – June 1st thru June 15th, 2020
• Staff can move in once Certificate of Occupancy (CO) is received from SC Office of School Facilities. Currently scheduled for mid June 2020.
ES # 11 – Initial Clearing
ES # 11 – Initial Clearing
ES # 11
Elementary # 10 – Masons Bend• Opens - August 2020
• Substantial Completion Date – June 15th, 2020
• Barring any additional weather delays.
• This date has already been pushed out 2 weeks because of weather & permit delay.
• Furniture Delivery and Install – June 15th thru June 30th, 2020
• Staff can move in once Certificate of Occupancy (CO) is received from SC Office of School Facilities. Currently scheduled for late June 2020.
ES # 10 – Initial Clearing
ES # 10 – Initial Clearing
Middle # 6 – White’s Road• Opens to Students - August 2021
• The District will be going out for contractor bids 2nd quarter 2019.
• Construction will begin summer 2019.
• Estimated substantial completion date scheduled for May 2019.
MIDDLE SCHOOL # 6