IndiaBuilding Capacities for Public Private Partnerships
June 2006
Energy and Infrastructure Unit andFinance and Private Sector Development Unit
South Asia Region
ContentsEXECUTIVE SUMMARY......................................................................................................................... 5
Approaches elsewhere to developing capacities for PPPs ............................................................... 5PPPs in India ................................................................................................................................... 6Developing and strengthening capacities for PPPs in India ............................................................. 7
1. INTRODUCTION .......................................................................................................................... 11Scope of this report ............................................................................................................... 11Outline of the rest of this report ............................................................................................ 12
2. DEVELOPING CAPACITIES FOR PPPs: INTERNATIONAL EXPERIENCES ...................................... 13Public sector capacities needed for a robust PPP program ..................................................... 14
Policy frameworks ............................................................................................................ 14Legal frameworks ............................................................................................................. 14Human resources ............................................................................................................. 15Procedures and guidelines ................................................................................................ 16Organizations: the role of cross-sectoral PPP units ......................................................... 16Purely public versus public-private crosssectoral units .................................................... 17Possible conflicts of interest within crosssectoral units .................................................... 18The roles of national and sub-national agencies .............................................................. 19
3. PPPs IN INDIA: ISLANDS OF PROGRESS ..................................................................................... 21The role of PPPs so far ........................................................................................................... 22Institutional frameworks for PPPs in India ............................................................................. 24The development of policies and standardization of contracts ............................................... 26Training and other information dissemination initiatives ........................................................ 26Where are the gaps in India compared to elsewhere? ............................................................. 27Expanding the use of PPPs to meet basic services needs ........................................................ 27
4. DEVELOPING AND STRENGTHENING CAPACITIES FOR PPPs IN INDIA .................................... 29Strengthening oversight of the fiscal costs of PPPs ................................................................ 30Policy frameworks .................................................................................................................. 30Legislative frameworks for PPPs .............................................................................................. 31Information dissemination ..................................................................................................... 31The development of guidance material for PPPs ...................................................................... 33PPP units to provide a pool of expertise ................................................................................ 34Project development funds ..................................................................................................... 35Funding of PPPs ..................................................................................................................... 36Recommendations: a role for the center in developing India’s PPP program .......................... 36
ANNEXES ........................................................................................................................................ 39Awarded Projects by States & Central Agencies ........................................................................... 39Awarded Projects by Sector .......................................................................................................... 46Project Pipeline by States & Central Agencies ............................................................................... 52Project Pipeline by Sector .............................................................................................................. 56Abandoned Projects ...................................................................................................................... 60Institutional Framework : Selected States & Central Agencies ....................................................... 62
India: Building Capacities for Public Private Partnerships
4
AcknowledgementsThis report has been prepared by Mark Dutz, CliveHarris, Inderbir Singh Dhingra (World Bank) and ChrisShugart (Consultant), at the request of Department ofEconomic Affairs (DEA), Ministry of Finance. The analysisof PPPs in India is supported by a short assignment byPwC involving a description of PPP projects undertakenin 12 states and 3 central agencies, together withsupporting capacity building measures. The databasewas assembled by PwC in January 2005, with updatesby the authors until March 2005. The Bank peerreviewers for the project were Alain Locussol,Mohammad Mustafa and Stephan van Klaudy. The reporthas benefited from feedback from the “Capacity BuildingWorkshop for Public Private Partnerships” which washeld in Delhi on February 7, 2005 in collaboration withDEA, and supported by the Bank’s Water and SanitationProgram. The report also has benefited from feedbackat an internal presentation to senior Ministry of Financeofficials held in Delhi on March 17, 2005.
Disclaimer
The policy note has been discussed with Government of India but does not necessarily bear theirapproval for all its contents, especially where the Bank has stated its judgments/ opinions/ policy
recommendations.
5
Both central government and the states are aimingto use public private partnerships (PPPs) moreintensively to help meet gaps in the provision ofbasic services. India has seen real progress overthe last 10 years in attracting private investmentinto the infrastructure sectors, first intelecommunications, and now in ports and roads,and in individual projects in other sectors. There isthe potential for PPPs to contribute more and helpmeet the infrastructure gap in India. But PPPs arenot a panacea. They represent a claim on publicresources that needs to be understood and assessedby the government, and are often complex and long-term transactions in which mistakes in design canbe costly.
The Department of Economic Affairs (DEA) askedthe World Bank to provide recommendations onhow capacities for identifying, procuring andmanaging PPPs could be further developed inIndia. Of particular focus is the possible role ofthe central government in developing thesecapacities. We look at both organizational andindividual capacities, the former including policyand legal frameworks, and institutions andprocesses.
For the purposes of this report, we concentrateon projects where private investment has beenmade, and where the government is either thepurchaser of services under the project, or whereit provides a financial contribution through directinvestment or through risk bearing. The mainsectors of focus are transportation (ports,airports, roads, and rail), water and sanitationand other urban infrastructure (solid wastemanagement, light rail, bus terminals).
Approaches elsewhere todeveloping capacities for PPPs
In shifting from more traditional methods ofservice provision, governments need to adaptboth their skills and their processes to ensurethat PPP programs deliver what is expected ofthem. The cornerstone of this is ensuring thatPPPs that proceed are those which representpriority projects and are best done through thePPP route rather than through traditional publicprocurement. Governments embarking on PPPprograms have often developed new policy, legaland institutional frameworks to provide therequired organizational and individual capacities.New agencies are sometimes created to bring infinancial and contract design skills not present inthe government, and existing processes, forexample in planning and budgeting, need to beadapted.
Although not all countries have developed specificnew PPP legislation, nearly all have felt it necessaryto amend existing legislation, if only to clarify thatpublic entities have the needed powers to contractout services under PPPs. Comprehensive cross-cutting PPP legislation has been used moreextensively in countries that operate under the civilcode. Where used, it often covers aspects such asspecifying which sectors PPPs can operate in, howtariffs for PPPs are set and adjusted, the role ofdifferent institutions in a PPP program, procurementof PPPs, and dispute resolution procedures. Evenwhere not necessary, such legislation can consolidateexisting provisions into one act, clarify processesfor approving and procuring PPPs, and create newinstitutions that will play a key role in the PPPprocess.
Executive SummaryExecutive Summary
India: Building Capacities for Public Private Partnerships
6
Most countries engaged in a broad-based PPPprogram have felt the need to develop a cross-sectoral pool of expertise in a dedicated PPP unit tosupplement capacities in the line agencies thatcontract for PPPs. These fulfill different rolesdepending on the needs of the situation. In somecases their role is limited to disseminatinginformation on PPPs and providing broad guidanceon good practices. In others they have an activerole in helping line agencies and ministriessuccessfully contract for PPPs, and in yet othersthey play a role in approving PPPs developed byother government agencies. Where they exist, thesecross-sectoral units are often located in, or attachedto, the Ministry of Finance or Treasury which mayreflect concerns about the need to strengthenunderstanding and monitoring of the fiscal costs ofPPPs. The functional nature of these units alsoreflects their roles. Units whose main focus istransactions are often established as companies, insome cases jointly owned by the government withthe private sector. Those that provide informationand guidance on PPP programs can functionadequately as units within an existing governmentdepartment.
There are risks of a conflict of interest in cross-sectoral PPP units that have multiple functions, evenwhere these are purely public sector agencies, forexample where a unit has a strong mandate topromote PPPs and increase deal flow, while at thesame time having the responsibility for screeningprojects. The potential for conflicts of interest maybe higher with respect to PPP units that are public-private joint ventures, and where success feesincentivize the closing of transactions. These haveto be recognized and dealt with.
The role of national agencies relative to sub-nationalones is often driven chiefly by basic legal and fiscal
relations between these levels of government, whichare often set out in the constitution. In Australia,the national government has virtually no role in statelevel PPPs. In Canada, the Federal Government’sP3 Office acts as a resource center and promoter ofthe benefits of rationale for using PPPs, rather thanacting in an advisory role. Other countries whichare more centralized have seen a stronger role fornational level agencies, for example in South Africawhere the Treasury’s PPP Unit plays a role in bothguidance and approval. Brazil intends to establishcapacities at the national level to offer detailedguidance to the states in the development of PPPs.
PPPs in India
In the 12 states and 3 central agencies surveyedthere are at least 86 PPP projects in our sectors offocus for which a contract has been awarded andprojects are underway (in the sense that the projectsare either operational, have reached constructionstage or at least construction/implementation isimminent).1 The estimated project cost of these PPPsis Rs 339.5 billion. There has been considerableinnovation in the design of these, with differentstructures now being developed to attract privateparticipation. But at the same time it is clear thatthis has been uneven – there are islands of progress,with some states having undertaken far more PPPsthan others, and a much heavier use of PPPs insome sectors (roads by number of projects andports by project size) than others. While there area number of successful projects, there have also beena number of poorly conceptualized PPPs broughtto the market that stood little chance of reachingfinancial closure.
Some states have made more attempts to develop abroad framework for PPPs, including cross-cuttinglegislation and the development of cross-sectoral
1 The 5 infrastructure sectors of focus where PPP contracts have been awarded in the surveyed states and federal agencies are roads& bridges, ports, airports, rail, and urban (water & sanitation, solid waste management, bus terminals, light rail, ferries and alogistics hub – although for the last 3 sub-sectors there have been preparatory activities but no contract awarded yet). There alsohas been activity in health & education and e-governance, in addition to sectors not covered in this report such as power, tourism,and other construction (convention centres, industrial, IT & biotech parks, SEZs, and housing). See the tables in the Annex for moredetails.
Executive Summary
7
units that play a role in the identification andpreparation of PPPs. While progress to date hasprobably been driven as much by fundamentals suchas political commitment, the lack of a cross-sectoralpool of knowledge makes it harder to transferexperiences across sectors.
Compared to other countries, some of the gaps inPPP frameworks and approaches in India are: thetendency for the policy rationale for PPPs to belimited to the use of PPPs as a source of investmentcapital when the public sector lacks funds; littlesystematic compilation and dissemination ofinformation, even within the public sector, on PPPsimplemented to date, including contractualapproaches and their results; and not much use ofrigorous ex-ante or ex-post assessments of theperformance of PPPs versus traditional publicoptions.
There is the potential for PPPs to play a greater rolein the provision of infrastructure services in India.A number of issues have to be addressed, however,including basic questions such as the extent to whichthese projects will be paid for by taxpayers or byusers, and if so whether the resources are available,and whether it will be possible, commercially andpolitically, to charge the required user fees.Improving capacities to identify potential PPPs willbe critical, to bring them to the market properlystructured, have them efficiently and competitivelyprocured, and to monitor their performance andcost.
Developing and strengtheningcapacities for PPPs in India
Both experience to date in India and internationallyshows that there is no unique formula fordeveloping a sound PPP framework. However,successful programs are characterized by clear policyand legal frameworks for PPPs, competent andenabled institutions that can appropriately identify,procure and manage PPPs, and efficient oversightand dispute resolution procedures. The center’s rolein developing capacities for sub-national PPPs needs
careful consideration taking into account the sizeof the country, center-state fiscal and other relations,as well as the variety of experiences so far, withsome states having made considerable strides andothers having made very little progress.
Oversight of the fiscal costs of PPPs.Oversight of the fiscal costs of PPPs.Oversight of the fiscal costs of PPPs.Oversight of the fiscal costs of PPPs.Oversight of the fiscal costs of PPPs. Regardless ofother actions, if there is to be an increase in the useof PPPs the center should work to strengthenoversight of the fiscal costs of PPPs. A priority needwould be for the development of guidance on howstates should approach the issues posed by PPPs.This should be supplemented by enhancing analysisof the fiscal costs of PPPs in central government,including the monitoring of the impact by PPPs onthe fiscal position of the states. Capacity-buildingefforts should be led by the Government of India(GoI) Finance Ministry, with involvement from theReserve Bank of India (RBI) as necessary.
PPPPPolicy rationale.olicy rationale.olicy rationale.olicy rationale.olicy rationale. A policy statement covering boththe rationale and also the limits to the use of PPPswould help to give the PPP program a clearer politicalmandate and could also be used to announce moreclearly the institutional framework for PPPs. Thesewould be useful at both the national and state level.While broad policies provide an important signal ofpolitical commitment, it may also be necessary totranslate this into action plans and policies forindividual sectors to provide a more preciseorientation to encourage line ministries and agenciesto pursue and implement PPP programs.
Legal frameworks.Legal frameworks.Legal frameworks.Legal frameworks.Legal frameworks. Cross-cutting PPP laws do notseem to be needed in India to permit central or stategovernments to enter into PPPs. Both the centerand many states have done so without such laws.Sector specific legislation has of course been usedto restructure industries and set up new institutionssuch as sector regulators. Cross-cutting legislationcould however be beneficial by consolidating relevantlegal provisions into one law, and legislating the useof certain processes for the procurement,development and regulation of PPP projects whichmay be better enforced if given the force of law.This might be more important at the state level, where
India: Building Capacities for Public Private Partnerships
8
checks and balances and oversight are not as strongas at the center. The legislation already passed byGujarat, Andhra Pradesh and Punjab providespossible models for other states. The developmentand passage of legislation also promotes an opendebate about the rationale for PPPs and theirexpected benefits, and thereby can help increase thepublic legitimacy of PPPs.
In formation disseminat ion and guidanceInformation disseminat ion and guidanceInformation disseminat ion and guidanceInformation disseminat ion and guidanceInformation disseminat ion and guidancematerials. materials. materials. materials. materials. Despite the fact that there are nearly 90PPPs in India under construction and operation,there is no publicly accessible database providingeven the most straightforward information on them.There is also relatively little available in terms ofinformation on the actual contracts used, and littleguidance available to government officers onappropriate clauses and conditions to be includedin PPP contracts. A number of practitioners in PPPsin India have argued that the lack of standardcontracts or standard clauses makes bureaucratsmore reluctant to sign off on PPP deals.
There is considerable scope for improving the flowof information regarding PPPs and for providingguidance materials to government officials on thedevelopment and implementation of PPPs. Guidancecould cover issues related to contract design,procedures for identifying, procuring and managingPPPs, and even model PPP legislation. Informationdissemination could cover a publicly-accessibledatabase on PPPs at the national, state and locallevels; training materials as well as workshops andother mechanisms to reach politicians, consumersand other stakeholders, so that they are betterinformed about the nature and structure of PPPs.Information on PPPs could be extended to analysisof successes and failures, case studies and a databaseon performance of projects.
Standardization and models have the potential toreduce transactions costs and diffuse good practices.There is however a risk that centrally sponsored modelcontracts could reduce the needed room for flexibilityand innovation even where these models are advisoryand not mandatory. This risk could be reduced by
having guidance provide a range of options whereappropriate and also by being guided by a public-private group containing representatives from stateas well as central agencies.
Information dissemination and guidance should beled from the center, given the public good nature ofthese activities. A single central ministry with cross-cutting responsibilities could take the lead in this.Specialized tasks would be contracted out and doneby others under the oversight of this unit – forexample the development and delivery of trainingmaterials would be undertaken by a specializedtraining institute.
A national PPP unit.A national PPP unit.A national PPP unit.A national PPP unit.A national PPP unit. Most countries engaged in abroad-based PPP program have felt the need to developa cross-sectoral PPP unit although the role that thisunit plays is sometimes restricted to informationdissemination and the preparation of guidance material.The design response to two key issues – the role of across-sectoral unit vis-à-vis line ministries and the roleof a national unit in sub-national PPPs – will be drivenby the business practices within governments and thefiscal, and other, relations between the center and thestates. This means that some models which are morecentralized, such as those in the UK and South Africawhere national level units have a prominent role insub-national PPPs, will not be workable approachesin India.
At the statestatestatestatestate level, a dedicated PPP unit can bothbroaden the PPP program by transferring lessonsand experiences across sectors, as well as improvethe quality of PPPs by bringing to bear bettertransactions skills. Particularly where there is not atrack record of PPPs, skills are probably best broughtin from the private sector to supplement availablecapacities in the state government.
At the nationalnationalnationalnationalnational level, a PPP unit could undertakethe information dissemination and guidance rolesdescribed above. It could also undertake atransaction advisory role by identifying areas wherePPPs could be undertaken by central agencies andministries, and working with these agencies to
Executive Summary
9
conceptualize and bring to the market individualPPPs. However, this role would not be well-suitedfor sub-national PPPs. A hands-on transaction rolein state and municipal PPPs would directly substitutefor the development of state-level capacity andwould be challenging to do for a large number ofdeals. Capacities should be developed at the statelevel, strengthened by the guidance and informationprovided by the national level unit.
A national level unit undertaking informationdissemination, guidance and transactions supportto central agencies could be established as a unitwithin a ministry or agency with cross-cuttingfunctions. This would allow it to be integrated intoexisting governmental processes of review, andneeded transactions skills could be contracted in byhiring consultants on long-term contracts.
If the center were to provide additional funding forPPPs (see para. xxvii below), then the national unitcould take on the additional mandate of reviewingthese PPPs to assess whether the contractualstructure proposed is robust, that risks are efficientlyallocated and that projects to be supported by thecenter are sound. The unit would need to provideclear guidance on what it viewed as being acceptablecontract structures, approaches to risk allocation,assessment of affordability and value-for-money, andprovider selection criteria.
Additional resources for PPPs.Additional resources for PPPs.Additional resources for PPPs.Additional resources for PPPs.Additional resources for PPPs. A catalytic role bythe center is likely to be needed to expand the usageof PPPs, particularly in states and sectors wherethey have been less used so far. This would consist,in addition to information dissemination andguidance, of financial resources both to develop PPPframeworks and contracts and to fund governmentcommitments under PPPs. This would help addressimportant constraints to further development ofPPPs in the country – namely, weak capacities toidentify realistic PPPs and bring them to the market;a lack of willingness to pay for project development;and a lack of creditworthiness on the part of statesto provide their financial contribution to PPPs.
A number of PPP units manage funds which defray
some of the costs of developing PPPs. There are twoarguments for the use of these funds. The first is thatmany governments new to PPPs do not appreciatethe need to spend more on preparation of PPP projectsthan was spent on developing procurement documentsfor civil works projects in the same sector. The secondis that since PPPs are relatively new, the costs ofpreparing initial projects may be higher and that withlearning some of these will come down. One importantissue is the terms on which this fund would be accessed– a matching grant scheme which combines centralgrant funding with contributions from the stategovernment provides some form of commitment byboth parties and can focus resources on projectsviewed as priorities by the state government.
The use of PPPs for the delivery of basic services bystate and municipal governments would beencouraged by the provision of central funds tosupport their payments under PPPs. A substantialmatching contribution from the governmentcontracting for the PPP would also be importanthere to provide commitment to the project.
The detailed design of such a PPP fund is beyondthe scope of this report and a significant effort wouldhave to go into this to ensure that it is well targetedand efficiently used. It would be important both toensure that projects supported by the fund arepriorities, and that competition for subsidies is usedto reduce the demands on public funds. On thislast point, it would be far more difficult to sizesubsidies – and also less transparent – were projectsfirst awarded by state governments and thensubsequently the chosen developers approached thefund for support.
As noted above, project design, risk allocation,affordability and value-for-money should also beassessed for these projects to ensure that the centeris supporting well-designed PPPs and this could bedone by the national PPP unit. There might howeverbe conflict of interest concerns if this unit received asuccess fee from working on transactions, in whichcase the involvement of others would be necessaryin clearances.
11
1.1 India has had policies in favor of attractingprivate participation in the infrastructuresectors since economic reforms wereintroduced in 1991. These initiatives have metwith varying degrees of success, but realprogress has been made in some sectors, firstin telecommunications, and now in ports androads, and with individual projects in othersectors. The central government and thestates are hoping to build on this progress,both in sectors where few private projectshave been realized as well as scaling up theiruse in sectors where progress has already beenmade. Many of these projects will not becommercially viable on the basis of user feesalone and will require financial contributionsfrom the public sector in addition tosubstantial amounts of risk bearing. In somecases the government will be the purchaserof the services.
1.2 These public private partnerships (PPPs) canhelp meet the infrastructure gap in India, butare not a panacea. They represent a claim onpublic resources that needs to be understoodand assessed. They are often complextransactions, needing a clear specification ofthe services to be provided and anunderstanding of the way risks are allocatedbetween the public and private sector. Theirlong-term nature means that the governmenthas to develop and manage a relationship withthe private providers to overcome unexpectedevents that over time can disrupt even well-designed contracts. And they all involveservices for which, in the eyes of citizens, thegovernment ultimately bears responsibility,
even if service delivery has been contractedout.
1.3 Governments embarking on PPP programshave often developed new policy, legal andinstitutional frameworks to provide therequired organizational and individualcapacities. These go beyond that neededto originate and financially close PPP deals,as they must also ensure that these dealsare affordable to users and the public sectorand provide ex-post evaluation of thesuccess of PPPs in meeting their objectives.This framework needs to be in place in Indiato ensure a robust and successful PPPsprogram.
Scope of this report
1.4 This report is prepared at the request of theDepartment of Economic Affairs (DEA), whichasked the World Bank for recommendationson how capacities for conceptualizing,structuring and managing PPPs could befurther developed in India. Of particular focusis the role of the center in developing thesecapacities. Our review covers bothorganizational and individual capacities. Theskills of the individuals working on PPPs arecritical. However, organizational capacity –the policy and legal frameworks, institutionsinvolved and the processes developed – areas, if not more, important. While the focusis on the capacities required of thegovernments we also look at the need todevelop capacities in the private sector andother stakeholders
1. Introduction1. Introduction
India: Building Capacities for Public Private Partnerships
12
1.5 Not all forms of private participation ininfrastructure should be considered PPPs.Though there is perhaps no standarddefinition of what a PPP is, they are generallyregarded to be contracts for servicestraditionally provided by the public sector thatcombine investment with service provisionand see significant risks being borne by theprivate sector. For the purposes of this report,we have focused on projects where privateinvestment has been made, and where thegovernment is either the purchaser of servicesunder the project, or where it provides afinancial contribution through directinvestment or through risk bearing.
1.6 The main sectors of focus are transportation(ports, airports, roads, and rail), water andsanitation and other urban infrastructure(solid waste management, light rail, busterminals). This represents the present areasof focus of many state governments in India.In consultation with DEA, it was decided toexclude the power sector from the analysis,given the complex issues involved in thatsector and the range of other efforts bothwithin the Bank Group and beyond focusedspecifically on power. We have also excludedmany sectors considered infrastructure bystate governments in India, including tourisminfrastructure, housing, and conventioncenters, but do provide some coverage of otherbasic services such as the social sectors(education and health) and e-governance.
1.7 There are several themes related to PPPs thatare not covered. We do not look in detail atthe successes and failures to date in individualPPPs. Although international experience
shows there are significant gains from well-designed PPPs, the report does not advocatethe use of PPPs in general nor particularapproaches to structuring PPP transactions.
Outline of the rest of this report
1.8 We first look at international experiences indeveloping frameworks for PPPs, focusing inparticular on two issues. The first is the roleof cross-sectoral PPP units vis-à-vis lineministries within a given level of government.The second is the role that nationalgovernment plays in overseeing or providingsupport to the PPP programs of sub-nationalgovernments. Although these solutions reflectcountry-specific conditions, they allow somegeneral lessons to be drawn and allow anassessment of the gaps in PPP frameworks inIndia.
1.9 We then provide an overview of the use todate of PPPs to provide infrastructure servicesin India. We present the results of a surveyof PPPs in 12 states and 3 central agencies/ministries in our sectors of focus, and alsoexamine efforts to develop PPP frameworks,particularly at the state level.
1.10 Finally, we look at what can be done tostrengthen and develop capacities for PPPs inIndia and in particular the role of the centralgovernment. This builds upon the survey andother analyses of the experience of developingPPPs in India. We present a range of optionsfor the role of the center, particularly where itconcerns possible steps to catalyze state andmunicipal level PPPs, and provide anassessment of these options.
13
2.1 An increasing number of governments areturning to the private sector to provideservices hitherto delivered by the public sector.The motives for pursuing public privatepartnerships (PPPs) vary from fiscalopportunism, simply seeking to replace publicfinance with private finance, to a genuinedesire to seek lower costs, both for taxpayersand consumers, or improved services.
2.2 There is no single accepted internationaldefinition of what a PPP is. In many countriesthe core of PPP programs are projects thatare for services traditionally provided by thepublic sector, combine investment and serviceprovision, see significant risks being borne bythe private sector, and also see a major rolefor the public sector in either purchasingservices or bearing substantial risks under theproject. PPPs are therefore more than servicecontracts although some would include thesein their definition of PPPs. A number ofgovernments have developed definitions ofwhat constitutes a PPP (Box 1). Developinga definition can facilitate the implementationof a process of oversight by clearly indicating
which projects should fall under a givenprocess, as was the case in South Africa.
2.3 In shifting from more traditional methods ofservice provision, governments need to adaptboth their skills and their processes to ensurethat PPP programs deliver what is expected.The cornerstone of this is ensuring that PPPsthat proceed are those which representpriority projects and that are best donethrough the PPP route rather than throughtraditional public procurement. Much of thiswill hinge on an assessment of the extent ofand benefits of risk transfer to the privatesector, and an understanding of the residualrisks and future payment obligations borneby the government. Once the project is underimplementation, the government then has tofulfill a contract management and oversightrole to ensure that services are delivered andboth sides live up to expectations.
2.4 Factors outside government are alsoimportant. A successful PPP programpresupposes that the private sector has theright skills and capabilities as well as access
Most countries embarking on PPP programs have attempted to provide some form of definition of what a PPP is. Brazil’snew PPP law defines, in its Article 2, that public private partnership contracts are agreements entered into betweengovernment or public entities and private entities that establish a legally binding obligation to manage (in whole or part)services, undertakings and activities in the public interest where the private sector is responsible for financing, investmentand management. Ireland defines PPPs as any arrangement made between a state authority and a private partner toperform functions within the mandate of the state authority, and involving different combinations of design, construction,operations and finance. In South Africa, a PPP is defined in law as a contract between a government institution and aprivate party where the latter performs an institutional function and/or uses state property, and where substantialproject risks are passed to the third party. The UK’s Private Finance Initiative (PFI), where the public sector purchasesservices from the private sector under long-term contracts is the best known component of that country’s PPP program.However, there are other forms of PPP used in the UK, including where the private sector is introduced as a strategicpartner into a state-owned business that provides a public service.
Box 1: PPPs – Some Definitions
2. Developing Capacities for PPPs:International Experiences2. Developing Capacities for PPPs:International Experiences
India: Building Capacities for Public Private Partnerships
14
to long-term finance in local currency forprojects where this is needed. Effective disputeresolution procedures are also essential,including informal and rapid procedures forinterim adjudication backed up by arbitration.Moreover, decisions reached in this way haveto be respected by the courts.
Public sector capacities neededfor a robust PPP program
2.5 Governments embarking on PPP programshave often developed new policy, legal andinstitutional frameworks to provide therequired organizational and individualcapacities. New agencies are sometimescreated to bring in financial and contractdesign skills not present in the government,and existing processes, for example in planningand budgeting, need to be adapted.
Policy frameworks
2.6 A clear policy advocating the use of PPPs, aswell as the rationale for their use, providespolitical commitment and support for theprogram. This is vital particularly in the earlyyears of a PPP program. It is important thatpolicies stress that PPPs are being pursued toprovide better services, not simply to attractprivate sector resources to supplement thosethat the government lacks. Policies can alsoprovide clarity on other aspects, such as the
approach towards risk transfer, procurement,financing, and the need for transparency. Settingpolicy also encourages the discussion of keyissues among different stakeholders, furtheringan increased understanding of the maincharacteristics of PPPs, their advantages, andtheir drawbacks. In addition, it may be importantto look at other ways of developing anunderstanding of PPPs by policy makers,government officials and other stakeholders (seeBox 2).
Legal frameworks
2.7 Although not all countries have developedspecific new PPP legislation, nearly all have feltit necessary to amend existing legislation, if onlyto clarify that public entities have the neededpowers to contract out services under PPPs. Inthe UK, the Local Government Contracts Actwas passed in 1997 to more clearly set out theability of local governments to enter into PPPcontracts and related arrangements. Irelandpassed the State Authorities (PPPArrangements) Act in 2002 which defined thepossible range of PPPs that State Authoritiescould enter into, as well as the role of theMinister of Finance in providing directions toministries aiming to enter into PPPs. However,in the state of Victoria in Australia, PPPs havebeen executed without the need for newlegislation.2
Box 2: Encouraging policy-makers and government officials to use PPPs
At the federal level, the P3 Office, located in Industry Canada (a federal government department that promotes Canadianindustry), has played the role of promoter and resource center. One of the main purposes of the P3 Office, with six full-time professionals at the peak of its activity, was to actively promote the idea of PPPs among politicians and officials inthe provinces and to provide information – and counter misinformation – about PPPs. They do not engage in project-specific advice, as expertise about how to develop PPPs was expected to flow naturally to wherever it was demanded,diffused largely by consulting firms. The main obstacle instead was a lack of political will and the need for a new policydirection in some of the provinces, and this is where the P3 Office could play a useful role. In addition, they found thatthere was a demand for information about PPPs from the Canadian engineering industry, which wanted to preparethemselves well to compete in this market both in Canada and internationally. Another important role of the P3 Officehas been to educate federal officials about PPPs. The main responsibility for PPPs lies with the provinces, but federalpolicies can either hinder or facilitate PPP programs at the provincial level.
2 However, in the UK and Australia sector-specific legislation has been used to introduce competitive markets, restructure industriesand introduce new regulatory frameworks.
Developing Capacities for PPPs: International Experiences
15
2.8 Secondary legislation and regulations can bedeveloped to use existing laws as a frameworkfor PPPs. In South Africa the nationalgovernment developed new regulations underexisting public financial managementlegislation to impose central governmentoversight and approval of PPPs beingdeveloped and signed by the provinces. Thisaddressed the national government’s mainconcern, namely that the provinces were usingPPPs as a means of off-balance sheet financingto get round budgetary constraints.
2.9 Cross-cutting PPP legislation has been usedmore extensively in countries that operateunder the civil code. Where used, it oftencovers aspects such as specifying whichsectors PPPs can operate in, how tariffs forPPPs are set and adjusted, the role of differentinstitutions in a PPP program, procurementof PPPs, and dispute resolution procedures.
2.10 Even where legislation is not strictly neededto permit PPPs, it can be helpful in a numberof ways. It can for example define and limitthe processes used in identifying and procuringPPPs. Many PPP laws for example go intoconsiderable detail prescribing theprocurement procedures that must befollowed, and the form and content of a PPPcontract. Legislation can also create newinstitutions which will play a key role in thePPP process. Finally, new laws can help clarifythe overall legal framework for PPPs byconsolidating, or referring to, all provisionsneeded in connection with PPP arrangements.Generally older laws were enacted without
PPPs in mind, and it may not be clear howthey would apply in the new context. As aresult, a number of countries have passedbroad legislation relating to PPPs.
Human resources
2.11 The public sector needs individual capacitiesto be strengthened to provide the gamut ofskills required for an effective PPP program,not just transactions skills, but also thoseinvolved in selecting which projects to bepursued as PPPs, estimating the fiscal costsof PPPs, oversight and contract management,and ex-post evaluation and auditing of theperformance of PPPs. Developing thecapacities to design and execute transactionsmay be the most difficult for the public sector,since the legal and financial skills may not bepresent and given public sector pay scales itmay be difficult to attract skilled individuals infrom the private sector.
2.12 Sustaining capacities is made more difficult bythe rotation of staff out of positions oncethey have built up knowledge by closingtransactions. This problem is likely to increaseat the municipal or local level, where capacitiesare likely to be lower and the number of PPPsfewer, offering a reduced opportunity forlearning-by-doing. Consultants can play alarge role in providing specialist skills for publicauthorities in any PPP program. But certaincore skills have to remain with the publicsector or it will be impossible to make the bestuse of the consultants. Training will also help,and, as noted below, the development of clear
Box 3: Brazil’s new PPP Law
Brazil has recently passed a new national PPP law that applies to all levels of government and to all entities/enterprisescontrolled by governments within Brazil. This law sets out the main guidelines to be followed in developing PPPs; thebroad types of activities possible under PPPs; sets of clauses that PPP contracts must include; the bidding processrequired for procuring PPPs; the creation of an agency, under the Ministry of Planning, Budget and Management, thatestablishes procedures for contracting out PPPs; and a requirement for contracting entities to estimate the costs of PPPs,and to ensure that these costs are consistent with multi-year budget plans and relevant legislation on fiscal costs and donot lead to breaches of budgetary plans and relevant fiscal legislation.
India: Building Capacities for Public Private Partnerships
16
processes and guidelines can accelerate thetransfer of knowledge and learning-by-doing.
Procedures and guidelines
2.13 Many PPP programs develop standardizedprocesses and approaches towardsstructuring contracts. The standardizationof common contractual provisions is alsorecommended as it firms up an acceptablepublic sector risk profile and creates certaintyin the market. It can also promote a commonunderstanding of the technical, operationaland financial risks that are typicallyencountered in PPPs, a commonunderstanding of how such risks should beallocated or shared, a consistent approach torisk transfer, risk sharing and value for moneyacross PPPs falling in the same sector, and areduction in time and cost of negotiations.Sector toolkits can be developed oncesufficient sector experience has been achieved.Guidelines are often developed which providespecific rules on how projects are to beselected for pursuit through PPPs, on contractdesign and procurement, and on contractmanagement. These can help ensure thatissues such as affordability of the PPP to thegovernment, value-for-money, overall fiscalcosts, and public legitimacy concerns areaddressed properly. Most countries thatdevelop guidelines and manuals developtraining courses on these for contractingauthority staff.
Organizations: the role of cross-sectoralPPP units
2.14 Most countries engaged in a broad-based PPPprogram have felt the need to develop a cross-sectoral pool of expertise in a dedicated PPPunit to supplement capacities in the lineagencies that contract for PPPs. These fulfilldifferent roles depending on the needs of thesituation. In some cases their role is limitedto disseminating information on PPPs and
providing broad guidance on good practices.In others they have an active role in helpingline agencies and ministries successfullycontract for PPPs, and in yet others they playa role in approving PPPs developed by othergovernment agencies, for example looking atthe quality of the PPP deal, affordability andexpected fiscal cost. Where developed, thesecross-sectoral units are often located in, orattached to, the Ministry of Finance orTreasury. This probably reflects concernsabout the need to strengthen understandingand monitoring of the fiscal costs of PPPs.
2.15 Line departments will usually retain theprimary responsibility for PPPs within theirmandate. The role that central units playdepends on a number of considerations. Themost important is the deal volume in the linedepartment. If a department develops a largenumber of PPPs, it may make the most senseto build up full capacity within the departmentto handle these activities. For example, in theU.K., the Prison Service and the HighwaysAgency both have their own dedicated PFIteams. However, many PFI projects forhospitals and schools are implemented byNational Health Service trusts and localeducation authorities, each responsible forone or two projects. It would not be costeffective for each trust or authority to set upa permanent dedicated PFI unit.
2.16 It may also be a matter of timing. It may beappropriate for a cross-sectoral unit toprovide assistance to a line department at thestart of its program, when the line departmentdoes not yet have sufficient experience. Theconverse may however also be true, with somepioneering line departments having morehands-on experience than a newly-created PPPunit. In these cases, it will be important for across-sectoral unit not to slow down thesemore experienced agencies, whilst at the sametime ensuring that critical issues (e.g.
Developing Capacities for PPPs: International Experiences
17
affordability and value-for-money) areproperly addressed.
2.17 Cross-sectoral units can perform a broad setof functions, including: undertaking thedevelopment of PPP policies and legislation;the development of guidance material includingstandard contracts, manuals and processesfor identifying and developing PPPs; clearanceand approval functions during the PPPprocess; a source of expertise in one or moreaspects of PPP procurement andmanagement; development of trainingprograms; dissemination of information onPPPs; and assessment of the fiscal costs (directand contingent) of PPPs. Box 4 shows therange of responsibilities granted to the SouthAfrican PPP unit. Like units or agencieselsewhere, such as in the Netherlands andwith several of the agencies involved in theUK PPP program, they have developedtraining material to supplement or reinforcethe guidance material and contractual orprocedural approaches they have developed.
2.18 One important policy decision is whether thecross-sectoral unit will have the power toimpose mandatory requirements on the linedepartments – and in that case, what kind ofrequirements. This is often done by involvingthe PPP unit in approval of the PPPs. InSouth Africa, the Treasury relies on the PPPUnit to assess whether the expenditures
incurred by PPPs developed by line agenciesand provinces can be met within their futurebudgets. The PPP Unit is involved at threedifferent points: after the feasibility study,before issuing the bidding documents, andbefore signing the contract. In contrast, insome countries – e.g. Italy– the national cross-sectoral PPP unit plays only an advisory role.
Purely public versus public-private cross-sectoral units
2.19 Particularly where PPP units are to providetransactions skills and experience carefulthought needs to be given to the nature ofthe unit and its ability to buy in these skillsfrom the private sector. One option is toestablish a unit within a ministry and rely onlong-term consulting skills to supplementcapacities. Greater independence can beachieved by setting up the unit as anautonomous entity, attached to but not fullypart of the government bureaucracy as withthe Philippines BOT center. A third approachcomes from Canada, where PartnershipsBritish Columbia is a government-ownedcompany that works with line departmentsand other agencies to identify and procurePPPs in that province. This is overseen by apublic/private board and offers salaries outsidethe normal civil service ranges to attractpeople with relevant financial and transactionsskills.
Box 4: The role of the South African PPP Unit
In 2000, South Africa set up a PPP Unit to serve as the focal point for coordinating and managing the PPP program. ThePPP Unit reports to the Budget Office of the National Treasury. The PPP Unit in South Africa is a good example of acentral organization with a wide range of tasks, both advisory and mandatory, relating to PPPs. The key functions ofSouth Africa’s PPP Unit, which has 11 professional staff at present, are: formal approval at three different stages ofproject preparation to ensure compliance with Treasury regulations; in-depth technical assistance to departmentsthroughout the PPP project cycle; assistance to departments in appointing transaction advisors; development of policy,guidelines, and instructions, including the PPP Manual and the Standardized PPP Provisions (contract terms); trainingcourses and workshops, based round this Manual; promotion of public awareness of PPPs through the PPP Quarterlypublication, website, and conferences; and management of the Project Development Facility that provides funding forthe government’s transaction costs.
India: Building Capacities for Public Private Partnerships
18
2.20 Another way is to set up a joint venturecompany that is owned in part by privatesector shareholders. This is usuallycomplemented by incentivizing the unit byallowing it to benefit financially from successfees to be paid by the winning bidder whenthe deal is closed. One example of this isPartnerships U.K. (PUK), established in 2000.PUK, 51% owned by the private sector,considers itself to be a bridge between thepublic and private sectors. It focuses onstructuring and negotiating the commercialaspects of the deal. PUK regards itself as aPPP “developer,” playing a more active rolealong with the public authority.
Possible conflicts of interest within cross-sectoral units
2.21 There are risks of a conflict of interest in cross-sectoral PPP units that have multiple
functions, even where these are purely publicsector agencies. A conflict of interest canoccur when the unit has a strong mandate topromote PPPs and increase deal flow, whileat the same time having the responsibility forscreening deals and ensuring that the projectsare affordable to the government. Conflictsalso arise if the same body promotes or assistsin developing projects and then is asked tocarry out ex post evaluations. The bestsolution in both cases may be to split thefunctions. In South Africa, the PPP unit faceda conflict of interest in providing transactionsadvice for projects and granting approvals.This was handled by seeking approvals onprojects from individuals from other groupswithin Treasury. In British Columbia, theTreasury retains approval powers, as theseare not granted to Partnerships BritishColumbia, as is also the case in the UK.
Box 5: Institutions involved in the UK’s PPP programs
The institutional system relating to the Private Finance Initiative (PFI) in the U.K. began in 1992 with the establishmentof the Private Finance Panel and then, in 1997, the Treasury Task Force. Since then, the system has gone through anumber of changes. At present, the main organizations dealing with PFI, in addition to the line departments and localgovernments that have primary responsibility, are the following:
The PPPPPrivate Frivate Frivate Frivate Frivate Finance Unit inance Unit inance Unit inance Unit inance Unit in the Treasury is the body responsible at present for formulating policy and preparing policyand practice guidelines for PFI – e.g. concerning the preparation of a “public sector comparator.”
Partnerships UK (PUK)Partnerships UK (PUK)Partnerships UK (PUK)Partnerships UK (PUK)Partnerships UK (PUK) was set up in 2000 to handle the development of specific projects. The focus is on structuringthe contracts, managing the procurement process, and supporting negotiations. PUK is now 51% owned by privateinstitutions (e.g. financial services companies involved in financing PFI projects) and 49% by the government. Its role isto work closely with government departments to develop PFI transactions. It commonly takes a success fee when dealsare closed.
The Office of Government CommerOffice of Government CommerOffice of Government CommerOffice of Government CommerOffice of Government Commerce (OGC)ce (OGC)ce (OGC)ce (OGC)ce (OGC), an independent office of the Treasury reporting to the Chief Secretary,focuses on improving central government procurement in all its aspects, not just PFI. Specific PFI-related responsibilitieshave now been taken over by the Private Finance Unit in the Treasury.
The Public Private Partnerships Programme (4ps)Public Private Partnerships Programme (4ps)Public Private Partnerships Programme (4ps)Public Private Partnerships Programme (4ps)Public Private Partnerships Programme (4ps) was set up in 1996 to provide support and advice to local governments,especially about procurement matters but extending over the entire project cycle. Advice concerns PPPs broadly, not justPFI projects. (In U.K. terminology, “PPP” can refer to a broader category that encompasses a number of different waysthat the public and private sectors can work together.)
The National Audit Office (NAO)The National Audit Office (NAO)The National Audit Office (NAO)The National Audit Office (NAO)The National Audit Office (NAO), as auditor of central government expenditure, carries out ex post reviews of PFIprojects and programs as part of its mandate to evaluate whether government departments are achieving value formoney. These are placed in the public domain.
Select Committee on PSelect Committee on PSelect Committee on PSelect Committee on PSelect Committee on Public Accounts of the House of Commons (Public Accounts of the House of Commons (Public Accounts of the House of Commons (Public Accounts of the House of Commons (Public Accounts of the House of Commons (PAAAAAC)C)C)C)C), as the parliamentary watchdog, preparesreports on PFI projects and questions on selective basis.
Developing Capacities for PPPs: International Experiences
19
Traditional oversight bodies also have a role— the U.K. National Audit Office hasundertaken a number of reviews of thegovernment’s PPP program.
2.22 There is a special risk of conflict of interestwith respect to PPP units that are public-private joint ventures, and where success feesincentivize the closing of transactions. Therisk of capture by private interests could behigh. Careful structuring of the arrangementsfor corporate governance is needed. Privatesector participation is added to orient the unitmore to the private sector’s mode of thinkingand working, but the unit still has to maintainthe policy perspective and objectives of thepublic sector. In the U.K, for instance, oneway that this is intended to be accomplishedin Partnerships UK is through an AdvisoryCouncil, made up exclusively of members fromthe public sector, which was established byTreasury to oversee PUK. The AdvisoryCouncil approves the selection criteria usedby PUK in deciding which projects to beinvolved in.
2.23 In general, it is clear that a public-private unitwould not be the right place to issue PPPpolicies, though they could play a role in theirdevelopment. Therefore, a public-private unitthat provided transactions support wouldneed to be complemented by the developmentof capacities elsewhere (typically in Finance)which could perform these functions. Thesetensions can mean that it may be useful tohave a number of different institutionsinvolved in different aspects of the PPPprogram (see Box 5), as is now the case inthe UK.
The roles of national and sub-nationalagencies
2.24 All the countries discussed so far haveundertaken many PPPs in areas whereservice responsibilities lie with sub-national
governments or agencies. The role ofnational agencies relative to sub-nationalones usually reflects legal and fiscal relationsbetween these levels of government,deriving from the constitution and existingbudgetary practices.
2.25 In the UK, there are many PPPs that havebeen entered into by Local Authorities. Theseaccess advisory support from national levelagencies, and all local government PFI projectsare approved by a central government inter-departmental committee chaired by Treasury.In South Africa, the oversight role of thenational PPP unit has already been mentioned.It has also played an important role indeveloping standards and procedures toimprove the quality of PPP transactions. Thelegislation recently passed in Brazil envisagesa role for a national level entity to establishprocedures for contracting PPPs and toidentify projects that should be taken up asPPPs as a priority.
2.26 Other countries have adopted a moredecentralized approach. In Canada, several ofthe provinces (for example British Columbiaand Quebec) have their own cross-sectoralPPP units. The federal government createdan agency, the P3 Office, to act as a resourcecenter and promoter of the benefits ofrationale for using PPPs, rather than in a morehands-on advisory role. This has included thedevelopment of information resourcesincluding a portal and guides and “self-help”tools.
2.27 The national government in Australia hasvirtually no role in state level PPPs and insteadhas largely focused on PPPs for services forwhich it, as national government, isresponsible. State governments have takenresponsibility for developi ng PPPs for theservices they are responsible for with very littleinvolvement by the national government. The
India: Building Capacities for Public Private Partnerships
20
states have established their own information-sharing structures, with a PPP forum, forgovernment policy-makers, meeting annually,and a PPP working group, for the heads ofPPP agencies, which meets more often with amandate to coordinate over the projectpipeline, provide consistent (though separatefor each state) guidance, and try to develop
standards for contract principles and drafting.However, as noted in Box 3, Brazil is intendingto establish capacities in the center to offerdetailed guidance to the states in thedevelopment of PPPs. Table 1 summarizes themain functions performed by existing cross-sectoral PPP units in a number of differentcountries.
Table 1 – Functions of Cross-sectoral PPP Units
Frame- Nature Approval Intensive Role as Role in Resource PPP Fundingwork law of PPP power project project contract center guidance forenacted unit over specific develop- over- *** material prepa-
establi- PPPs** advice er (a)** sight** *** ration(b)shed
Australia: Victoria ① � �
Canada: British Columbia ③ � � (f) � �
Ireland � (c) (d) � �
Italy(h) � ① � � �
Netherlands ① � � � � (g)
Philippines � ② � � � � �
South Africa ① � � � � �
U.K.(i) ④ (e) � � (f) � �
Notes:Notes:Notes:Notes:Notes:
***** “PPP unit” in this table means a cross-sectoral unit. Legend for this column: ① = unit is part of ministry or department;② = autonomous or quasi-autonomous administrative unit; ③ = public authority or publicly owned company (outsidecivil service); ④ = public-private joint venture company; x = no distinct cross-sectoral PPP unit exists.
** Refers to the dedicated PPP unit.*** Might be provided by the dedicated PPP unit or by another cross-sectoral department or central ministry.(a) Greater responsibility than an advisor and charges fees that are based on some measure of performance (e.g. achievement
of milestones or close of deal).(b) Refers to funding (outside the normal budget) to pay for consultants working with the line department or local government,
not with the PPP unit.(c) In Ireland, Central PPP Unit (dealing with policy and general PPP procurement issues) is ① ; National Development Finance
Agency (giving advice about financial structuring, financing, and risk evaluation) is ③.(d) In Ireland, the National Development Finance Agency gives p roject-specific advice about financing and financial
structuring. The Central PPP Unit was involved in project-specific work for the pilot projects so that they could get hands-on knowledge to develop the policy and guidance material. But now, they do not become involved in specific projects.
(e) Partnerships UK prepares a report for each local government PFI project; the report goes to an interdepartmentalcommittee that has the power of approval.
(f) Can be requested by its clients (line departments and local governments) to play a role in oversight and monitoring, butthere is no obligation to use the unit for this purpose.
(g) EU provides grant funding for the transaction costs for some large-scale transportation PPPs (rail and roads).(h) This refers to the central PPP unit. There are also PPP units of various kinds in six of Italy’s regions. Certain regions have
considerable autonomy.(i) This row refers just to Partnerships UK.
Source: World Bank analysis
21
3.1 There is now over 10 years experience in Indiain the development and use of PPPs fordelivering infrastructure services. Policies infavor of attracting private participation havemet with varying degrees of success, but realprogress has been made in some sectors, firstin telecommunications, and now in ports androads, and with individual projects in othersectors. There has been considerableinnovation with different structures nowbeing developed to attract privateparticipation. But at the same time progresshas been uneven: there are islands ofprogress, with some states having undertakenfar more PPPs than others, and a much heavieruse of PPPs in some sectors than others. Andwhile there are a number of successfulprojects to the present date, there have alsobeen a number of poorly conceptualized PPPsbrought to the market that stood little chanceof reaching financial closure. In terms offrameworks for PPPs, some states have mademore attempts to develop this, includingcross-cutting legislation and the development
of cross-sectoral units that play a role in theidentification and preparation of PPPs. Othershowever have worked within the bounds oftheir existing organizational structure.
3.2 Given the lack of an existing database onPPPs in India, a survey was undertakenboth to provide information on the currentusage of PPPs as well as the frameworksdeveloped for their implementation. Themain sectors of focus are the basic publicservices excluding power: transportation(ports, airports, roads, and rail), water andsanitation, and other urban infrastructure(solid waste management, light rail, busterminals).3 This represents the presentareas of focus of many state governmentsin India. The survey covered 12 of the statesregarded to have been most active in thedevelopment of PPPs, as well as the 3central agencies undertaking PPPs in theareas of focus.4 The survey also providessome indication of the possible pipeline ofPPP projects in India.
3 We also provide some coverage of other basic services such as the social sectors (education and health) and e-governance, but theyare not reflected in the main text charts as the available data are not as comprehensive in their coverage. In consultation with DEA,it was decided to exclude the power sector from the analysis, given the complex issues involved in that sector and the range of otherefforts focused specifically on power both within the Bank Group and beyond.4 This analysis is based on a non-comprehensive survey of PPP activities to-date in 3 central agencies – National Highways Authorityof India (NHAI), Ministry of Shipping, Road Transport and Highways (MOSRTH) and Rail Vikas Nigam Ltd. (RVNL)— and 12 statesacross basic infrastructure sectors, supported by PwC; although it does not cover the universe of PPPs, it reflects most projects inbasic infrastructure sectors in the most active states. The 5 infrastructure sectors of focus where PPP contracts have been awardedin the covered states and federal agencies are roads & bridges, ports, airports, rail, and urban, which in turn includes water &sanitation, solid waste management, bus terminals, light rail, ferries and a logistics hub (although for the last 3 sub-sectors therehave been preparatory activities but no contract awarded yet). There also has been activity in health & education and e-governance, in addition to sectors not covered in this report such as power, tourism, and other construction (convention centers,industrial, IT & biotech parks, SEZs, and housing). The states covered are Andhra Pradesh, Delhi, Gujarat, Karnataka, Kerala,Madhya Pradesh, Maharashtra, Orissa, Punjab, Tamil Nadu and West Bengal (though the survey did not include any awarded PPPproject in Orissa, only pipeline projects).See the tables in the Annex for more details.
3. PPPs in India: Islands of Progress3. PPPs in India: Islands of Progress
India: Building Capacities for Public Private Partnerships
22
The role of PPPs so far
3.3 In the surveyed states and central agencies,there have been at least 86 PPP projects inour main sectors of focus where a contracthas been awarded and projects are underway– in the sense that they are either operational,have reached construction stage, or at leastconstruction/implementation is imminent.Over 70% of these are in the roads sector.The other transport sectors have seen muchfewer projects, with 8 ports (4 major and 4minor ports), 2 airport and 2 rail projectsunderway. In the urban infrastructure sector,11 PPP projects have been awarded, with 8solid waste management, 2 water andsanitation and one bus terminal projects.Outside of the sectors of immediate interestand hence not included in the main text totalsand charts, the survey found 6 PPP projectsin e-governance and 2 in education. Thoughthe coverage may not have been exhaustivefor these last two sectors, it is clear that thepotential use of PPPs in e-governance andhealth and education sectors remains largelyuntapped across India as a whole.
3.4 When looking at the total estimated projectcost of PPPs, we see that road projects
account only for 36 percent of the totalbecause of the small average size of projects.Ports, with a much larger average size ofproject, account for 56 percent of the total.It is noteworthy that if ports and central roadprojects are excluded from the total, there isin fact a relatively small value of deal flow, atonly Rs 30 bn in basic infrastructure PPPsto-date, suggesting a significant potentialupside for PPP projects across sectors wherestates and municipalities have primaryresponsibility.
3.5 Across states and central agencies, the leadingusers of PPPs by number of projects have beenMadhya Pradesh and Maharashtra, with 21and 14 awarded projects respectively, all inthe roads sector, and the National HighwaysAuthority of India (NHAI), with 16 projects.The other states or central agencies that havebeen important users of PPPs are Gujarat (9projects) and Tamil Nadu (7), Karnataka (4)and Ministry of Shipping, Road Transport andHighways (MOSRTH) (4). However, lookingat a breakdown by estimated project size, wesee that MP becomes significantly lessprominent due to the large number of relativelysmall-sized projects in its portfolio, falling to3 percent of total project costs. Gujarat
Figure 2: Project cost of awardedPPPs by sector (total = Rs. 339.5 bn.)
Figure 1: Number of awarded PPPsby sector (total = 86)
Source: PWC analysis Source: PWC analysis
PPPs in India : Islands of Progress
23
Figure 3: Awarded PPP projects bystates & central agencies (total = 86)
accounts for 48 percent of total project costsdue to its four large port projects. NHAI(17%) and MOSRTH (12%) are the othersignificant players. Karnataka accounts for 7percent of total project costs given that itsone awarded PPP project, the Bangalore-Mysore road corridor (currently underconstruction) had a reported project cost ofRs 22.5 billion.
3.6 In terms of main types of PPP contracts,almost all contracts have been of the BOT/BOOT type or close variants. While it maybe appropriate for central, state or municipalgovernments to promote PPPs that can bepaid for by users if they are priorities, theymay be missing out on other opportunitiesfor more efficient private sector service deliverysupported by ongoing public payments overtime. Some examples of such other types ofPPP contracts used to-date in India includethe annuity contracts awarded by NHAI forroads, a small number of affermage-type(O&M with private investment) contracts,and a long lease in Maharashtra for theMumbai-Pune expressway.
3.7 Anecdotal comments from the private sectorsuggest that a considerable number of un-
bankable and unrealistic PPP projects arebrought to the market by state governments.Data from the survey presented in the Annexshow that there were 15 projects that havenot moved forward past the award stageeither because they have been abandoned orremained dormant. Of these, several had nogood offers forthcoming in response tosuccessive requests for expressions of interest.Although this number is not obviously highcompared to the number of projectsunderway, it nonetheless suggests that theremay be significant benefits from capacitybuilding in identification and preparation ofPPPs to ensure that more bankable projectsare brought to market.
3.8 In terms of approach to provider selection,93 percent of the projects in the samplewere competitively bid (of which four-fifthsused national competitive bidding), withonly 7 percent procured either throughMemorandums of Understanding (MOUs)or negotiated. However, it is worth notingthat in value terms 42 percent of theprojects were awarded on a negotiated/MoUbasis.
Figure 4: PPP projects by states ¢ral agencies (total = Rs. 339.5 bn.)
Source: PWC analysis Source: PWC analysis
India: Building Capacities for Public Private Partnerships
24
Institutional frameworks for PPPsin India3.9 A wide range of institutional structures and
capacity approaches have been adopted forconceptualizing and procuring PPPs acrossstates and central agencies, different variantsof which have had some degree of success.At the state level, the three main approacheshave been: combining dedicated institutionswith cross-cutting legislation; establishing andusing cross-sectoral PPP advisory units tohelp line departments in the absence of over-arching legislation; and relying on linedepartments and sectoral agencies to buildcapacities. Table 2 provides a summary ofstate-level approaches.
3.10 Gujarat, AP and Punjab have developedspecialized institutions and legislation. Each
of these states has constituted an agency(respectively the Gujarat InfrastructureDevelopment Board, the AP InfrastructureAuthority and the Punjab InfrastructureDevelopment Board) and passed acts topromote private sector participation ininfrastructure projects across sectors. As anillustration, the Gujarat InfrastructureDevelopment Act, 1999, gives force of law tothe provision of entering into a concessionagreement with a private sector developer,provides transparent procedures for selectionof the developer, and provides for levying usercharges for the facilities provided by thedeveloper.
3.11 A second category of states, includingKarnataka, Rajasthan, Uttaranchal and WestBengal, have developed cross-sectoral
Table 2: Institutional Frameworks for PPPs in India
Framework Nature of Approval Intensive Resource PPP guid- Fundinglaw PPP unit power project- center ance mate- for PPP
enacted established over specific *** rial*** prepara-* PPPs** advice** tion (b)***
Gujarat � ② � � � � �
Andhra Pradesh � ② � � � � �
Punjab � ② � � � (b)
Madhya Pradesh (a) (b)
Maharashtra (b)
Tamil Nadu (b)
West Bengal ④ (b)
Karnataka ④ (b)
UP (b)
Orissa (b)
Delhi (b)
Notes:***** “PPP unit” in this table means a cross-sectoral unit. Legend for this column: ① = unit is part of ministry or department;
② = autonomous or quasi-autonomous administrative unit; ③ = public authority or publicly owned company (outsidecivil service); ④ = public-private joint venture company.
** Refers to the dedicated PPP unit.*** Might be provided by the dedicated PPP unit or by another department or ministry.(a) – sector specific, (b) – limited to some sectors/agencies/projects
Source: World Bank analysis
PPPs in India : Islands of Progress
25
facilitation entities, but have not passedcomprehensive legislation. In Karnataka, theInfrastructure Development Corporation ofKarnataka (iDeCK) is a joint venture betweenthe state government and IDFC modeled onPartnerships UK, providing advisory servicessuch as enabling frameworks, projectdevelopment and structuring, andmanagement of a Project Investment Fund.The Rajasthan Project DevelopmentCorporation (PDCOR) is similar in structure,a joint venture between the state governmentand IL&FS to facilitate private investment ininfrastructure, including policy advisoryservices to the state government, andinstitutional support to structure andimplement PPPs. The ICICI – West BengalInfrastructure Development CorporationLimited (IWIN) is a joint venture betweenICICI Bank Group and Government of WestBengal formed with the objective ofaccelerating the development of infrastructure.
3.12 Finally, a third category of states, includingMP, Maharashtra and Tamil Nadu, have reliedon sectoral and line agencies to develop andimplement PPPs. In Madhya Pradesh (MP),for example, initially the MP Public WorksDepartment (PMMWD) and then thespecially-created MP Road DevelopmentCorporation (MPRDC) act as the agency fordevelopment of road projects on a BOT basis.In the process of developing projects, MPRDChas developed policy, guidance materials andskills. In Maharashtra, the State RoadDevelopment Corporation (MSRDC) andMumbai Metropolitan Region DevelopmentAuthority (MMRDA) have developed policiesfor infrastructure development through privatesector participation, including a “Policy onimplementation of Road & Bridge Projectsthrough private sector participation”.
3.13 At the central level, the NHAI has developedand modified standard concession agreements,
and has developed different approaches forextending government financial support forPPPs. The capacity building measures underway at NHAI focus on improving humanresources, financial systems, bid processmanagement and include internal training,study tours and the development of a robustMIS system. However, it is understood thata number of personnel are on deputation andthey leave once their tenure is over. Thoughthis is not an unusual situation for publicagencies, it does of course lead to a loss ofexpertise and knowledge. For the rail sector, aspecial purpose vehicle called Rail Vikas NigamLimited (RVNL) has been floated to develop,mobilize resources and implement PPPs. Thereare no obvious structures in place at thecentral level to transfer expertise andknowledge built up in one agency – forexample NHAI – to a second that is justembarking on PPPs.
3.14 There is no clear link between institutionalstructures and success in developing PPPs inIndia. It would seem clear from the experienceof MP and Maharashtra in the developmentof PPPs for roads that it is possible to developa PPP program in a single sector by buildingup capacities in line departments. However,these states are conspicuous by their absenceof PPPs in other sectors, no doubt at least inpart driven by the absence of platforms totransfer acquired skills to other departments.Gujarat, AP and Punjab have all developedcross-sectoral enabling legislation anddedicated agencies but have had very differenttrack records in terms of taking PPPssuccessfully to the market. Some other states– such as Tamil Nadu – have also developed afew PPPs across a wide range of sectors,without explicit cross-sectoral PPP units orlegislation.
3.15 Fundamentals such as political commitmenttowards the use of PPPs, sufficient trained
India: Building Capacities for Public Private Partnerships
26
staff, and strong links between built-upcapacity and implementation responsibility inthe respective line departments are probablythe most important ingredients of success.
The development of policies andstandardization of contracts
3.16 Although some states have developed policiesthat advocate the use of PPPs, the underlyingpolicy rationale is by and large one of usingPPPs to substitute for capital investments bythe state. PPPs have therefore been used morein situations where substantial capitalinvestments are required, and where user feescan be accessed to defray much of the costs.To the extent that it is possible, user feesshould be used to pay for projects. However,purely seeing PPPs as a substitute for publicinvestment has drawbacks. It can be illusory,since many of these PPPs will have fiscal costs,as noted above. It can also lead toinconsistent signals to private developers, asarises when governments have reduced orscaled back PPP programs when additionalfunding – for example provided by multilateralagencies – has become available for publicinvestments.
3.17 In some cases, PPPs are overseen byregulatory agencies, such as in the portssector, where TAMP, the sector regulator setstariffs for port services for the major ports.In most cases however, the PPPs are regulatedthrough the contract between thegovernment agency and the service provider.Here the need will not be for a regulatoryauthority with substantial discretion, butrather for an efficient method for settling thedisputes between the contracting parties thatare likely to arise in even well-designedcontracts. Monitoring by consumer andstakeholder groups of the performance of PPPshas been tested in India and is one way ofsupplementing the capacities of the
government to oversee contractorperformance.
3.18 There have been some efforts by stategovernments and central agencies to developstandard contracts. At the state level, ashighlighted in the Table 2 above and in greaterdetail in the Institutional Framework table inthe Annex, Gujarat and AP have developedcross-sectoral model contracts and Punjab aswell to a more limited extent. Madhya Pradeshhas developed some standard documents inthe road sector. At the central level, NHAIhas developed model contracts and standarddocuments for the road sector.
3.19 There have not been systematic attempts todevelop and use methodologies to evaluatewhether particular projects are best donethrough a PPP route or through traditionalpublic procurement. Tools such as PublicSector Comparators (PSCs) have not beenused very widely in India so far, even on asimplified basis. The lack of an adequatebaseline on the actual costs of delivery by thepublic sector admittedly makes suchcomparisons more difficult, but undertakingthese comparisons would help ensure that thePPP route is best for the priority project.Moreover, anecdotal evidence from othercountries suggests that PSCs are useful inclarifying approaches to risk allocation, andthe expected benefits of this, in the contractingagencies.
Training and other informationdissemination initiatives
3.20 In terms of formalized individual capacitybuilding, the number of specialized coursesoffered on PPPs in India has been limited. Thereare some training programs at central or statelevel, as well as those organized industryorganizations such as Confederation of IndianIndustry (CII). Many of the government
PPPs in India : Islands of Progress
27
organizations – both at the senior levels andmiddle levels – take part in these programs.However, with civil servant staff in generalshifting position every few years, most of thetraining imparted can be quickly lost.
3.21 Perhaps more importantly, there is relativelylittle information on PPPs either in the publicdomain, or commonly available togovernment officials developing PPPs. Thisincludes examples of contracts and clauses,and assessments of the success of differentapproaches both in terms of contractingstructures as well as institutional frameworksfor PPPs.
Where are the gaps in Indiacompared to elsewhere?
3.22 While some states in India have madeimportant progress towards developing theframeworks needed for broad and robust PPPprograms, others have developed policies andapproaches in a single sector only, and mostother states are yet to seriously commencePPP programs. As a result, there isconsiderable diversity in both the strength ofpolicy and legal frameworks in place, and thelevel of transactions capacities andexperiences.
3.23 Even taking this diversity into account, thereare some common areas where frameworksin India need to be developed. As noted earlier,the policy rationale for PPPs is often limitedto the use of PPPs as a source of investmentcapital when the public sector lacks funds.As a result, there is not much championingof PPPs on the grounds that they will lead tomore efficient service delivery and better valuefor consumers and taxpayers. There is limitedsystematic compilation, analysis and transferwithin the public sector of knowledge andexperiences between PPP projects, sectors and
different governments; to the extent that thereis a lack of confidence in civil servants toundertake PPPs, greater awareness of goodexamples and established procedures can helpmake it more acceptable to follow, with thebest antidote to inaction being precedence.Capacities for evaluation and oversight inparticular need to be built up: there is littleevidence so far that there has been muchprogress in developing capacities to decidewhich projects are best done through PPPs,and ex-post evaluation of the performance ofPPPs versus expectations has been limited sofar.5 Finally, the processes for identifying andprocuring PPPs are often not clearly laid out.
3.24 That there are gaps should not be surprising,in part because most state governments inIndia are at an early stage in the developmentof their PPP programs. Nonetheless it isimportant that the right frameworks andcapacities are further developed in the statesand agencies where PPP programs are goingto be pursued.
Expanding the use of PPPs tomeet basic services needs
3.25 The survey of state and central agenciesrevealed that, at present, they have 52 PPPprojects at various stages of development priorto contract award. Roads, rail and ports aremost prevalent, with 39 of the pipelineprojects in these sectors (13, 14 and 12 PPPs,respectively). In urban infrastructure, thereare 12 PPP projects in the pipeline, with 3 inwater & sanitation, 6 bus terminals, onewaste management, one light rail and oneferry project. Across states and centralagencies, the leading developers of thesepipeline projects are RVNL (12 rail), followedby Karnataka (9), Maharashtra (7), andOrissa (7).
5 The exception to this are reviews of the power sector, which in turn are largely focused on the Orissa distribution privatization andDabhol.
India: Building Capacities for Public Private Partnerships
28
3.26 PPPs have the potential to be used more widelyin India for the delivery of basic infrastructureservices. But a set of policy, regulatory andcapacity issues will need to be addressed forthis to happen.
3.27 As noted earlier, PPPs have been used morein situations where substantial capitalinvestments are required, and where user feescan be accessed to defray much of the costs.This approach excludes projects where thegovernment remains the purchaser of servicesbut where efficiency gains can be achievedthrough going the PPP route relative totraditional public procurement. A clearer policyrationale, and one that does not rely largelyon the “substitution” rationale and more onthe role that PPPs can play in improving theefficiency and quality of service delivery willbe important in broadening their usage wherethey lead to lower life-cycle costs.
3.28 Political and regulatory risks involved in PPPsare still perceived to be substantial by theprivate sector. These risks are likely to beperceived as lower where a state governmentor a particular agency has developed a trackrecord of bringing well conceptualized PPPs
to the market and honoring contractualcommitments, particularly where stategovernments or state enterprises are notfinancially strong. Although there aredifferences within the country, these risksremain.
3.29 Some of these risks are manifested in slow andfragmented approval processes forinfrastructure projects that successful biddersmust negotiate. As well as increasing risks,the delays increase the overall cost to bidders,and hence the costs to taxpayers andconsumers.
3.30 Finally, a broader, but successful PPP programwill require the public sector to develop bettercapacities to identify possible PPPs, to developbankable contracts and bid them out, and tomonitor their performance and costs.Informal feedback from the private sectorsuggests that governments still float unrealisticPPPs, for example. Moreover, since PPPs arenot a panacea and entail costs to thegovernment, capacities must be strengthenedif these programs are not, down the road, tolead to substantial costs for the governmentsconcerned.
29
4.1 While progress has been made, both byhaving a substantial number of PPPs now inoperation, and by putting in place legislativeand institutional frameworks for PPPs in somestates, scaling-up the use of PPPs will requireaddressing the gaps identified in the previoussection. Many PPPs will be for services whichare state, and, in some cases municipalsubjects, and capacities have to be developedat this level, where service responsibilities lie.However, there are roles the center could playin developing capacities at the sub-nationallevel, in addition to developing capacities atthe central level.
4.2 Both experience to date in India, andinternationally, shows that there is no uniqueformula for developing a sound PPPframework. However, successful programs arecharacterized by clear policy and legalframeworks for PPPs, competent and enabledinstitutions that can appropriately identify,procure and monitor PPPs, and efficientoversight and dispute resolution procedures.We look at the following main steps that willbe critical to scaling up the PPP program inIndia and assess the actions that could betaken by the center in the following areas:
Strengthening the monitoring of theirfiscal costs;
Policy and legislative frameworks;
Information dissemination;
The development of guidance material;
Setting up a PPP unit to serve as a poolof expertise;
Project development funds for thepreparation of PPPs; and
Funding for PPP payments made by stategovernments.
4.3 The center’s role in developing capacities forsub-national PPPs needs careful considerationtaking into account the size of the country,center-state fiscal and other relations and thevariety of experiences so far, with some stateshaving made considerable strides and othershaving made very little progress. Its role alsodepends on the extent to which the centerwishes to proactively catalyze the increaseduse of PPPs by states and municipalities.Information dissemination and guidanceefforts can be expected to lead to results.However, a catalytic role by the center is likelyto be needed to expand the usage of PPPs,particularly in states and sectors where theyhave been less used so far. This would consist,in addition to information dissemination andguidance, of resources to develop PPPprojects and frameworks, and to fundgovernment commitments under PPPs. Thiswould help address important constraints tofurther development of PPPs in the country– namely, weak capacities to identify realisticPPPs and bring them to the market; a lack ofwillingness to pay for project development;and a lack of creditworthiness on the part ofstates to provide their financial contributionto PPPs. However, there are considerablymore risks in this catalytic role than in morelimited information dissemination andguidance roles.
4. Developing and StrengtheningCapacities for PPPs in India4. Developing and StrengtheningCapacities for PPPs in India
India: Building Capacities for Public Private Partnerships
30
Strengthening oversight of thefiscal costs of PPPs
4.4 Regardless of whether or not the other actionslisted in para. 4.2 above are taken, if there isto be an increased use of PPPs the centershould work to strengthen oversight of theirfiscal costs. PPPs can involve substantialcontingent liabilities as well as long-termpurchase obligations. Fiscal Responsibility Actspassed at the central level and by the statesof Karnataka, Uttar Pradesh, Punjab andKerala all include statements on fiscal prudenceand treatment of contingent liabilities that arerelevant to PPPs. State legislation typicallylimits total liabilities as a percentage of GDPand includes provisions related to contingentliabilities. Karnataka’s Act breaks new groundby including off-budget borrowing and otherdebt-equivalent instruments within the annualborrowing (consolidated fiscal deficit) cap.Nonetheless, implementing this may not bestraightforward.6 More generally, while debtguarantees are often published, the values ofother kinds of guarantees are not. Nor is itclear that governments value or calculate in-kind support provided to many PPPs, forexample real estate development options,which can be a further source of fiscal costsas well as an important factor in decidingwhether a PPP offers value-for-money.
4.5 There are only emerging practices and modelsinternationally since this is also new for mostother countries. In general, reporting anddisclosing PPP contracts and governmentguarantees and reporting the stream of futurepayments under existing PPP contracts wouldbe good practice and, where a PPP programis of fiscal significance, a report on PPPscovering these areas should be included aspart of the budget documentation. Somecountries have started to implement enhanced
programs of disclosure. Chile, starting withthe October 2003 Report on Public Finances,now reports the contingent liabilities arisingfrom PPPs as well as the cash payments toand from concession firms. Monte Carlosimulations and option-pricing models areused to value minimum revenue guarantees,revenue sharing agreements, and the exchangerate guarantees.
4.6 The center should work to strengthenoversight of the fiscal costs of PPPs, includingassisting state governments in this area andenhancing analysis of the fiscal costs of PPPsin central government monitoring of the fiscalposition of the states. Capacity-buildingefforts should be led by the GoI FinanceMinistry, with involvement from otheragencies, such as the Reserve Bank of India,as necessary. This capacity building effortshould go forward regardless of any othersteps taken by the center.
Policy frameworks
4.7 Both the center and some of the states havehad in place for some time policies on privateparticipation for specific sectors: in ports, forexample the center issued “Guidelines onPrivatization” for the major ports in 1996 andGujarat preceded this with a ports policy in1995.
4.8 New policy initiatives would however be usefulin an effort to scale up and broaden the PPPprogram, both at the central and state level.Importantly, this would have the governmentconcerned set out clearly why PPPs are beingpursued and the benefits sought; and indicatethat they will only be pursued where thesebenefits can realistically be expected. As notedin Section 3, one of the gaps in PPPframeworks in India compared to many other
6 It is understood that the annuity scheme used to finance the expansion of the existing Bangalore-Mysore road has not beenincluded in these consolidated calculations even though it could be regarded as a “debt-equivalent” instrument.
Developing and Strengthening Capacities for PPPs in India
31
countries is the emphasis on PPPs as raisingadditional capital, rather than only beingpursued where services will improve andtaxpayers and consumers will get value-for-money. This could be addressed by a clearpolicy statement which would make clear boththe rationale and also the limits to the use ofPPPs. This would help to give the PPP programa clearer political mandate.
4.9 Broad policy initiatives would also enablegovernments to announce more clearly theinstitutional framework for PPPs. This couldinclude the regulation, oversight andevaluation of PPPs, all areas which needstrengthening, as well as the role of anynew cross-sectoral units in developing andimplementing PPPs. Another importantarea to be addressed would be proceduresfor the procurement of PPPs, in particularthe use of competitive processes, andapproaches to be adopted towardsunsolicited projects.
4.10 While broad policies provide an importantsignal of political commitment, it may also benecessary to translate this into action plansand policies for individual sectors. These couldprovide a more precise orientation toencourage line ministries and agencies topursue and implement PPP programs.
Legislative frameworks for PPPs
4.11 Cross-cutting PPP laws are not needed inIndia to permit central or state governmentsto enter into PPPs. Both the center and manystates have done so without such laws.Sector specific legislation has of course beenused to restructure industries, introducecompetitive markets and set up newinstitutions, such as sector regulators.
4.12 In Section 2 it was argued that one of thebenefits of cross-cutting PPP legislation is thatit allows the consolidation of relevant legal
provisions into one law, and also allows thegovernment to legislate the use of certainprocesses for the development, procurementand regulation of PPP projects. While notstrictly necessary, the use of new processesmight be better enforced if given the force oflaw. This might be more important at thestate level, where checks and balances andoversight are not as strong as at the center.
4.13 Particularly at the state level, therefore,consideration should be given to thedevelopment of cross-cutting PPP legislation.The legislation already passed by Gujarat, AndhraPradesh and Punjab provides possible modelsfor other states. One important aspect thatcould be addressed by such legislation ismechanisms for dispute resolution. The nationallegislation in telecommunications provides onemodel of how such as process and institutioncan be created that leads to a quicker and moreefficient process of settling disputes. Legislationcould also establish alternative disputeresolution procedures that could be used toefficiently settle differences between the parties.
4.14 The development and passage of legislationalso allows for consultation and open debateabout the government’s policy for pursuingPPPs, including the expected benefits andrationale. This could be an importantmechanism to help increase the publiclegitimacy of PPPs.
Information dissemination
4.15 Despite the fact that there are nearly 90 PPPsin India under construction and operation,there is no publicly accessible databaseproviding even the most straightforwardinformation on them. The database presentedin Section 3 could however provide thenucleus for this. There is no organized forumfor state level PPPs, or even central agencies,to share experiences, and it is difficult tocompare contracts for similar services since
India: Building Capacities for Public Private Partnerships
32
these are not in the public domain. Improvingthe flow of information would helpgovernment officials planning and developingPPPs, the private sector interested inparticipating in PPPs, and stakeholdersinterested or concerned about PPPs.
4.16 One main component of an informationdissemination program would be a web-basedportal that would feature: a publicly-accessiblenational database that would contain on aproject level basis information on its basicstructure including sector, expected/actualcontract award date, capital cost, executinggovernment agency and private developer, andmethod of tender; links to websites of bothIndian and foreign PPP agencies and contactinformation for agencies in India developingPPPs; and PPP pipelines for different statesand municipalities. Sufficient resources forongoing maintenance of the database mustbe provided to ensure continued relevance.
4.17 A second major component would be thedevelopment of training materials. The maintarget group would be project teams incontracting authorities, but training could alsobe targeted at more senior governmentofficials, as well as those in other ministries,such as Finance, that interact with thecontracting authorities and have an oversightrole. The private sector may also benefit fromsuch training. Substantive evaluation efforts,for example analysis of successes and failures
of individual projects, and case studies wouldassist in the development of training materialsand help both in designing new PPPs andmanaging existing ones. Over time this couldbe broadened into the provision of data onthe performance of PPPs to improve decisionmaking on the use of PPPs versus traditionalpublic procurement.
4.18 Finally, efforts could also be made throughworkshops and other informationdissemination mechanisms to reach politicians,consumers and other stakeholders, so thatthey are better informed about the nature andstructure of PPPs. This would also be helpedby greater transparency including placing PPPcontracts in the public domain (see Box 6).There may be concerns over disclosure.However, there is relatively little that isgenuinely commercially confidential in PPParrangements, and though these are complexdocuments, this does not seem to be a validreason not to allow citizens to access them.
4.19 The public good nature of informationdissemination means that it would make sensefor this to be led by a unit located within asingle central ministry with cross-sectoralresponsibilities, such as Finance. Most of thework would be contracted out and deliveredby others, including the development andmaintenance of the portal and database onPPPs, and training material and case studiescould be developed by a national training
Box 6: Encouraging transparency in PPPs
Public disclosure of PPPs promotes consumer rights, helps enforcement of obligations, and reduces incentives forcorruption and special treatment of certain private providers. A number of countries have taken the initiative to placecontracts for public services in the public domain. In some situations, more general policies and legislation on access toinformation motivate this. In the UK, the Freedom of Information Act, now in force since January 2005, will allow peopleto access information on PFI and other PPP contracts, including provisions relating to payment terms, incentivemechanisms, performance standards, dispute resolutions, and other procedures. It will also be possible to obtaininformation on evaluations and compliance reports under PFI projects. To help promote the practice of routine disclosure,the World Bank maintains an Infrastructure Contracts & Licenses Database that provides links to government andregulatory agency web sites that contain the main instruments – contracts and licenses – used to regulate public andprivate provision of infrastructure services. This can be found at http://ppi.worldbank.org/icl/
Developing and Strengthening Capacities for PPPs in India
33
institute and/or think tanks, with deliverysupported by a number of regional centersfor PPP training. These could also undertakeoutreach efforts outside of the government.
The development of guidancematerial for PPPs
4.20 Guidance material can offer a number ofbenefits, including more rapidly diffusing goodpractices and lowering transactions costs. Thestandardization of contract clauses can helpreduce both the complexity of PPParrangements and project preparation costs.A number of practitioners in India have alsoargued that the lack of standard contracts orstandard clauses that are approved by thecenter makes bureaucrats more reluctant tosign off on PPP deals.
4.21 Another possible role for the center wouldtherefore be to develop guidance materials tosupport the development and implementationof PPPs. This could cover issues related tocontract design, procedures for identifying,procuring and managing PPPs, and evenmodel PPP legislation.7 It could also covershort guidance notes on focused topics ofinterest. Such notes could be a helpfulcomplement to case studies, allowing for thediscussion of nuances and recommendationsfor differing local contexts.8
4.22 Model contract clauses, template contracts,guidelines and process-related tools have
however already been developed to varyingdegrees by some states and central entities.One option would be to rely on a morenatural diffusion of these approaches withstates copying other approaches held to besuccessful. Although there are examples frominternational practice of detailed guidancebeing provided by the national government –such as in South Africa, for example – in anumber of other countries (for exampleCanada and Australia), the center providesno guidance to sub-national governments.There are also risks that centrally sponsoredmodel contracts can reduce the needed roomfor flexibility and innovation even where thesemodels are advisory and not mandatory.
4.23 Despite these concerns, a central effort toproduce guidance material clauses could leadto the more rapid adoption of good practiceapproaches by states, reducing learning andtransactions costs for private companies andtheir advisors. This is probably true in mostcountries, but will likely be as applicable, ifnot more so, in India where the mechanismsfor sharing information and experiences arestill limited. Some of the risks associated withguidance being seen as mandatory could beaddressed by having guidance indicate a rangeof options wherever appropriate – for exampledifferent options for using particularformulations for contractual clauses, orprocesses or methodologies for estimatingaffordability to the government or value-for-money of a PPP.
7 Model contract clauses —for instance for force majeure, refinancing, termination and dispute resolution— can help injectinternational or national best practice, and avoid each contract re-inventing the wheel. Process-related guidance could concernstep-by-step directions on how to undertake a variety of the tasks required for project preparation, provider selection and contractmanagement, such as how to appoint and manage transaction advisers to the contracting authority, how to prepare an initialbusiness case (demonstrating affordability & market appetite, and the tradeoffs in choosing between traditional procurement andthe variety of PPP options), how to construct a public sector comparator (a benchmark on which to judge the value for money ofbids), how to prepare a value for money report (and clarifying the extent of risk transfer), how to undertake stakeholderconsultations, and how to conduct independent auditing of projects.8 Some of the possible topics that have been suggested as being relevant in India are: how to reduce time from pre-feasibility tocontract award; benefits of concurrent project review by government entities; why it may be better to award part-success fee toadvisers at financial close; how to design an effective first-step pre-arbitration dispute resolution; and why a state may benefit froma dedicated PPP unit and how to set one up.
India: Building Capacities for Public Private Partnerships
34
4.24 This relatively limited role could be led by asingle central agency, though would benefitfrom input and oversight from a public-privateadvisory group to guide where this centraleffort could add most value, and what typesof materials are most needed. On the publicsector side, this should containrepresentatives from state governments as wellas the center. Much of the actual preparationof material should be contracted out toconsultants experienced in the field.
PPP units to provide a pool ofexpertise
4.25 As noted in Section 2, most countries engagedin a broad-based PPP program have felt theneed to develop a cross-sectoral PPP unitalthough the role that this unit plays issometimes restricted to informationdissemination and the preparation of guidancematerial. The design response to two keyissues – the role of a cross-sectoral unit vis-à-vis line ministries and the role of a nationalunit in sub-national PPPs – will be driven bythe business practices within governmentsand the fiscal, and other, relations betweenthe center and the states. This means thatsome models which are more centralized, suchas those in the UK and South Africa wherenational level units have a prominent role insub-national PPPs, will not be workableapproaches in India.
4.26 At the statestatestatestatestate level, a dedicated PPP unit canboth broaden the PPP program bytransferring lessons and experiences acrosssectors, as well as improve the quality of PPPsby bringing to bear better transactions skills.Particularly where there is not a track recordof PPPs, skills are probably best brought infrom the private sector to supplementavailable capacities in the state government.A number of states have done this through apublic-private company, for example
Rajasthan and Karnataka. While this may bea straightforward route for bringing inexpertise, the possible conflicts of interest (seeSection 2) have to be addressed and dealt with.
4.27 A nationalnationalnationalnationalnational PPP unit could undertake theinformation dissemination and guidance rolesdescribed above. It could also usefully playan active role in identifying areas where PPPscould be undertaken by central agencies andministries, and working with these agenciesto conceptualize and bring to the marketindividual PPPs. To do this, it would need theright transactions skills, most likely broughtin from the private sector. There might alsobe concerns that the line agency would, forturf reasons, not work or cooperate with thisunit in the development of its PPPs. Theseconcerns would be reduced both if the unitwas seen to be highly skilled and itscontribution valued, as well as if there wererequirement for the vetting of central agencyPPP proposals by this unit, prior to theirclearance.
4.28 It is not so clear that this unit should have anactive transactions advisory role with respectto state and municipal PPPs, in the manner,for example, that Partnerships UK does. Thiswould directly substitute for the developmentof state-level capacity. It may also bechallenging to do this for a large number ofdeals, and there might need to be some formof prioritization most likely for sectors thathave seen fewer PPP deals in India to date -given the number of PPP road projects doneto date, this might not be a major focus ofthe advice being provided by this unit. Thisunit would however build up state levelcapacities through information disseminationand guidance, and also by furthering thenational level PPP program.
4.29 However, if the center were to provide additionalfunding for PPPs (see below) then this unit could
Developing and Strengthening Capacities for PPPs in India
35
review these PPPs to assess whether thecontractual structure proposed is robust, thatrisks are efficiently allocated and that projectsto be supported by the center are sound. Thisoversight role may eventually develop into aprescriptive role, with states interested inaccessing the central fund having an incentiveto use the national unit’s approaches andrecommendations to increase the likelihood ofacceptance of their project. It would beimportant therefore that if this clearance andoversight is done that the national unit makeclear its guidance and approaches on contractdesign, risk allocation, affordability and value-for-money assessment, and provider selection.
4.30 The two main options for constituting thenational unit are either as a cell or groupwithin an existing ministry or agency, or as acompany, either owned solely by thegovernment or a joint public-private company.The right choice depends in part upon whatrole the unit is to fill. The first option is likelyto be the best approach if it is to play primarilyan information dissemination and guidancerole. Within this set-up, whatevertransactions skills may be needed could besecured through hiring consultants on long-term contracts. The second option would bepreferable were the unit mainly to focus ontransactions and undertake a bigger volumeof deals, as setting it up as a company willfacilitate paying salaries to attract staff withfinancial and legal skills, and make it easier toprovide monetary incentives for closing deals.However, it is likely to take more time toimplement and establish compared to creatinga unit within an existing agency. There is athird possibility, a separate agency or authoritybut this would perhaps not offer the benefitsof speed of establishment and integration withexisting budgeting and approval processesthat a unit within an existing ministry wouldhave, nor the flexibility that a company wouldhave in terms of pay scales and incentives.
4.31 The need for such a unit, and the roles it willplay over the life cycle of PPPs, should beagreed and accepted by both line ministriesand Finance and Planning. Up-front agreementwould help ensure that it serves a well-definedpurpose and at its inception neither isperceived as a threat nor suffers fromunrealistic expectations.
Project development funds
4.32 A number of PPP units manage funds whichdefray some of the costs of developing PPPs(see Table 1 in Section 2). There are twoarguments for the use of these funds. Thefirst is that many governments new to PPPsdo not appreciate the need to spend more onpreparation of PPP projects than was spenton the procurement documents for civil worksprojects in the same sector. The second isthat since PPPs are relatively new, the costsof preparing initial projects may be higher andthat with learning some of these will comedown.
4.33 One important issue is the terms on whichthis fund would be accessed. A purely grant-based fund would maximize chances of uptake,but would bring with it risks that it was notbeing used for priorities. This could bemitigated to some extent by having cleareligibility criteria for accessing thesedevelopment funds – for example in particularpre-specified sectors, or sectors where the stateconcerned had done no previous PPPs, orprojects serving mainly the poor. Havingstates borrow these funds would reduce theneed for this but may negate the rationale forthe funds, as given above. An alternative maybe to have some form of matching grantscheme, with the states providing somefinancing to complement what comes fromthe project development fund. A national PPPunit could oversee the project developmentfund.
India: Building Capacities for Public Private Partnerships
36
Funding of PPPs
4.34 The use of PPPs for the delivery of basicservices by state and municipal governmentswould be stimulated by the provision ofcentral funds to support their payments underPPPs. Any additional funding of PPPs shouldbe complemented by a more rapiddevelopment of capacities to monitor the fiscalcosts of PPPs.
4.35 The detailed design of such a PPP fund,including the type of support, project eligibilitycriteria, selection mechanism and how thequantum of support for a project isdetermined is beyond the scope of this report.A significant effort would have to go into thisto ensure that it is well targeted and efficientlyused. There is considerable experienceinternationally with the use of subsidy fundsfor the expansion of infrastructure servicessuch as telecommunications and power,where government funds complement userfees. These are relatively straightforward, witha competition for funds typically being doneon a minimum subsidy basis, for example pernew connection to be made. A fund thatspans different sectors and also allows fordifferent structures (for example wheregovernments are the sole purchasers of PPPsunder contracts rather than governmentfunds being used to supplement user fees)would be more challenging to implement.Consultation with lenders, sponsors and stategovernments will be an important step inimproving the design whilst at the same timeensuring that key central government concernsare met.
4.36 It will be important to ensure that projectssupported by the fund are priorities for thecontracting governments. A substantialmatching contribution from the state/municipal government contracting for the PPPwould be important to provide commitmentto the project and indicate that the project
was a priority. It would however be importantto clarify what, out of different possible formsof government support (e.g. land grants, taxbreaks, risk-bearing, cash subsidies), wouldrepresent a matching contribution.
4.37 It will be equally important to ensure thatcompetition is used to reduce the demandsfor public funds. It would be far more difficultto size subsidies – and also less transparent– were projects first awarded by stategovernments on the basis of particular criteriaand then subsequently developers approachedthe fund for support. Otherwise a promotercould “low-ball” on the tariffs for a project tosucceed in getting a project awarded, and thenaccess monies from the PPP fund to make upthe difference.
4.38 Project design, risk allocation, affordability andvalue-for-money should also be assessed forthese projects to ensure that the center issupporting well-designed PPPs, as notedabove. This could be done by the central PPPunit – though there might be conflict ofinterest concerns if this unit received a successfee from working on transactions, in whichcase the involvement of others would benecessary in clearances.
Recommendations: a role for thecenter in developing India’s PPPprogram
4.39 There are a number of steps the center cantake to expand the role that PPPs play in basicservice delivery at both the national, state andmunicipal levels. The main components of astrategy to catalyze the broader use of PPPswould be:
A clearly articulated policy statement onthe use of PPPs at the national level,including their rationales and the benefitsexpected, backed up by concrete plans
Developing and Strengthening Capacities for PPPs in India
37
and targets for increasing the use of PPPsin national programs
The creation of a national level PPP unitthat would undertake informationdissemination and guidance functions asdiscussed above, and provide advisorysupport to the central PPP program;
A project development fund to reduce thetransactions costs to state and localgovernments of preparing and bidding outPPPs; and
A fund to partly cover the cost of stateand local government commitments underPPP contracts.
4.40 The primary responsibility for developing stateand municipal level PPPs lies at those levels ofgovernment. The actions outlined above canencourage the development of capacities andPPP programs at sub-national levels, butshould not substitute for needed actions bythe governments contracting for these PPPs.Perhaps most importantly, the scale andquality of the national PPP program providesa model for state and local governments. Thisincludes not just the transactions themselves,but also commitments to disclosure ofagreements and transparency and also theregular ex-post review of PPPs to assess
whether the hoped-for benefits had beenrealized in practice.
4.41 The activities outlined above will need someform of coordinated effort. A PPP unit set upwithin a single ministry or agency with cross-cutting responsibilities, for example Financeor Planning, could readily undertakeinformation dissemination and guidance roles,given budget, staff and oversight. It couldalso provide transactions expertise to a limitedset of projects by buying-in expertise from theprivate sector on long-term consultingcontracts. However, a broader transactionsrole across a range of central agencies andministries and in particular developing sub-national PPPs will require more humanresources. Were these activities to be pursuedon a larger scale then this might better be donethrough a separate authority or companythan a unit within an existing ministry oragency.
4.42 Regardless of whether or not the steps outlinedin para. 4.39 are undertaken, the center shouldwork through existing approaches to improvethe monitoring of the fiscal costs of PPPsentered into by central agencies and stategovernments.
39
SectorSectorSectorSectorSector
UrbanInfrastructure
Airport
UrbanInfrastructure
UrbanInfrastructure
Ports
Ports
Ports
Ports
Railways
Roads
Roads
Roads
Cost (Rs. Mn)Cost (Rs. Mn)Cost (Rs. Mn)Cost (Rs. Mn)Cost (Rs. Mn)
4500
14000
590
7
23418
55478
34415
34000
3730
3300
3780
273
StructureStructureStructureStructureStructure
BOT
BOO
Affermage
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
TTTTTenderenderenderenderender
ICB
ICB
ICB
ICB
Negotiated
Negotiated
ICB
Negotiated
Not Available
Negotiated
Negotiated
Domestic
Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Larsen and Toubro
GMR and Malaysian AirportHolding Berhad
Subhash Projects and MarketingLimited for Central, City andSouth Zone, City Life Lineconsultants for west zone andAnthony waste management forKarol bagh and Sadar pahar GanjZone.
Exel Industries Pvt. Ltd.
Gujarat Pipavav Port Ltd
Gujarat Adani Port Limited
SHELL-ESSAR Consortium; Bid onLand premium and concessionperiod
Petronet LNG Ltd.
Gujarat Pipavav Ports Ltd.(GPPL)and Ministry of Railways
JV of Punj Lloyd Ltd. & IRCONIntl., IL&FS
L&T Ltd.-ECCIL&FS
JMC-Bright-Bharat JV
AWARDED PROJECTS BY STATES & CENTRAL AGENCIES
Agency Agency Agency Agency Agency
APIIC
APTR&B
MunicipalCorporation ofDelhi
MunicipalCorporation ofDelhi
GMB
GMB
GMB
GMB
Ministry of Railway
R&B Dept
R&B Dept
GSRDC
Project NameProject NameProject NameProject NameProject Name
Andhra PradeshVisakhapatnamIndustrial Water SupplyProject
Hyderabad InternationalAirport at Shamshabad
DelhiDelhiDelhiDelhiDelhi
Collection andtransportation ofMunicipal Solid Waste
Compost Plant
GujaratGujaratGujaratGujaratGujarat
Pipavav Port
Mundra Port
Hazira LNG Terminal
Dahej LNG Terminal
Surendranagar MahuvaGauge Conversion(Pipavav RailwayCorporation Ltd PRCL)
Vadodara - Halol Road
Ahmedabad - MehsanaRoad
Deesa-Panthwada-Gundri Road
AnnexesAnnexes
India: Building Capacities for Public Private Partnerships
40
GSRDC
KRDCL /PWD
Bangalore MahanagaraPalike (BMP) withassistance fromInfrastructureSecretary, Governmentof Karnataka
Karnataka RoadDevelopmentCorporation Ltd.
InfrastructureDevelopmentDepartment, Govt. ofKarnataka
Govt of Kerala
ThiruvananthapuramMunicipalCorporation
Public WorksDepartment,Government of Kerala/ Greater CochinDevelopmentAuthority
Railways
Roads
UrbanInfrastructure
Roads
Roads
Airport
UrbanInfrastructure
Roads
270.6
22500
300
2300
200
3030
35
256
BOT
BOT
BOT
BOT
BOT
BOO
BOT
BOT
Domestic
Negotiated
ICB
Domestic
Domestic
NotApplicable
Domestic
Domestic
Ranjit Projects Pvt. Ltd.Mehsana [7 bidders were pre-qualified. 7 purchased RFPdocuments. 2 submitted thebids]
Consortium - NICE (NandiInfrastructure CorridorEnterprises Ltd) - The Kalyanigroup leading with 51 %, itsinternational partners SABInternational and VHBInternational 23 % and FIs ledby the ICICI Bank - 26%
Ramky Infrastructure Ltd.,Hyderabad
Nagarjuna ConstructionCompany Ltd., Hyderabad,RMC Constructions Ltd. &Maytas Ltd.
DS Constructions
10,000 private shareholders,mostly NRIs of Keralite originincl: (1) Geo ElectricalsContracting and Trading CoSharjah, (2) Emke Group,AbuDhabi,(3) Gulfar Group,Oman, (4) Majeed BukataraTrading Dubai
Ramky Infrastructure Ltd.,Hyderabad
Cochin Bridge InfrastructureCompany Ltd./ Gammon IndiaLtd.
ROB - Chhayyapuri Rail
KarnatakaKarnatakaKarnatakaKarnatakaKarnataka
Bangalore-MysoreInfrastructure Corridor
Development ofIntegrated WasteProcessing andEngineered SanitaryLandfills in Bangalore
Four laning ofBangalore-Maddur StateHighway SH-17 underAnnuity Scheme
Development of BypassRoads for Sandur Town,Bellary District underdirect tolling scheme
KeralaKeralaKeralaKeralaKerala
Cochin InternationalAirport
Development ofEngineered SanitaryLandfill in Villapilsala inThiruvananthapuram
Development of NewMattancherry BridgeBuild – Operate –Transfer project inCochin
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Annexes
41
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Madhya PradeshMadhya PradeshMadhya PradeshMadhya PradeshMadhya Pradesh
Bridge on IndoreKhandwa stretch
5 Bridges on IndoreDhar Road
Bridge on BenarasNagpur Road
Bridge on ChindwadaMutkuli Road
Bridge of Satna NagrodBela Road
Bridge on ChindwaraNagpur Road
Bridge on BilaspurMandla Road
Bridge on BalaghatSiwni Road
Bridge on ChindwadaNarsingpur Road
Indore-Sanawad-Burhanpur-EdlabaadRoad
Ujjain-Agar-Susner-Jhalawad Road
Hoshangabad-Harda-Khandwa Road
Rewa-Jaisinghnagar-shahdol-AmarkantakRoad
Satna-Maihar-Tala-Umaria Road
Sagar-Damoh-JabalpurRoad
Jabalpur-Narsinghpur-Pipana Road
Bina-Siranj-Guna Road
Raisen-Rahatgarh Road
Scom-Balaghat-GondiaRoad
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
4.8
15.2
28
4.3
15.1
13.6
9.6
18.1
13.5
1230
651.9
810
1100
542.2
897
741.6
410
577.2
598
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Ayushyaraj constructions
Vinod Kumar ShuklaConstructions
Vinod Kumar ShuklaConstructions
Vinod Kumar ShuklaConstructions
Vinod Kumar ShuklaConstructions
Narmada Constructions
PD Agrawal Constructions
PD Agrawal Constructions
Not Available
M/s VIVA Highways Pvt. Ltd.Nasik
NVS Agroh Infrastructuredevelopers pvt. Ltd.
MSK infrastructure and tollbridge ltd.
Rewa Tollways
Rewa Tollways
MA Jabalpur Corridor India Pvt.
Tapti Prestressed products pvtltd
Bina Sinronj Toll Road Ltd.
MSK
AAP Infrastructure
India: Building Capacities for Public Private Partnerships
42
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Dewas-Ujjain-Badnagar-BadnawarRoad
Hoshangabad-Piparia-Pachmarhi Road
MaharashtraMaharashtraMaharashtraMaharashtraMaharashtra
Maujhi Bridge +Karmala Norma bridge
Kharpada Bridge
Major bridge -Dharamtar Creek
Bridge across Waigangariver
Mumbai - PuneExpressway
Pune Ahmednagar road
Khambatki TunnelN.H.-4
Ahemadnagar KarmalaTembhurni road
Bhiwandi Ambadi Road
Nashik - Niphad -Aurangabad Road
ROB near villageNardana &strengthening existing2-lane pacement fromTapi Bridge
Ambadi - Wada Road
Chinchoti naka KamanPaygaon Bhiwandi road
Vadgaon - Chakan -Shikrapur Road
PunjabPunjabPunjabPunjabPunjab
Up-gradation, operationand maintenance ofAmritsar bus terminal
PWD
PWD
PWD
PWD
PWD
PWD
MSRDC
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PunjabInfrastructureDevelopment Boardwith Punjab PublicWorks Department
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
UrbanInfrastructure
493
598.8
67.5
330
150
325.7
12180
1050
37.8
230
360
146.5
342.1
76.7
113.2
2.2
180
BOT
BOT
BOT
BOT
BOT
BOT
Lease
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
ICB
RV Infrastructure engineers
NVs Chetak Enterprises
Nirman, Nashik
Ideal Road Builders
Patvardhan Infrastructure PvtLtd
Ashoka Buildcom
Ideal Road Builders
Ashoka Buildcom
Ideal Road Builders
Ideal Road Builders
Ideal Road Builders
I.S. Infrastructure & BuildingConstruction (P) Ltd, Nashik
Ayushajay Construction Limited
Ideal Road Builders
Ideal Road Builders
VCR Toll Services Pvt Ltd
Local Contractor (Rohan andRajdeep Builders Limited)
Annexes
43
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
TTTTTamil Naduamil Naduamil Naduamil Naduamil Nadu
East Coast Road
Karur Toll Bridge
Madurai Inner RingRoad
Coimbatore BypassRoad on NH47
Solid wastemanagement inChennai
Tirupur Water SupplyScheme
Alandur (AM)SewerageProject
Uttar PradeshUttar PradeshUttar PradeshUttar PradeshUttar Pradesh
Delhi - Noida TollBridge
TNRDC
Karur Municipality(KM) & Tamil NaduUrban DevelopmentProject (TNUIFSL)
Corporation ofMadurai (COM) &TNUIFSL.
Ministry of SurfaceTransport (MoST) &GoTN
Corporation ofChennai (CoM) &TIDCO.
NTADCL. SPVformed by TamilNadu WaterInvestment Limited- ((TWIL),InfrastructureLeasing & FinancialServices Limited(ILFS) and TirupurExportersAssociation (TEA).
AlandurMunicipality & TamilNadu UrbanDevelopmentProject (TNUIFSL).
New OkhlaIndustrialDevelopmentAuthority (NOIDA),Delhi Government,Government of UP,Government of India.
Roads
Roads
Roads
Roads
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
Roads
600
154.5
430
900
400
1850
400
3900
BOT
BOT
BOT
BOT
Affermage
BOT
BOT
BOT
Domestic
Domestic
NotApplicable
Domestic
ICB
ICB
ICB
ICB
TNRDC awarded the contractthrough competitive bidding toAshoka Buildcon Ltd forconstruction & maintenance.The project engineers forsupervision and monitoringwere awarded on competitivetendering basis to SheladiaAssociates & Consultants.
East Coast Constructions andIndustries Private Limited(ECCI)
Not Decided
L&T TransportationInfrastructure Ltd (LTTIL)
C.G.E.A. Asia Holdings,Singapore was selected throughICB to implement the project.
Consortium - Mahindra, UU,WSA (USA), Design - Bechtel,HCC, L&T; Procurement-HCC,L&T – Construction - HCC, L&T;Supervision- GKW(Germany)/CES; Project Management -WSA (USA); O&M - UnitedUtilities (UK); IndependentEngineer-Pell Frischmann (UK/India
First STP Pvt Ltd, the companyfloated for the project by VATech Wabag Limited (erstwhile,Balcko Duo and WabagTechnologies Ltd., - BDWT) andIVRCL Infrastructures andProjects
Mitsui, Marubeni, KampsaxInternational (Denmark),Intetroll (SA)
India: Building Capacities for Public Private Partnerships
44
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Solid WasteManagement Initiatives
West BengalWest BengalWest BengalWest BengalWest Bengal
Solid WasteManagement
NHAINHAINHAINHAINHAI
Maharashtra Border -Belgaum Road
Nellore By-Pass
Nellore- TADA Road
Tumkur-NeelmangalaRoad
Nandigama - VijaywadaRoad
Mahapura - Kishangarh,6 lane
Satara - Kagal Road
Ankapalli- Tuni Road
Tuni- DharamavaramRoad
Dharmavaram -Rajahmundry Road
Panahgarh Palsit Road
Palsit-Dankuni Road
Vivekananda Bridge
Delhi - Gurgaon Road
Tambaram - TindivanamRoad
Greater New OkhlaIndustrialDevelopmentAuthority(GNOIDA)
Haldia DevelopmentAuthority (HAD).
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
UrbanInfrastructure
UrbanInfrastructure
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
13.5
540
3320
1432
6213.5
1550
1386.5
6440
6000
2832
2319
2060
3500
4324
6410
5550
3750
Affermage
BOO
Annuity
Annuity
BOT
BOT
BOT
BOT
BOT
Annuity
Annuity
Annuity
Annuity
Annuity
BOT
BOT
Annuity
ICB
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Antony Waste Handling Cell isthe solid waste managementdivision of Antony MotorsPrivate Limited
Ramky Enviro Engineers Limited(REEL)
North Karnataka ExpresswayPrivate Limited (IL and FS andPunj Loyd)
Soma enterprises and NavayugEng co Ltd
CIDB ( Malaysia)
Jas Toll Road co Ltd (Consortiumof Jayaswals and - AshokaBuildcon SERI International
CIDB (Malaysia)
GVK International-BSCPL
MSRDC Ltd
GMR - Tuni - Ankapalli ExpressLtd
Andhra Expressway Ltd
Rajamundry Expressway Ltd -Gammon (JV)
Gamuda Malaysia - WCT(Malaysia)
Gamuda and WCT (Malaysia)
SVBTG Consortium of AIDCgroup (USA), STRADC(Phillipines)
Jaiprakash Industries Limited -DS Constt Ltd
Tambaram - TindivanamExpressway Pvt Ltd (consortiumof GMR and UE Malaysia)
Annexes
45
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Pune - Khed Road
MOSRTHMOSRTHMOSRTHMOSRTHMOSRTH
International ContainerTranshipment Terminal,Vallarpadam
JNPT - 2nd containerterminal
JNPT - 3rd containerterminal
Chennai ContainerTerminal
NHAI
Cochin Port Trust
JNPT
JNPT
Chennai Port Trust(CPT)
Roads
Ports
Ports
Ports
Ports
1276
21180
7000
9000
4000
BOT
BOT
BOT
BOT
BOT
Domestic
ICB
ICB
ICB
Limited Tender
ATR Infrastructure Pvt Ltd
Dubai Ports International
P&O Ports
Maersk and Concor JV
CCTL is a special purposevehicle created by P&O to runthe Chennai ContainerTerminal (CCT) for 30 years.
India: Building Capacities for Public Private Partnerships
46
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
AirportsAirportsAirportsAirportsAirports
Hyderabad InternationalAirport at Shamshabad
Cochin InternationalAirport
PortsPortsPortsPortsPorts
Pipavav Port
Mundra Port
Hazira LNG Terminal
Dahej LNG Terminal
International ContainerTranshipment Terminal,Vallarpadam
JNPT - 2nd containerterminal
JNPT - 3rd containerterminal
Chennai ContainerTerminal
RailwaysRailwaysRailwaysRailwaysRailways
Surendranagar MahuvaGauge Conversion(Pipavav RailwayCorporation Ltd PRCL)
ROB - Chhayyapuri Rail
APTR&B
Govt of Kerala
GMB
GMB
GMB
GMB
Cochin Port Trust
JNPT
JNPT
Chennai Port Trust(CPT)
Ministry of Railway
GSRDC
Airport
Airport
Ports
Ports
Ports
Ports
Ports
Ports
Ports
Ports
Railways
Railways
14000
3030
23418
55478
34415
34000
21180
7000
9000
4000
3730
270.6
BOO
BOO
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
ICB
NotApplicable
Negotiated
Negotiated
ICB
Negotiated
ICB
ICB
ICB
LimitedTender
Not Available
Domestic
GMR and Malaysian AirportHolding Berhad
10,000 private shareholders,mostly NRIs of Keralite originincl: (1) Geo ElectricalsContracting and Trading CoSharjah, (2) Emke Group,AbuDhabi,(3) Gulfar Group,Oman, (4) Majeed BukataraTrading Dubai
Gujarat Pipavav Port Ltd
Gujarat Adani Port Limited
SHELL-ESSAR Consortium; Bidon Land premium and concessionperiod
Petronet LNG Ltd.
Dubai Ports International
P&O Ports
Maersk and Concor JV
CCTL is a special purpose vehiclecreated by P&O to run theChennai Container Terminal(CCT) for 30 years.
Gujarat Pipavav Ports Ltd.(GPPL)and Ministry of Railways
Ranjit Projects Pvt. Ltd. Mehsana[7 bidders pre-qualified, 7purchased RFP documents, 2submitted bids]
AWARDED PROJECTS BY SECTOR
Annexes
47
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
RoadsRoadsRoadsRoadsRoads
Vadodara - Halol Road
Ahmedabad - MehsanaRoad
Deesa-Panthwada-Gundri Road
Bangalore-MysoreInfrastructure Corridor
Maujhi Bridge +Karmala Norma bridge
Kharpada Bridge
Major bridge -Dharamtar Creek
Bridge acrossWaiganga river
Mumbai - PuneExpressway
Pune Ahmednagarroad
Khambatki TunnelN.H.-4
Ahemadnagar KarmalaTembhurni road
Bhiwandi AmbadiRoad
Nashik - Niphad -Aurangabad Road
ROB near villageNardana &strengthening existing2-lane pacement fromTapi Bridge
Ambadi - Wada Road
R&B Dept
R&B Dept
GSRDC
KRDCL /PWD
PWD
PWD
PWD
PWD
MSRDC
PWD
PWD
PWD
PWD
PWD
PWD
PWD
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
3300
3780
273
22500
67.5
330
150
325.7
12180
1050
37.8
230
360
146.5
342.1
76.7
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
Lease
BOT
BOT
BOT
BOT
BOT
BOT
BOT
Negotiated
Negotiated
Domestic
Negotiated
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
JV of Punj Lloyd Ltd. & IRCONIntl., IL&FS
L&T Ltd.-ECCIL&FS
JMC-Bright-Bharat JV
Consortium - NICE (NandiInfrastructure CorridorEnterprises Ltd) - The Kalyanigroup leading with 51%, itsinternational partners SAB Intland VHB Intl 23% and FIs led bythe ICICI Bank – 26%
Nirman, Nashik
Ideal Road Builders
Patvardhan Infrastructure PvtLtd
Ashoka Buildcom
Ideal Road Builders
Ashoka Buildcom
Ideal Road Builders
Ideal Road Builders
Ideal Road Builders
I.S. Infrastructure & BuildingConstruction (P) Ltd, Nashik
Ayushajay Construction Limited
Ideal Road Builders
India: Building Capacities for Public Private Partnerships
48
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Chinchoti naka KamanPaygaon Bhiwandi road
Vadgaon - Chakan -Shikrapur Road
Bridge on IndoreKhandwa stretch
5 Bridges on IndoreDhar Road
Bridge on BenarasNagpur Road
Bridge on ChindwadaMutkuli Road
Bridge of Satna NagrodBela Road
Bridge on ChindwaraNagpur Road
Bridge on BilaspurMandla Road
Bridge on BalaghatSiwni Road
Bridge on ChindwadaNarsingpur Road
Indore-Sanawad-Burhanpur-EdlabaadRoad
Ujjain-Agar-Susner-Jhalawad Road
Hoshangabad-Harda-Khandwa Road
Rewa-Jaisinghnagar-shahdol-AmarkantakRoad
Satna-Maihar-Tala-Umaria Road
Sagar-Damoh-JabalpurRoad
Jabalpur-Narsinghpur-Pipana Road
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
PWD
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
113.2
2.2
4.8
15.2
28
4.3
15.1
13.6
9.6
18.1
13.5
1230
651.9
810
1100
542.2
897
741.6
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Ideal Road Builders
VCR Toll Services Pvt Ltd
Ayushyaraj constructions
Vinod Kumar ShuklaConstructions
Vinod Kumar ShuklaConstructions
Vinod Kumar ShuklaConstructions
Vinod Kumar ShuklaConstructions
Narmada Constructions
PD Agrawal Constructions
PD Agrawal Constructions
Not Available
M/s VIVA Highways Pvt. Ltd.Nasik
NVS Agroh Infrastructuredevelopers pvt. Ltd.
MSK infrastructure and tollbridge ltd.
Rewa Tollways
Rewa Tollways
MA Jabalpur Corridor India Pvt.Ltd.
Tapti Prestressed products pvtltd
Annexes
49
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Bina-Siranj-Guna Road
Raisen-RahatgarhRoad
Scom-Balaghat-GondiaRoad
Dewas-Ujjain-Badnagar-BadnawarRoad
Hoshangabad-Piparia-Pachmarhi Road
Maharashtra Border -Belgaum Road
Nellore By-Pass
Nellore- TADA Road
Tumkur-NeelmangalaRoad
Nandigama -Vijaywada Road
Mahapura -Kishangarh, 6 lane
Satara - Kagal Road
Ankapalli- Tuni Road
Tuni- DharamavaramRoad
Dharmavaram -Rajahmundry Road
Panahgarh Palsit Road
Palsit-Dankuni Road
Vivekananda Bridge
Delhi - Gurgaon Road
PWD
PWD
PWD
PWD
PWD
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
410
577.2
598
493
598.8
3320
1432
6213.5
1550
1386.5
6440
6000
2832
2319
2060
3500
4324
6410
5550
BOT
BOT
BOT
BOT
BOT
Annuity
Annuity
BOT
BOT
BOT
BOT
BOT
Annuity
Annuity
Annuity
Annuity
Annuity
BOT
BOT
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Bina Sinronj Toll Road Ltd.
MSK
AAP Infrastructure
RV Infrastructure engineers
NVs Chetak Enterprises
North Karnataka ExpresswayPrivate Limited (IL and FS andPunj Loyd)
Soma enterprises and NavayugEng co Ltd
CIDB ( Malaysia)
Jas Toll Road co Ltd(Consortium of Jayaswals and- Ashoka Buildcon SERI Intl
CIDB (Malaysia)
GVK International-BSCPL
MSRDC Ltd
GMR - Tuni – Ankapalli ExpressLtd
Andhra Expressway Ltd
Rajamundry Expressway Ltd -Gammon (JV)
Gamuda Malaysia - WCT(Malaysia)
Gamuda and WCT (Malaysia)
SVBTG Consortium of AIDCgroup (USA), STRADC(Phillipines)
Jaiprakash Industries Limited -DS Constt Ltd
India: Building Capacities for Public Private Partnerships
50
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Tambaram - TindivanamRoad
Pune - Khed Road
East Coast Road
Karur Toll Bridge
Madurai Inner RingRoad
Coimbatore BypassRoad on NH47
Delhi - Noida TollBridge
Development of NewMattancherry BridgeBuild – Operate –Transfer project inCochin
Four laning ofBangalore-MaddurState Highway SH-17under Annuity Scheme
Development of BypassRoads for Sandur Town,Bellary District underdirect tolling scheme
Urban InfrastructureUrban InfrastructureUrban InfrastructureUrban InfrastructureUrban Infrastructure
VisakhapatnamIndustrial Water SupplyProject
NHAI
NHAI
TNRDC
Karur Municipality(KM) & Tamil NaduUrban DevelopmentProject (TNUIFSL)
Corporation ofMadurai (COM) &TNUIFSL.
Ministry of SurfaceTransport (MoST) &GoTN
New Okhla IndustrialDevelopmentAuthority (NOIDA),Delhi Government,Government of UP,Government of India.
Public WorksDepartment,Government of Kerala/ Greater CochinDevelopmentAuthority
Karnataka RoadDevelopmentCorporation Ltd.
InfrastructureDevelopmentDepartment, Govt. ofKarnataka
APIIC
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
UrbanInfrastructure
3750
1276
600
154.5
430
900
3900
256
2300
200
4500
Annuity
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
Domestic
Domestic
Domestic
Domestic
Not Applicable
Domestic
ICB
Domestic
Domestic
Domestic
ICB
Tambaram - TindivanamExpressway Pvt Ltd (consortiumof GMR and UE Malaysia)
ATR Infrastructure Pvt Ltd
TNRDC awarded the contractthrough competitive bidding toAshoka Buildcon Ltd forconstruction & maintenance. Theproject engineers for superv. &monitoring were awarded oncompetitive tendering basis toSheladia Associates &Consultants
East Coast Constructions andIndustries Private Limited (ECCI)
Not Decided
L&T Transportation InfrastructureLtd (LTTIL)
Mitsui, Marubeni, KampsaxInternational (Denmark), Intetroll(SA)
Cochin Bridge InfrastructureCompany Ltd./ Gammon India Ltd.
Nagarjuna ConstructionCompany Ltd., Hyderabad, RMCConstructions Ltd. & Maytas Ltd.
DS Constructions
Larsen and Toubro
Annexes
51
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Private contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developerPrivate contractor/developer
Collection andtransportation ofMunicipal Solid Waste
Compost Plant
Up-gradation, operationand maintenance ofAmritsar bus terminal
Solid wastemanagement in Chennai
Tirupur Water SupplyScheme
Alandur (AM)SewerageProject
Solid WasteManagement Initiatives
Solid WasteManagement
Development ofEngineered SanitaryLandfill in Villapilsala inThiruvananthapuram
Development ofintegrated WasteProcessing andEngineered SanitaryLandfills in Bangalore
MunicipalCorporation of Delhi
MunicipalCorporation of Delhi
Punjab InfrastructureDevelopment Boardwith Punjab PublicWorks Department
Corporation ofChennai (CoM) &TIDCO.
NTADCL. SPV formedby Tamil Nadu WaterInvestment Limited -((TWIL),InfrastructureLeasing & FinancialServices Limited(ILFS) and TirupurExportersAssociation (TEA).
Alandur Municipality& Tamil Nadu UrbanDevelopment Project(TNUIFSL).
Greater New OkhlaIndustrialDevelopmentAuthority(GNOIDA)
Haldia DevelopmentAuthority (HAD).
ThiruvananthapuramMunicipalCorporation
Bangalore MahanagaraPalike (BMP) withassistance fromInfrastructureSecretary, Governmentof Karnataka
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
590
7
180
400
1850
400
13.5
540
35
300
Affermage
BOT
BOT
Affermage
BOT
BOT
Affermage
BOO
BOT
BOT
ICB
ICB
ICB
ICB
ICB
ICB
ICB
Domestic
Domestic
ICB
Subhash Projects and MarketingLtd for Central, City and SouthZone, City Life Line consultantsfor west zone and Anthonywaste management for Karolbagh and Sadar pahar Ganj Zone.
Exel Industries Pvt. Ltd.
Local Contractor (Rohan andRajdeep Builders Limited)
C.G.E.A. Asia Holdings,Singapore was selected throughICB to implement the project.
Consortium - Mahindra, UU,WSA (USA), Design - Bechtel,HCC, L&T; Procurement-HCC,L&T – Construction - HCC, L&T;Supervision- GKW(Germany)/CES; Project Management - WSA(USA); O&M - United Utilities(UK); Independent Engineer-PellFrischmann (UK/ India
First STP Pvt Ltd, the companyfloated for the project by VA TechWabag Limited (erstwhile, BalckoDuo and Wabag Technologies Ltd.,- BDWT) and IVRCL Infrastructuresand Projects
Antony Waste Handling Cell isthe solid waste managementdivision of Antony MotorsPrivate Limited
Ramky Enviro Engineers Limited(REEL)
Ramky Infrastructure Ltd.,Hyderabad
Ramky Infrastructure Ltd.,Hyderabad
India: Building Capacities for Public Private Partnerships
52
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/developerdeveloperdeveloperdeveloperdeveloper
Andhra PradeshAndhra PradeshAndhra PradeshAndhra PradeshAndhra Pradesh
Gangavaram Port
Krishnapatnam Port
Development ofHyderabad InternationalAirport Rail link
GujaratGujaratGujaratGujaratGujarat
Positra Port
Mundra-PortGandhidham MissingLink (Adipur MundraPort Railway Link AMPL)
Himmatnagar Bypass
Kim-Mandvi Road
KarnatakaKarnatakaKarnatakaKarnatakaKarnataka
Bangalore InternationalAirport
Development of AirportRail Link to newBangalore airport
Development ofToranagallu Roads
Rehabilitation,Operation andManagement of WaterSupply in SelectedDemonstration Zones inBelgaum, Gulbarga andHubli – DharwadMunicipal Corporationsunder World Bankassisted KUWASIP
Development of ModernPrivate Bus Terminal atKalasipalyam, Bangalore
APIIC
APTR&B
Government ofAndhra Pradesh,Ministry of Railways
GMB
Ministry of Railway
GSRDC
GSRDC
KSIIDC
Government ofKarnataka, Ministryof Railways
InfrastructureDevelopmentDepartment, Govt.of Karnataka
Government ofKarnataka KUIDFC /World Bank
BangaloreMahanagara Palike
Ports
Ports
Roads
Ports
Railways
Roads
Roads
Airport
Railways
Roads
UrbanInfrastructure
UrbanInfrastructure
16000
10000
To be finalised
38880
1600
83.5
270
16000
5300
100
620
300
BOT
BOT
To befinalised
BOT
BOT
BOT
BOT
BOO
BOT
BOT
Affermage
BOT
ICB
ICB
To be finalised
ICB
NotApplicable
Domestic
Domestic
ICB
To be finalised
Domestic
ICB
Domestic
Selection of Bidder on ICB basis: DVS Raju, Dubai PortInternational
NATCO Pharma
GPPL
Gujarat Adani Ports Limited(GAPL)
Not Decided
Not Applicable
Siemens Project Ventures,Germany 40%, Unique Airport,Zurich 17%, L&T 17%, KSIIDC13% and AAI 13%
To be finalized
Technical Studies underway
Compagnie Generale Des Eaux,France
Ramky Infrastructure Ltd.
PROJECT PIPELINE BY STATES & CENTRAL AGENCIES
Annexes
53
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/developerdeveloperdeveloperdeveloperdeveloper
Development ofInertisation and Landfillfacilities in Urban LocalBodies in 8 towns
Development ofModern Private BusTerminal atChannapatna
Development of anIntegrated Bus Terminalat Shimoga
Development of TruckTerminal at Toranagallu,Bellary
KeralaKeralaKeralaKeralaKerala
Vizhinjam PortInternational
Capacity Augmentationof Kottayam-Nedumbassery Road
Madhya PradeshMadhya PradeshMadhya PradeshMadhya PradeshMadhya Pradesh
Dewas Industrial watersupply project
MaharashtraMaharashtraMaharashtraMaharashtraMaharashtra
Multi-Purpose Terminal
Rewas Greenfield Port
Dighi Port
MTHL Road
Thane - Ghodbunderroad
Andheri - GhatkoparELRT
DMA / RespectiveUrban Local Bodies
KUIDFC
DMA, Shimoga CityMunicipality, KSRTC
InfrastructureDevelopmentDepartment, Govt.of Karnataka
Ministry of Ports,GoK
PWD, Kerala
Madhya PradeshState IndustrialDevelopmentCorporation Ltd.
MMB
MMB
MMB
MSRDC
MSRDC
MMRDA
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
Ports
Roads
UrbanInfrastructure
Ports
Ports
Ports
Roads
Roads
UrbanInfrastructure
200
23
100
To be finalised
40000
800
Not Available
250
43230
6070
39999
50
12000
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
Domestic
Domestic
Domestic
Domestic
ICB
Domestic
Domestic
NotApplicable
Negotiated
Negotiated
ICB
Domestic
ICB
Bidding in progress
Bid process to commence
Documentation for bid processunderway
Technical Studies underway
7 private palyers in the fray: Hili(Malta), Beckett Rankine (UK),Port Cons International (SAfrica), Afcons(Mumbai), L&TChennai, Adani Ports(Ahmedabad) and GammonIndia (Mumbai).
To be finalised
Not Decided
Great White Marine Services,Mumbai
Amma Lines
Balaji Leasing & Financial Ltd
Currently at RFQ stage
Not Decided
Not Decided
India: Building Capacities for Public Private Partnerships
54
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/developerdeveloperdeveloperdeveloperdeveloper
Water TransportServices - Mumbai
OrissaOrissaOrissaOrissaOrissa
Dhamra Port
Gopalpur Port
Paradip port iron oreberth
Palaspanga-BamberiRoad
Joda-BamberiRoad(Expressway-II)
Narangpur-Pandapara-HarichandanpurRoad(MDR-12A &ODR)
Tomka-Mangalpur Road
PunjabPunjabPunjabPunjabPunjab
Road projects on BOTbasis in the state ofPunjab
Up-gradation,operation andmaintenance ofLudhiana bus terminal
TTTTTamil Naduamil Naduamil Naduamil Naduamil Nadu
Sea Water DesalinationPlant
MSRDC
Department ofCommerce andTransport, GoO
Department ofCommerce andTransport, GoO
Paradip Port Trust
Works Deprtament,GoO
Works Deprtament,GoO
Works Deprtament,GoO
Works Deprtament,GoO
PunjabInfrastructureDevelopment Boardwith Punjab HealthSystem Corporation
PunjabInfrastructureDevelopment Boardwith Punjab PublicWorks Department
ChennaiMetropolitan WaterSupply & SewerageBoard (CMWSSB)
UrbanInfrastructure
Ports
Ports
Ports
Roads
Roads
Roads
Roads
Roads
UrbanInfrastructure
UrbanInfrastructure
6000
17000
12000
4499
223
241
152
271
Not available
Not available
NotApplicable
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
Domestic
Negotiated
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
Satyagiri Shipping
L&T had floated an SPV (ISPL)along with 2 foreign promoters.However, due to delays bothPrecious Shipping of Thailandand SSA of the USA havewalked out and now Tata Steelis joining hands with L&T todevelop the project.
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not applicable
Not applicable
Not Decided
Annexes
55
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/developerdeveloperdeveloperdeveloperdeveloper
Uttar PradeshUttar PradeshUttar PradeshUttar PradeshUttar Pradesh
Taj Expressway highway
West BengalWest BengalWest BengalWest BengalWest Bengal
Kulpi Port
Logistics Hub
MOSRTHMOSRTHMOSRTHMOSRTHMOSRTH
Ennore terminal
RVNLRVNLRVNLRVNLRVNL
Delhi - Rewari Rail
Ajmer-Phulera-Ringus-Rewari Rail
Vallarpadam - IdapallyRail
Hastavaram-Krishnapatnam Rail
Surat- Hajira Rail
Bharuch – Samni -Dahej Rail
Cuddalore–Salem viaVridhachalam Rail
Tuglakabad – Dadri ICD
Thanjavur - VillupuramRail
Jn. Cabin-Palwal Rail
Haridaspur-ParadeepRail
Hospet-Guntakal Rail
Greater New OkhlaIndustrialDevelopmentAuthority(GNOIDA)
Bengal Port Limited(BPL)
KolkataMetropolitanDevelopmentAuthority (KMDA)
Ennore Port Trust(EPT)
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
Roads
Ports
UrbanInfrastructure
Ports
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
16500
17000
Not Applicable
3500
1400
3520
1030
3900
800
1300
1990
5720
2310
2100
3450
1540
BOT
BOT
BOT
BOT
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
ICB
Negotiated
Domestic
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
The Jaypee Group (earlier knownas Jaiprakash Associates).
P&O Ports is the world leaderin cargo handling and portmanagement servicesthroughout the world.
Not Decided
Project is yet to awarded
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
India: Building Capacities for Public Private Partnerships
56
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/developerdeveloperdeveloperdeveloperdeveloper
AirportsAirportsAirportsAirportsAirports
Bangalore InternationalAirport
PortsPortsPortsPortsPorts
Gangavaram Port
Krishnapatnam Port
Positra Port
Vizhinjam PortInternational
Multi-Purpose Terminal
Rewas Greenfield Port
Dighi Port
Dhamra Port
Gopalpur Port
Paradip port iron oreberth
Kulpi Port
KSIIDC
APIIC
APTR&B
GMB
Ministry of Ports,GoK
MMB
MMB
MMB
Department ofCommerce andTransport, GoO
Department ofCommerce andTransport, GoO
Paradip Port Trust
Bengal Port Limited(BPL)
Airport
Ports
Ports
Ports
Ports
Ports
Ports
Ports
Ports
Ports
Ports
Ports
16000
16000
10000
38880
40000
250
43230
6070
17000
12000
4499
17000
BOO
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
ICB
ICB
ICB
ICB
ICB
NotApplicable
Negotiated
Negotiated
Negotiated
ICB
ICB
Negotiated
Siemens Project Ventures,Germany 40%, Unique Airport,Zurich 17%, L&T 17%, KSIIDC13% and AAI 13%
Selection of Bidder on ICB basis :DVS Raju, Dubai PortInternational
NATCO Pharma
GPPL
7 private palyers in the fray: Hili(Malta), Beckett Rankine (UK),Port Cons International (SAfrica), Afcons(Mumbai), L&TChennai, Adani Ports(Ahmedabad) and GammonIndia (Mumbai).
Great White Marine Services,Mumbai
Amma Lines
Balaji Leasing & Financial Ltd
L&T had floted an SPV (ISPL)alongwith Precious Shipping ofThailand and SSA of USA to takeup the development of theproject. Howvere, due to delaysboth the foreign promoters havewalked out and now Tata Steel isjoining hands with L&T todevelop the pr
Not Decided
Not Decided
P&O Ports is the world leader incargo handling and portmanagement servicesthroughout Europe and UnitedStates, South America, Asia,
PROJECT PIPELINE BY SECTOR
Annexes
57
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/developerdeveloperdeveloperdeveloperdeveloper
Ennore terminal
RailwaysRailwaysRailwaysRailwaysRailways
Mundra-PortGandhidham MissingLink (Adipur MundraPort Railway LinkAMPL)
Delhi - Rewari Rail
Ajmer-Phulera-Ringus-Rewari Rail
Vallarpadam – IdapallyRail
Hastavaram-Krishnapatnam Rail
Surat- Hajira Rail
Bharuch – Samni -Dahej Rail
Cuddalore–Salem viaVridhachalam Rail
Tuglakabad – DadriICD
Thanjavur - VillupuramRail
Jn. Cabin-Palwal Rail
Haridaspur-ParadeepRail
Hospet-Guntakal Rail
Development ofAirport Rail Link tonew Bangalore airport
RoadsRoadsRoadsRoadsRoads
Himmatnagar Bypass
Ennore Port Trust(EPT)
Ministry of Railway
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
RVNL
Government ofKarnataka, Ministryof Railways
GSRDC
Ports
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Railways
Roads
3500
1600
1400
3520
1030
3900
800
1300
1990
5720
2310
2100
3450
1540
5300
83.5
BOT
BOT
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
BOT
BOT
ICB
NotApplicable
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
ICB
To be finalised
Domestic
Africa and Australia. They areheadquartered in London with27 container terminals andlogistic operations in over100 p
Project is yet to awarded
Gujarat Adani Ports Limited(GAPL)
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
To be finalized
Not Decided
India: Building Capacities for Public Private Partnerships
58
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/developerdeveloperdeveloperdeveloperdeveloper
Kim-Mandvi Road
MTHL Road
Thane - Ghodbunderroad
Palaspanga-BamberiRoad
Joda-BamberiRoad(Expressway-II)
Narangpur-Pandapara-HarichandanpurRoad(MDR-12A &ODR)
Tomka-Mangalpur Road
Road projects on BOTbasis in the state ofPunjab
Taj Expressway highway
Capacity Augmentationof Kottayam-Nedumbassery Road
Development ofToranagallu Roads
Development ofHyderabad InternationalAirport Rail link
Urban InfrastructureUrban InfrastructureUrban InfrastructureUrban InfrastructureUrban Infrastructure
Andheri - GhatkoparELRT
Water TransportServices - Mumbai
Dewas Industrial watersupply project
GSRDC
MSRDC
MSRDC
Works Deprtament,GoO
Works Deprtament,GoO
Works Deprtament,GoO
Works Deprtament,GoO
Punjab InfrastructureDevelopment Boardwith Punjab HealthSystem Corporation
Greater New OkhlaIndustrialDevelopmentAuth.(GNOIDA)
PWD, Kerala
InfrastructureDevelopmentDepartment, Govt. ofKarnataka
Government ofAndhra Pradesh,Ministry of Railways
MMRDA
MSRDC
Madhya PradeshState IndustrialDevelopmentCorporation Ltd.
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
Roads
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
270
39999
50
223
241
152
271
Not available
16500
800
100
To be finalised
12000
6000
Not Available
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
BOT
To befinalised
BOT
BOT
BOT
Domestic
ICB
Domestic
ICB
ICB
ICB
ICB
ICB
ICB
Domestic
Domestic
To be finalised
ICB
Domestic
Domestic
Not Applicable
Currently at RFQ stage
Not Decided
Not Decided
Not Decided
Not Decided
Not Decided
Not applicable
The Jaypee Group (earlierknown as JaiprakashAssociates).
To be finalized
Technical Studies underway
Not Decided
Satyagiri Shipping
Not Decided
Annexes
59
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/Likely Private contractor/developerdeveloperdeveloperdeveloperdeveloper
Up-gradation,operation andmaintenance ofLudhiana bus terminal
Sea Water DesalinationPlant
Logistics Hub
Rehabilitation,Operation andManagement of WaterSupply in SelectedDemonstration Zonesin Belgaum, Gulbargaand Hubli – DharwadMunicipal Corporationsunder World Bankassisted KUWASIP
Development ofModern Private BusTerminal atKalasipalyam,Bangalore
Development ofInertisation and Landfillfacilities in Urban LocalBodies in 8 towns
Development ofModern Private BusTerminal atChannapatna
Development of anIntegrated Bus Terminalat Shimoga
Development of TruckTerminal at Toranagallu,Bellary
PunjabInfrastructureDevelopment Boardwith Punjab PublicWorks Department
ChennaiMetropolitan WaterSupply & SewerageBoard (CMWSSB)
KolkataMetropolitanDevelopmentAuthority (KMDA)
Government ofKarnataka KUIDFC /World Bank
BangaloreMahanagara Palike
DMA / RespectiveUrban Local Bodies
KUIDFC
DMA, Shimoga CityMunicipality, KSRTC
InfrastructureDevelopmentDepartment, Govt.of Karnataka
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
UrbanInfrastructure
Not available
NotApplicable
NotApplicable
620
300
200
23
100
To befinalised
BOT
BOT
BOT
Affermage
BOT
BOT
BOT
BOT
BOT
ICB
ICB
Domestic
ICB
Domestic
Domestic
Domestic
Domestic
Domestic
Not applicable
Not Decided
Not Decided
Compagnie Generale Des Eaux,France
Ramky Infrastructure Ltd.
Bidding in progress
Bid process to commence
Documentation for bid processunderway
Technical Studies underway
India: Building Capacities for Public Private Partnerships
60
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Reason for abandonmentReason for abandonmentReason for abandonmentReason for abandonmentReason for abandonment
Andhra PradeshAndhra PradeshAndhra PradeshAndhra PradeshAndhra Pradesh
Development of SpecialTransport Corridor
Sewage , Urban RoadManagement, WaterSupply Management
Krishna Water SupplyProject
GujaratGujaratGujaratGujaratGujarat
Maroli Port
Dholera Port
Simar
Mithivirdi
Vansiborsi
Bedi
Jamnagar - Vadinar Road
Bharuch - Dahej Road
Savli ROB
APIIC
VisakhapatnamMunicipalCorporation
HMWSSB
GMB
GMB
GMB
GMB
GMB
GMB
GSRDC
GSRDC
GSRDC
Roads
UrbanInfrastructure
UrbanInfrastructure
Ports
Ports
Ports
Ports
Ports
Ports
Roads
Roads
Roads
Not available
Not available
8,200
10378
7500
20720
5034
2749
29050
2200
2400
130
BOT
BOT
NotApplicable
BOOT
BOOT
BOOT
BOOT
BOOT
BOOT
BOOT
BOT
BOT
NotApplicable
NotApplicable
Domestic
ICB
NotApplicable
ICB
ICB
ICB
ICB
Domestic
Domestic
Domestic
The project is connected withSEZ development and will takeoff only after SEZ development
Change in the Commissioner(the lead implementingposition)
Private operator offered muchhigher price (Rs42/k. litre) whilethe price of HMWSSB wasabout Rs. 3/ k. litre domesticand about Rs. 10/ k.litre forindustrial customer at that time
LOI has been forfeitted. The porthas been put up for rebiddingand EOI has been invited. Localagitations be fishermen createdproblems for the project
No good offers received in 2004
No good offers received in 2004
No good offers received in 2004
No good offers received in 2004
No good offers received in 2004
None submitted bid. Due toRPPL deciding to transportusing pipelines, the liquid cargotraffic was gone. Along witheconomic recession, this proveddisadvantageous to the project.
Private developers found it nonprofitable
Concession period quoted in therange of 21.5 years to 23 years,which was found to be too high.Therefore, bidding cancelled andproject development to beexplored again when traffic levelgoes up.
ABANDONED PROJECTS
Annexes
61
Project NameProject NameProject NameProject NameProject Name AgencyAgencyAgencyAgencyAgency SectorSectorSectorSectorSector Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.)Cost (Rs. Mn.) StructureStructureStructureStructureStructure TTTTTenderenderenderenderender Reason for abandonmentReason for abandonmentReason for abandonmentReason for abandonmentReason for abandonment
KarnatakaKarnatakaKarnatakaKarnatakaKarnataka
Elevated Light RailTransit System
PunjabPunjabPunjabPunjabPunjab
Privatisation ofS u p e r r s p e c i a l i t yfacilities in Amritsarand Bhatinda
West BengalWest BengalWest BengalWest BengalWest Bengal
Vivekanand FlyoverProject
BMRTL
ExecutingGovernmentAgency
Department ofTransport, Govt. ofWest Bengal
UrbanInfrastructure
Health
Roads
25,000
Not available
650
BOOT
BOT
BOT
ICB
ICB
Domestic
Project not functional - UBTransit Systems Team has beenasked to opt for VRA
Lack of political support andagitation from the public ledto withdrawal of two bidders.
Problem in evacuating the landbelow the flyover which in theconcession agreement was tobe given to the operator fordevelopment
India: Building Capacities for Public Private Partnerships
62
INST
ITU
TIO
NA
L FR
AM
EWO
RK
: S
ELEC
TED
STA
TES
& C
ENTR
AL
AG
ENC
IES
Stat
e/ a
genc
ySt
ate/
age
ncy
Stat
e/ a
genc
ySt
ate/
age
ncy
Stat
e/ a
genc
y
Guj
arat
And
hra
Prad
esh
Mad
hya
Prad
esh
Mah
aras
htra
Tam
il N
adu
Wes
t Ben
gal
Lega
lLe
gal
Lega
lLe
gal
Lega
lFr
amew
ork
Fram
ewor
kFr
amew
ork
Fram
ewor
kFr
amew
ork
Guj
arat
Infra
stru
ctur
eDe
velo
pmen
tA
ct, 1
999
AP
–In
frast
ruct
ure
Deve
lopm
ent
Enab
ling
Act
2001
For s
elec
tse
ctor
s, e
g- M
.P.H
ighw
ay B
ill20
01;
Gove
rnm
ent
Ord
ers
for R
oad
and
Port
Sec
tors
.M
IDA
S A
ctaw
aitin
g Ca
bine
tA
ppro
val
X X
Dec
isio
n M
akin
gD
ecis
ion
Mak
ing
Dec
isio
n M
akin
gD
ecis
ion
Mak
ing
Dec
isio
n M
akin
gRe
spon
sibi
lity
Resp
onsi
bilit
yRe
spon
sibi
lity
Resp
onsi
bilit
yRe
spon
sibi
lity
GID
B &
Dep
artm
ents
Infra
stru
ctur
eA
utho
rity
Dep
artm
ents
Dep
artm
ents
Dep
artm
ents
Dep
artm
ents
Proj
ect
Proj
ect
Proj
ect
Proj
ect
Proj
ect
Dev
elop
men
tD
evel
opm
ent
Dev
elop
men
tD
evel
opm
ent
Dev
elop
men
tRe
spon
sibi
lity
Resp
onsi
bilit
yRe
spon
sibi
lity
Resp
onsi
bilit
yRe
spon
sibi
lity
GID
B
API
IC (a
s a
noda
lag
ency
)
Dep
artm
ents
and
agen
cies
suc
h as
MPR
DC
and
MPP
WD
Dep
artm
ents
and
agen
cies
such
as
MSR
DC
Dep
artm
ents
and
agen
cies
such
aTI
DCO
, TN
RDC,
TWIC
Dep
artm
ents
and
agen
cies
such
as
KMD
A
Stat
e Su
ppor
tSt
ate
Supp
ort
Stat
e Su
ppor
tSt
ate
Supp
ort
Stat
e Su
ppor
tFu
ndin
gFu
ndin
gFu
ndin
gFu
ndin
gFu
ndin
g
Dep
artm
ents
;ca
se to
cas
e ba
sis
Dep
artm
ents
;ca
se to
cas
e ba
sis;
API
IC/IA
isin
volv
ed.
Dep
artm
ents
;ca
se to
cas
e ba
sis.
Dep
artm
ents
;ca
se to
cas
e ba
sis.
Dep
artm
ents
;ca
se to
cas
e ba
sis.
Dep
artm
ents
;ca
se to
cas
e ba
sis.
Mod
elM
odel
Mod
elM
odel
Mod
elC
ontr
acts
Con
trac
tsC
ontr
acts
Con
trac
tsC
ontr
acts
� � X X X X
Stan
dard
Stan
dard
Stan
dard
Stan
dard
Stan
dard
Doc
umen
tD
ocum
ent
Doc
umen
tD
ocum
ent
Doc
umen
t
� � X X X X
Proj
ect
Proj
ect
Proj
ect
Proj
ect
Proj
ect
Prep
arat
ion
Prep
arat
ion
Prep
arat
ion
Prep
arat
ion
Prep
arat
ion
Gui
delin
esG
uide
lines
Gui
delin
esG
uide
lines
Gui
delin
es
� � X X X X
Esta
blis
hed
Esta
blis
hed
Esta
blis
hed
Esta
blis
hed
Esta
blis
hed
Regu
lato
ryRe
gula
tory
Regu
lato
ryRe
gula
tory
Regu
lato
ryA
genc
yA
genc
yA
genc
yA
genc
yA
genc
y
X � X X X X
Dis
pute
Dis
pute
Dis
pute
Dis
pute
Dis
pute
Reso
luti
onRe
solu
tion
Reso
luti
onRe
solu
tion
Reso
luti
on
GID
BSu
ppor
t;Ca
se to
case
basi
s
Conc
iliat
ion
boar
d
Cont
ract
ual
Cont
ract
ual
Cont
ract
ual
Cont
ract
ual
Con
flict
Con
flict
Con
flict
Con
flict
Con
flict
Reso
luti
onRe
solu
tion
Reso
luti
onRe
solu
tion
Reso
luti
onw
ithi
n G
ovt
wit
hin
Gov
tw
ithi
n G
ovt
wit
hin
Gov
tw
ithi
n G
ovt
GID
B
Infra
stru
ctur
eA
utho
rity
X X X X
Gu
ida
nce
Ma
teri
als
Gu
ida
nce
Ma
teri
als
Gu
ida
nce
Ma
teri
als
Gu
ida
nce
Ma
teri
als
Gu
ida
nce
Ma
teri
als
Annexes
63
Punj
ab
Karn
atak
a
UP
Oris
sa
Del
hi
Nat
iona
lH
ighw
ayA
utho
rity
ofIn
dia
Rail
Vik
asN
igam
Lim
ited
Punj
abIn
frast
ruct
ure
Deve
lopm
ent
Act
199
8
X X X X Nat
iona
lH
ighw
ays
Aut
horit
y of
Indi
a A
ct, 1
988
Crea
ted
unde
rN
atio
nal R
ail
Vika
s Yoj
ana
(NRV
Y)
Punj
ab In
frast
ruct
ure
Dev
elop
men
t Boa
rd
Dep
artm
ents
and
gove
rnm
ent a
genc
ies
Dep
artm
ents
and
gove
rnm
ent a
genc
ies
Dep
artm
ents
and
gove
rnm
ent a
genc
ies
such
as
Oris
saIn
dust
rial
Infra
stru
ctur
eDe
velo
pmen
tCo
rpor
atio
n (ID
CO)
Dep
artm
ents
and
gove
rnm
ent a
genc
ies
such
as
DSI
DC,
DTTD
C
Nat
iona
l Hig
hway
sA
utho
rity
of In
dia
and
Min
istr
y of
Roa
dTr
ansp
ort a
ndH
ighw
ays
Min
istr
y of
Rai
lway
s,RV
NL
Punj
abIn
frast
ruct
ure
Dev
elop
men
t Boa
rd(a
lso
othe
r age
ncie
ssu
ch a
s PU
DA
)
iDeC
K
Dep
artm
ents
Stat
e A
genc
ies s
uch
as ID
CO
Dep
artm
ents
and
gove
rnm
ent
agen
cies
Nat
iona
l Hig
hway
sA
utho
rity
of In
dia
RVN
L
Punj
abIn
frast
ruct
ure
Ince
ntiv
e Fun
d(P
IIF)
Dep
artm
ents
;ca
se to
case
basi
s.
Dep
artm
ents
;ca
se to
case
basi
s.
Dep
artm
ents
;ca
se to
case
basi
s.
Dep
artm
ents
;ca
se to
case
basi
s.
Cent
ral R
oad
Fund
and
Aid
from
Don
orA
genc
ies
Min
istr
y of
Railw
ays
Exec
utiv
eCo
mm
ittee
of P
IDB
X X X X
MoR
TH
Min
istr
y of
Railw
ays
� X X X X � X
� X X X X � X
� X X X X � X
X X X X X
MoR
TH
X
Cont
ract
ual
Cont
ract
ual
Cont
ract
ual
Cont
ract
ual
Cont
ract
ual
Cont
ract
ual
X
Stat
e/ a
genc
ySt
ate/
age
ncy
Stat
e/ a
genc
ySt
ate/
age
ncy
Stat
e/ a
genc
yLe
gal
Lega
lLe
gal
Lega
lLe
gal
Fram
ewor
kFr
amew
ork
Fram
ewor
kFr
amew
ork
Fram
ewor
kD
ecis
ion
Mak
ing
Dec
isio
n M
akin
gD
ecis
ion
Mak
ing
Dec
isio
n M
akin
gD
ecis
ion
Mak
ing
Resp
onsi
bilit
yRe
spon
sibi
lity
Resp
onsi
bilit
yRe
spon
sibi
lity
Resp
onsi
bilit
yPr
ojec
tPr
ojec
tPr
ojec
tPr
ojec
tPr
ojec
tD
evel
opm
ent
Dev
elop
men
tD
evel
opm
ent
Dev
elop
men
tD
evel
opm
ent
Resp
onsi
bilit
yRe
spon
sibi
lity
Resp
onsi
bilit
yRe
spon
sibi
lity
Resp
onsi
bilit
y
Stat
e Su
ppor
tSt
ate
Supp
ort
Stat
e Su
ppor
tSt
ate
Supp
ort
Stat
e Su
ppor
tFu
ndin
gFu
ndin
gFu
ndin
gFu
ndin
gFu
ndin
gPr
ojec
tPr
ojec
tPr
ojec
tPr
ojec
tPr
ojec
tPr
epar
atio
nPr
epar
atio
nPr
epar
atio
nPr
epar
atio
nPr
epar
atio
nG
uide
lines
Gui
delin
esG
uide
lines
Gui
delin
esG
uide
lines
Esta
blis
hed
Esta
blis
hed
Esta
blis
hed
Esta
blis
hed
Esta
blis
hed
Regu
lato
ryRe
gula
tory
Regu
lato
ryRe
gula
tory
Regu
lato
ryA
genc
yA
genc
yA
genc
yA
genc
yA
genc
y
Dis
pute
Dis
pute
Dis
pute
Dis
pute
Dis
pute
Reso
luti
onRe
solu
tion
Reso
luti
onRe
solu
tion
Reso
luti
onC
onfli
ctC
onfli
ctC
onfli
ctC
onfli
ctC
onfli
ctRe
solu
tion
Reso
luti
onRe
solu
tion
Reso
luti
onRe
solu
tion
wit
hin
Gov
tw
ithi
n G
ovt
wit
hin
Gov
tw
ithi
n G
ovt
wit
hin
Gov
t
Gu
ida
nce
Ma
teri
als
Gu
ida
nce
Ma
teri
als
Gu
ida
nce
Ma
teri
als
Gu
ida
nce
Ma
teri
als
Gu
ida
nce
Ma
teri
als
Mod
elM
odel
Mod
elM
odel
Mod
elC
ontr
acts
Con
trac
tsC
ontr
acts
Con
trac
tsC
ontr
acts
Stan
dard
Stan
dard
Stan
dard
Stan
dard
Stan
dard
Doc
umen
tD
ocum
ent
Doc
umen
tD
ocum
ent
Doc
umen
t