Transcript
Page 1: Brighton Secondary College- Case Study · Case Study Brighton Secondary College Brighton, Victoria Replacement of a synthetic hockey facility Name of Project Brighton Secondary College

Case Study Brighton Secondary College Brighton, Victoria Replacement of a synthetic hockey facility

Name of Project Brighton Secondary College

Date of Project February 2015

Value of Project P.O.A

FIH/ITF Certification Fully Compliant

Health and Safety Full Compliance

Project Description Removal and replacement of synthetic hockey facility

Ø Size: 6100m 2 Ø Removal of existing 25mm sand filled

surface and roll out shock pad. Ø Installation of new 12mm insitu rubber

shock pad.

Ø Surfacing with POLIGRAS H.T Coolplus

Ø Line marking for 8 tennis courts, hockey and 2 half hockey fields.

Page 2: Brighton Secondary College- Case Study · Case Study Brighton Secondary College Brighton, Victoria Replacement of a synthetic hockey facility Name of Project Brighton Secondary College

Brighton Secondary College Brighton, Victoria Replacement of a synthetic hockey facility

Key Personnel Bernard Evans Managing Director Paul Ford Construction Manager Jason De Winter Senior Site Foreman Installation Team Greg Austin, Dale Angus, Nick Feather, Sam Layton, Ed Nethery, Ahmed Saraya

Subcontractors Designer Paradise