Airport Project Presentation
16 October 2014
Services from the Ground
Green Airport No APU on Ground(Aircraft 400Hz and PCA Service)
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
2/26
Services from the Ground
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
3/26
Service from the Ground
Before- Service to aircraft docking is by mobile GPU or 400Hzand PCA equipment attach to the passenger boarding bridge.
Today- Underground PITS system designs is acceptedeverywhere in new airport. At Terminal PBB, Ramp, Apron andespecially in the Maintenance Hangar.
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
4/26
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
5/26
Underground Type of Pits
There are 2 type of Underground Pit
Galvanized Steel
Pit
Concreate Structure
Pit
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
6/26
Underground Type of Cover
There are 2 type of Cover for the Pit
Galvanized SteelCounterweight Balance
Galvanized SteelGas Spring
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
7/26
Underground Pit can be design and set up to all requirements
115V/90-180kVA 400Hz, 28VDC &270VDC
380/220V 50/60Hz Main Power Supply
Pre-Conditioned Air Earth Grounding cable reel
Aircraft Washing Hot & Cold Water
Fuel Ventilation and vacuum
Hydraulic
Air Start and Compressed Air
Tele & Data
Pit Application
400Hz Pit
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
8/26
Features of Jet Fuel Pit Application
Jet Fuel Pit
Positive sealing for protection of the environment. Rugged steelconstruction for long service life. Large positively sealed catchmentarea. Absorbs large vertical and Horizontal ground movement.
Installation Lo Point Drain Pit
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
9/26
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
10/26
Pre-conditioned Air
Heavy duty wire reinforcedflexible PCA hose
8 Aircraft adapter
Motorize actuator
Manual mechanism Butterfly damper
Auto condensate trap
Others as need
Option for PCA Application
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
11/26
Factory in Den Haag, Netherlands
Modern factory with high- tech equipment
Workshop area 2000 m
Storage Area 1000 m
Complete production line are made in-house
Professional engineers and co-workers High speed delivery with quality product
Packing and loading before transport
Manufacture Testing Facilities
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
12/26
Cover Manufacturing
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
13/26
Cover Assembly
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
14/26E124 F900 Load Test
Design and Testing
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
15/26
Compete all-in-one design
Easy aircraft service
NO accident from mobile GSE
NO APU, Safe operation cost
NO carbon, environment friendly
Increase security around aircraft
Increase service space
Whats Benefit
Keeps a clear and safe area around the aircraft, minimize risk for GSEvehicles accidents with aircraft and ground handling staff. Enablesfast aircraft turnaround and better environment.
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
16/26
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
17/26
Green Airport
No APU on Ground(Aircraft 400Hz and PCA Service)
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
18/26
Green Airport No APU on Ground(Aircraft 400Hz and PCA Service)
Aircraft during ground time require 400Hz electrical energy for flight
system and utilities onboard with Pre-Conditioned Air to cool thecockpit and the cabin. There are 3 ways of providing energy to theaircraft on ground.
1. Aircraft build-in APU
2. Mobile Ground System
3. Ground Energy System
Ground Energy SystemMobile Ground SystemAircraft build-in APU
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
19/26
Environment Assessment
Below shown different of CO2 emission between using Aircraft APU
compare to Ground Power Unit and fixed energy system.
AircraftType
AircraftAPU
DieselGPU
FixedEnergy
Unit
Shorthaul 737 320 337 19.1 0.7 Kg/CO2/Hrs
Longhaul 777 380 758 38.2 1.2 Kg/CO2/Hrs
Emission inventories often include the full ICAO certification LTO up to3,000 ft. The current main guidance is ICAO Doc 9889.
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
20/26
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
21/26
Economy of the System
Cost of service to parking aircraft is depending on required service.Information below is basis on 12,000 flight per month to provide
aircraft with 400Hz and PCA.
AircraftType
Electric400Hz
Pre-AirPCA
TotalUSD/Hrs
Medium size 737 320 64 134 198
Large size 777 340 89 194 283
Service charge above is calculated basis on investment of 400HzFrequency Converter and 60 TON Precision-Air Conditioned fitting tothe bridge with 10 years of equipment service life.
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
22/26
Parking Aircraft without GPU service
GPU Service Project Proposal
Objective
To service parking aircraft at the airport without running it own APU
To return collected service fees to The Airport Authority
To maintenance airport 400Hz and PCA equipment
To invest on additional 400Hz, 28VDC and PCA with air start need
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
23/26
Parking Aircraft with GPU service
GPU Service Project Proposal
No APU GPU supply
Electrical power supply with 400 Hz frequency converter
Electrical power supply with 28 VDC
Cabin climate control supply with Pre-Conditioning Air
400HZ PCA
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
24/26
GPU Service Project Proposal
Schedule and Procedure
Description M1 M2 M3 M4 M5 M6
Project study MOU agreement
Research and Data collection
Preliminary project proposal
Preliminary project revision
Final project submission
Contract and Agreement
Project start
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
25/26
BPS Aviation and Partners, are an international company with its
headquarter in Phuket, Thailand. BPS Aviation and Partners, provides underground systems and
service support for the aircraft at the Airport terminal and in themaintenance Hangar.
BPS Aviation and Partners, supplies complete systems ofunderground service, pits for Electrical Power Supply, Pre-
Conditioned Air, Potable Water, Aircraft Sewage and Jet fuel to allaviation requirements.
BPS Aviation and Partners, Supervision installation and civilengineering work to support customer requirement.
BPS Aviation and Partners, study and design project to minimizeoperational and maintenance costs.
BPS Aviation and Partners, provide project management andresearch to customer requirement.
Our Company and PartnersConcept
-
8/11/2019 BPS Presentation Pit n Green Airport 2014
26/26
Thank You
Asia Regional Office
AEC Country
BPS Aviation Company Limited
39/2 Moo 6 Maikhao, Thalang District, Phuket 83110. Thailand
Telephone: 66 76 20 51 90 Fax: 66 76 20 51 89 Mobile 66 87 683 8038