Transcript
Page 1: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Bond Construction Bond Construction UpdateUpdate

Citizen’s Oversight Citizen’s Oversight CommitteeCommittee

Bond Construction Bond Construction UpdateUpdate

Citizen’s Oversight Citizen’s Oversight CommitteeCommittee

Long Beach Community College District April 26, 2010

EDUCATE ENGAGE EMPOWER 1

Page 2: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Agenda Latest Completed Construction Projects

PCC Industrial Tech Phase 1 (January 2010) Bldg. Z – Warehouse Retrofit (April 2010)

Current & Upcoming Construction Projects LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements LAC Building I (Bookstore)LAC Building I (Bookstore) PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide – Electronic Signage Plan LAC South Walkway Extension LAC Building P FPP Upcoming Projects

Planned Phasing of Future Projects

Q & A

2

Page 3: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Latest CompletedConstruction Projects

Modern facility houses Welding Department and other trade programs

Ribbon Cutting Ceremony April 2, 2010 New Northern face of the campus Buildings UU & VV demolition will be

completed April 2010 Exterior Lighting & Landscape

completion anticipated Summer 2010

PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1

Measure E 2002Measure E 2002

3

Page 4: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Facilities Department building retrofit from warehouse and classrooms to shop areas

Exterior car wash structure

Charging station for electrical powered vehicles

Additional Visitor’s Parking lot

Completed April 2010

Latest CompletedConstruction Projects

LAC Building Z – Warehouse RetrofitLAC Building Z – Warehouse Retrofit

Measure E 2002Measure E 2002

4

Page 5: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit

Measure E 2008Measure E 2008

5

Plans submitted to DSA September 2009 Adds 6,500 Sq. Ft. to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Fall 2010

Page 6: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

Completed Schematic Design Will house Math and Culinary Arts instructional

program as well as Reprographics Estimated start of construction Fall 2012

LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008

6

Page 7: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

LAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008

7

Spaces for 900 Vehicles Photovoltaic Electrical Generation Array on top level To be located Southeast corner of Lot J adjacent to the Verizon building Outfitted with single-axis tracking system Minimum 450 KW+ output Curriculum building opportunity Exhibit classroom Groundbreaking anticipated Summer 2010

Page 8: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

LAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008

8

Two structures totaling 87,000 square feet

Current Occupants: ERD, Foundation, Warehouse

Facility, and one leasee Future Occupants:

IITS and BMT Potential rental spaces being

assessed Start of construction of

Building O1 began April 2010

Page 9: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

9

LAC Infrastructure Improvement ProjectsLAC Infrastructure Improvement Projects

Measure E 2008Measure E 2008

Current and UpcomingConstruction Projects

Project to be completed in a phased construction schedule

Total annual estimated savings of 1.5 million Kwh

Project started Fall 2009. Anticipated completion Summer 2011; in Phase 3 and 3A currently

Upgrades include; Reclaimed Water, Domestic Water, Data, etc.

Majority of existing building HVAC systems to be connected to new infrastructure

Landscaping upgrades to be implemented in conjunction with infrastructure project phasing

Page 10: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

10

Add additional 4,000 square feet to existing building

Architecture to match LAC Mediterranean Theme

Submitted for DSA review

Construction scheduled for Summer 2010

Bookstore Swing Space installation began April 2010

LAC Building I - Measure E 2008LAC Building I - Measure E 2008

Page 11: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002(Multi-Disciplinary Academic Building) - Measure E 2002

11

Currently out for bid Install portables for swing space Summer 2010 Anticipated start of MDAB construction Fall 2010 Project to be completed in two phases

Page 12: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

PCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008

12

Currently in DSA for plan check Houses the Fitness Center, Gymnasium, Weight Room, and

Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. GG) To be completed concurrently with MDAB project phase 2 Anticipated start of construction 2012

Page 13: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

District Wide – Electronic Signage PlanDistrict Wide – Electronic Signage Plan Measure E 2008Measure E 2008

13

District Wide Signage Plan complete for LAC & PCC Construction anticipated to start May 2010 Anticipated construction completion of Marquee Signs

Fall 2010

Page 14: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

l i b

e r

a l

a r

t s

Liberal Arts CampusSite Plan

Page 15: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

p a

c i f

i c

c

o a

s t

Pacific Coast CampusSite Plan

Page 16: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Current and UpcomingConstruction Projects

16

LAC Relocate Bond Management Team Offices to O Building and

remove W Trailers (Fall 2010) Increase parking at Faculty and Lew Davis St.

IITS relocation to O building Bldg. K – Roof extension over Kiln area Bldg. J – Theater lighting control panel replacement Bldg. E – Renovation upgrades CDC – new carpet installation Installation of Monument Signs at Conant/Clark and Bldg. O

(Summer 2010) PCC

Bldg. JJ – Add new landscaping around perimeter MDAB swing space preparation Installation of Monument Signs PCH/Walnut and 20th/Walnut

(Summer 2010)

Upcoming ProjectsUpcoming Projects

Page 17: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

17

2009-10 Began infrastructure construction – Fall 2009

Master landscaping implementation will follow this project

Parking Structure – groundbreaking anticipated May 2010

Install portables for swing space at PCC – Summer 2010

Anticipating swing space move for Building A at LAC – Summer 2010

Page 18: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

18

2010-11 Begin construction of Buildings DD and EE at PCC – Fall 2010

Marquees complete – Fall 2010

Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010

Building O2 occupancy scheduled

BMT and IITS – Fall 2010

Begin construction of Building A at LAC – Fall 2010

Begin schematic design of Math/Technology Building at LAC – Winter 2011

Begin Building R (Gym) HVAC and ADA upgrades – Winter 2011

Page 19: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

19

2011-12 Infrastructure project complete at LAC – Summer 2011 Begin Schematic Design for Buildings C and F at LAC –

Summer 2011 Submit plans to DSA for Math/Technology Building at LAC –

Fall 2011 Anticipated construction completion of Parking Structure at

LAC – Fall 2011 Anticipated construction completion of Building I (Bookstore)

at LAC – Winter 2012 Anticipating construction completion of Building R (Gym)

HVAC and ADA upgrades - Winter 2012 Submit plans to DSA for Buildings C and F at LAC - Spring

2012 Begin schematic design for Building GG at PCC – Spring 2012

Page 20: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

20

2012-13 Begin Schematic Design for Building M/N – Summer 2012

Construction completion of Buildings DD and EE at PCC – Summer 2012

Anticipated Construction completion of Building A at LAC – Summer 2012

Begin construction of Math/Technology Building at LAC – Fall 2012

Begin construction of Buildings AA, BB and CC at PCC – Fall 2012

Begin Schematic Design for Building GG at PCC – Fall 2012

Begin Schematic Design for Buildings J and P at LAC – Winter 2013

Begin Schematic Design for Building MM (Phase 1) at PCC – Winter 2013

Page 21: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

21

2012-13 (continued) Move Buildings C and F programs into Swing Space (M/N

Building) and begin construction – Spring 2013

Submit plans to DSA for M/N Building at LAC – Spring 2013

Page 22: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

22

2013-14 Submit plans to DSA for Building P at LAC and Building MM

(Phase 1) at PCC – Fall 2013

Begin schematic design for Building FF at PCC – Fall 2013

Submit plans to DSA for Building J at LAC – Fall 2013

Begin Schematic Design for Building D at LAC and Building MM (Phase 2) at PCC – Winter 2014

Anticipated Construction completion of Building CC at PCC – Winter 2014

Begin construction on Building GG at PCC – Winter 2014

Anticipated Construction completion of Buildings AA and BB at PCC – Spring 2014

Page 23: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

23

2014-15 Submit plans to DSA for Building FF at PCC – Summer 2014

Begin construction on Building P at LAC and Building MM at PCC (Phase 2) – Fall 2014

Anticipated construction completion of Math/Technology Building at LAC – Summer 2014

Begin construction of Building M/N at LAC – Fall 2014

Anticipated construction completion of Buildings C and F at LAC – Fall 2014

Begin construction on Building J at LAC –Fall 2014

Submit plans to DSA for Buildings D at LAC and MM (Phase 2) at PCC – Winter 2015

Begin schematic design for Performing Arts Building (G & H) LAC – Winter 2015

Begin schematic design for Building E at LAC – Spring 2015

Page 24: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

24

2015-16 Anticipated construction completion of Building GG at PCC –

Summer 2015

Anticipated start of construction of Building FF at PCC – Summer 2015

Submit plans to DSA for Performing Arts Building at LAC – Fall 2015

Begin construction on Building D at LAC and Building MM (Phase 2) at PCC – Winter 2016

Submit plans to DSA for Building E at LAC – Winter 2016

Anticipated construction completion of Building P at LAC – Spring 2016

Anticipated construction completion of Building J at LAC – Spring 2016

Page 25: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

25

2016-17 Anticipated construction completion of Building FF at PCC – Fall

2016

Anticipated start of construction of Building E at LAC – Spring 2017

Anticipated construction completion – Spring 2019

Anticipated construction completion of Building M/N at LAC – Fall 2016

Anticipated construction completion of Building MM (Phase 1) at PCC – Winter 2016

Anticipated start of construction for Performing Art Building at LAC – Fall 2016

Anticipated construction completion – Fall 2018

Anticipated construction completion of Building D at LAC – Winter 2017

Begin schematic design for Building K at LAC – Winter 2017

Page 26: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

Planned Phasing of Future Projects

26

2017-18

Anticipated construction completion of Building MM (Phase 2) at PCC – Summer 2017

Submit plans to DSA for Building K at LAC – Fall 2017 Anticipated start of construction Fall 2018

Anticipated completion Spring 2020

Page 27: Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1

QUESTIONS&

ANSWERS

EDUCATE ENGAGE EMPOWER 27