AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR & IBenguet & Ilocos
SurBakun & Cervantes Hedcor, Inc. Mankayan 2
Non-compliant with:
-PERFORMANCE BOND
-RESHERR
-WORK PROGRAM
20.30
CAR Benguet AmbuklaoSN Aboitiz Power -
Benguet, Inc.Ambuklao 104.55
Bakun Hedcor, Inc. Ampohaw Non-compliant with:
• RESHERR8.00
F. L. Singit Non-compliant with:
• RESHERR5.90
Lon-oy Non-compliant with:
• RESHERR3.60
Lower Labay Non-compliant with:
• RESHERR2.40
Bakun & Mankayan Hedcor, Inc. Mankayan 1 Non-compliant with:
RESHERR , Work Program, PB12.70
Bokod & Kabayan Hedcor Benguet, Inc. Kabayan-Bokod Non-compliant with:
PB, RESHERR, WP27.00
BuguiasBenguet Electric
Cooperative, Inc.Man-asok
Compliant with:
-Work Plan -
Performance Bond
Non-compliant with:
- RESHERR
3.00
Buguias & Kabayan Hedcor Benguet, Inc. Kabayan 1Compliant with:
PB, WP, RESHERR 20.00
Itogon Hedcor, Inc. Sal-angan Non-compliant with:
• RESHERR2.40
SN Aboitiz Power -
Benguet, Inc.Binga 140.00
Strategic Power
Development Corp.
San Roque Lower East
Pumped-Storage
Compliant with:
-Work Program
-Posting of performance bond
-RESHERR
400.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR Benguet ItogonStrategic Power
Development Corp.
San Roque Upper East
Pump Storage
Compliant with:
Work Program, Posting of Performance
Bond
Non-compliant with:
RESHERR
600.00
San Roque West Pump
Storage
Compliant with:
RESHERR , Work Program, PB 400.00
Kabayan Hedcor Kabayan, Inc. Kabayan 2
Non-compliant with:
- Work Plan
-Performance bond
-RESHERR
52.00
Kapangan and
Kibungan
Cordillera Hydro Electric
Power CorporationKapangan
Compliant with:
-RESHERR
-PERFORMANCE BOND
Non-compliant with:
-WORKPLAN
60.00
KibunganCoheco Badeo
CorporationKibungan Pumped-Storage
Compliant with:
PB
Non-compliant with:
RESHERR, WP
500.00
Kibungan Hydropower
CorporationKibungan
Non-compliant with:
Work Program RESHERR 1,000.00
La Trinidad Hedcor, Inc. Bineng 1-2B Combination Non-compliant with:
PB, RESHERR, 19.00
Bineng 3 Non-compliant with:
• RESHERR4.50
Sablan Hedcor, Inc. Bagulin 1 10.00
TubaAV Garcia Power
Systems Corp.Abdao
Compliant with:
-RESHERR
Non-compliant with:
-Work Plan
-Performance bond
2.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR Benguet TubaAV Garcia Power
Systems Corp.Abdao 2
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
3.00
Goldlink Global Energy
CorporationKanggas
Non-compliant with:
Performance Bond; Work Plan; RESHERR3.00
Tadiangan
Non-compliant with:
PB, Progress Reports, RESHERR, Work
Program
4.70
Hedcor, Inc. Irisan 1 Compliant with:
Work Plan; RESHERR 3.80
Irisan 3 Non-compliant with:
• RESHERR1.20
Tublay AT Dinum Company Tublay 2
Compliant with:
WP, PB
Non-compliant with:
RESHERR,
6.00
Tublay 3
Compliant with:
-PERFORMANCE BOND
Non-compliant with:
-WORK PROGRAM
-RESHERR
1.00
Tublay & La Trinidad AT Dinum Company Tublay 1
Compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
Non-compliant with:
-RESHERR
0.90
Ifugao AsipuloIfugao Electric
Cooperative, Inc.Likud 2
Compliant with:
-Work Program
Non-compliant with:
-RESHERR -
Performance Bond
0.60
Asipulo & KianganProvincial Government
of IfugaoLikud
Non-compliant with:
RESHERR0.82
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR Ifugao IlaganSN Aboitiz Power -
Ifugao, Inc.Olilicon
Non-compliant with:
PB, WP10.00
KianganEnerhighlands
CorporationIbulao 2
Non-compliant with:
-WORKPLAN
-RESHERR
-PERFORMANCE BOND
8.80
Kiangan Mini Hydro
CorporationAsin
Compliant with:
WP, Progress Reports, Performance Bond
Non-compliant with:
RESHERR
7.04
Hungduan
Compliant with:
WP, Progress Reports, Performance Bond
Non-compliant with:
RESHERR
4.04
Ibulao 1
Compliant with:
-Work Plan
Non-compliant with:
-RESHERR -
Performance bond
6.75
Provincial Government
of IfugaoAmbangal
Non-compliant with:
RESHERR0.20
Lagawe Hydrocore, Inc. Ibulao
Compliant with:
- RESHERR
- Performance bond
Non-compliant with:
- Work Plan
4.50
SN Aboitiz Power -
Ifugao, Inc.Alimit
Non-compliant with:
PB100.00
Lagawe & MayoyaoSN Aboitiz Power -
Ifugao, Inc.Alimit-Pumped Storage
Non-compliant with:
PB240.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR Ifugao LamutEnerhighlands
CorporationLamut
Compliant with:
Work Plan; Performance Bond
Non-compliant with:
RESHERR
6.00
RamonSN Aboitiz Power -
Magat, Inc.Maris Main Canal 2
Compliant with:
RESHERR
Non-compliant with:
PB, Progress Report, WP
1.75
TinocPhilnew Hydro Power
CorpTinoc 4
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan
5.00
Philnewriver Power
Corp.
Tinoc 5 (Lower Luhong)
HEP
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan
6.90
Tinoc 6 (Wangwang) HEP
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan
8.00
Quadriver Energy
CorporationTinoc 1
Non-compliant with:
-Work Plan
-Performance bond
-RESHERR
4.10
Tinoc 2
Non-compliant with:
-Work Plan
-Performance bond
-RESHERR
11.00
Tinoc 3
Non-compliant with:
-Work Plan
-Performance bond
-RESHERR
8.00
Kalinga BalbalanBiyao Hydro Power
CorporationBiyao
Non-compliant with:
RESHERR , Work Program, PB0.80
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR Kalinga Pasil I-Magat Renewable
Energy CorporationPasil B
Compliant with:
-PERFORMANCE BOND
Non-compliant with:
-WORK PROGRAM
-RESHERR
14.00
Pasil C
Compliant with:
-PERFORMANCE BOND
Non-compliant with:
-WORK PROGRAM
-RESHERR
11.00
Markham Resources
CorporationPasil 3 10.00
Tapao
Non-compliant with:
WP, RESHERR, PB
10.00
TabukDPJ Engineers and
ConsultantsBulanao
Non-compliant with:
RESHERR 1.00
San Lorenzo Ruiz
Builders & Developers
Group, Inc.
Chico River
Compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
Non-compliant with:
-RESHERR
45.00
TinglayanPan Pacific Renewable
Power Philippine Corp.Tinglayan
Compliant with:
- Work Program - RESHERR
Non-compliant with:
• RESHERR
4.32
San Lorenzo Ruiz Piat
Energy & Water, Inc. Chico
Compliant with:
WP 150.00
ApayaoCabarroguis &
Nagtipunan
Pan Pacific Renewable
Power Philippine Corp.Gened 1
Compliant with:
-Work Program -
Performance Bond -
RESHERR
600.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR Apayao ConnerStrategic Power
Development Corp.Nabuangan River
Compliant with:
-Work Program
-Posting of performance bond
-RESHERR
10.00
Abra Lagayan Sta. Clara Power Corp. Tineg Non-compliant with:
RESHERR , Work Program, PB16.00
Manabo Sta. Clara Power Corp. Three Rivers Non-compliant with:
RESHERR , Work Program, PB10.00
Tineg & LagayanFirst Gen Mindanao
Hydro Power Corp.Binongan-Tineg
Compliant with:
WP, PB, RESHERR 175.00
Tubo Sta. Clara Power Corp. Amtuagan Non-compliant with:
RESHERR , Work Program, PB8.50
Gayaman (Tubo)
Non-compliant with:
-WORKPLAN
-PERFORMANCE BOND
-RESHERR
8.50
Mt. Province BaukoKadipo Bauko Hydro
Power Corp.Ampassit
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
1.20
Boga
Compliant with:
-WORK PROGRAM
Non-compliant with:
-PERFORMANCE BOND
-RESHERR
1.00
Enodey 1A
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
1.80
Lower Chico
Compliant with:
-Work Program
Non-compliant with:
-RESHERR -
Performance Bond
3.40
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR Mt. Province BaukoKadipo Bauko Hydro
Power Corp.Upper Chico
Compliant with:
-Work Program
Non-compliant with:
-RESHERR -
Performance Bond
2.10
Kadipo Bauko
Hydropower Corp.Enodey-Abit 1
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
2.00
Enodey-Abit 2
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
1.20
Enodey-Abit 3
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
2.00
Besao
BIMAKA Renewable
Energy Development
Corporation (BREDCO)
Besao 1
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
5.00
Besao 1A
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
2.30
Besao 1B
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
1.70
Besao 2
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
7.00
Besao 2A
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
1.50
Besao 3
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
4.50
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon CAR Mt. Province Bontoc
Mountain Province
Electric Cooperative,
Inc.
Talubin Non-compliant with:
PB, RESHERR4.90
Natonin
Asiapac Green
Renewable Energy
Corporation
Lower Siffu
Compliant with:
Performance Bond; RESHERR
Non-compliant with:
Work Program
8.00
Upper Siffu
Compliant with:
Performance Bond; RESHERR
Non-compliant with:
Work Program
8.00
Southeast Asia
Renewable Power
Corporation
Malecom
Non-compliant with:
• Work Plan
• Performance Bond
• RESHERR
0.80
Malig
Non-compliant with:
• Work Plan
• Performance Bond
• RESHERR
1.10
Pantor
Non-compliant with:
• Work Plan
• Performance Bond
• RESHERR
1.20
Sabangan Hedcor Sabangan, Inc. Sabangan Compliant with:
Work Plan; RESHERR 14.00
Tadian
Asiapac Green
Renewable Energy
Corporation
Dicapan
Compliant with:
Performance Bond; RESHERR
Non-compliant with:
Work Program
3.00
I Ilocos Sur AlilemLuzon Hydro
CorporationBakun AC 70.00
Philnewriver Power
Corp.Alilem HEP
Non-compliant with:
Performance Bond (PB), RESHERR,
Progress Reports, Work Program
16.20
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon I Ilocos Sur QuirinoPhilnewriver Power
Corp.Quirino HEP
Compliant with:
'• Submitted Construction Environmental
Safety and Health Program in compliace to
RESHERR requirement on Oct. 6, 2010
Non-compliant with:
• Performance Bond
11.50
San Emilio Sta. Clara Power Corp. Matibuey
Compliant with:
- Work Program
- Posting of performance bond
- RESHERR
16.00
Sigay & SuyoMarkham Resources
CorporationSigay 2
Non-compliant with:
progress report, RESHERR, PB
10.00
SugponPhilnewriver Power
Corp.Danac HEP
Non-compliant with:
PB, WP13.20
SuyoSatrap Power
CorporationSuyo 2
Compliant with:
PB
Non-compliant with:
RESHERR, WP
3.00
La Union Bagulin
Team (Philippines)
Renewable Energy
Corporation
Baroro 1
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
1.00
Baroro 2
Non-compliant with:
-WORKPROGRAM
-PERFORMANCE BOND
-RESHERR
3.00
Baroro 3
Non-compliant with:
- Work Program
- RESHERR
-Performance bond
1.50
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon I La Union NaguilianNaguilian Mini-Hydro
Electric CorporationNaguilian
Compliant with:
Performance Bond; Work Program
Non-compliant with:
RESHERR
6.10
San GabrielMarkham Resources
CorporationBaroro
Non-compliant with:
WP, RESHERR, PB
6.00
TubaoTubao Mini Hydro-
Electric CorporationTubao
Compliant with:
Work Program
Non-compliant with:
Posting of Performance Bond, RESHERR
1.50
Ilocos Norte DumalnegPhildane Resources
CorporationBulo 2
Non-compliant with:
PB, RESHERR, WP
5.00
II Cagayan PeñablancaSunwest Water &
Electric Company, Inc.Pinacanauan River
Non-compliant with:
Work Plan, Posting of Performance Bond,
RESHERR
6.00
Isabela Alicia
Ganano Energy &
Environment Electric
Cooperative
Ganano River 50.00
Cordon PhilCarbon Inc. Magat F Non-compliant with:
PB, RESHERR, WP0.60
EchagueIsabela Power
CorporationIlaguen 3
Compliant with:
• Work Program
• Posting of performance bond
• Complied RESHERR requirements on Feb
7, 2017
11.00
Ilaguen 4
Compliant with:
• Work Program
• Posting of performance bond
• Complied RESHERR requirements on Feb
7, 2017
10.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon II Isabela Ilagan
Trans-Asia Oil and
Energy Development
Corp,
Ilagan
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
10.00
Lagawe & MayoyaoGreenpower Resources
CorporationAbuan River 1
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
10.80
NagtipunanIsabela Power
CorporationIlaguen 2
Compliant with:
• Work Program
• Posting of performance bond
14.00
RamonI-Magat Renewable
Energy CorporationMagat A
Non-compliant with:
Non submission of Quarterly report, PB,
WP, and RESHERR
1.30
Magat B
Non-compliant with:
Non submission of Quarterly report, PB,
WP, and RESHERR
1.00
SN Aboitiz Power -
Magat, Inc.Maris Main Canal 1
Compliant with:
RESHERR, WP, Progress Reports
Non-compliant with:
PB
6.00
San AgustinGreenpower Resources
CorporationDibuluan
Compliant with:
-Performance bond
Non-compliant with:
-Work Plan
-RESHERR
5.00
Ilaguen 5
Compliant with:
Posting of Performance Bond
Non-compliant with:
Work Program RESHERR
8.60
San MarianoGreenpower Resources
CorporationCatalangan North 4.40
Catalangan South 6.50
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon II Isabela San MarianoGreenpower Resources
CorporationDisabungan
Compliant with:
-Performance bond
Non-compliant with:
-Work Plan
-RESHERR
4.80
San Mariano & San
GuillermoIsabela Power Corp. Ilaguen
Compliant with:
- Posting of performance bond
Non-compliant with:
- Work Plan
-RESHERR
19.00
San Mateo National Irrigation
AdministrationLateral B
Non-compliant with:
RESHERR0.05
San PabloGreenpower Resources
CorporationSan Pablo
Compliant with:
PB
Non-compliant with:
RESHERR, Progress Report
8.00
San Pablo Site 2
Compliant with:
PB
Non-compliant with:
RESHERR, Progress Report
3.00
TumauiniPhilnew Hydro Power
CorpTumauini (Upper Cascade)
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan
14.00
Quadriver Energy
CorporationTumauini (Lower Cascade)
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan
7.80
Nueva Vizcaya Alfonso CastañedaJRV Renewable Energy
CorporationDenip
Non-compliant with:
Work Program; RESHERR; Performance
Bond
2.30
United Hydro Power
BuildersMangayngay
Non-compliant with:
RESHERR , Work Program, PB1.60
AmbaguioAurora All Asia Energy
CorporationMatuno 2 15.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon II Nueva Vizcaya AmbaguioSmith Bell Mini-Hydro
Corp.Matuno 1
Non-compliant with:
-WORKPLAN
-PERFORMANCE BOND
-RESHERR
7.40
BambangEpower Technologies
Corp.Matuno
Non-compliant with:
-Work Plan
-Performance bond
-RESHERR
8.00
Smith Bell Mini-Hydro
Corp.Matuno 2
Non-compliant with:
-WORKPLAN
-PERFORMANCE BOND
-RESHERR
7.90
Dupax del Norte and
Alfonso Castañeda
JRV Renewable Energy
CorporationCasignan
Non-compliant with:
Work Program; RESHERR; Performance
Bond
5.00
Dupax del SurJRV Renewable Energy
CorporationAbaca
Non-compliant with:
Work Program; RESHERR; Performance
Bond
3.20
Kasibu AT Dinum Company Didipio 1 Non-compliant with:
WP, RESHERR, PB, Progress Report2.10
Edralin
Compliant with:
-Work Program -
Posting of performance bond
Non-compliant with:
RESHERR
1.20
Namanaan
Compliant with:
-Performance bond
Non-compliant with:
- Work Program
-RESHERR
0.60
Kasibu & Nagtipunan Alimit Hydro Corp. Didipio 2 Non-compliant with:
WP, RESHERR, PB, Progress Report9.40
SolanoSmith Bell Mini-Hydro
Corp.Commonal-Uddiawan
Non-compliant with:
RESHERR 1.80
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon II Quirino AglipayQuirino Power Energy
CorporationAddalam
Compliant with:
• Work Program
Non-compliant with:
• RESHERR
3.80
CabarroguisQuirino Resources
Development Corp.Addalam
Compliant with:
Work Plan, Posting of Performance Bond
Non-compliant with:
RESHERR
14.20
MaddelaGreenpower Resources
CorporationDibuluan 2
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
3.20
NagtipunanAsiapacific Renewables
CorporationDakgan 1
Non-compliant with:
-Work Program
-Performance bond
RESHERR
9.00
Dakgan 2
Non-compliant with:
-Work Program
-Performance bond
RESHERR
12.00
Gawagan Hydro Power
Corp.Gawagan 1
Non-compliant with:
RESHERR, Work Program, PB4.30
Gawagan 2 Non-compliant with:
RESHERR, Work Program, PB2.60
Geblem 1 Non-compliant with:
RESHERR, Work Program, PB0.70
United Hydro Power
BuildersDagkan
Non-compliant with:
RESHERR , Work Program, PB142.00
Isabela IlaganGreenpower Resources
CorporationAbuan 2
Compliant with:
-PERFORMANCE BOND 8.10
RamonSN Aboitiz Power -
Magat, Inc.Magat 360.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon II Isabela San PabloGreenpower Resources
CorporationSan Pablo Site 3
Compliant with:
PB
Non-compliant with:
RESHERR, Progress Report
4.90
Isabela &
Quirino
San Agustin &
Maddela
Greenpower Resources
CorporationDabubu
Compliant with:
-Performance bond
Non-compliant with:
- Work Program -RESHERR
4.50
III Aurora Dinalungan PTC Energy, Inc. Talaytay
Non-compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
-RESHERR
1.45
Dingalan PTC Energy, Inc. Davildavilan
Compliant with:
RESHERR
Non-compliant with:
PB, Work Program
1.00
Strategic Power
Development Corp.Dingalan Pumped-Storage
Compliant with:
-Work Program
-Posting of performance bond
-RESHERR
500.00
San Luis PTC Energy, Inc. Diteki
Non-compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
-RESHERR
1.67
Nueva Ecija GabaldonConstellation Energy
CorporationDupinga
Non-compliant with:
Performance Bond; Work Plan; RESHERR3.00
General Tinio LGU of Gen. Tinio Rio Chico Non-compliant with:
Performance Bond; Work Plan; RESHERR2.00
PantabanganFirst Gen Hydro Power
CorporationMasiway
Compliant with:
RESHERR 12.00
PantabanganCompliant with:
RESHERR 120.80
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon III Nueva Ecija PantabanganFirst Gen Prime Energy
Corporation
Pantabangan (Pump
Storage) HEP
Compliant with:
-Work Program -
Perfromance Bond -RESHERR
300.00
San Lorenzo Ruiz
Builders & Developers
Group, Inc.
Sampaloc 14.00
United Hydro Power
BuildersDiaman
Compliant with:
Work Program
Non-compliant with:
RESHERR; Performance Bond
1.80
RizalPNOC-Renewables
CorporationPrismc 1.00
San JosePNOC-Renewables
CorporationSDC
Compliant with:
-RESHERR
-Performance bond
Non-compliant with:
- Work Program
0.50
Bataan Mariveles
Southeast Asia
Renewable Power
Corporation
Mariveles
Non-compliant with:
• Work Plan
• Performance Bond
• RESHERR
1.10
Morong Sta. Clara Power Corp. Morong 2.00
Tarlac MayantocNorthgreen Energy
CorporationCamiling 1
Compliant with:
- Posting of performance bond
Non-compliant with:
RESHERR, Work Program
5.40
Camiling River 3
Compliant with:
Work Program, Progress Reports,
Performance Bond.
Non-compliant with:
RESHERR
3.40
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon III Zambales IbaMarkham Resources
CorporationIba 2
Non-compliant with:
progress report, RESHERR, PB
5.00
Masinloc AT Dinum Company Coto 3
Compliant with:
Posting of Performance Bond
Non-compliant with:
RESHERR
2.20
Coto Hydro Corp. Coto 1 Non-compliant with:
RESHERR6.50
Coto 2 Non-compliant with:
RESHERR2.80
Pangasinan San Quintin
Power Beacon
Renewable Solutions,
Inc.
Dipalo
Compliant with:
PB
Non-compliant with:
WP, RESHERR
2.50
Nueva Ecija /
AuroraGabaldon / San Luis
United Hydro Power
BuildersLingod River 2.50
IV-A Bulacan NorzagarayStrategic Power
Development Corp.Angat Run-of-River
Compliant with:
PB, WP
Non-compliant with:
RESHERR
10.00
Quezon General NakarLaguna Hydroenergy
CorporationUmiray 1
Compliant with:
Performance Bond
Non-compliant with:
Work Program; RESHERR
6.00
Umiray Site 2 River
Compliant with:
Work Program; Performance Bond
Non-compliant with:
RESHERR
3.90
Umiray Site 4 River
Compliant with:
Work Program; Performance Bond
Non-compliant with:
RESHERR
2.80
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon IV-A Quezon LucbanRenesons Energy
CorporationMaapon
Compliant with:
- Work Plan
- RESHERR
Non-compliant with:
-Performance bond
2.60
MaubanAurora All Asia Energy
CorporationMauban
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
10.00
Enervantage Supplier's
Co., Inc.
(Laguio) Laginbayan
Malaki 2
Compliant with:
-Work Plan
Non-compliant with:
-RESHERR -
Performance bond
3.10
Laguio (Laginbayan)
Malaki 1
Compliant with:
-Work Plan
Non-compliant with:
-RESHERR -
Performance bond
1.60
RealAurora All Asia Energy
CorporationTignoan
Non-compliant with:
Performance Bond; Work Program;
RESHERR
20.00
Tignoan (Lower) 8.00
Enervantage Supplier's
Co., Inc.Lubayat River 3.50
Municipality of Real,
QuezonKinanliman
Non-compliant with:
- Work Program
- Posting of performance bond
- RESHERR
1.60
Repower Energy
Development
Corporation
Labayat River (Lower
Cascade)
Compliant with:
-WORKPLAN
-RESHERR
Non-compliant with:
-PERFORMANCE BOND
1.40
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon IV-A Quezon Real
Repower Energy
Development
Corporation
Labayat River (Upper
Cascade)
Compliant with:
WP, RESHERR, Progress Reports,
Performance Bond
3.00
Lalawinan
Compliant with:
- Work Program - Posting of performance
bond
Non-compliant with:
• RESHERR
3.00
Piapi River
Compliant with:
-WORKPLAN
-RESHER
Non-compliant with:
-PERFORMANCE BOND
3.30
Tibag
Compliant with:
- Work Program - Posting of performance
bond
Non-compliant with:
• RESHERR
4.40
Tignoan River (Upper
Cascade) 1.50
Rizal Jala-Jala Citicore Power, Inc. Jala-Jala Pumped Storage 750.00
Jala-Jala Pumped Storage
Site 4 300.00
Jala-Jala Pumped Storage
Site 5 300.00
Pililla
Trans-Asia Oil and
Energy Development
Corp,
Pililia Pumped Storage
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
300.00
RodriguezOlympia Violago Water
& Power, Inc.Wawa Pumped Storage 1
Compliant with:
Work Program, PB
Non-compliant with:
RESHERR
500.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon IV-A Rizal RodriguezOlympia Violago Water
& Power, Inc.Wawa Pumped Storage 2
Compliant with:
Work Program, PB
Non-compliant with:
RESHERR
100.00
Wawa Pumped Storage 3 50.00
LagunaCalauan and San
Pablo City
Philippine Power and
Development CompanyPalakpakin 1.00
Kalayaan Citicore Power, Inc. Kalayaan Pumped Storage 600.00
MajayjayAurora All Asia Energy
CorporationUpper Botocan River
Non-compliant with:
Performance Bond; Work Program;
RESHERR
8.64
Majayjay Hydropower
Company, Inc.Majayjay
Compliant with:
WP, RESHERR, Progress Reports
Non-compliant with:
Performance Bond
3.00
Majayjay &
Magdalena
Repower Energy
Development
Corporation
Balanac (Middle)
Compliant with:
RESHERR
Non-compliant with:
Work Program; Performance Bond
5.00
NagcarlanPhilippine Power and
Development CompanyBalugbog 0.70
Paete Citicore Power, Inc. Paete Pumped Storage 350.00
Pangil Belisama Hydropower
CorporationDambo Pumped Storage
Compliant with:
-Work Program
-Posting of performance bond
Non-compliant with:
-RESHERR
800.00
San PabloPhilippine Power and
Development CompanyCalibato 0.22
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon IV-A CaviteIndang &
MaragondonEnergywise Corporation Indang
Compliant with:
Work Program
Non-compliant with:
Posting of Performance Bond, RESHERR
1.50
Laguna &
Quezon
Pangil & Real &
Mauban
Sierra Madre Water
CorporationSiniloan
Non-compliant with:
-Performance bond
-Work Program
- RESHERR
35.00
IV-BOriental
MindoroBaco
Alpaparay Resort &
Development
Corporation
San Ignacio
Non-compliant with:
- Work Program
- Posting of performance bond -
RESHERR
0.50
Oriental Mindoro
Electric Cooperative,
Inc.
*Linao-Cawayan (Lower
Cascade) 2.10
Linao-Cawayan (Upper
Cascade)
Compliant with:
RESHERR; Work Plan 2.10
PNOC - Renewables
Corp.Dulangan
Compliant with:
-RESHERR
Non-compliant with:
-Performance bond
-Work Program
8.25
Bansud & GloriaSunwest Water and
Electric Co., Inc.Bansud
Compliant with:
PB
Non-compliant with:
RESHERR, Work Program
1.50
Bongabong S&B Power Corporation Bongabong 2.60
NaujanCatuiran Hydro Power
Corp.Catuiran
Compliant with:
RESHERR , Work Plan, PB 8.00
Philnew Hydro Power
CorpCatuiran (Upper Cascade)
Non-compliant with:
RESHERR , Work Program, PB8.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon IV-BOriental
MindoroSan Teodoro
Constellation Energy
CorporationAlag Tributary 1
Compliant with:
-Posting of performance bond
Non-compliant with:
- RESHERR
-Work Program
2.80
Alag Tributary 2 Non-compliant with:
WP, RESHERR2.80
Mindoro Grid
Corporation
Linao Cawayan Phase 2
(Tail-End)
Compliant with:
Work Program
Non-compliant with:
Posting of Performance Bond, RESHERR
1.00
Ormin Power, Inc Inabasan
Compliant with:
RESHERR
Non-compliant with:
Work Plan, Performance Bond
10.00
San Teodoro &
Puerto GalleraOrmin Power, Inc. Inabasan Phase II
Non-compliant with:
Non submission of Quarterly report, PB,
WP, and RESHERR
10.00
Palawan Alfonso ListaAlternergy Viento
Partners CorporationBulalakao 1 North River
Compliant with:
- Work Program
- Posting of performance bond -
RESHERR
0.34
Bataraza AQA Global Power Inc. Marangas River
Non-compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
-RESHERR
12.00
Brooke's Point AQA Global Power Inc. Sologon River HEP Non-compliant with:
RESHERR, WP, PB12.00
Busuanga AQA Global Power Inc. Busuanga River 1 HEP
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
8.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon IV-B Palawan El NidoAlternergy Viento
Partners CorporationBulalakao 2 South River
Compliant with:
- Work Program
- Posting of performance bond -
RESHERR
0.44
Narra AQA Global Power Inc. Bato-Bato (Kaliwa) HEP
Non-compliant with:
Work Program; RESHERR; Performance
Bond
12.00
Estrella River HEP Non-compliant with:
Work Program; RESHERR8.00
Malasgao (Kaliwa) HEP
Non-compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
-RESHERR
10.00
Langongan Power
CorporationBatang-Batang
Non-compliant with:
- Work Plan
-Performance bond
- RESHERR
9.00
Puerto PrincesaLangongan Power
CorporationLangogan
Non-compliant with:
Performance Bond; Work Plan; RESHERR6.80
Puerto Princesa AQA Global Power Inc. Inaguan River HEP Non-compliant with:
RESHERR, WP, PB12.00
Rizal AQA Global Power Inc. Culasian River HEP
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
10.00
Romblon CajidiocanRomblon Electric
Cooperative, Inc.Agbalit 0.89
Lumbang 0.49
Silum 1.52
San FernandoRomblon Electric
Cooperative, Inc.*Cantingas
Non-compliant with:
RESHERR0.90
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon IV-B Quezon General NakarEnergy World Kanan
River, Inc.Kanan B-1
Non-compliant with:
last submission of progress report June
2016.Non submission of Quarterly report,
WP, and RESHERR
150.00
Oriental
MindoroNaujan
Philippine Hybrid Energy
Systems, Inc.Mag-asawang Tubig B
Non-compliant with:
PB, Progress report, WP, RESHERR1.00
V Camarines Sur BuhiNASCENT Technologies
Corp.Barit Irrigation Discharge
Non-compliant with:
Performance Bond; Work Plan; RESHERR0.40
People's Energy Services
Inc.Barit 1 1.80
Barit 2
Compliant with:
Work Program, Posting of Performance
Bond
Non-compliant with:
RESHERR
0.60
Goa & TigaonClean and Green Energy
Solutions, Inc.Ranggas
Compliant with:
Work Plan, RESHERR, Progress Reports
Non-compliant with:
Performance Bond
1.50
Catanduanes CaramoranSunwest Water &
Electric Company, Inc.*Hitoma 1
Compliant with:
RESHERR 1.50
San MiguelSunwest Water &
Electric Company, Inc.
*Solong Hydroelectric
Powr Plant
Compliant with:
RESHERR; Work Plan 2.10
Kapipian
Non-compliant with:
- Work Plan
-RESHERR
-Performance bond
2.40
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Luzon V Camarines Norte BasudLevan Marketing
CorporationSan Pascual
Compliant with:
-Work Program
-Posting of performance bond
Non-compliant with:
-RESHERR
1.40
Mercedes
Colasi Mini Hydro
Electric Power Plant
Corporation
Colasi
Non-compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
-RESHERR
0.96
San VicenteMingeophil
Meadowland, Inc.Mananap River 1.00
Sorsogon SorsogonSunwest Water and
Electric Co., Inc.Cawayan 2
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
0.99
Sunwest Water and
Electric Co., Inc. -
Sorsogon II Electric
Cooperative, Inc.
(SUWECO-SORECO II)
Upper Cawayan (Cawayan
1)
Compliant with:
Work Program
Non-compliant with:
• RESHERR
0.60
Visayas VI Aklan LibacaoSunwest Water &
Electric Company, Inc.Main Aklan
Non-compliant with:
Work Plan; RESHERR; Performance Bond15.00
Madalag
Oriental Energy and
Power Generation
Corporation
Timbaban
Compliant with:
-Performance Bond
-RESHERR
Non-compliant with:
-Work plan
18.00
MalayStrategic Power
Development Corp.Aklan Pumped-Storage
Compliant with:
Work Program; Performance Bond;
RESHERR
300.00
Antique BugasongSunwest Water &
Electric Company, Inc. 2Villasiga
Compliant with:
Work Plan
Non-compliant with:
RESHERR
8.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Visayas VI Antique BugasongSunwest Water and
Electric Co., Inc.Villasiga 2
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
9.40
San RemigioCentury Peak Energy
CorporationManinila (Lower Cascade)
Non-compliant with:
RESHERR , Work Program, PB4.50
Maninila (Upper Cascade) Non-compliant with:
RESHERR , Work Program, PB3.10
Sibalom (LowerCascade)
Non-compliant with:
-Work Plan
-Performance bond
-RESHERR
3.30
Sibalom (Middle Cascade)
Non-compliant with:
-Work Plan
-Performance bond
-RESHERR
4.00
Sibalom (Upper Cascade) Non-compliant with:
Work Plan, PB, RESHERR4.20
SebasteAntique Electric
Cooperative, Inc.Caro-an
Non-compliant with:
-Work Plan -RESHERR
-Performance Bond
0.84
Ipayo
Non-compliant with:
-Work Plan -RESHERR
-Performance Bond
0.84
Iloilo IgbarasCentury Peak Energy
CorporationIgbulo (Bais)
Non-compliant with:
RESHERR, PB , UPDATING OF WORK PLAN,
FS NEW CAPACITY
5.10
Negros
OccidentalBago & Murcia
Alsons Energy
Development
Corporation
Bago 4
Compliant with:
Work Plan, Progress Reports
Non-compliant with:
RESHERR, Performance Bond
11.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Visayas VINegros
OccidentalKabankalan
Century Peak Energy
Corporation
Hilabangan ( Lower
Cascade)
Non-compliant with:
-Work Plan -
Posting of performance bond -
RESHERR
3.00
Hilabangan ( Upper
Cascade)
Non-compliant with:
-Work Plan -
Posting of performance bond -
RESHERR
4.80
Sagay City LGU of Sagay Lower Himogaan
Non-compliant with:
Work Plan, Posting of Performance Bond,
RESHERR
4.00
San Carlos City
Alsons Energy
Development
Corporation
Bago 1
Compliant with:
WP
Non-compliant with:
RESHERR, PB
4.00
Bago River Hydro Power
CorporationBago Prosperidad 2
Compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
Non-compliant with:
-RESHERR
3.50
Initihan
Compliant with:
WORK PROGRAM
-PERFORMANCE BOND
Non-compliant with:
-RESHERR
3.50
San Carlos City &
Murcia
Alsons Energy
Development
Corporation
Bago 2
Compliant with:
Performance Bond
Non-compliant with:
Work Program; RESHERR
10.00
Silay & E. B
Magalona
Vivant-Malogo
Hydropower, Inc.Malogo Phase 3
Compliant with:
-Posting of performance bond
-Work Program
2.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Visayas VINegros
OccidentalSilay City
Vivant-Malogo
Hydropower, Inc.Malugo
Compliant with:
Posting of Performance Bond
Non-compliant with:
Work Plan, RESHERR
6.00
Victorias and CadizVivant-Malogo
Hydropower, Inc.Malogo Phase 2 5.00
VII Bohol BatuanGeohydro Power
CorporationBatuan 0.68
DanaoQuadriver Energy
CorporationCantakoy
Non-compliant with:
Work Plan, Posting of Performance Bond,
RESHERR
8.00
Loboc Sta. Clara Power Corp. Loboc 2
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
1.20
Sta. Clara Power
CorporationLoboc
Non-compliant with:
RESHERR 1.20
SevillaBOHECO 1 Sevilla Mini
Hydro Corp.Sevilla
Non-compliant with:
RESHERR2.50
Cebu AlegriaT.A.G Mineral
Resources, Inc.Compostela
Non-compliant with:
RESHERR, Progress Report, Performance
Bond, WP
0.50
ArgaoUniversal
Hydrotechnologies, Inc.Argao
Non-compliant with:
• Work Plan
• Performance Bond
• RESHERR
0.80
Badian Rapids Innoenergy, Inc. Basak II Non-compliant with:
Work Plan; RESHERR; Performance Bond0.50
Negros
OccidentalIsabela
888 Blue Energy
CorporationLimalima-Sacop Phase 1
Non-compliant with:
-Work Program
-RESHERR
-Performance Bond
2.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Visayas VIINegros
OccidentalIsabela
888 Blue Energy
CorporationLimalima-Sacop Phase 2
Non-compliant with:
-Work Program
-RESHERR
-Performance Bond
8.00
Negros Oriental AmlanAmlan Hydroelectric
Power CorporationAmlan
Non-compliant with:
RESHERR0.80
Natural Power Sources
Intergration,Inc.Amlan (Plant A)
Non-compliant with:
- Work Plan
-Performance bond
- RESHERR
3.20
Amlan (Plant B)
Non-compliant with:
Non submission of Quarterly report, PB,
WP, and RESHERR
1.50
Amlan (Plant C)
Non-compliant with:
- Work Plan
- Posting of performance bond
- RESHERR
0.80
La LibertadPNOC - Renewables
Corp.Pacuan-Guinobaan
Non-compliant with:
Work Plan; Performance Bond; RESHERR13.80
Mabinay
Trans-Asia Oil and
Energy Development
Corp,
Ilog
Compliant with:
PB
Non-compliant with:
RESHERR
21.60
Siaton Orbysy Holdings, Inc. Canaway 1
Compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
-RESHERR
1.60
Canaway 2
Compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
-RESHERR
1.40
Siquijor Lazi AQA Global Power Inc. Gabangan Non-compliant with:
RESHERR, Work Program, PB4.14
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Visayas VII Siquijor Lazi AQA Global Power Inc. Senona
Non-compliant with:
RESHERR; Work Program and Performance
Bond
3.20
VIII Eastern Samar LawaanSan Lorenzo Ruiz Samar
Energy and Water, Inc.Pumped Storage Bolusao
Non-compliant with:
WP, PB, RESHERR300.00
Run-of-River Bolusao
Compliant with:
Work Program
Non-compliant with:
• Performance Bond
• RESHERR
12.00
MaslogIraya Energy
CorporationMaslog 40.00
Upper Maslog 9.00
Maydolong Vivant Energy Corp. Buhid
Compliant with:
PB
Non-compliant with:
RESHERR
20.20
Leyte InopacanLeyte IV Electric
Cooperative, Inc.Caminto River
Non-compliant with:
WP, RESHERR, Progress Reports,
Performance Bond
0.50
Jaro & Pastrana
Engineering &
Development
Corporation of the
Philippines
Binaha-an River
Compliant with:
RESHERR
Non-compliant with:
Work Program; Performance Bond
2.20
Southern Leyte St. BernardSouthern Leyte Electric
Cooperative, Inc.Hinabian
Non-compliant with:
• RESHERR0.81
Leyte Kananga
Leyte V Electric
Cooperative, Inc
(LEYECO V)
Bao
Non-compliant with:
- Work Program
- RESHERR
-Performance bond
1.50
Western Samar Calbayog CityClean and Green Energy
Solutions, Inc.Bugtong Falls
Non-compliant with:
WP RESHERR PB1.80
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Visayas VIII Western SamarCalbiga &
Pinabacdao
Meadowland
Developers, Inc.Calbiga
Compliant with:
-Work Plan
Non-compliant with:
-RESHERR -
Performance bond
15.00
Mindanao IXZamboanga del
SurBayog
Global Sibagat Hydro
Power Corp.Bayog
Non-compliant with:
RESHERR, Work Program, PB6.00
Dumingag &
Midsalip
Alsons Energy
Development
Corporation
Sindangan 4 Non-compliant with:
WP, PB, RESHERR8.00
Zamboanga CityMeadowland
Developers, Inc.Saaz
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
1.00
Zamboanga del
NorteLeon Postigo
Euro Hydro Power (Asia)
Holdings, Inc.Polandoc
Non-compliant with:
• Performance Bond
• RESHERR
• Annual and Quarterly Progress Reports
• NWRB, LGU Permit
5.70
MutiaEuro Hydro Power (Asia)
Holdings, Inc.Dapitan River (Middle)
Compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
Non-compliant with:
-RESHERR
3.60
Dapitan River (Upper)
Compliant with:
-WORK PROGAM -
PERFORMANCE BOND
Non-compliant with:
-RESHERR
3.60
Sergio Osmeña Sr.,Clean and Green Energy
Solutions, Inc.Salug-Daku 2
Compliant with:
WP
Non-compliant with:
RESHERR
3.20
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao IX Zamboanga City Zamboanga City PhilCarbon Inc. Pasonanca
Non-compliant with:
Work Program; Performance Bond;
RESHERR
0.05
Pasonanca (Upstream)
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
1.00
Everhydro Corporation Alimpaya
Compliant with:
-Performance bond
-RESHERR
Non-compliant with:
-Work Program
1.20
Ayala
Compliant with:
Performance Bond; RESHERR
Non-compliant with:
Work Program
1.00
Patalon
Compliant with:
PB
Non-compliant with:
Work Plan, RESHERR
0.50
Tagpangi
Compliant with:
- RESHERR
Non-compliant with:
- Postng of performance bond
-Work Program
0.50
(blank) Zamboanga City Everhydro Corporation Curuan 0.70
X Bukidnon BaungonBubunawan Power
Company, Inc.Bubunawan
Non-compliant with:
RESHERR7.00
Rio Verde Water
Constortium, Inc.Rio Verde Inline (Phase I)
Compliant with:
-Work Program -Posting of
performance bond -RESHERR
0.50
Baungon and LibonaFGEN Bubunawan
Hydro CorporationBubunawan
Compliant with:
RESHERR; Performance Bond
Non-compliant with:
Work Plan
23.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao X Bukidnon Cabanglasan
Repower Energy
Development
Corporation
Katipunan River
Compliant with:
WP, RESHERR, Progress Reports
Non-compliant with:
Performance Bond
6.20
Dancagan Hedcor Bukidnon, Inc. Kitaotao 1
Compliant with:
-Posting of performance bond
Non-compliant with:
-Work Program
-RESHERR
70.00
ImpasugongGerphil Renewable
Energy, Inc.Atugan 1 River
Non-compliant with:
- Work Program
- Posting of performance bond
- RESHERR
2.40
Atugan 4
Non-compliant with:
- Work Program
- Posting of performance bond
- RESHERR
3.50
Panoon Non-compliant with:
RESHERR, Generation Reports0.22
LGU of Impasugong Gakaon
Non-compliant with:
- Work Program
-Performance bond
- RESHERR
2.23
Impasugong and
Sumilao
FGEN Tagoloan Hydro
CorporationTagoloan
Compliant with:
Posting of performance bond, RESHERR
Non-compliant with:
Work Plan
39.00
Kalilangan & WaoBukidnon Maladugao
Hydro Power Corp.
Maladugao River (Lower
Cascade)
Compliant with:
-PERFORMANCE BOND
Non-compliant with:
-WORKPLAN
-RESHERR
15.70
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao X Bukidnon LibonaMeadowland
Developers, Inc.Umalag 2
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
2.50
Malaybalay
Repower Energy
Development
Corporation
Sawaga
Compliant with:
WP, RESHERR, Progress Reports
Non-compliant with:
Performance Bond
4.50
Sta. Clara Power Corp. Middle Canayan
Non-compliant with:
-RESHERR -Work
Program -Posting of PB
3.00
MalitbogPhilnewriver Power
Corp.Malitbog HEP
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan, RESHERR
3.40
Silo-o HEP
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
3.29
Manolo FortichFG Bukidnon Power
Corp.Agusan River
Compliant with:
RESHERR; Work Plan 1.60
Oriental Energy and
Power Generation
Corporation
Culaman
Compliant with:
Posting of Performance Bond
Non-compliant with:
Work Plan, RESHERR
10.00
Philnewriver Power
Corp.Mangima HEP
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan; RESHERR
10.00
MaramagMaramag Mini-Hydro
CorporationMaramag
Non-compliant with:
RESHERR , Work Program, PB4.40
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao X Bukidnon Maramag
Repower Energy
Development
Corporation
Pulangui IV
Compliant with:
-Work Program
-Performance bond
- RESHERR
10.00
Santiago Hedcor Bukidnon, Inc. Manolo Fortich 1Compliant with:
Work Plan - RESHERR 43.40
Manolo Fortich 2Compliant with:
Work Plan - RESHERR 25.40
Talakag Markham Resources
CorporationTalakag 3 12.00
ValenciaBukidnon II Electric
Cooperative, Inc.Upper Manupali
Compliant with:
-PERFORMANCE BOND
-RESHERR
Non-compliant with:
-WORKPLAN
4.40
Matic Hydropower
CorporationManupali
Non-compliant with:
Non submission of Quarterly report, PB,
WP
9.00
WaoUPHC Bukidnon Hydro
Power I Corp.
Maladugao River (Upper
Cascade)
Compliant with:
-PERFORMANCE BOND
Non-compliant with:
-WORKPLAN
-RESHERR
8.40
Repower Energy
Development
Corporation
Pulanai River
Compliant with:
WP, RESHERR, Progress Reports
Non-compliant with:
Performance Bond
10.60
Misamis
OccidentalCagayan de Oro City
Meadowland
Developers, Inc.Umalag 1
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
1.80
Turbines Resource &
Development Corp.Limbatangon HEP
Non-compliant with:
RESHERR, PB ,WP9.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XMisamis
OccidentalCalamba
Kaltimex Langaran
Hydro Inc.Langaran
Compliant with:
Work Program
Non-compliant with:
- Posting of performance bond -
RESHERR
3.60
ClarinPhilnew Hydro Power
CorpClarin
Compliant with:
• Submitted Construction Environmental
Safety and Health Program in compliace to
RESHERR requirement on Oct. 6, 2010
5.00
Misamis Oriental ClaveriaMindanao Energy
Systems, Inc.Cabulig
Non-compliant with:
RESHERR 8.00
Philnewriver Power
Corp.Mat-i 2 HEP
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan; RESHERR
1.60
Mat-i 3 HEP
Compliant with:
RESHERR
Non-compliant with:
Performance Bond; Work Plan
3.25
Gingoog CityJE Hydropower
Ventures, Inc.Odiongan River A
Non-compliant with:
RESHERR, PB, Work Program0.25
Oriental Energy and
Power Generation
Corporation
Odiongan (Lower Cascade)
Compliant with:
Performance Bond
Non-compliant with:
RESHERR; Work Program
9.00
Odiongan (Middle
Cascade)
Compliant with:
Performance Bond
Non-compliant with:
RESHERR; Work Program
10.00
Odiongan (Upper Cascade)
Compliant with:
Performance Bond
Non-compliant with:
RESHERR;Work Program
3.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao X Lanao del Norte BacolodLiangan Power
CorporationLiangan
Non-compliant with:
• RESHERR11.90
Iligan CityBukidnon Hydro Energy
CorporationBulanog-Batang
Compliant with:
-Work Program
Non-compliant with:
-RESHERR
-Performance bond
150.00
Euro Hydro Power (Asia)
Holdings, Inc.Bayug HEP
Non-compliant with:
PB,WP, RESHERR17.81
Lower Bayug
Compliant with:
Performance Bond; RESHERR
Non-compliant with:
Work Program
4.00
Upper Bayug
Compliant with:
Performance Bond; RESHERR
Non-compliant with:
Work Program
3.30
First Gen Mindanao
Hydro Power Corp.Cagayan 1N
Compliant with:
WP, PB, RESHERR 160.00
KolamboganEuro Hydro Power (Asia)
Holdings, Inc.Titunod HEP
Non-compliant with:
PB, WP, RESHERR3.60
Cagayan de Oro ClaveriaPhilnew Hydro Power
CorpMat-I 1
Compliant with:
• Submitted Construction Environmental
Safety and Health Program in compliace to
RESHERR requirement on Oct. 6, 2010
Non-compliant with:
• Performance Bond
4.85
X/ARMM
Lanao del
Norte/Lanao del
Sur
Pantar &
Baloi/SaguiaranMaranao Energy Corp. Agus III
Compliant with:
RESHERR
Non-compliant with:
Work Plan, PB
225.00
XI Davao del Sur Davao City Hedcor, Inc. Talomo 1Compliant with:
RESHERR 1.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XI Davao del Sur Davao City Hedcor, Inc. Talomo 3 Compliant with:
RESHERR 1.92
Davao City Hedcor, Inc. Talomo 2ACompliant with:
RESHERR 0.65
Talomo 2BCompliant with:
RESHERR 0.30
Digos CityDavao de Sur Electric
Cooperative, Inc.Ruparan
Compliant with:
- RESHERR
Non-compliant with:
- Posting of performance bond -Work
Program
5.00
Goa & TigaonEuro Hydro Power (Asia)
Holdings, Inc.Guma
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
1.70
MalitaLGU of Malita, Davao
del SurMalita
Non-compliant with:
RESHERR , Work Program, PB2.50
Sta. CruzEuro Hydro Power (Asia)
Holdings, Inc.Napon River
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
2.50
Hedcor Sibulan, Inc . Sibulan ACompliant with:
RESHERR 16.50
Sibulan BCompliant with:
RESHERR 26.00
Tudaya 1 Compliant with:
Work Plan - RESHERR 6.60
Hedcor Tudaya, Inc. Tudaya 2 Compliant with:
RESHERR 7.00
Compostela
ValleyMaco Sta. Clara Power Corp. Hijo River I
Non-compliant with:
- Work Program
-Performance bond
- RESHERR
3.00
Hijo River II
Non-compliant with:
- Work Program
- Posting of performance bond
- RESHERR
3.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XICompostela
ValleyMaco Sta. Clara Power Corp. Mt. Leonard
Non-compliant with:
PERFORMANCE BOND
-WORK PROGRAM
-RESHERR
2.00
Tagum R
Compliant with:
- Work Plan
- Performance bond
Non-compliant with:
- RESHERR
2.60
MaragusanVolga Power
CorporationCaraga 1 4.00
Caraga 2 15.00
New BataanEuro Hydro Power (Asia)
Holdings, Inc.New Bataan HEP
Compliant with:
WP, RESHERR, Progress Reports
Non-compliant with:
PB
2.40
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XI Davao Oriental BagangaFirst Gen Mindanao
Hydro Power Corp.Cateel
Compliant with:
WP, PB
Non-compliant with:
RESHERR
17.50
Global Sibagat Hydro
Power Corp.Baganga River
Compliant with:
RESHERR; Performance Bond
Non-compliant with:
Work Program
11.00
Cateel
Compliant with:
Performance Bond
Non-compliant with:
Work Program; RESHERR
16.00
CaragaLGS Renewable Energies
CorporationCaraga 4
Non-compliant with:
RESHERR, Work Program, PB35.00
Manorigao Non-compliant with:
RESHERR, Work Program, PB17.00
Volga Power
CorporationCaraga A1
Compliant with:
Posting of Performance Bond
Non-compliant with:
Work Program, RESHERR
6.50
Caraga A2
Compliant with:
Posting of Performance Bond
Non-compliant with:
Work Program, RESHERR
7.00
Caraga A3
Compliant with:
Posting of Performance Bond
Non-compliant with:
Work Program, RESHERR
4.50
Governor GenerosoLGS Renewable Energies
CorporationOsmena
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
2.00
Tibanban Non-compliant with:
RESHERR, Work Program, PB2.00
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XI Davao Oriental Governor GenerosoVolga Power
CorporationMagdao
Compliant with:
Posting of Performance Bond
Non-compliant with:
Work Program, RESHERR
2.00
Lupon
Alsons Energy
Development
Corporation
Sumlog 1
Compliant with:
Work Plan, Progress Reports
Non-compliant with:
RESHERR, Performance Bond
8.00
Lupon & Mati
Alsons Energy
Development
Corporation
Sumlog 2 Non-compliant with:
WP, PB, RESHERR15.00
ManayGlobal Sibagat Hydro
Power Corp.Casauman
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
34.00
(blank) Davao CityApo Agua
Infrastructura, Inc.Apo Agua
Compliant with:
PB
Non-compliant with:
RESHERR
2.20
Hedcor, Inc. Talomo 2Compliant with:
RESHERR 0.60
Davao City
San Lorenzo Ruiz
Olympia Energy &
Water, Inc.
Davao Non-compliant with:
WP, PB, RESHERR140.00
Compostela
Valley / Davao
Oriental
Maragusan / CaragaVolga Power
CorporationCaraga 3 16.00
XII North Cotabato AlamadaEuro Hydro Power (Asia)
Holdings, Inc.Alamada HEP
Compliant with:
Work Plan; RESHERR
Non-compliant with:
Performance Bond
2.84
Magpet Universal
Hydrotechnologies, Inc.Magpet 1
Compliant with:
Work Program
Non-compliant with:
• Performance Bond
• RESHERR
9.80
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XII North Cotabato Magpet Universal
Hydrotechnologies, Inc.Magpet 2
Non-compliant with:
- Work Program
- Posting of performance bond
- RESHERR
1.30
MakilalaUniversal
Hydrotechnologies, Inc.Makilala-1
Non-compliant with:
Work Program; RESHERR & Performance
Bond
2.00
Sultan Kudarat Isulan
Engineering &
Development
Corporation of the
Philippines
Kabulnan 4 10.00
Philnewriver Power
Corp.Kabulnan 2 HEP
Non-compliant with:
Non submission of Quarterly report, PB,
WP, and RESHERR
110.00
Sen. Ninoy Aquino
Engineering &
Development
Corporation of the
Philippines
Kabulnan 3 5.00
Sarangani AlabelEuro Hydro Power (Asia)
Holdings, Inc.Lun River 2.82
Maasim
Alsons Energy
Development
Corporation
Siguil
Compliant with:
-Work Program
Non-compliant with:
-RESHERR
15.10
Maitum
Alsons Energy
Development
Corporation
Kalaong 1
Compliant with:
-WORK PLAN
Non-compliant with:
-PERFORMANCE BOND
-RESHERR
7.40
Kalaong 2
Compliant with:
-Work Plan
Non-compliant with:
-RESHERR -
Performance Bond
4.80
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XII Sarangani Maitum
Alsons Energy
Development
Corporation
Kalaong 3
Compliant with:
Work Plan, Progress Reports
Non-compliant with:
RESHERR, Performance Bond
4.00
Malungon
Kiblat Malandag Royeca
Mini-Hydro Power
Project
Kiblat-Royeca Malandag
Power House 1-A
Non-compliant with:
WP,PB, RESHERR
1.46
Kiblat-Royeca Malandag
Power House 2
Non-compliant with:
WP,PB, RESHERR
0.80
South CotabatoKoronadal &
Tampakan
Euro Hydro Power (Asia)
Holdings, Inc.Marbel 1
Non-compliant with:
RESHERR, Work Program, PB0.50
Lake SebuEuro Hydro Power (Asia)
Holdings, Inc.Laconon
Compliant with:
Performance Bond; RESHERR
Non-compliant with:
Work Program
4.85
Lanon (Lam-alu) Non-compliant with:
RESHERR , Work Program, PB9.50
South Cotabato I
Electric Cooperative,
Inc.
Takbo
Non-compliant with:
Work Program; RESHERR; Performance
Bond
15.00
XIIIAgusan del
NorteButuan City
Equi-Parco Construction
Co.Taguibo 1
Non-compliant with:
- Posting of performance bond
- RESHERR -Work Program
2.00
Taguibo 2
Non-compliant with:
Work Program; RESHERR; Performance
Bond
2.00
Global Sibagat Hydro
Power Corp.Bugsukan
Non-compliant with:
Work Program, Posting of Performance
Bond, RESHERR
5.00
CabadbaranFGEN Cabadbaran
Hydro CorporationCabadbaran
Non-compliant with:
-Work Plan
-RESHERR -
Performance bond
9.75
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XIIIAgusan del
NorteJabonga
Agusan Power
CorporationLake Mainit
Compliant with:
- Work Plan
- RESHERR
- Posting of performance bond
25.00
FGEN Puyo Hydro
CorporationPuyo
Compliant with:
- Performance bond
Non-compliant with:
-RESHERR
-Work Plan
30.00
SantiagoAsiga Green Energy
CorporationAsiga
Non-compliant with:
RESHERR, PB8.00
Surigao del Sur CantilanMeadowland
Developers, Inc.Lower Carac-an
Non-compliant with:
RESHERR, Performance Bond, WP5.00
Carrascal and
Cantilan
Hydro Link Projects
CorporationCarac-an
Non-compliant with:
-RESHERR -Work
Program
25.00
San Miguel
Surigao del Sur II
Electric Cooperative,
Inc.
Carromata Non-compliant with:
PB, Progress Reports , RESHERR5.60
Sagbayan 0.64
Tandag City and San
Miguel
Surigao del Sur II
Electric Cooperative,
Inc.
Calatngan 3.60
Agusan Del Sur SibagatEqui-Parco Construction
Co.Wawa 1
Non-compliant with:
- Work Program
- Posting of performance bond -
RESHERR
7.70
Wawa 2
Compliant with:
-WORK PROGRAM
-PERFORMANCE BOND
Non-compliant with:
-REHERR
7.00
Wawa 3
Non-compliant with:
- Performance bond
- RESHERR
5.60
AWARDED HYDROELECTRIC POWER PROJECTS as of June 30, 2017
ISLAND /
REGIONREGION PROVINCE MUNICIPALITY COMPANY NAME NAME OF PROJECT STATUS
POTENTIAL
CAPACITY
(MW)
INSTALLED
CAPACITY
(MW)
Mindanao XIII Agusan Del Sur Sibagat
Global Sibagat
Hydropower
Corporation
Managong
Non-compliant with:
RESHERR; Performance Bond; Work
Program
6.00
Wawa
Compliant with:
Performance Bond; Work Program
Non-compliant with:
RESHERR
13.00
Sta. Clara Power Corp. Hilong-hilong 4 5.00
ARMM Lanao del Sur Malabang AQA Global Power Inc. Matadi River HEP
Compliant with:
• Work Program
• Posting of performance bond
• RESHERR
• Posted Performance Bond for Year 2 on
July 5, 2016 under Pacific Union Insurance
Co., Inc. covering the period from July 7,
2016 to July 7, 2017.
Non-compliant with:
• Work Plan
• Performance Bond
• RESHERR
27.00
Malabang & Tubaran AQA Global Power Inc. Maitling River HEP Non-compliant with:
WP, RESHERR50.00
Pualas & Ganassi AQA Global Power Inc. Lake Dapao HEP
Compliant with:
PB
Non-compliant with:
RESHERR , Work Program
50.00
Grand Total 13,419.73 965.04