ALC+2 ODU view
ALC+2 IDU view
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
2/15
We need to collect USB driver (software) from SIAE persons
Before login we need install Erio USB
driver(collect form SIAE)
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
3/15
After Log in This page will show (Inside equipment)
User ID: SYSTEM
Password: siaemicr
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
4/15
IDU Commissioning
ODU Commissioning-put Tx-Power here (by moving mouse)
ODU Commissioning-put frequency here (by UP & Down option)
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
5/15
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
6/15
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
7/15
Interference cheek(Go to Main menu and click Active manual Operation)
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
8/15
For Inventory reports
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
9/15
Enable LAN ports
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
10/15
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
11/15
NMS connectivity procedure
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
12/15
For getting both sites view one menu
For Local site(user
site)
For Remorte site
(far end site)
Put IP here
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
13/15
To set equipment properties & time
Enabling ACM (Adaptive code modulation)
QoS Settings
-
8/17/2019 ALC+2 IDU & ODU commissioning procedure
14/15
Diffserve/ classification settings
DSCPVLAN
priority
Internal
Priority
NEC
Ingress
Internal
Priority
NEC
Egress
PHB
Huawei
Internal
Priority
SIAE
Egress
0~7 0
8~15 1
16~23 2
24~31 3
32~39 4
40~47 5 2 EF 2
48~55 6
56~63 73 CS7 3
0 AF3 0
1 AF4 1
-