HP+™ Wall SystemsAdvanced wall assembly systems for 2016 Title 24 compliance
High Performance Structural Foam Wall SystemWhat’s in a wall
BASF HP+ Wall Assemblies
How do they comply with 2016 Title 24
How can they help your business
What must a wall do to be “high performance”?
• Structure – gravity, uplift, lateral (shear)
• Moisture– control rain and drain the assembly
• Air – control air transported heat and moisture
• Vapor– control condensation risk / drying potential
• Thermal– control energy efficiency and comfort
High Performance = All above + Affordability
Moisture Air Vapor Thermal
HP+ Systems 4.28.2016 3
Structure
Housewrap
Fiberousinsulation
Detailed air sealing
Studs and sheathing
Standard Construction
HP+™ Wall Systems (Patents pending)
Values• Integrated control layers• Higher effective R-value means
lower total U-value• Material efficiency• Decreased moisture risk• Improved structural performance• 3rd party validated• Suitable for any climate zone
Components• Optional Advanced framing• Walltite HP+ closed cell SPF• Neopor continuous insulation• WRB (housewrap, or Enershield)• Optional fire rated or wood
sheathings• Optional fill insulation
E Series | X Series | FR Series | XR Series4HP+ Systems 4.28.2016
HP+ E Series
HP+ Systems 4.28.2016 5
Advanced FramingSaves wood and cost
Neopor GPS BoardVapor permeable continuous insulation
Liquid or Sheet WRBWeather barrier
SealantsAdditional air sealing
Optional FillUp to R-24 in 2x4 (U=0.050)
Walltite HP+ ccSFPLateral strength, air/vapor barrier
HP+ X Series
HP+ Systems 4.28.2016 6
Advanced FramingSaves wood and cost
Neopor GPS BoardVapor permeable continuous insulation
OSBAdditional lateral strength
Liquid or Sheet WRBWeather barrier
SealantsAdditional air sealing
Optional FillUp to R-24 in 2x4 (U=0.050)
Walltite HP+ ccSFPLateral strength, air/vapor barrier
HP+ FR Series
HP+ Systems 4.28.2016 7
Fire Rated GypsumUL 1-hour rated V306 design
Advanced FramingSaves wood and cost
SealantsAdditional air sealing
Optional FillUp to R-24 in 2x4 (U=0.050)
Walltite HP+ ccSFPLateral strength, air/vapor barrier
Neopor GPS BoardVapor permeable continuous insulation
Liquid or Sheet WRBWeather barrier
HP+ XR Series
HP+ Systems 4.28.2016 8
Wood spacerForms continuous layer of ccSPF
Advanced FramingSaves wood and cost
OSB
SealantsAdditional air sealing
Optional FillUp to R-24 in 2x4 (U=0.050)
Walltite HP+ ccSFPLateral strength, air/vapor barrier
Liquid or Sheet WRBWeather barrier
Uavg =84% × 0.04 + 16% × 0.10
100%
= 𝟎𝟎.𝟎𝟎𝟎𝟎𝟎𝟎
R = �1U = �1
0.050 = 𝐑𝐑 𝟐𝟐𝟎𝟎.𝟏𝟏
9
R-13+5 2x4 (2013 Title 24)HP+ E Series 2x4 with AWS
U = ⁄1 R R = ⁄1 𝑈𝑈
Uavg =A1 × U1 + A2 × U2 + …
Atotal
Uavg =75% × 0.05 + 25% × 0.09
100%
= 𝟎𝟎.𝟎𝟎𝟎𝟎𝟏𝟏
R = �1U = �1
0.061 = 𝐑𝐑 𝟏𝟏𝟎𝟎.𝟒𝟒
HP+ Systems 4.28.2016
R-13+5 2x4 @ 16"o.c. Cavity StudAir films, wrb, gyp 1.36 1.363/8" 1-coat Stucco 0.08 0.087/16" OSB 0.44 0.44Continuous Insulation 5 5Spray foam - -Fill insulation 13 -Wood Stud - 3.5Total R-value R1 19.9 R1 10.8Total U-value U1 0.05 U1 0.09Area A1 75% A1 25%
HP+ E Series + AWS Cavity StudAir films, wrb, gyp 1.36 1.363/8" 1-coat Stucco 0.08 0.087/16" OSB - -Neopor rigid foam 5 5ccSPF (R-6.7/in) 10.05 -Fill insulation (R-4.2/in) 8.4 -Wood Stud - 3.5Total R-value R1 24.9 R1 10.4U-value U1 0.04 U1 0.10Area A1 83% A1 17%
Uavg =84% × 0.04 + 16% × 0.10
100%
= 𝟎𝟎.𝟎𝟎𝟎𝟎𝟎𝟎
R = �1U = �1
0.050 = 𝐑𝐑 𝟐𝟐𝟎𝟎.𝟏𝟏
10
R-19+5 2x6 (2016 Title 24)HP+ E Series 2x4 with AWS
U = ⁄1 R R = ⁄1 𝑈𝑈
Uavg =A1 × U1 + A2 × U2 + …
Atotal
Uavg =75% × 0.05 + 25% × 0.09
100%
= 𝟎𝟎.𝟎𝟎𝟎𝟎𝟎𝟎
R = �1U = �1
0.061 = 𝐑𝐑 𝟐𝟐𝟎𝟎.𝟏𝟏
HP+ Systems 4.28.2016
R-19+5 2x6 @ 16"o.c. Cavity StudAir films, wrb, gyp 1.36 1.363/8" 1-coat Stucco 0.08 0.087/16" OSB 0.44 0.44Continuous Insulation 5 5Spray foam - -Fill insulation 18 -Wood Stud - 5.5Total R-value R1 24.9 R1 12.8Total U-value U1 0.04 U1 0.08Area A1 75% A1 25%
HP+ E Series + AWS Cavity StudAir films, wrb, gyp 1.36 1.363/8" 1-coat Stucco 0.08 0.087/16" OSB - -Neopor rigid foam 5 5ccSPF (R-6.7/in) 10.05 -Fill insulation (R-4.2/in) 8.4 -Wood Stud - 3.5Total R-value R1 24.9 R1 10.4U-value U1 0.04 U1 0.10Area A1 83% A1 17%
• Quantifies degrading effect of air leakage across full wall assemblies under pressure (like that created by wind) at various temperatures
• 2x4 HP+ assemblies thermally outperform walls with full cavity insulation, even vs. 2x6 construction
• Air tight construction gives HP+ a 95% less risk of condensation, 98% reduction in energy used to condition air from air leaks
HP+ Wall – Thermal Metric StudyConducted by RDH Building Science Inc.
11HP+ Systems 4.28.2016
144 107.6 35.6 0 -18.4
Climate Box Temperature (F)
R-V
alue
(ft2 F
·h/B
tu)
• 2x4 studs, R-10 (1.5”) Walltite HP+ with added fill insulation, R-5 Neopor continuous insulation
• 25% higher effective R-value than R-21 fiberglass in 2x6 cavity
HP+ Wall – Thermal Metric Study Results
12HP+ Systems 4.28.2016
25%
25%
Technical Evaluation Report (TER)
• Provides structural design values based on testing data suitable for prescriptive code, or engineering based bracing methods
• Allows engineer to reduce burden on engineered bracing solutions
• Aids in creation of braced wall design drawing of the lateral load system
HP+ Systems 4.28.2016 13
What is the Quality Assurance Plan (QAP)?• The QAP is a series of documents and guidelines designed to work in concert
with one another to, collectively, ensure the highest quality standards that are required for the installation of HP+ Wall Systems
What is the Quality Assurance & Training Program (QATP)?• Teaches the Installer specific requirements of processing and applying BASF’s
liquid spray foam compounds in the field following the Engineer product testing• Certifies each individual Installer fully understands expectations of each and
every application of WALLTITE® HP+ and installation of the HP+ Wall System, • Understand the consequences for non-compliance
Why should builder care? What does it mean for them?• Reduces liability • Ensures proper SPF installation• Results in a higher performing product (versus other insulation options)• Differentiation from competition • 10 year system warranty
Why should installer care? Why would they want to be part of the program?• Demonstrates high level of craft • Become a reliable asset for the builder• Differentiate from competition • Strengthen industry
BASF’s Quality Assurance Program
14HP+ Systems 4.28.2016
• Quality Assurance (QA) – explains in-field procedures
• Quality Control (QC) – explains QC specifications of the system components
• Quality Assurance Training Program (QATP) – certifies individual applicators
• Daily Work Record – applicator documents site conditions and on-site test results
• Technical Evaluation Report (TER) – validates how the wall system meets code
• Technical Installation Manual – explains how to properly construct each wall system
• Field Assembly Guide – graphic step-by-step installation guide
• HP+ System Quick Reference – helps site supervisors ensure accurate installation
• Builder Checklist – required completion by builder documents specific installation conditions
BASF’s Quality Assurance Program Training and documentation tools
15HP+ Systems 4.28.2016
The HP+ Wall System enables:
• Decreased condensation risk while maintaining drying strategy
• 30-60% more effective R-value in walls (with 30% less wood)
• Reduce air infiltration to 3 ACH50 or less
• 10-15% cooling load reduction (downsizing)
• Meet or exceed 2016 Title 24 performance
• Suitable for on-site or panelized construction
• Monthly energy savings can exceedmonthly mortgage increase from day one!
Create value through high performance
What does all this mean for you?
16HP+ Systems 4.28.2016
[email protected] | www.construct ion.basf.us | (888) 307-6602
Chris Rosemond, Assoc. AIA, HERS
Construction Science Architect
BASF Center for Building Excellence
[email protected] | 980.218.1884
18