Download - A9130 BSC Evolution Commissioning Ed20
Alcatel BSS
A9130 BSC Evolution
Commissioning
BSC & TC Document
Commissioning Manual
Release B9
3BK 17422 3121 RJZZA Ed.20P08
Status IN PREPARATION
Short title mxbsccom
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel/Evolium.
BLANK PAGE BREAK
2 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
1.1.1 Hardware Description - Rack Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.1.3 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.1.4 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.1.5 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.2.2 Site-Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.4 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
1.4.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.4.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.4.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
2 A9130 BSC Evolution Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.1 Before Going on Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.2 Before You Start (On Arrival at the Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
2.3 Complete BSC Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.3.1 Install Boards in ATCA Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.3.2 Check Boards Position in LIU Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.3.3 Check the ATCA-LIU Ethernet Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272.3.4 Check the JSXLIU Shelf Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.3.5 Connect PCM Cables to JSXLIU Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
2.4 Hardware Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.4.1 Check the Equipment Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.4.2 Check the JAXPC Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.4.3 Check the JBXFAN Switch Position . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
2.5 Powering Up the BSC Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342.5.1 Check the Customer Power Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342.5.2 Check Polarity of DC Cables on BSC Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342.5.3 Powering Up the BSC Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362.5.4 Check Power Line Redundancy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
2.6 Check BIOS Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 382.7 Software Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 382.8 Check the Firmware Version . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 382.9 Commissioning Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
2.9.1 Option: LMT Installation (O1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 392.9.2 Connect the LMT to the BSC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 392.9.3 Option: Connect O&M cables from MFS to BSC (O2) . . . . . . . . . . . . . . . . . . . . . . 402.9.4 Perform the Rack Inventory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
2.10 Connect the OMC-R . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.11 Option: Check the Connection with the CBC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
2.11.1 Open a Telnet Session . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 422.11.2 Ping the CBC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
2.12 End of Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 3 / 44
Contents
4 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
Preface
Preface
Purpose This document describes the configuration and verification procedures to becarried out when commissioning the A9130 BSC Evolution in release B9.
What’s New In Edition 20The reference to IO 114 was removed.
Figures 2, 3, 12 , 15 and 18 were updated.
Description update in Powering Up the BSC Rack (Section 2.5.3).
In Edition 01First official release of the document.
Audience This document is addressing to the following:
Site administrators
Supervisors
Project managers
Field service technicians
Occasional users
Assumed Knowledge The personnel involved must be familiar with:
Commissioning tools
Personal Computers using the Windows 2000/XP environment
Digital’s UNIX operating system environment.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 5 / 44
Preface
6 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
1 Overview
1 Overview
This Overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 7 / 44
1 Overview
1.1 Presentation
1.1.1 Hardware Description - Rack Configurations
The following figure shows the rack layout for an A9130 BSC Evolution in 600TRX configuration.
123456789012345678912345678901234567891234567890123456789
−48 / 60 VDC
4A
−48 / 60 VDC
4A
XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX
LIUShelf 1
Free Space(ATCA Shelf 4)
ATCAShelf 3
JSXPDU
JBX
SS
W
JBX
SS
W
JBX
OM
CP
JBX
OM
CP
JBX
CC
P
JBX
CC
P
JBX
TP
JBX
TP
Not
Use
d
JBX
CC
P
JBX
CC
P
Free space(LIU Shelf 2)
Air inlet
Not
Use
d
Not
Use
d
Not
Use
d
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Figure 1: Example of A9130 BSC Evolution Rack Layout - Front View
8 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
1 Overview
The following figure shows the rack layout for an A9130 BSC Evolution 600TRX configuration /A9130 MFS Evolution 9 JBXGPU configuration in case ofrack shared configuration.
1234567890123456789123456789012345678912345678901234567891234567890123456789
CLOSED / OPEN
H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
−48 / 60 VDC
4A
−48 / 60 VDC
4A
XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX
LIUShelf 1
ATCAShelf 3
ATCAShelf 4
JSXPDU
JBX
SS
W
JBX
SS
W
JBX
OM
CP
JBX
OM
CP
JBX
GP
U
LIUShelf 2
Air inlet
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
JBX
GP
U
JBX
GP
U
JBX
GP
U
JBX
GP
U
JBX
GP
U
JBX
GP
U
JBX
GP
U
JBX
GP
U
JBX
GP
U
−48 / 60 VDC
4A
−48 / 60 VDC
4A
XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX
1234567890123456789123456789012345678912345678901234567891234567890123456789
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
Air inlet
JBX
TP
JBX
TP
No
t U
sed
JBX
CC
P
JBX
SS
W
JBX
SS
W
JBX
OM
CP
JBX
OM
CP
JBX
CC
P
JBX
CC
P
JBX
CC
P
No
t U
sed
No
t U
sed
No
t U
sed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
graphics/174223121003.cgm
Figure 2: Example of A9130 BSC Evolution Rack Layout - Front View
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 9 / 44
1 Overview
The following figure shows the rack layout in case of rack shared by two A9130BSCs Evolution 600 TRX configuration.
−48 / 60 VDC
4A
−48 / 60 VDC
4A
XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX
LIUShelf 1
ATCAShelf 3
ATCAShelf 4
JSXPDU
LIUShelf 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
−48 / 60 VDC
4A
−48 / 60 VDC
4A
XPEM XLIU XMUXXLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEMXMUX
1234567890123456789123456789012345678912345678901234567891234567890123456789
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
Air inlet
JBX
TP
JBX
TP
No
t U
sed
JBX
CC
P
JBX
SS
W
JBX
SS
W
JBX
OM
CP
JBX
OM
CP
JBX
CC
P
JBX
CC
P
JBX
CC
P
No
t U
sed
No
t U
sed
No
t U
sed
1234567890123456789123456789012345678912345678901234567891234567890123456789
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
Air inlet
JBX
TP
JBX
TP
No
t U
sed
JBX
CC
P
JBX
SS
W
JBX
SS
W
JBX
OM
CP
JBX
OM
CP
JBX
CC
P
JBX
CC
P
JBX
CC
P
No
t U
sed
No
t U
sed
No
t U
sed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
graphics/174223121006.cgm
Figure 3: Example of Two A9130 BSC Evolution Rack Layout - Front View
10 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
1 Overview
The following figure shows the back rack layout for an A9130 BSC Evolutionin any configuration.
JAX
SS
W
JAX
SS
W
−(P
OW
ER
)
+(R
ET
UR
N)
−(P
OW
ER
)
+(R
ET
UR
N)
−(P
OW
ER
)
+(R
ET
UR
N)
−(P
OW
ER
)
+(R
ET
UR
N)
OOS
OK
ACT
H/S
OOS
OK
ACT
H/S
12345678901234567890123456789012345678901234567890123456789012345678901234567890
Air outlet
GND
JBXPS JAX
SM
M
JAX
PC
JAX
PC
JBXPS JBXPS JBXPS
ATCAShelf 3
(rear side)
JAX
SM
M
Open
Closed
OOS
OK
Ha
nd
le
H/S
Alarm/Reset
Te
lco
Ala
rms
& R
ela
ys
JAXPC
Open
Closed
OOS
OK
Ha
nd
le
H/S
Alarm/Reset
Te
lco
Ala
rms
& R
ela
ys
JAXPC
graphics/174223121002.cgm
Figure 4: Example of A9130 BSC Evolution Rack Layout - Rear View
1.1.2 Cases
None.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 11 / 44
1 Overview
1.1.3 Options
The following option applies:
O1: Install LMT
O2: Connect O&M cables from MFS to BSC, in rack shared configuration
1.1.4 Restrictions
None.
12 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
1 Overview
1.1.5 Grouped Task Sequence
The following figure shows the task sequence for the A9130 BSC Evolutioncommissioning.
Before going site
Before you start
Boards installation
Hardware check
Set LIU shelf address
Power up rack
Check firmware version
Commisioning test
Connect the OMC−R
Check connection to CBC
End commissioning
graphics/174213121opprinc.cgm
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 13 / 44
1 Overview
1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply:
The site must conform to the "Safety rules" (see BSS Methods Handbook).
The site must conform to SPP- 59, Specification for Site Preparation
A9130-BSC
The OMC-R must be operational and ready for connection to the BSC.
The router must be configured and ready for connection (if applicable).
1.2.2 Site-Specific Information
Network information:
BSC Id and name
External Host name, external IP address and netmask for each OMCPstation
IP address of the alias host name for active station ("station_BSC")
IP address for the default gateway for external network used for connection
BSC - OMC
IP address for the CBC
User name and password for external router between BSC and CBC
Ports in external router where to connect the Ethernet cables
Routing configuration between OMC-R and BSC
Local network sockets position to plug in the OMCP Servers networkcables (if applicable)
Position of cables connection on the CISCO router to plug in the OMCPServers network cables (if applicable).
BSC configuration: Number of CCP boards.
14 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
1 Overview
1.3 SchedulingThe following table gives the duration for each task.
Task Duration (min)
Preliminary checks
Preparation before leaving for the site 15
Before starting (on arrival at the site) 10
Boards installation 20
Hardware check 10
Set LIU shelf address 5
Powering up the BSC rack
Check the power panel 5
Check the polarity on the BSC side 10
Powering up the BSC rack 5
Check power line redundancy 10
Check firmware version 30
Commissioning tests
Option: LMT installation 20
Connecting LMT to the BSC 2
Software installation 65
Perform rack inventory 15
Connecting the OMC-R 10
Option: Check the connection with the CBC 5
End of commissioning 10
Total 4h10
Table 1: Scheduling
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 15 / 44
1 Overview
1.4 Resources
1.4.1 Tools
1.4.1.1 Hardware ToolsThe following table is used to check, at base, the availability of the necessarytools.
SeeTools Catalogue for Field Activity for checking the content.
Kit name Reference Calibration
Basic kit OUT 001 NO
Test cables and plugs (BSC) OUT 013 NO
Utility PC (IMT) DES 002 NO
Digital multimeter DES 001 NO
1.4.1.2 Software ToolsThe following table is used to check, at base, the availability and the versionof the necessary software.
Refer to the corresponding document for checking the SW version.
Name Version checking
Windows 2000/XP -
Netscape Communicator 4.78 -
1.4.1.3 FormsNone.
1.4.2 Supplies
None.
16 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
1 Overview
1.4.3 Applicable Documents
The following list is used to check, at base, the availability of the necessarydocuments.
Catalogue of Technical and Logistic Information (ITL), 3DF 00462 0004AAAGA
Catalogue of Instruction Operation (IO), 3DF 00300 0004 UAZZA
B9 BSS Methods Handbook, 3BK 17422 0002 PCZZA
CI 08 - Site Equipment Inventory, 3BK 17257 0001 RJZZA
Tools Catalogue for Field Activity, 3BK 20458 0001 RJZZA
SPP-59, Specification for Site Preparation A9130 MFS/BSC Evolution,
8BL 00704 0076 DRZZA
BSS site premises inspections, post handover, 8BL 00704 0016 DRBRA
Site Premises Inspection Form (CEL), 8BL 00704 0015 DRBRA
A9130 BSC Evolution Software Installation, 3BK 17422 3126 RJZZA
A9130 BSC Evolution Firmware Upgrade, 3BK 17422 3106 RJZZA.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 17 / 44
1 Overview
18 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2 A9130 BSC Evolution Commissioning
This section describes the tasks to be performed during A9130 BSC Evolutioncommissioning.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 19 / 44
2 A9130 BSC Evolution Commissioning
2.1 Before Going on SiteBefore going on site you must check the following:
All Prerequisites (Section 1.2.1) are fulfilled
The customer has been informed of the
Date and time
Site name and address
Purpose of the operation.
Personnel are available and ready for operation (refer to Scheduling(Section 1.3)
Site-Specific Information (Section 1.2.2) is available
Tools (Section 1.4.1) are available and ready for operation
Software Tools (Section 1.4.1.2 ) are available and ready for operation
Applicable Documents (Section 1.4.3) are available.
2.2 Before You Start (On Arrival at the Site)
2.2.1 Checks
Before you start, perform the following operations:
Check that all Prerequisites (Section 1.2.1) are fulfilled
Check applicable notifications and operating instructions (refer to the
Applicable Notifications List and Applicable Operation Instructions List)
Check the availability of all necessary tools and supplies.
Refer to BSS site premises inspections, post handover and complete the
Site Premises Inspection Form (CEL).
Check that the safety precautions have been taken in accordance with the
safety instructions described in the B9 BSS Methods Handbook.
Check which Cases (Section 1.1.2) or Options (Section 1.1.3) apply
Complete the header field of the CCL. The CCL is completed as eachinstruction is carried out.
2.2.2 Required Knowledge
You must be familiar with the following:
The safety rules and precautions given in the B9 BSS Methods Handbook.
How to document faults and anomalies as described in the B9 BSS
Methods Handbook.
20 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.3 Complete BSC Configuration
2.3.1 Install Boards in ATCA Shelf
To install the boards:
1. Check the configuration requested by the customer. Refer to Site-SpecificInformation (Section 1.2.2) for details.
Note: Shelf filling is done from center to shelf sides.
The following tables gives the JBXCCP boards allocation in ATCA shelf.
Physical slotsBoards Configuration(No. of TRX)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
200 - - - - x - - - - x - - - -
400 - - - - x - - - - x x - - -
JBXCCP
600 - - - x x - - - - x x - - -
Table 2: JBXCCP Position in ATCA Shelf
The ATCA configuration is described in the following figure:
123456789012345678901234567890121123456789012345678901234567890121123456789012345678901234567890121123456789012345678901234567890121123456789012345678901234567890121
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
CLOSED / OPEN H/S OOS
JBX
SS
W
JBX
SS
W
JBX
OM
CP
JBX
OM
CP
JBX
CC
P
JBX
CC
P
Not
Use
d
JBX
TP
JBX
TP
JBX
CC
P
JBX
CC
P
CLOSED / OPEN H/S OOS
Air inlet
Physicalslot
1 2 3 4 5 6 7 8 9 10 11 1312 14
Not
Use
d
Not
Use
d
Not
Use
d
graphics/174223121004.cgm
Figure 5: ATCA Shelf Boards
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 21 / 44
2 A9130 BSC Evolution Commissioning
2. Put on an ESD wrist strap and connect it to the shelf by attaching the frontor rear ESD jack.
3. Ensure that the lower and upper handles are in the outward position.
4. Insert the board into the shelf by placing the top and bottom edges of theboard in the card guides of the shelf.
Ensure that the guiding module of shelf and board are aligned properly.Press the lower and upper parts of the handle together.
graphics/174213111018.cgm
Figure 6: Insert the Board
5. Slide the board into the shelf until you feel resistance.
22 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
6. Simultaneously move the top and bottom handles to the inward position tolock the board to the shelf.
graphics/174213111blade.cgm
Figure 7: Board in ATCA Shelf, Secured with Handles to the Inward Position
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 23 / 44
2 A9130 BSC Evolution Commissioning
7. Install one by one all the boards for the requested configuration. Duringboards insertion:
Holes on back side of the board must be in line with guiding pins on
the back plane
graphics/174213111008.gif
Figure 8: Holes in Line with Guiding Pins
EMI stripes must not be damaged when inserting the boards
graphics/174213111009.gif
Figure 9: EMI Stripes
8. Tighten the front plate screws to secure the board to the shelf.
9. Insert a filler (JBXFILL) in each unused slot.
10. Tighten the front plate screws to secure the filler to the shelf.
24 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.3.2 Check Boards Position in LIU Shelf
Check the configuration requested by the customer. Refer to Site-SpecificInformation (Section 1.2.2) for details.
In case of 200 and 400 TRX configurations check that there are boards onslots 19 and 20 (for slot numbering, see Figure 2), otherwise you must replacethe JBXDUM fillers from slots 19 and 20 with the JBXLIU boards from slots 8and 9, using the procedure below.
The following table shows the boards correspondence in case of replacingJBXLIU with JBXDUM:
JBXLIU JBXDUM
8 19Slot No. in LIUShelf
9 20
Table 3: Boards Correspondence
To move the boards from slots 8 and 9 to slots 19 and 20, in LIU shelf:
1. Put on an ESD wrist strap and connect it to the shelf by attaching thefront or rear ESD jack
2. Unfasten the top and the bottom screws of the JBXDUM fillers.
3. Remove the JBXDUM fillers.
4. Unfasten the top and the bottom screws of the JBXLIU boards.
The bottom screw is located under the handle.
5. Using the board handle, remove the JBXLIU boards.
6. Using the board handle, insert the JBXLIU boards to the correspondingslots, until you feel resistance (for boards correspondence see Table 3).
7. Fasten the top and the bottom screws of the JBXLIU boards.
8. Insert the JBXDUM fillers in the empty slots.
9. Fasten the top and the bottom screws of the JBXDUM fillers.
The following figures show the LIU shelf for different A9130 BSC Evolution200 and 400 TRX configurations.
−48 / 60 VDC
4A
−48 / 60 VDC
4A
JBXPEM JBXLIU JBXMUXJBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXPEMJBXMUXJBXDUM JBXDUM JBXDUM JBXDUM JBXDUM JBXDUM JBXDUMJBXDUM
graphics/174213121001.cgm
Figure 10: LIU Shelf for BSC with 200 and 400 TRX Configuration
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 25 / 44
2 A9130 BSC Evolution Commissioning
The following figures show the LIU shelf for different A9130 BSC Evolution600 TRX configuration.
−48 / 60 VDC
4A
−48 / 60 VDC
4A
JBXPEM JBXLIU JBXMUXJBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXPEMJBXMUX
graphics/174213121002.cgm
Figure 11: LIU Shelf for BSC with 600 TRX Configuration
26 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.3.3 Check the ATCA-LIU Ethernet Cables
Shelves used for A9130 BSC Evolution configurations are:
ATCA shelf 3 with LIU shelf 1
ATCA shelf 4 and LIU shelf 2.
Therefore the inter-shelves Ethernet cables are always connected between:
ATCA shelf 3 and LIU shelf 1
ATCA shelf 4 and LIU shelf 2.
To connect ATCA-LIU Ethernet cables:
1. Connect the first JLCAT6 Ethernet cable (1AB 22983 0005) on ATCA shelf3/4, JAXSSW1, Ethernet port 2. See Figure 12.
ETH8
OOS
OK
ACT
HS
ETH1
ETH2
ETH3
ETH4
ETH5
ETH6
ETH7
ETH8
OOS
OK
ACT
HS
ETH1
ETH3
ETH4
ETH5
ETH6
ETH7
ATCA Shelf 3Rear side
JAXSSW2 JAXSSW1
JBXMUXJBXLIU JBXMUXJBXLIU JBXLIU JBXLIUJBXDUM
TestTest
GbEGbE
JLCAT6 Ethernet cables1AB 22983 0005
LIU Shelf 1Front side
ETH2
graphics/174213111013.cgm
Figure 12: JLCAT6 Cable Connection
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 27 / 44
2 A9130 BSC Evolution Commissioning
2. Run the cable under the JSXLIU shelf 1
ATCA Shelf 4
LIU Shelf 1
ATCA Shelf 3
Free Space(LIU Shelf 2)
FRONT REAR
123456789012345678123456789012345678
graphics/174213111014.cgm
Figure 13: JLCAT6 Cable Routing
3. Connect the first JLCAT6 Ethernet cable (1AB 22983 0005) to the GbE porton JBXMUX1 (slot 10) in JSXLIU shelf 1/2. See Figure 12.
4. Connect the second JLCAT6 Ethernet cable (1AB 22983 0005) on ATCAshelf 3/4, JAXSSW2, Ethernet port 2. See Figure 12.
5. Run the cable under the JSXLIU shelf 1. See Figure 13.
6. Connect the second JLCAT6 Ethernet cable (1AB 22983 0005) to the GbEport on JBXMUX2 (slot 12) in JSXLIU shelf 1/2. See Figure 12.
To connect the OMC-R Ethernet cables:
1. Identify the OMC-R Ethernet cables
2. Connect the first OMC-R Ethernet cable to the ATCA shelf 3/4 JAXSSW1,Ethernet port 3
3. Label the cables near the connectors.
28 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.3.4 Check the JSXLIU Shelf Address
To check the JSXLIU shelf address:
1. Remove the dummy panel from the slot 11 in JSXLIU shelf
2. On the slot 11 check that the shelf address is set to ”1”, jumper from position1 is removed
PE
M A
LIU
1
MU
X A
LIU
2
LIU
3
LIU
4
LIU
5
LIU
6
LIU
7
LIU
8
MU
X B
LIU
9
PE
M B
LIU
10
LIU
11
LIU
12
LIU
13
LIU
14
LIU
15
LIU
16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
12345678
graphics/174213111001.cgm
Figure 14: Slot 11 Back Panel Jumper Numbering
3. If the shelf address is set to “1” continue with step 8
4. If the shelf address is not set to “1”, set it following the next steps
5. Remove the JBXMUX boards and some JBXLIU boards to have betteraccess to the back panel
6. On the slot 11 on back panel remove the jumper from position 1, if equipped,in order to set the shelf address to "1” (See Figure 14)
7. Insert the JBXLIU and JBXMUX boards and secure it with the screws
8. Fix the dummy panel on slot 11 and fix it with the screws.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 29 / 44
2 A9130 BSC Evolution Commissioning
2.3.5 Connect PCM Cables to JSXLIU Shelf
To connect the PCM cables to the JSXLIU shelf:
1. Connect the cables to the JBXLIU boards
2. Check that there is a good connection of the cables
3. Close the front door to check if the cables are not stressed by it
4. Open the front door and arrange the cables if necessary
5. Attach the cables to the rack
6. Label the cables near the connectors.
30 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.4 Hardware Checks
2.4.1 Check the Equipment Configuration
The hardware check is done to see if the equipment configuration correspondsto the customer’s order.
Check the presence and position of the boards according to the requestedconfiguration.
Refer to the Site-Specific Information and Hardware Description - RackConfigurations sections.
2.4.2 Check the JAXPC Address
To check the JAXPC address:
1. Put on an ESD wrist strap and connect it to the shelf by attaching the frontor rear ESD jack.
2. Unfasten the screws fixing the JAXPC card to the ATCA shelf.
3. Carefully remove the JAXPC card from the slot.
4. Check if S2 switch is set to “0” and S1 switch is set to “3” for shelf 3 and to”4” for shelf 4 . If different setting is present correct it as follows.
S2
S1
graphics/174213111010.cgm
Figure 15: Rotary Switches on JAXPC Card
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 31 / 44
2 A9130 BSC Evolution Commissioning
5. On the JAXPC board set the S2 switch to ”0”.
6. On the JAXPC board set the S1 switch to ”3” for shelf 3 and to ”4” for shelf 4.See Figure 2 for shelf numbering.
7. Carefully insert the JAXPC card in the slot.
8. Tighten the screws fixing the JAXPC card to the ATCA shelf.
9. Place the JAXPC board handle switch to Closed position.
32 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.4.3 Check the JBXFAN Switch Position
To check the JBXFAN switch position:
1. Unfasten the screws fixing the JBXFAN cover plate.
graphics/174213111011.gif
Figure 16: JBXFAN Cover Fixing Screws
2. Remove the JBXFAN cover plate.
graphics/174213111012.gif
Figure 17: Remove JBXFAN Cover
3. Check if JBXFAN switch is set to Closed position otherwise set it to Closeposition.
4. Perform the check for all four JBXFAN units and for all equipped ATCAshelves.
5. Fit back the JBXFAN cover and fasten the fixing screws.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 33 / 44
2 A9130 BSC Evolution Commissioning
2.5 Powering Up the BSC Rack
Two people are needed for performing this task.
2.5.1 Check the Customer Power Panel
To check the rating of the fuses:
1. On the customer power panel, check for the existence of two DC powersupply distribution circuits. Each distribution circuit is provided with aDC circuit breaker (fuse holder).
(See Site-Specific Information (Section 1.2.2) )
2. On the power panel, disconnect the two -48V power supply lines by usingthe fuse holders for the rack.
3. Check that the fuse ratings are in accordance with the SPP document(See SPP-59).
2.5.2 Check Polarity of DC Cables on BSC Side
To check the connection of the power cables between the site power panel andthe power interface on the BSC side:
1. At the customer power panel, make sure the two power lines for the BSCare disconnected (breakers OFF) (See Site-Specific Information (Section1.2.2) ).
2. At the A9130 BSC, check that the A1 to A5 and B1 to B5 switches, located atthe front of the PDU, are OFF. If not, switch them OFF.
I
O
I
O
I
O
I
O
I
O
I
O
I
O
I
O
I
O
I
O
B1 B2 B3 B4 B5A2 A3 A4 A5A1
Shelf 4 Shelf 2 Shelf 3 Shelf 1 Shelf 4 Shelf 2 Shelf 3 Shelf 1
graphics/174213111pdu.cgm
Figure 18: PDU on top of A9130 BSC (JSXPDU)
34 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
3. At the top of the BSC rack, remove the PDU cover.
35 mm 2 from power station
16 mm 2 to ATCA shelf
Cover (made of two independent parts for branch A and B)
VBAT
BATR
GND
Cables must be fixed on this plane
VBAT
Breaker
VBAT
graphics/174213111pducover.cgm
Figure 19: Connections for One Single Breaker
4. Check the power line connections for both lines A and B:
Blue cables in the BATA and BATB position
Black cables in the BATR position
Yellow-green cable in GND position
5. Check that nothing can cause a short circuit between the BATA, BATB andBATR connectors.
Line cable from power station (branch A)35 mm2 diameter 14 mm
Racking braket Battery return connection plate (BATR)
Earthing(GND)
75A 75A 75A10A 10A
Line cable from power station (Branch B) 35 mm2 diameter 14 mm
BATB
BATR
75A 75A 75A10A 10A
BATR
BATA
graphics/174213111pducon.cgm
Figure 20: Connections from Power Station to PDU
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 35 / 44
2 A9130 BSC Evolution Commissioning
6. On the site power panel, connect the power supply line, using fuse holder Afirst.
Circuit A is connected.
7. Test the A circuit.
Check with the multimeter the presence of -48V and the polarity betweenBATA and BATR.
8. On the site power panel, disconnect the power supply line, using fuseholder A.
9. Repeat the previous operations for circuit B. Check the presence of -48Vand the polarity between BATA/B and BATR on each circuit, then leavethe circuits disconnected.
10. Replace the PDU cover plate.
2.5.3 Powering Up the BSC Rack
In the following steps power up only the shelves used by the installedconfiguration.
To power up the BSC rack:
1. On the JSXPDU, check that the corresponding switches, Ax and BX are inthe OFF position (see Figure 18) where:
x is 1 for Shelf 4
x is 3 for Shelf 3
2. Check that switches on JBXPS modules are switched OFF, otherwiseset them OFF.
3. On the site power panel, connect the DC power supply lines (circuitsA and B).
DC Lines A and B are connected.
Power Up ATCA3 Shelf 4. If ATCA3 shelf is used, switch ON (engage) the breakers A3 and B3.
5. Check on each JBXPS front panel that Rev. Power LED is OFF. If Rev.Power LED is ON switch OFF the breakers A3 and B3 and check powerpolarity on JBXPS terminals.
6. Switch ON the breaker on all JBXPS modules.
Power Up ATCA4 Shelf 7. If ATCA4 shelf is used, switch ON (engage) the switches A1 and B1.
8. Check on each JBXPS front panel that Rev. Power LED is OFF. If Rev.Power LED is ON switch OFF the breakers A1 and B1 and check powerpolarity on JBXPS terminals.
If two shelves are used for the MFS, both shelves must be powered up.
9. Switch ON the breaker on all JBXPS modules.
Power Up JSXLIU1 Shelf 10. Switch ON (engage) the switches A4 and B4, if JSXLIU1 shelf is used.Power LED on JBXPEMs in JSXLIU shelf switches ON.
Power Up JSXLIU2 Shelf 11. Switch ON (engage) the switches A2 and B2, if JSXLIU2 shelf is used.Power LED on JBXPEMs in JSXLIU shelf switches ON.
36 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.5.4 Check Power Line Redundancy
2.5.4.1 Check Power Redundancy for ATCA ShelvesTo check the power line redundancy for ATCA shelves:
1. On the power distribution unit (JSXPDU), switch OFF the -48 V DC powersupply lines A3 (if ATCA shelf 3 is used) or A1 (if ATCA shelf 4 is used)using the corresponding fuse holders.
If two shelves are used for the MFS, A3 and A1 lines must be switched OFF.
2. Check that the ATCA shelves remain powered up and the boards are notaffected (check the LED states).
3. Switch ON the -48 V DC power supply lines A3 (if ATCA shelf 3 is used) orA1 (if ATCA shelf 4 is used).
No boards are affected and lines A3 and A1 are connected.
If two shelves are used for the MFS, A3 and A1 lines must be switched ON.
4. On the power distribution unit (JSXPDU), switch OFF the -48 V DC powersupply lines B3 (if ATCA shelf 3 is used) or B1 (if ATCA shelf 4 is used)using the corresponding fuse holders.
If two shelves are used for the MFS, B3 and B1 lines must be switched OFF.
5. Check that the ATCA shelves remain powered up and the boards are notaffected (check the LED states).
6. Switch ON the -48 V DC power supply lines B3 (if ATCA shelf 3 is used) andB1 (if ATCA shelf 4 is equipped)
No boards are affected and lines B3 and B1 are connected.
If two shelves are used for the MFS, B3 and B1 lines must be switched ON.
2.5.4.2 Check Power Redundancy for LIU ShelfTo check the power line redundancy for JSXLIU shelf:
1. On the power distribution unit (JSXPDU), disconnect the -48 V DC powersupply line A4 (if JSXLIU shelf 1 is used) or A2 (if JSXLIU 2 is used).
2. Check that the boards in JSXLIU shelf remain powered up and are notaffected (The LED on the left JBXPEM front plate is orange).
3. Reconnect the -48 V DC power line A4 (if JSXLIU shelf 1 is used) or A2 (ifJSXLIU 2 is used).
No boards are affected and line A4 or A2 are connected.
4. On the power distribution unit (JSXPDU), disconnect the -48 V DC powersupply line B4 (if JSXLIU shelf 1 is used) or B2 (if JSXLIU 2 is used).
5. Check that the boards in JSXLIU shelf remain powered up and are notaffected (The LED on the right JBXPEM front plate is orange).
6. Reconnect the -48 V DC power line B4(if JSXLIU shelf 1 is used) or B2 (ifJSXLIU 2 is used).
No boards are affected and line B4 or B2 are connected.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 37 / 44
2 A9130 BSC Evolution Commissioning
2.6 Check BIOS Settings
Perform the following steps for both OMCP1 and OMCP2 boards.
To check System Date & Time and Boot Sequence on the OMCPs:
1. Connect to OMCP console:
For WinXP:telnet 172.17.y.8 <port number>
Port number is 4503 for OMCP1Port number is 4504 for OMCP2y is 3 if the subrack is in lower positiony is 4 if the subrack is in upper position
For Win2000:telnetset term vt100open 172.17.y.8 <port number>
Port number is 4503 for OMCP1Port number is 4504 for OMCP2y is 3 if the subrack is in lower positiony is 4 if the subrack is in upper position
2. Reset the OMCP board:reboot
3. In order to enter in OMCP BIOS use the sequence ESC+2 from theinstallation PC keyboard. You must enter this sequence during the stationreboot with OMCP console window selected.
4. Check that the System date and time are the current ones, otherwiseyou must correct it.
5. Check that in the boot sequence, the Hard drive is on the first position,otherwise you must modify it.
6. Save the changes you made and exit the BIOS.
2.7 Software InstallationTo install the A9130 BSC Evolution software, refer to the A9130 BSC EvolutionSoftware Installation document (3BK 17422 3126 RJZZA).
After finishing the software installation perform the commissioning tests.
2.8 Check the Firmware VersionFor checking the Firmware Version please refer to A9130 BSC EvolutionFirmware Upgrade.
38 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.9 Commissioning Tests
2.9.1 Option: LMT Installation (O1)
For B9 Release: If you have not already installed the LMT, refer to the A9130BSC Evolution Terminal User Guide for how to install and configure the LMT.
2.9.2 Connect the LMT to the BSC
The LMT cable (with RJ45 connector) must be available at ATCA shelf rearside (shelf 3 or 4).
1. Connect the LMT to the JAXSSW1 (position 7 on used ATCA shelf rearside), port ETH8.
See Tools (Section 1.4.1)
ETH8
OOS
OK
ACT
HS
ETH1
ETH2
ETH3
ETH4
ETH5
ETH6
ETH7
wrtm.cgm
Figure 21: JAXSSW at the ATCA Rear Side
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 39 / 44
2 A9130 BSC Evolution Commissioning
2. Check on the front panel that the LED corresponding to the connection portis lit (for the port Eth8 the corresponding LED is situated on row 8 column C).
BASE
12345678
INTERFACE
A B C
graphics/174223121005.cgm
Figure 22: Part of JBXSSW Front Plate
2.9.3 Option: Connect O&M cables from MFS to BSC (O2)
In case of rack shared configuration, O&M link can be transported from MFSto OMC-R via BSC.
On ATCA rear side, connect the O&M Ethernet cables as follows:
1. Connect the first JLCAT6 cable (1AB229830001) from ATCA Shelf 4JAXSSW1 port ETH1 to ATCA Shelf 3 JAXSSW1 port ETH1.
2. Connect the second JLCAT6 cable (1AB229830001) from ATCA Shelf 4JAXSSW2 port ETH1 to ATCA Shelf 3 JAXSSW2 port ETH1.
ETH8
OOS
OK
ACT
HS
ETH1
ETH2
ETH3
ETH4
ETH5
ETH6
ETH7
ETH8
OOS
OK
ACT
HS
ETH1
ETH2
ETH3
ETH4
ETH5
ETH6
ETH7
ETH8
OOS
OK
ACT
HS
ETH1
ETH2
ETH3
ETH4
ETH5
ETH6
ETH7
ETH8
OOS
OK
ACT
HS
ETH1
ETH2
ETH3
ETH4
ETH5
ETH6
ETH7
1234567890123456789012345678901234567890123456789012345678901234567890123456789012345678901234567890
ATCA 3rear side
ATCA 4rear side
Ethernet cables between
ATCAs
123456789012345678912345678901234567891234567890123456789
1234567890123456789012345678901234567890
JAXSSW2
JAXSSW1
JAXSSW2
JAXSSW1
graphics/174213111interatca.cgm
Figure 23: ATCA Shelf 3,4 rear side
40 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.9.4 Perform the Rack Inventory
To check the firmware status and the hardware technical level of the hardwareby performing a rack inventory:
1. Check the hardware technical level of modules and boards by performingthe rack inventory.
To perform the A9130 BSC Evolution rack inventory, refer to the CI 08 - SiteEquipment Inventory document (3BK 17257 0001 RJZZA).
2. Check that there are no errors reported by the Inventar software regardingthe technical level of modules and boards.
2.10 Connect the OMC-R1. Ask the OMC-R operator to check the network connection to the A9130
Evolution BSC for all the fixed and floating IP addresses (to open forexample some telnet sessions).
See Site-Specific Information (Section 1.2.2)
2. Ask the OMC-R operator to declare in /etc/hosts all the BSC fixed andfloating IP addresses together with the host names of BSC stations and"station_bsc"
3. Wait for OMC-R confirmation that the connection is OK.
Check the Equipment
Status
4. Wait for the telecom boards to finish their initialization
Check the equipment status.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 41 / 44
2 A9130 BSC Evolution Commissioning
2.11 Option: Check the Connection with the CBC
2.11.1 Open a Telnet Session
To open a Telnet session:
1. In Windows 2000/XP, select:
Start ⇒ Run
2. In Open window enter:telnet
3. Click on [ Ok ]
A telnet window opens.
4. Connect to the station as follows:
Under Windows 2000, the connection is done as follows:set term vt100open 172.17.y.x
Under Windows XP, the connection is done as follows:open 172.17.y.x
where:
x is 3 for OMCP1
x is 4 for OMCP2
y is 3 for Shelf 3
y is 4 for Shelf 4
5. Click on [ Enter ]
6. In the Telnet window enter the login name and password.
7. Connect to the router used for connection with CBC servertelnet <IP address of the gateway for LSN>
By default IP address of the gateway for LSN1 is172.17.y.10, for LSN2 is 172.18.y.10user:password:
where:
y is 3 for Shelf 3
y is 4 for Shelf 4
8. Press [ Enter ] to start.
42 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08
2 A9130 BSC Evolution Commissioning
2.11.2 Ping the CBC
To ping the CBC:
1. Enter the following command to check the connection between the BSCand the CBC:
ping <IP address of the CBC>
If answers from the CBC are received, the connection between the BSCand the CBC server is established.
2. Exit from the router:quit
3. Exit from BSC Control Stationexit
2.12 End of Commissioning1. Leave the A9130 Evolution BSC powered up
2. Close the doors of the rack
3. Check the CCL
4. Leave the site tidy:
Remove all packaging and unused equipment.
Clean the site.
5. Close the site and hand the keys to the key holder
6. Return the completed forms and the inventory files relating to the operationto base.
3BK 17422 3121 RJZZA Ed.20P08 IN PREPARATION 43 / 44
2 A9130 BSC Evolution Commissioning
BLANK PAGE BREAK
44 / 44 IN PREPARATION 3BK 17422 3121 RJZZA Ed.20P08