5S ProjectISAIAH VILLALONBUSM 390R
Activity
Current Situation:
We currently spending about $1248 a year on Labor Cost alone in regular cleaning of the Recycling Center
There is a lot of unnecessary equipment and materials in the area.
No segregation of recycling materials
Before Pictures
After Pictures:
New Situation:
Organized materials in proper location Removed equipment and other unnecessary materials Savings of $624 a year for Labor Cost Segregation of Recycling Materials with appropriate signs