Download - 3177-13568-1-PB.pdf

Transcript
  • 8/11/2019 3177-13568-1-PB.pdf

    1/21

    CHAPTER 1 2 8

    CONCEPT

    OF

    MINIMUM

    SPECIFIC

    ENERGY

    AND

    ITS

    RELATION

    TO

    NATURAL

    FORMS

    by

    Gordon

    R .McKay

    B.Eng.,Ph.D.(Liverpool)

    and

    Ahad

    K.

    Kazemipour

    B.Eng.(Tehran),M.Eng.Sc.(NSW)

    Iti s

    proposedt o

    show

    inthis

    paperthatthere

    isasolution

    t otheproblem ofnon-uniformflow

    and

    thissolution

    not

    only

    explains

    in

    detailmany

    land

    forms

    whichoccur

    naturally,but

    thereby,

    yields

    a

    definition o f'form'

    loss.

    If

    achannel,in

    which

    the

    transversedistribution

    of

    specific

    energy

    is

    uniform,

    convergesand/ordiverges,andthe

    bedchangesso

    that

    the

    flow

    willbecritical

    at

    all

    cross-sections

    at

    the

    sametime,

    the

    channel appears

    to

    beclose

    to

    beinghydraulicallysmooth.

    Manynatural

    forms,

    particularly

    estuaries,are

    readily

    explicable

    in

    this

    way.

    he

    most

    obvious

    one

    i sthebarat

    themouth

    of

    a

    river.

    t

    follows,

    if

    the

    riverenters

    the

    sea

    with

    reasonable

    uniform

    grade,

    which

    most

    rivers

    d o ,

    the

    bed

    must

    rise

    as

    the

    flow

    loses

    the

    restrictinginfluence

    of

    the

    banks

    (i.e.

    the

    width

    increases)

    ifconstant

    specificenergyi sto

    bemaintained.

    Iti spossible

    to

    calculate

    with

    considerable

    accuracythe

    dimensions

    ofuseful

    structuresbasedonthisconcept. largenumber

    offull

    size

    but neverthelessexperimental

    structureshave beenbuilt

    making use o fthe

    resultant benefits which

    develop:-

    low

    turbulence,

    accurate differential

    water

    levelsand a

    clearlydefinedflowpattern,

    allowingveryconsiderable

    savings

    t o

    be

    made byeliminating

    expensive

    protectiveworks.

    Professor

    of

    CivilEngineering,

    Universityof

    Queensland,Australia.

    Iranian GovernmentPostgraduate Research

    Fellow

    in Hydraulic

    Engineering,University

    of

    Queensland,

    Australia.

    2186

  • 8/11/2019 3177-13568-1-PB.pdf

    2/21

    MINIMUM

    SPECIFIC

    ENERGY 187

    INTRODUCTION

    For

    more

    thantwo

    centuries,

    the

    calculation

    of

    openchannel

    flow,

    steady

    orunsteady,uniform or

    non-uniform,

    hasbeenbased

    on

    the

    concept

    of

    a

    longuniform channelin whichthe boundaryshearin

    somewaydeterminesthe

    total

    head

    loss. Euler-Bernoulliprinciple

    (1700-1782),

    Chezy's

    (1718-1798),

    Poiseuille's

    (1799-1869),

    Darcy-

    Weisbach's(1803-1871),Bazin's(1829-1917)

    and

    Manning's

    (1816-1897)

    formulas,

    allo f

    whichare

    in

    regularuse

    today,

    are

    basedonthe

    concept

    of

    such

    a

    long

    uniform

    channel.

    daptation

    of

    the

    relatively

    modern

    Karman-Prandtle's

    (1930-32)theory

    of

    boundary

    layer

    and

    velocity

    distribution

    t o

    openchannels

    is

    alsobased

    On

    the

    concept

    of

    the

    long

    uniform

    channel.

    Thisassumption

    wasreasonableinthepastforartificial

    channels

    sincemosto fthe

    channel

    works(sewersand

    storm drains)

    were

    constructeds o

    that

    thecross-section

    of

    the

    channelwasoften

    semi-

    circular

    and

    thereforethedistribution ofthe

    shear

    stress

    around

    the

    boundary

    could

    be

    consideredmore

    or

    less

    uniform.

    Therei s

    strongevidence

    intheliterature

    1

    *

    thatthe

    studies

    of

    energy

    losses

    in

    openchannels

    have

    been

    closely

    related

    to

    the

    phenomena

    ofthe boundary

    layer.or

    fullydevelopedflowin

    auniform

    channel

    of

    any

    size,

    the

    boundarylayer

    will

    occupy

    all

    of

    the

    channel,

    butin partlydevelopedturbulentflow,

    the

    energylossduet o

    frictional

    resistance

    i srelated

    to

    thestage

    o fthedevelopment

    of

    the

    boundary

    layer.

    gain,pastresearchon boundarylayer

    has

    been

    concen-

    trated

    on

    flow

    through

    circular

    pipes

    and

    pastflatplates

    parallel

    t o

    thestream.

    Th epractisingengineer

    may

    rightlyquestion

    the

    abovephilos-

    ophies

    andassumptions,

    but

    what

    alternativehas

    been

    possible?

    rom

    Reporto f

    Task Force

    on

    Friction

    Factors

    in Open

    Channels

    1

    -

    At

    east,

    it

    coulde

    oped

    here

    would

    e

    made

    available

    omething

    imilar

    o

    he

    resistanceiagrams

    ow

    used

    or

    teady

    low

    n

    uniform

    pipes

    nd

    or

    frictional

    resistance

    fhips.

    Ithould

    e

    tated

    at

    he

    beginning

    thatheseopesannot

    e

    realised

    at

    hisime.

    Principle

    bstacles

    are

    he

    wide

    ange

    of

    urfaceoughness

    izes

    nd

    ypes

    ncountered

    n

    practical

    hannels

    (frommooth

    concrete

    inings

    o

    boulder-stream

    canyons),

    the

    effect

    ofbed

    movement

    n

    unlined

    channels,nd

    he

    numerousbendsnd

    tructureshat

    preventheattainment

    of

    teady,

    uniform,ully

    eveloped

    low .

    Inorder

    to

    allow a

    solutiont o

    the apparently

    simple

    problem

    ofdetermining

    the

    flow

    capacity

    ofabridge

    opening

    orculvert,

    the

    U.S.BureauofPublicRoads

    2

    publishesa manual

    of

    90pagesof

    tabul-

    ated

    data. If

    the

    bridgetypeand

    flow

    pattern

    can

    bereasonably

    compared withone

    of

    thosein

    the

    manual,

    a

    solutioncan beassessed.

    Such

    techniques

    do

    little

    to

    validate

    the

    basic

    principle.

    *umbersrefer

    to

    the

    referencesinthe Appendix.

  • 8/11/2019 3177-13568-1-PB.pdf

    3/21

    2188

    OASTAL

    ENGINEERING-197

    6

    Inderiving andapplyingthebasicformulaeandprinciples

    of

    uniform

    flowt oopen

    channels,

    aquantity

    'hydraulic

    radius',R ,

    representing

    thechannel

    geometry,

    is

    used.

    iameter

    ofthe

    pipe,

    D ,

    is

    replacedby

    4R.

    his

    substitution

    carries

    withit

    the

    assumption

    that

    thedistribution ofshear

    stress

    around

    theboundaryofthe

    channel

    is

    uniform.t

    is

    well

    known

    now

    thatin

    open

    channels,espec-

    ially

    wit h

    non-circularcross-sections,

    such

    uniformity

    of

    shearstress

    is

    afalseassumption.

    This

    fact

    clearly

    pointsoutthefailure

    of

    hydraulic

    radius

    to

    bethe

    sole

    geometricquantityrepresentative

    of

    the

    channelcross-section.he

    effect

    of

    cross-sectionalshapemust

    be

    takenintoaccountin

    t h e

    analysis

    and

    prediction

    of

    theenergy

    lossesin

    open

    channels.

    Suchstudies

    have

    beenmade

    by

    someinvestig-

    ators

    inrecent

    years,

    amongwhom

    are

    F.Engelund

    (1964)

    3

    ,H .Rouse

    (1965)",

    E.O.Macagno

    (1965)

    5

    ,

    C.C.

    Shih

    and

    N.S.Grigg

    (1967)

    6

    ,

    E .

    Marchi(1967)

    7

    ,

    N .Narayana Pillai(1970)

    8

    and

    C.L.Yenand D.E.

    Overton

    (1973)

    9

    .he

    results

    of

    these

    investigationsare

    yetincon-

    clusive.

    ccording

    to

    H .Rouse

    1

    ,

    the

    ffectf

    change

    n

    hapepon

    theresistance

    unctionisactuallywofold.

    O n

    heneand,t

    pvoduaes

    hange

    n

    he

    wetted

    perimeter,

    P ,

    per

    unit

    cross-sectional

    area, A ,

    thereciprocal

    of

    which

    s

    esignated

    y

    hehydraulic

    radius,

    R .

    n

    hether

    and,it

    produces

    hangen

    he

    distributionof

    velocityand

    hear;

    s

    result,

    the

    hear

    will

    generallyary

    rom

    point

    o

    point

    of

    heperimeter

    .

    oth

    ffects

    rehusnvolved

    n

    theequilibriumrelationship

    between

    hegravitationalmotive

    orce

    and

    heurfaceresistancewhichhe

    low

    entails .

    He

    supports

    t h e

    validity

    ofthe

    hydraulic

    radiusconcept,

    butconcludes

    thatthe

    effect

    of

    cross-sectional

    shape

    is

    related

    to

    the

    variation

    inthe

    hydraulic

    radius

    and

    two

    coefficients

    of

    asemi-logarithmic

    resistance

    function.

    ealsorefers

    to

    the

    importance

    of

    theaspect

    ratio

    n

    the analysisinrelationtotheeffect

    of

    cross-sectional

    shape.

    The

    junior

    author

    inanother

    work*

    has

    proposed

    other para-

    meters

    as

    beingmore

    representative

    of

    the

    cross-sectional

    shape

    on

    flow

    resistancein

    smoothchannels.his

    method

    offers

    a

    far

    more

    rational

    solution

    thanmethods

    previously

    proposed

    byothers.

    Iftheflowtakesplacein

    a

    naturalstream

    with

    erodiblebed

    and

    banks,

    the

    calculations

    which

    are

    at

    all

    possibledo

    littlet o

    determinethe proportionsof

    any

    change

    which

    is

    likely

    to

    occurand

    in

    fact

    hardly assistinallowingpredictionsofeventhegeneralform

    ofthechange.ecause

    of

    the

    ever

    varying

    shapeand

    size

    of

    the

    channelcross-section andunavoidableirregularitiesinchannelalign-

    ment,

    the

    flow

    is

    rarelyuniform

    in

    natural

    streams.

    Itshouldbe

    appreciated

    thatopen

    channel

    formulaebased

    on

    observations

    of

    pipe

    experiments

    or

    from

    small

    scale

    physical models

    ofchannelsand

    canals

    orrivers,cannot

    and

    do

    not

    represent natural

    situations because :

    *

    nder

    preparation forpublication.

  • 8/11/2019 3177-13568-1-PB.pdf

    4/21

    MINIMUM

    SPECIFIC

    ENERGY

    189

    ( i ) Thedimensionsandproportionsofnaturalriversarecompletely

    different

    from

    those

    of

    the

    pipes

    for

    which

    energylosses

    have

    been

    determined

    experimentally. In

    practice

    the

    pipes

    are

    almost

    invariably

    round,

    ranging

    in

    diameterfrom1cm

    t o

    about

    10m. Thecross-sectional

    shape

    ofa

    natural

    watercourseis

    quiteindeterminate;the

    width

    can

    vary

    from

    afewcentimetres

    t o

    many

    kilometres,while

    the

    depth

    varies

    from

    a

    f ew

    milli-

    metres

    t o

    averylimited

    amountcomparedwith

    the

    width.

    ( i i )

    It

    is

    quite

    impossiblet o

    represent

    allthedetailed

    features

    andirregularities

    ofa

    river

    on

    the

    model.

    ecannot

    truly

    conform

    t othelaws

    of

    similarity.

    Any

    researcher

    using

    largearealandscapetype

    models

    soon

    appreciates

    that

    suchmodels

    are

    fartoosmoothalthough

    boundary

    shear

    relationshipssaytheyshouldbe

    fartoo

    rough.

    Insmall

    scale

    models,losses

    due

    to

    boundary

    shear

    willalways

    berelativelylarge

    because

    of

    the

    effect

    of

    scale

    on both

    thesize

    and

    velocityinReynoldsnumber. However,t oassume

    these

    lossesrepresent

    thetotalenergy

    loss

    mustleadt oseriouserror.

    Al lenergy

    losses

    will

    be

    represented

    as

    turbulence.

    Eddy

    size

    islargely afunction of

    thesize

    of

    the

    solid

    boundary generating

    the

    eddy.

    The

    velocity

    will

    determine

    thenumber

    of

    eddies.ddies

    from

    boundary

    shearare

    small

    and

    becauseof

    their

    size,dissipate

    quickly.

    Incontrasteddiesgenerated

    by

    channelirregularitiesandchangesin

    cross-section

    willbelargeand willpersistdownstream

    addingconsider-

    ably

    t otheapparent roughness. Th ereaction of

    movable

    boundariesin

    naturalstreamst olocallygeneratedturbulencecannot be

    joinedwit h

    the

    overallaverageconditions.

    Often

    theenergylossesdue

    t o

    boundary

    roughness,

    cross-sectional

    shape

    and

    the

    boundary

    irregularities

    have

    been confused

    with

    oneanother.

    For

    example,

    H.A.EinsteinandN.L.Barbarossa(1951)

    1

    separatedthe

    total

    energy

    lossof

    the

    naturalflow

    intofrictional

    losses

    andform

    losses. Frictional

    losses

    were

    defined

    asthose

    due

    t o

    grain roughness

    and

    form

    losses

    those

    duet osize,shapeandspacingoftheindividual

    irregularitiesandpresenceofsandripples

    anddunes..Bajorunas

    11

    ,

    inthe

    discussionofthe

    samepaper

    statesthat:theroughnessfactor

    that

    reflects

    the

    channel

    irregularitiesdecreases

    and

    approacheszero

    wit h

    increasingflow.

    nthe

    other

    handin V.A.

    Vanoni

    and

    Li

    San

    Hwang's

    (1967)

    results,

    the

    bedroughness

    due

    to

    form

    of

    the

    ripples

    and

    dunes

    is

    the

    major

    partofthe

    total

    roughness

    and doesnot

    approach

    zero withincreasing

    flow.

    In

    the

    discussion of

    EinsteinandBarbarossa's

    paper,

    Sir.

    C .Inglis

    categorisesthe

    total

    lossesinto

    ( i )

    those

    due

    t otextural

    roughness;

    ( i i )thoseduet o

    ripple

    roughness;

    and(iii)

    thosecausedby

    form drag

    resulting

    from

    the

    majorirregularitiesof

    the

    banks,bed,islands

    and

    sandbanks.

    Inglis

    does

    not

    believein

    combining

    groups( i i )and

    (iii)

    because

    ofa

    different

    time

    scale

    by

    which

    they

    change.

  • 8/11/2019 3177-13568-1-PB.pdf

    5/21

    2190

    OASTAL

    ENGINEERING-1976

    The

    question i s ,whatconstitutesthetotalenergylossin

    natural

    rivers

    and

    howmuch

    ofthe

    total

    lossi s

    due

    to

    boundary-

    shearand how

    much

    i sdue

    to

    form?

    CONDITION

    FORNOFORM

    LOSS

    It

    i s

    proposed

    to

    show

    in

    this

    paper

    that

    there

    isa

    solution

    totheproblemof

    non-uniform f low

    and

    thissolutionnot

    only

    explains

    precisely many

    landformswhich

    occurnaturally,butthereby

    yields

    a

    definition of

    'form'

    loss.

    Th e

    only

    channel

    which

    gives

    truly

    no

    'form'

    loss

    is

    of

    rectangularsection.nany

    otherchannel

    the

    specific

    energy

    must

    vary acrossthechannel.hiswouldgenerateturbulence

    not

    associated

    with boundaryshear.

    he

    elementsofflow

    across

    thesection

    can

    be

    shown

    to

    respondin different

    wayst o

    an

    overallchangeinsection

    shape.

    B.A.

    Bakhmeteff

    (1932)^

    showed

    that

    if

    the

    flow

    in

    a

    channel

    is

    tranquilandthechannelconvergesslowly,thesurface

    will

    fall,

    the

    velocity

    will

    increase

    and,if

    the

    channelthen divergesslowlyt o

    itsoriginalwidth,theflow

    will

    return

    virtually

    without

    extra

    loss,

    t o

    its

    originaluniformflow

    pattern;

    i.e.

    the'form'

    loss

    iszero.

    f,

    however,the

    convergence

    continues,the

    flowwill

    ultimately become

    critical(i.e.,

    the

    depthyill be2/3(y V

    2g)wheny

    nd

    v

    arethedepth and velocityintheinitialchannel,g

    is

    theacceleration

    due

    to

    gravity

    and y

    s

    the critical

    depth).ny

    further

    convergence

    will

    lead

    t o

    a

    rise

    level

    upstreamoftheconstriction anda

    corres-

    ponding headlossthroughi t .

    Similarly,

    it

    was

    shown

    that

    if

    in

    a

    uniform rectangular

    channel

    asmooth hump

    is

    introduced,the

    water

    surface

    levelfalls,the

    velocityincreasesand

    the

    depth

    decreases.

    he heightof

    the

    hump

    for

    no

    'form'

    lossi slimited

    to

    that

    which

    creates

    criticalconditions

    at

    the

    hump;

    i.e.

    2 / 3

    [ ( y

    Q

    +

    v

    o

    2

    /

    2g

    )

    -

    A z

    ]

    2 g '

    Az

    being

    the

    heighto f

    the

    hump.f

    the

    height

    of

    the

    humpi sincreased

    beyondthislimit,

    the

    upstreamlevelwill riseand

    a

    'form'

    lossoccurs

    attherestriction.

    Therei s ,

    however,

    in

    addition

    tothese

    particularcases,a

    conditionwhichoffers

    a

    widerange

    of

    cross-section proportionswhich

    will

    offer

    no

    'form'loss.

    If v

    2

    /2g+y

    H Az

    everywhere,

    andthetransition i sa s

    beforereasonablyslow,

    therewill be

    no

    'form'

    loss.

  • 8/11/2019 3177-13568-1-PB.pdf

    6/21

    MINIMUM

    SPECIFICENERGY

    2191

    is

    the

    initial

    specificenergy

    =

    /2g

    +

    Az is

    now

    the change

    in levelofthe

    bed

    v

    is

    thecriticalvelocity

    both H

    nd

    Az have

    thesame

    sign

    andfor

    convenience

    are

    measured

    o

    positively

    downfrom

    thetotalenergy

    line.

    In

    manynaturalchannels

    the

    'form'

    loss

    i sthe major

    portion

    ofthe

    total

    headloss.t

    is

    then

    possible,

    by building

    anon-unifor-

    mity

    to

    thisconcept

    to

    create useful

    structures

    which

    cause

    no

    afflux.

    Anyincrease

    in

    boundaryshear

    loss

    due toincreasedvelocities

    can

    be

    offsetby

    areduction

    in'form'loss.

    Theproposition

    was

    not

    determined

    initially

    asa

    result

    of

    a

    theoretical or

    laboratory

    research.

    t

    arose

    from

    thesuccessful

    solution

    of

    anumber

    of

    ad

    hoc

    problems.

    DESIGNED

    SMOOTHTRANSITION

    STRUCTURES

    TheCity of

    Redcliffe

    is

    asatellite

    town

    of

    Brisbane,the

    capital

    of

    Queensland.

    It

    has

    extensive

    i fquite beacheson

    Moreton

    Bay

    and

    i s

    the

    nearestseasideholiday resort

    to

    Brisbane.

    he

    road

    pattern

    i s

    justabout45

    o

    thenaturaldrainagelines.ne

    of

    these

    drainage

    lines

    -

    Humpy Bong

    Creek

    -

    literally

    splitsthecentre

    of

    the

    town

    in

    two.

    n

    1958the

    sole

    crossingof

    thiscreekwas

    anarrow

    wooden

    bridge joining

    the

    shopping

    centre

    to

    the

    south,

    wit h

    the

    munici-

    palbuildings

    to

    the north.

    he

    shopping

    centre

    wasalong

    the

    beach

    promenade.

    -There were

    justabout

    enough parking

    placesfor

    the

    shop

    assistants'

    cars.

    Shoppingon anySaturdayinthe holidayseason

    was

    quitean

    adventure.

    FIG.l.GENERAL VIEWOFREDCLIFFEANDPROPOSED

    IMPROVEMENT ON THE

    CREEK

  • 8/11/2019 3177-13568-1-PB.pdf

    7/21

    2192

    OASTALENGINEERING-1976

    The

    flow in thecreekwaslargely

    sullage water.he banks

    weresteep,raggedand

    overgrown.

    ltogetherit was

    a

    smelly,unpleas-

    ant

    area.

    t

    was

    therefore proposed

    that

    amultipurpose

    improvement

    be

    made.

    (Fig. ) .

    ( i )uild

    aweirto

    raisethe

    fresh

    water

    level

    inthecreek

    to

    cover

    the

    raggedsteepbanks

    andallow

    the

    area

    t o

    be

    dressed,

    grassed

    and

    easily maintainedas

    a

    park.

    t

    the

    sametime

    the

    weir would

    exclude

    the

    tideandeliminate

    thesmell of

    rotting

    vegetation.

    ( i i )

    Culvertthe creekt o

    removeaccess

    problems

    and

    createan

    extensive

    car

    park

    onandadjacentt o

    the

    culvert.he

    car

    park

    would

    serve

    the

    shopsandpublic

    offices

    by

    day

    and

    inaddition

    theproposed

    Civic

    Centre

    and

    R.S.L.

    Hall

    by

    night.

    (iii) Toalleviate

    flooding

    of

    the

    shops

    andadjacent

    area.

    An admirable

    proposal,

    but

    how

    todo

    it?

    particularlyat

    a

    pricethe

    towncouldafford..The

    catchment

    of

    thecreekwasrapidly

    urbanizing

    andtheestimatedmaximumflow

    was910

    cusecs

    (25.8

    m

    3

    /see).

    The

    general level of

    the

    land

    adjoining,

    andhence

    floodlevel,

    at

    the

    creekmouth

    was

    R.L.

    8.0

    ft

    (2.440m)L.W.O.S.T. This

    would

    preferably

    also

    be

    the

    level

    o f

    the

    carpark.

    igh

    tide

    was

    R.L.4.5

    ft

    (1.370m)

    L.W.O.S.T.

    and experience

    had

    shown

    that

    anyoutlet

    wit han

    invert

    below high

    tide

    became

    stuffed

    with

    sandin

    the dry

    winter

    season.

    It

    was

    also

    necessarythatthe

    standingwater

    level

    in

    the

    lake

    should

    not

    beless

    than

    R.L.5.25

    ft

    (1.600m)

    L.W.O.S.T.

    to

    cover

    all

    the

    trash

    growthonthe

    verticalbanksandallow

    easy

    maintenance.

    t

    thattime

    the

    wholearea

    flooded

    atleast

    onceevery

    two

    years

    and

    by

    traditional

    hydraulicstheproblem appeared

    to

    be

    unsolvable as

    the

    length

    of

    the

    culvert

    wassome

    60 0

    ft

    (180m).

    Th e

    Department

    of

    CivilEngineering,Universityo fQueensland,

    suggestedthesolutionillustratedin Fig. . Th e

    logic

    ofthis

    solution

    was: -hedischarge

    i s910

    cusecs

    (25.8

    m

    3

    /sec)flowingup-

    stream

    of

    the weir

    at

    a

    level

    of

    R.L.

    8. 0

    ft

    (2.440m).

    If

    we

    neglect

    thevelocity headwecantake R.L.

    8.0ft(2.440m)

    a sthe

    level

    of

    the

    total

    energy

    lineattheweir.heweir

    level

    was

    se t

    atR.L.

    5.25

    ft

    (1.600m)

    togive

    satisfactory

    pondage

    conditions.

    hemaximum available

    specificenergy

    at.theweir

    i s2.75

    ft

    (838mm).Thusthecriticaldepth

    i s

    2/3

    x

    2.75

    =

    1.83

    ft

    (558mm).

    he

    maximum

    flowper

    foot

    width

    of

    weir

    i sthus14.2

    cusecs

    (1.327m

    3

    /sec/m

    width),

    so

    the

    minimumwidth

    of

    the

    weiri s

    64ft

    (19.5m).

    he

    culvert

    barrel

    was18.0

    ft

    (5.480m)

    wide,

    a

    Queensland Main Roads'Departmentstandard width. The flow

    per

    ftwidth

    must

    be

    50.51

    cusecs 4.7m

    /sec/m)

    so

    the

    minimum

    (critical)

    depth

    i s

    4.30ft

    (1.304m).

    he

    corresponding velocity

    head

    i s

    2.15

    ft

    (652mm),

    so

    total

    specific

    energy

    i s6.45ft(1.956m).

    Thereforethelevel

    of

    the

    culvertinvert

    at

    entrance

    is

    R.L.8. 0f t ,

    less

    boundary

    shear

    fall,less6.45=

    approximatelyR.L.

    1.43ft

    (440mm).

  • 8/11/2019 3177-13568-1-PB.pdf

    8/21

    MINIMUM

    PECIFIC

    ENERGY

    2193

    ?ARCENGTH

    75

    Redcliffe

    Culvert;

    NOTE:AC At HORIZONTAL

    -M

    CHOnOS

    _

    FU)W

    RLM3\

    ~45ff

    LONGITUDIN L SECTION

    LONG CENTRELINE

    FIG.2.

    DETAILSOFREDCLIFFE

    CULVERT

    An

    arbitrary

    assumption

    was

    madethat

    there

    would

    be

    1. 0

    f t

    (305mm)of

    headloss

    due

    t oboundaryshear

    so

    thelevelof

    the

    energy

    lineat

    the

    outleti s

    R.L.

    7.0

    f t

    (2.130m).

    Th e

    hightide

    level

    is

    R.L.

    4.5

    ft(1.370m)

    L.W.O.S.T.

    so

    the

    availablespecific

    energy

    is

    7.0

    -

    4.5

    =

    2.5

    ft(762mm). Th e

    minimum

    depth

    is

    2/ 3

    x

    2. 5

    =

    1.67

    ft(509mm)

    andthemaximumflow

    per

    ftwidth

    at

    outlet

    i s

    12.25

    cusecs

    (1.139

    m

    /sec/m)

    s o

    minimum

    outlet width

    is

    74.3

    ft

    (22.620m).

    In

    plan

    the

    inlet

    weir

    wasjoinedt otheculvert

    with

    an

    arbitrary

    shapeand

    the

    culvertt o

    the

    outlet weirlikewise.

    Th einlet

    and

    outlet

    floorswere

    designeds othat

    everywhere

    we had

    critical

    flow.

    Theculvert

    slab

    fitted

    very

    conveniently between R.L.

    8. 0

    ft(2.440m)

    and

    thewater

    surface

    to

    give amplefreeboard. Despite

    much

    criticalcomment

    the

    Department was

    commissionedt o

    build

    a

    model.

    A

    very

    big

    model

    1

    =

    1

    ft

    (1:12)

    wasbuilt.

    ery quickly

    we

    learnedthat

    the

    inlet

    andoutlethad

    to

    bepart

    of

    flow

    nets.

    it h

    this

    singlemodification

    the

    model

    performed

    perfectly. Therewas

    anamazingcorrelation betweenthe

    calculated

    and

    modelwater

    levels,everywhere within

    0.01f t(3mm onthe

    model).

    There

    was

    apparently nodifficulty

    inimposing

    this

    flowsystem.

    Th e

    culvert

    wasbuilt.oflow measurementshave

    been

    taken

    but

    noflooding whatsoever

    has

    occurredsince,althoughtherehavebeenat

    least

    three

    occasionswhen

    the

    design

    flow

    has

    probably

    been

    exceeded.

    Thisincludes1974

    when

    Brisbanesuffereddevastatingflooding,bothfrom

    the

    local

    creeks

    and

    the

    Brisbane

    River.

    Some

    years

    later wewere

    asked

    t oinvestigate

    theaugmentation

    o f

    the

    watersupplyforasmalltown,

    Clermont,

    inCentral Queensland.

    it h

    this

    requestwasattached

    avery

    odd

    condition

    -

    that

    any

    weirin

    theriver

    mustnot

    cause

    flooding

    at

    alesser

    flow

    than

    at

    presentnor

    atmore

    frequent

    intervals.

    There

    was

    good

    reason

    for

    this

    condition.

    Clermont

    lies

    in

    the

    junction

    of

    two

    streams,

    the

    Belyando

    River

    and

    Rocky

    Creek.

    Typical

    of

    westernQueenslandthehighest

    land

    for

    somemilesaroundisthe

    river

    bank.

    Once

    the

    flood

    breaks

    out

    it

    spreadsthrough

    the

    town

    and

    over

    the

    adjacent

  • 8/11/2019 3177-13568-1-PB.pdf

    9/21

    2194

    OASTAL

    ENGINEERING-19

    7

    6

    country.

    In

    1916

    a major

    floodpeaked

    on a

    Saturday night

    and

    nearly

    one

    hundred peoplewere

    drowned.aturally

    Clermonti s

    nowa little

    sensitive

    t o

    flooding.

    There

    is

    alwaysa

    minimum

    storage

    belowwhich

    storage haslittle

    purpose.

    hisminimum

    storagedetermines

    the

    minimum

    weir height

    and,

    in

    thiscase,

    the

    requiredweir wasrelatively high

    comparedto

    the banks

    of

    theriver.

    Th ewholeregion

    i s

    alluvium

    andconsequently maintainingthe

    weirin

    theriver

    was

    alsoan

    equallydifficult

    problem.aving

    tried

    a

    whole

    array

    of

    strange

    shapesand arrangements,

    we

    failed

    to

    satisfythese

    conditionsandreportedaccordingly.

    However,reflectingontheRedcliffeoutfall,

    there

    were

    second

    thoughts. If

    this

    culvert

    werecutintwo

    and placedendtoend,

    it

    gave

    a

    system of weirwithoutafflux.he

    bank

    full

    flowcould betaken asthe

    design

    flow,

    Q .

    Th e

    slope

    of

    thewater

    surface

    at

    thisstage

    is

    known.

    Th e

    velocity,

    V,is

    Q/Awhen A

    is

    the

    cross-sectionalareaat

    'bank

    full'.

    Th e

    energy

    line

    will

    then

    beV

    2

    /2g above

    and

    parallelto

    thebankfull-flow

    surface.

    The

    heightof

    the weircrest;

    i.e.

    Storage

    Level,

    isalready

    determined. Th e

    difference

    between

    storagelevel

    and

    the

    energylinelevel

    is

    thespecific

    head. Forthwith

    the

    critical

    depth,the

    maximum

    flow

    per

    unit

    width and

    theminimumlength(width)of

    thecrest

    can

    be

    calculated.

    Thiscrest

    width

    was

    very

    much

    widerthantheriver

    itself.

    By

    choosing

    an

    arbitrary

    planshape,the

    height

    atany

    othertransverse

    section

    of

    the weircanbereadilycalculated andthelongitudinal profiledetermined;

    alternatively a

    profile

    of

    theweir

    can bechosenand

    the

    widths

    calculated.

    Th eClermont

    Weir

    (Fig.3 )

    was

    20ft

    ( 6 m )

    high,

    350

    ft

    (106.8

    m)

    wide

    alongthe

    crest.

    he

    bank

    slopeswere,ofnecessity,

    flat

    toobtain

    asmoothtransition. The problemnowwas nottheadequacy ofthe

    design

    buthow

    to

    build

    i t .

    Th e

    only

    possible

    solution

    for

    such

    a

    bigvolume

    structurewas

    somehow

    to

    build

    the

    bulk

    ofit

    in

    earth.

    FIG.3.

    HOTOGRAPH

    OF

    CLERMONT

    WEIR

    This wasdone

    (not

    without

    incident)

    and

    theearth

    protected

    by

    a

    filteredconcreteslab.ootherprotectiont obedandbankswasfound

  • 8/11/2019 3177-13568-1-PB.pdf

    10/21

    MINIMUM

    PECIFICENERGY

    2195

    necessary. Again nomeasurements

    have

    beenmade

    but

    there

    have

    beenmany

    flows

    over

    the

    weir

    and

    at

    least

    there

    have

    been

    no

    complaints

    in

    the

    twelveyearsofitsexistence.

    muchlarger but

    similarweir has

    since

    been

    built. Thissecond

    weir(Fig.4 )is

    at

    Chinchilla,

    South-West

    Queensland.

    t

    i s40f t(12.2 m )igh

    and

    has

    a

    crest

    of

    750ft

    (228.300m).

    It

    stores

    7,500

    acrefeet( 3

    x10

    6

    m

    3

    )andthecrest

    is

    actually

    level

    with

    the

    adjacentbank

    contour.

    A

    bank

    six

    feet

    high

    ties

    the

    end

    o f

    the

    weirto

    higher

    ground

    somedistanceaway.

    hen

    the

    flow

    starts

    to

    overtop

    this

    bank;

    i.e.

    when

    floodingcommences

    upstream,

    the

    flow

    issome

    35,000

    cusecs

    (1000

    m

    3

    /sec)

    andthe measured

    afflux

    was

    4 .0

    inches

    (100

    mm). Below the

    design

    flow theexcessenergy

    isdissipated

    in

    asingleroller

    on

    the

    faceof

    the weir. No

    other protective works

    are

    provided. Abovethedesign

    flow,

    all

    traceofthe

    weirdisappears.

    I

    8 1

    FIG.4. PLAN OFCHINCHILLAWEIR

    Thestrangely

    smoothturbulentfreeflowoverthese

    weirsposed

    thequestion,

    wasthe

    concrete

    protection

    necessary?

    ventually

    the

    opportunity

    aroseto

    build

    an earth weir

    protected

    only by

    grass. It was

    designedt o

    have

    no

    effect

    at

    a

    levelat

    whichtheflow

    wouldcause

    flooding

    or

    nuisanceifexceeded-

    not

    themaximum

    flow.

    It

    has

    been

    completelysuccessful.

    The

    earthformation

    wascompleted

    on

    the

    5th

    November,

    1967.

    The bank wassown

    with

    GreenleafSudan

    -

    a

    fast

    growing

    sorghum

    andspriggedwith Kikuyu. Thefirst

    flowoverit

    occurred

    exactly

    five

    weeks

    later.

    In

    January,

    1968,

    two

    months

    after

    completion,

    the

    weir

    was

    submerged

    completelyearly

    on

    a

    Saturday

    eveningand

    remained

    completely

    submerged

    until

    Tuesday

    mid-day.

    Th ephoto

    (Fig.

    5 )

    was

    taken

    ontheWednesday.

    Th egrowth

    was

    adequateprotection

    andthe

    weir

    has

    survived

    ever

    since.

    In

    order

    tosecuretheseweirsin

    the

    early

    vulnerable

    period

    before

    the

    grass

    is

    established

    they

    have

    beenreinforced

    with

    a

    cheapplastic

    mesh.

    As

    grass had

    proved

    completely adequate

    as

    protection

    in

    these

    smooth

    flowstructures,they becamefar

    moreattractivecost-wise,

    despite

    thestrangeshape,than

    more

    traditional

    designs.

    A

    number

    of

    smaller

    butidentical

    weirs

    have

    been

    built

    and

    protected

    by

    grassonly. Th ecost

    is

    $50-$100

    per

    million gallons

    stored

    (500-1000

    m

    3

    per

    dollar). This

    type

  • 8/11/2019 3177-13568-1-PB.pdf

    11/21

    2196

    COASTAL

    ENGINEERING-1976

    FIG.5.

    PHOTOGRAPH

    OF YULEBA WEIR

    of

    weir

    makes

    possible

    extensive

    storageatsites

    which

    have

    previously

    been

    discarded.

    Theoptimumsiteis

    the

    widest, shallowest, andhence

    highest

    part

    of

    the

    riverbed.

    The

    farm

    dams

    were nothigh,averaging5ft(1.5

    m);

    the highest

    hasbeen ninefeet

    (2.74m).tsmall

    overflows

    the

    bank

    is

    subjected

    to

    velocitiescloset ov ' g h

    when

    h

    isthe

    height

    ofthedam. Even

    ata height

    of

    five

    feet,

    this

    amountst o

    over

    12

    ft/sec(4m/sec).

    There wasnever

    suspicion

    of

    scour.

    Thecalculationsassociated wit hthesedesignsareindeedsimple.

    Th e

    accuracyof

    thecalculations

    is

    very

    good

    andtheperformance

    completely

    predictable. Th econfidencegainedfrom thesesuccessesenabled

    much

    more

    exoticstructurest obedesignedand

    builtt oachieve

    solutions not

    previously

    possible,in

    particular

    culvertsand

    bridges

    without

    afflux

    butdischargingathigh

    velocities

    s othat

    the

    span

    is

    minimized.

    Typical

    is

    the

    NudgeeRoad Bridgeover

    the

    Kedron Brook

    in

    Brisbane.

    Atthe point

    of

    thecrossing

    the

    naturalstreamchannelhad

    completely

    degenerated havingleft

    its

    well

    defined

    steep

    watercourse

    andentered

    the

    coastal

    swamp.

    Longsince

    the

    area

    had

    been drained

    by

    a

    small

    canal-like

    waterway

    to

    a

    well

    definedtidalinlet

    some

    miles

    away.hischannelcould

    notevencarrytheannual

    flow.

    Th edesignfloodof

    30,000cusecs(850m

    3

    /

    sec)

    spread

    overawidth of

    1320

    ft(404m)

    increasing

    downstream.

    heroad

    crossed

    the

    swampon a lowembankmentrisingt o

    a

    short

    timber

    bridgeover

    the

    canal,and

    the

    floods

    roseoverthe

    embankmentand

    cut

    the

    traffic.

    A

    major

    shopping

    complex

    had

    been

    built

    upstream of

    the

    crossing

    but

    stillwithin

    the

    swamp

    zone. Th ecouncilhadrequired

    a

    considerable

    portion

    of

    their

    area

    to

    be

    retained

    asa

    floodreliefchannel

    andthe

    remainderhad hadto be

    filled

    t oaconsiderable

    depth. The

    area

    had

    continued

    to

    develop

    and

    Nudgee

    Road

    became

    amajor

    trafficroute

    andat

    thispoint

    the

    timber

    bridge

    failed.

    The

    situationrequired

    theimmediate

    construction

    of

    a newtwo-lane

    all-weather

    crossing(subsequently

    to

    be

    four-lane).

    There

    could

    be

    no

    raising

    of

    the

    flood

    level

    for

    fear

    of

    damage

    inthe

    shopping

    complex;the1967

    flood

    having

    risen

    t o

    within

    1

    ft

    (300mm)

    ofthefloorlevels.

    he

    differencein

    cost

    ofembankment

  • 8/11/2019 3177-13568-1-PB.pdf

    12/21

    MINIMUM

    PECIFICENERGY 2 1 9 7

    to

    bridge

    structure was

    $1000

    per

    ftlength.

    The

    constant

    energydesign

    gave

    certainty

    of

    calculation

    and

    the

    absolute

    minimum

    span.heground(bed)

    level

    was

    determinedby

    the

    lowest

    level

    at which

    itwaspossiblet ogrow

    grass

    -

    the

    areabeing

    tidal.

    This

    was

    taken

    at

    R.L.

    7.5

    ft

    (2.280m)

    L.W.O.S.T.

    The

    design

    flood

    (30,000

    cusecs)

    level

    was

    R.L.

    15.6

    ft

    (4.750m);

    the

    existing

    ground

    level

    was

    R.L.

    10.0

    ft

    (3.047m).

    The

    slope

    is

    surface

    fall

    onlyand

    in

    flood,

    amounts

    to

    less

    than

    1foot

    per

    mile.

    The

    approach,

    being

    s owide,

    was

    considered

    rectangular.

    Approach velocity

    =

    30,000/(1320

    x

    5.6)

    =

    4 .0ft/sec(1.22m/sec)

    R.L.Energy

    line

    is

    15.85

    ft

    (4.830m)

    Forgroundlevel at R.L.

    10.0

    ft

    (3m),

    y

    c

    =

    3.9

    ft

    (1.19m)and

    critical

    unit

    flow

    q

    c

    = 43

    cusecs

    (4m

    3

    /sec/m),

    soflow

    can

    be

    restricted

    t o688

    ft

    (210m)

    width

    only.nderbridgethe

    availablespecific

    head

    H

    s

    8. 1ft(2.470m),y

    c

    =

    5.4ft(1.645m)and

    q

    c

    =

    71

    cusecs/ft

    (6.6

    m

    3

    /sec/m),

    therefore

    the

    minimumwidth

    is

    423

    ft(129m).

    Th e

    bridge wasbuilt

    wit h

    9

    x

    50

    ft

    ( 9

    x

    15.26m)

    spans

    with

    round

    piers.

    Th e

    lip

    ofinlet

    fanwas

    400

    ft(122m)

    above

    the

    bridge.he

    shape

    of

    the

    fanisshown inFig.

    6 .

    modelscale1:48gaveresults

    which agreedwit hthecomputedresultst o within0.2ft(61mm). These

    models must

    betruly

    three-dimensional

    as

    itis

    no

    longer

    possible

    t ostudy

    a

    'representative'

    longitudinalsection. Themodel

    showed

    thatif

    the

    approaches

    were not

    depressed

    wit h

    the 4 50

    ft

    (137m)wide

    opening,

    the

    KL.1SS- JSiWSfUNL

    5 6 W^RSURFAci

    12

    9

    RUO-0

    wwr

    ffl.7 5

    FIG.6 .

    NDDGEE

    ROAD BRIDGEINLET

  • 8/11/2019 3177-13568-1-PB.pdf

    13/21

    2198

    COASTAL

    ENGINEERING-1976

    flood

    levelrose

    aboveR.L.

    18.5

    ft(5.650m),the

    minimum

    road

    embankment

    level,

    and

    overtoppingoccurred. The

    minimum

    span

    t opassthe

    flood

    at

    groundlevel

    R.L.10.0ft

    (3m)was

    688 ft(210m).

    Themodel

    again

    showed

    theremarkablysmooth

    turbulent

    free

    flowandasa

    result

    grass

    onlywas

    usedasprotection on

    the

    inletandoutletfanseventhoughthe

    velocity

    exceeds13

    ft/sec

    (3.96 m/sec). The outlet

    fanwasanexactimageof

    theinlet

    fan.

    The

    cost

    oftheearthworksinthefanswas$10,000,the

    saving

    on

    the bridge

    about

    $240,000.

    Th e

    design procedure wasusedindifferentcircumstancesinStawell,

    Victoria,Australia,by

    N .Cottmann,ShireEngineer. bridgeon

    the

    Stawell-Newington

    road hadacapacity

    of

    80 0

    cusecs(22.62

    3

    /sec)before

    theroad

    overtopped

    -which happened

    in

    every

    flood.

    he

    bridge

    approaches

    were

    redesignedso

    that

    thesamebridgecould

    carry

    5,000

    cusecs. Fig.

    showsthebridgecarrying4,300cusecs

    (122

    m

    3

    /sec)

    in

    February,1975.

    Although

    the

    water

    level

    underthe

    bridge

    was

    well

    below

    theapproach

    level

    it

    recovered

    the

    leveland

    passed

    through

    virtuallywithout

    afflux.

    gain,

    despite15ft/sec(4.57/sec)

    velocity

    and

    minimal

    protection,no

    scour

    occurred.

    FIG.7.

    STAWELL BRIDGECARRYING

    4300

    CUSECS

    (122

    m

    3

    /sec)

    IN

    1975

    Th econcept

    lendsitself

    to

    use

    in dualor

    multipurpose

    structures,

    inparticular

    the

    combinationof

    flood

    alleviation withstreamcrossings.

    Th eSouth

    East

    Freewayoutof Brisbane

    was

    deliberatelyroutedthrough

    the

    valley

    of

    theNorman

    Creek

    in

    order

    tominimize

    the

    number

    of

    housesit

    was

    necessary

    t oresume.

    utthevalley was

    free

    ofhouses

    becausethe

    area

    wassubject

    to

    severe

    short

    floods

    from theadjoining

    urban

    areas.

    Retardation

    basins

    in

    the

    formofplaying

    fieldshad

    been

    established

    along

    much ofthelengthofthe

    creek. The freeway

    not

    only

    crossed

    the

    creek

    on

    numerousoccasionsbuttheembankment occupiedasignificantportionof

    the

    available

    retardation

    basin

    area.

    Because

    ofthecertainty of

    the

    calculation,

    minimum

    energy

    culverts

    were

    used

    throughout.

    Theinlet

    fan

    to

    eachculvert

    was

    so

    arranged

    as

    to

    act

    as

    a

    minimum

    energy

    weirand

    to

    discharge

    a

    particular

    flood

    at

    aparticular

    level; i.e.

    thehighest

    possible.(Fig.

    8). Th e

    flow

    through one

    culvert

    is

    not

    affected

    by

    the

    backwater

    of

    the

    culvert/weir

  • 8/11/2019 3177-13568-1-PB.pdf

    14/21

    MINIMUMSPECIFIC

    ENERGY

    2199

    FIG.

    8 .

    PHOTOGRAPHOFCULVERT

    ENTRANCE

    downstream. The lossofdetention

    area

    was

    amply

    compensated

    by

    the

    increaseddepth

    madeavailable.

    A

    different

    version

    of

    this

    same

    theme,

    floodalleviationand

    a

    stream

    crossing,

    i sthat

    atSettlement

    Shores,

    Macquarie,

    N.S.W.

    This

    i s

    a

    very

    popular

    holiday

    area

    conveniently

    situated

    north

    ofSydney. Th e

    HastingRiver

    flows

    out

    ofthe

    ranges

    andmeandersin

    a

    large

    loopthrough

    the

    coastalswamps.ven

    in

    smallfloodsthe

    area

    presented

    was

    flooded

    andis

    unsuitable

    for

    development.

    A

    largechannelwill

    be

    builttoshortcircuittheloop

    butatthe

    lower

    end

    a minimum energyweir

    isto

    be built high

    enoughto

    prevent

    egress

    ofthetide.

    Atthesametimetheweir

    allows

    the

    free

    discharge

    of

    the

    flood

    water

    virtually

    without head

    lossat

    a

    lower

    level

    and

    thus

    freesthe

    area

    from

    danger

    ofinundation. Immediately below

    theweir

    a

    very

    rapid

    convergenceallows

    economicconvenient

    bridgingas

    accesst o

    ^

    12

    11

    10

    9

    8

    7

    s s

    S

    Settlement Shores

    HEADWATER AND

    TAILWATER

    LEVELS VIS

    FLOWS

    3W

    ^

    jr rliw

    ys

    A,

    ^

    i

    6

    y

    Measured Values

    O

    MinimumHW.RL.

    VH.WRLat

    T.WRL.7 7

    > BHW.RL.acT.WRL.6 2

    mLimit.W.R.L.

    FIG.9.

    24 56789

    1

    00

    40

    SO

    Discharge

    Thousands

    of

    Cusecs

    SETTLEMENT

    SHORES

    -

    HEAD-DISCHARGE

    RELATIONSHIP

  • 8/11/2019 3177-13568-1-PB.pdf

    15/21

    2200

    OASTAL

    ENGINEERING-1976

    the

    area.ig.

    9shows

    therelationship

    between

    the

    calculated

    and

    measured head water/tail wateronthe

    model.

    rom

    ourexperience,

    the

    prototype

    losses will be

    relativelyfar

    less.

    NATURALSMOOTHTRANSITIONS

    It becameincreasingly

    clearthateachof

    these

    structures

    had

    counterparts

    in

    nature.

    Th e

    Redcliffe

    tidaloutfall

    is

    surely

    an

    idealized

    and

    miniaturized

    river

    barformation.f

    a

    river

    enters

    theseawith

    reasonably uniform energy,

    then

    as

    theriverlosesthe

    constricting

    influenceofthebanks,thebed

    must

    rise

    t o

    maintain

    constantenergy.f

    thedivergence

    ofthe

    banks

    is

    uniform

    thebar

    is

    infactcurved.

    If

    the

    banks

    are

    curvedthe

    bar

    is

    straight.

    n

    the

    days

    of

    sail,

    it

    wasalways

    saidthat

    'shipssailedup-hill

    overthebar',and

    how

    true

    thiscould be.

    Equallyit

    is

    claimed,againwit h

    some

    truth,that

    it

    is

    alwayschoppyover

    the

    bar.

    It

    makesno

    difference

    whether

    thetide

    is

    ebbingor

    flooding,the

    same

    shape

    is

    demanded

    by

    the

    concept

    of

    constant

    energy.

    It

    is

    not

    surprising

    that

    CD.

    Floyd

    (1968)

    s

    reports

    on

    rivermouth

    training

    in

    Ne w

    South

    Wales,

    Australia

    t o

    thePublic Works

    Department.

    A

    ummary

    s

    given'ofhe

    results

    of

    raining

    ixteenrivers

    nnendeavour

    o

    norease

    bar

    depths. Thebarsareof

    imple

    oreseent

    ormationed

    yittoral

    drift.

    Whilsthe

    raining

    works

    ave

    mproved

    conditionsornavigation,

    theya ve

    not

    resultedn

    n y

    appreciable

    ncrease

    n

    bar

    depths.

    Despitehecomplex

    mechanismsnvolvedn

    bar

    ormation

    consistent

    imple

    relationshipisoundoxist

    between

    channelnd

    bar

    depths.

    This

    correlationeemso

    apply

    o

    all

    rivers

    nd

    nlets

    with

    simple

    ar

    ystemsnd

    extends

    over

    ange

    rom

    a rdepth

    ofw o

    eet

    to

    0

    eet

    Themajorityof

    he

    work

    the

    raining)

    ascarriedout

    n

    he

    period880

    o

    910

    with

    minorchangesnd

    additions

    n

    he

    period

    910

    to930 .

    Commencingnhe950

    's

    }

    majorrainingcheme

    w as

    tarted

    onheClarence

    River

    nd

    also rogrammeof

    development

    of

    mallriver

    entrances

    or

    ishing

    craft."

    The

    inlet

    and outletfeatures

    oftheculverts

    aresurely

    the

    correspondingscours o

    often appended

    by

    nature

    to

    man-made

    structures.

    A

    perfectfan

    completelyformed

    naturallyis

    given

    in

    Fig.

    0 .

    This

    is

    below

    a

    small

    portal bridgeover

    a

    gravelbedstream afterashort

    sharp

    fresh

    flow.he

    complete

    culvert

    form

    is

    the

    shape

    which

    alwaysdevelops

    between

    the

    tidal

    lagoon

    and

    the

    ocean.

    This

    is

    so

    well

    illustrated

    by

    Per Bruun(1966)

    16

    .e writesof'the

    gorge'

    and

    the

    'shoals'

    and

    illustrates

    it

    profuselywhenhe

    is

    searching

    for

    a

    relationship

    forthe

    stability

    of

    this

    strange

    shape

    which

    is

    deeperin

    its

    middle

    than

    at

    eitherend.

    (Fig.

    11).

    Th eentrancet oSanFranciscoBay,

    both

    inside

    and

    out,

    is

    a perfect

    major

    exampleofthis

    form

    (Fig.

    12).

    That

    this

    complete

    culvertshape

    isa notuncommon

    geological

    feature,

    many

    arch dam

    buildershave

    foundt otheircost.

    The

    Gordon

    River

    inTasmania,Australia,

    is

    typical.

    The

    gorge narrowsto

    provide

    theperfect

    abutmentsbutthesolidfloor

    is

    along

    way

    below

    that

    atthe

    entrance

    to

    thegorge.f world

    renownbecause

    it

    i s

    so

    well

    advertised,

    is

    thatmysterious

    gorgeon

    theRiverAare

    in Switzerland.tplaces

  • 8/11/2019 3177-13568-1-PB.pdf

    16/21

    MINIMUM

    SPECIFIC

    ENERGY

    2201

    FIG.10

    FA NT

    LYTH

    REEK

    OMA

    -Littoral Ddtt

    *>*,A57i7W '. ' . :3S

    oastal

    nlet

    with

    redoninant

    B ar

    By-Fassing

    Bruun

    nd

    Cerritsen,

    1961)

    FIG.11.

    TIDALAGOON (FROMREF.

    16)

  • 8/11/2019 3177-13568-1-PB.pdf

    17/21

    COASTAL

    ENGINEERING-1976

    Th e

    Golden

    Gate

    and

    its Ocean

    Shoals

    ( U . S .

    Corps

    of

    Engineers

    Annual

    Report,SanFrancisco

    District,

    1952).

    FIG.12. SANFRANCISCOB AY-

    (FROMREF.16)

    t h i sislittle

    morethana

    meter

    wideand

    it s

    depthisa

    hundred

    metres

    below

    t h e

    river

    bedat

    eachend.

    TheGorge

    of

    he

    Aare

    near

    Meiringen

    by

    ProfessorDr..rbenz

    (Berne)).

    Halfan

    our

    eyond

    Meiringen

    he

    Haslitals

    blockedn

    he

    wholeof

    its

    breadth

    y

    barrier,

    n

    he

    teep

    walls

    of

    which

    greyohalk

    is

    verywhere

    oeeen. Its

    not

    he

    result

    ofa

    andslip,

    ors

    it

    a

    moraine,

    butrathercrossbar

    ofrock,

    mall

    mountain

    angen

    he

    valley,

    bounding

    n

    mall

    peaks

    nd

    valleys

    nd

    abyrinth

    of

    wooded

    indentures

    nd

    defiles.

    The

    riverAare

    pierces

    hrough

    his

    ocky

    obstaclenheamousorge

    of

    he

    Aare.

    It

    asaten

    its

    wayhrough

    the

    ock

    at

    o

    greatdepth,

    that

    heall

    n

    its

    way

    hroughhe

    gorge

    isbut

    light.

    A

    evelpath

    eads

    o

    nnertkirchen

    nheother

    ide

    of

    this

    rocky

    crossbar.

    Howe l s e

    could

    a'blind'c hann elb e

    formed

    across

    half

    t i d e

    sand

    banks

    i n

    anestuary?

    Th eearthweirs

    arise

    int h ecentralr e a c h e sofmanyriv erswhere

    a

    well

    formed

    c hann el

    su f f e r s

    a

    c hangeofgrade,

    widens

    and

    shoa lsqui te

  • 8/11/2019 3177-13568-1-PB.pdf

    18/21

    MINIMUM

    PECIFICENERGY

    2203

    severely

    to

    form

    pools

    in

    low

    flow

    periods

    -

    thesilt banks

    of

    Australian

    streams-

    below

    which

    the

    streamwillconverge

    againtoawell-defined

    channel.

    Theseare

    thesitest obe

    chosen for

    farm

    dams

    and

    farfrom

    scouring,

    manyof

    the

    grassedweirs

    are

    actually

    growing.

    Avery good example

    of

    accidental

    minimum

    energy

    culvertmust

    surely

    be

    the

    old

    London

    Bridge

    (Fig.

    13).

    As

    little

    as

    25 %

    ofstream

    area

    was

    available

    t o

    thetide

    passingthrough

    the

    bridge. Th e

    tidal

    range

    is

    high

    but

    up

    to

    hightide

    the

    planshape

    is

    ideal

    and

    the

    Thamesmudwas no

    doubtdulyscouredto

    give

    thecorrect

    profile.

    This

    bridgesurvivedfrom

    1209

    to

    1825A.D.orfivecenturiesit

    wastheonly

    bridge.

    FIG.13.

    OLD LONDON BRIDGE

    Obviously

    if

    aform

    persiststhere

    must

    be

    some

    mechanism by

    which

    it becomes

    self

    sustaining

    and

    able

    to

    resist

    any

    destructive

    forces.

    The

    concept

    of

    minimum energy

    is

    justsuch

    a

    mechanism.

    inimum energy

    introduces

    critical

    velocities;

    i.e.

    the

    maximum

    velocity which

    canexist

    at

    that

    energy

    condition

    orfor

    that

    flowperunit

    width.

    Itis

    wrong

    to

    assume

    that

    critical

    velocitiesare

    high,

    they

    can be

    so

    small

    that

    they

    areunable

    to

    move

    even

    sandparticles. Theconceptallowsthe

    velocity

    to

    diminish

    without

    reducingthe

    total

    discharge.

    hus

    the

    natural

    fan

    shape

    at

    both

    inlet

    and

    outlet

    becomes

    quitestable

    andselfsustaining.

    As

    thevelocity of

    theflow

    in

    the

    connectingdeeper

    channel

    is

    alwaysgreater

    than

    the

    approachingflow,

    any

    bed

    load

    i scarriedthrough

    the

    deepersection. Anyfloatingmaterial will move mucheasierinthe

    deeperchannel

    so

    anything

    which

    i scarried

    in

    will be

    carried

    out.f

    thetotal

    flowincreases

    forsome

    reason,theinletfan

    will

    erode

    back

    to

    a

    higher,

    longer

    lip.he

    central

    sectionwill

    either becomedeeperor

    wider

    andthe

    erodedmaterial will becarried up

    the

    outletfan

    todeposit

    there

    again

    to

    form

    a

    higher,

    longer

    lip.

    Th e

    concept

    does

    not

    restrict

    a

    river,alluvial

    or

    otherwise,t o

    oneparticular

    shape

    s o

    much

    sought

    by

    many

    researchers

    -

    G .Lacey(1930)

    T .

    Blench

    (1957)

    18

    ,F.M.

    Henderson

    (1963)

    19

    ,

    D.B.

    Simons

    and

    M.L.

    Albertson

    (I960)

    2

    .nyrectangular

    shape

    is

    acceptable.

    rovided

    there

    is

    everywhere

  • 8/11/2019 3177-13568-1-PB.pdf

    19/21

    2204

    OASTAL

    ENGINEERING-1976

    therightrelationship between widthanddepththeenergygrade willbe

    uniform.

    Th eriver

    can

    become

    narrower

    if

    i tdeepensor

    can

    become wider

    provided

    it

    shallows. The actualcross-sectional

    shape

    is

    a

    function

    of

    the

    materialof

    the

    bed

    and

    banks. Ifyou

    addthehypothesisofL.B.

    Leopold

    and

    W.B.

    Langbein

    (1966) thatmeandersarecurvesof minimum

    energy

    in bending(and

    thereareany

    numberofsuitable

    curves

    for

    any

    situation),

    then

    a

    riverhas

    almost

    complete

    choice

    of

    cross-section

    and

    position andcanstillsatisfytheoverallconcept.

    CONCLUSIONS

    -Therei s no

    doubt

    that

    the

    concept

    ofminimum

    and

    constant

    energy

    unfolded here

    doesallow

    the

    quantitativedetermination ofsmooth

    transitionsinopenchannels

    and

    these

    transitionscan have useful

    applications.

    -

    It

    was

    shownthatinadditiont othepreviously

    known

    applications

    of

    specific

    energy,

    therei saconditionwhich

    offersa widerange

    of

    cross-section proportionswithoutadditional

    'form'

    loss. This

    condition

    is

    the

    reduction

    of

    ground

    (bed)

    level

    to

    satisfy

    a

    further

    convergence

    of

    the

    flow;

    i.e.

    t o

    reduce

    spanort odropthe

    water

    surface

    to

    increaseheadroom.

    -

    A solutionwasofferedt otheproblem

    of

    non-uniform

    flow

    andan

    explanation was

    given

    for

    the

    occurrence

    of

    manyland

    forms

    in

    nature,

    such

    as

    formationofa

    river

    bar

    and

    estuaries.

    -

    The

    transition

    shapes

    areessentially

    selfsustaining.

    hey

    are

    'smooth'with

    no

    'form'

    loss.

    There

    is

    noenergy

    change andthere

    is

    no

    turbulence,

    hence

    no

    scour.

    As

    any

    other

    shape

    would

    require

    more

    energyt o

    conveythe

    flow,

    there

    i s

    also

    no

    deposition.

    -

    To

    imposean

    unacceptable

    changeon

    such

    a

    system

    is

    courting

    disaster

    as

    is

    evidenced

    b y

    the

    many

    vainattempts

    to

    change

    estuarine

    conditions

    which

    are

    essentialt otheestuary's very

    survival.

    qually

    futile

    is

    t o

    attemptt orid

    rivers

    of

    the

    'bar'.

    e

    can

    learn

    much

    by

    studyingthenatural

    shapes.

    -By

    simply

    using

    constant

    energy rather

    thanconstant

    discharge,

    we

    can

    accurately predetermine

    the

    dimensionsofthe

    appropriate

    shapeand

    this

    shapewill bewithout

    'form'

    loss. Structurescan be

    builtt oother

    forms

    butthey

    willhavet obe

    defended,

    to

    retaintheirform,by

    solid

    protection

    or

    continual

    maintenance.

    -Always

    the

    shape

    isthe

    same

    -a

    strange

    fan

    shape.he

    shape

    ofa

    scourhole below

    a

    culvert.heshape

    of

    the

    old

    London Bridge.he

    shape

    of

    a

    tidal

    inlet

    t oa

    lagoon.

    Th e

    shapeoutside

    San

    Francisco

    Bay;of

    a

    channel

    very much

    deeper

    than

    the

    lakes

    itconnectsor

    the

    channel

    through

    a

    sandyestuary.ll

    these

    shapes

    are,we

    aresure,

    conformingto

    the

    concept

    ofv

    c

    2

    /2g+y

    c

    Az.

    APPENDIX

    EFERENCES

    1 .rogressReportoftheTask ForceonFrictionFactorsinOpenChannels

    of

    theCommitteeon

    Hydromechanics

    of

    theHydraulicDivision,"Friction

    Factors

    in

    OpenChannels",J .

    of

    Hydraulic

    Division,Proc.ASCE,Vol.

    89,

    No.

    HY2,March,

    1963,

    pp.

    97-143 Discussions.

    2 .

    Capacity

    Charts

    for

    the

    HydraulicDesign ofHighway

    Culverts",

    U.S.

    Bureau

    of

    Public

    Works,

    Hydraulic

    Engineering

    Circular

    No.

    10,

    March,

    1965.

  • 8/11/2019 3177-13568-1-PB.pdf

    20/21

    MINIMUM

    SPECIFICENERGY

    205

    3 .

    .

    Engelund,

    "Flow

    Resistance

    and

    Hydraulic

    Radius",

    Acta Polytechnica

    Scandinavica,

    Civil

    Engineering

    andBuilding

    Construction

    Series

    No.

    24,1964,pp .

    1-23.

    4 .

    .

    Rouse,

    "Critical

    Analysis

    ofOpenChannel

    Resistance",

    J .of

    Hydraulic

    Division,Proc.

    ASCE,

    Vol.

    9 1 ,

    No.

    HY4,

    July

    1965,pp.

    1-25.

    5 .

    .O.

    Macagno,

    "Resistance

    t o

    Flow

    in

    Channels

    of

    Large

    Aspect

    Ratio",

    J .

    of

    Hydraulic

    Research,Vol.

    3 ,

    No.

    ,1965,

    pp.41-57.

    6 .

    .C.

    Shih

    and

    N.S.Grlgg,

    "AReconsideration

    of

    the

    Hydraulic

    Radius

    as

    a

    Geometric

    Quantity

    inOpen

    Channel

    Hydraulics",Proc.

    12th

    Congress,

    I.A.H.R.,Vol.

    1 ,

    (PaperA36),Sept.,1967,pp .288-296.

    7 ..March ,

    "Resistancet o

    Flow

    in

    Fixed-Bed

    Channels

    withthe

    Influence

    ofCross-sectionalShape

    and

    Free

    Surface",

    Proc.

    12thCongress,

    I.A.H.R.,

    Vol.

    1 ,

    (PaperA5),

    Sept.,

    1967,pp.

    32-40.

    8 .

    .NarayanaPillai,"OnUniform Flow

    through

    SmoothRectangularOpen

    Channels",

    J .of

    HydraulicResearch,Vol.

    ,

    No.

    4 ,1970,pp.403-417.

    9 .

    .L.

    Yen

    and

    D.E.

    Overton,

    "Shape

    Effect

    on

    Resistance

    in

    Flood-Plain

    Channels",

    J .of

    Hydraulic

    Division,Proc.ASCE,Vol.

    9 9 ,No.HYl,

    Jan.,1973,pp.219-238.

    1 0 .

    H.A.

    Einstein

    and

    N.L.

    Barbarossa,"RiverChannel

    Roughness",

    J .

    of

    Hydraulic

    Division,

    Trans.ASCE,Vol. 7 ,Separate

    No.

    8 ,July,1951,

    pp.

    1121-1146.

    1 1 .

    L .

    Bajorunas,

    Discussion

    of

    "River

    Channel

    Roughness"- Reference

    1 0 .

    1 2 .

    V.A.Vanoniand

    Li

    SanHwang,"Relation

    Between

    BedForms

    and

    Friction

    in

    Streams",J .

    ofHydraulicDivision,

    Proc.

    ASCE,Vol.93 ,

    No.

    HY3,

    May,

    1967,

    pp.

    121-144.

    1 3 .

    Sir

    C .

    Inglls,

    Discussion

    of

    "River

    ChannelRoughness"

    -

    Reference

    1 0 .

    1 4 .

    B.A.

    Bakhmeteff,"Hydraulics

    of

    Open

    Channels",McGraw-Hill,

    1932.

    15.

    CD.

    Floyd,

    "River

    Mouth

    Training

    in

    New

    SouthWales,Australia",

    Proc.11th

    Conference

    on

    CoastalEngineering,

    London,

    England,

    Vol.

    ,

    Part

    4 ,

    Chapter

    80,Sept.,

    1968.

    1 6 .

    P .

    Bruun,

    "Tidal-Inletsand LittoralDrift-

    Vol.

    ,

    of

    Stability

    of

    CoastalInlets",Universitestsforlaget,

    Trondheim,

    1966.

    1 7 .

    .Lacey,

    "Stable

    Channels

    in

    Alluvium",Proc.

    Institution

    of

    Civil

    Engineers,

    Vol.

    229,

    Part

    1 ,1930.

    1 8 .

    T .

    Blench,

    "Regime

    Behaviour

    of

    Canals and

    Rivers",Chapter

    3 ,

    Civil

    Engineering Handbook,

    Butterworth's

    Scientific

    Publications,

    London,

    1957.

    1 9 .F.M.Henderson,

    "Stability

    of

    AlluvialChannels",

    Trans.ASCE,

    Vol.

    128,

    Part

    1 ,

    1963,pp.

    657-686 Discussion.

    2 0 .D.B.SimonsandM.L.Albertson,"Uniform

    WaterConveyanceChannels

    in

    Alluvial

    Material",

    Proc.

    ASCE,

    Vol.

    86,

    No.HY5,

    May1960,pp.

    33-71.

    2 1 .L.B.

    Leopoldand

    W.B.

    Langhein,

    "River

    Meanders",

    ScientificAmerican,

    Vol.

    214,No.

    6 ,

    June,1966,

    p p .

    60-70.

  • 8/11/2019 3177-13568-1-PB.pdf

    21/21


Top Related