2014 Campus Construction
2016 Campus Construction Projects
April 21st, 2016
![Page 2: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/2.jpg)
Objectives
• Provide an overview of 2016 projects to assist University entities with operational planning.
• Assist project teams by developing criticalconstraints so that both projects and Universityoperations are successful.
• Provide an overview of 2016 Parking & Transportation projects.
![Page 3: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/3.jpg)
Agenda
• Projects Overview • Project Details & Discussion • Core Campus Road/Site Work • Douthit/Hwy 93 Road Work • Electrical Infrastructure • Central Campus Paving • Other Disruptions • Parking & Transportation Update
![Page 4: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/4.jpg)
NW NE
SW SE N
2 5
6
7
15
1
9
10
14
11
3
12 13
8
16
17 1
18
8.1
Construction Projects 1. Electrical Duct Bank (BrM) 2. Hwy 93 Sanitary Sewer (CC) 3. Football Operations Facility (PB) 4. Not Used 5. Little John Renovation (BM) 6. West Campus Energy Plant (SZ) 7. West Campus Satellite Parking (JG)
8. Ravenel Rd Stormwater (JG) 8.1 Ave of Champions Closure (DF) 9. Core Campus (TJ) 10. Douthit Hills / Hwy 93 (MP) 11. Watt 4th Floor Completion (BM) 12. Central Campus Paving (BT) 13. Barnes Student Activity Center (KM) 14. East Campus Satellite Parking Lot (MS)
15. Jordan Hall Various Improvements (Various, MS) 16. Lee I & III Various Improvements (Various, MS) 17. Water Tower (MP) 18. Byrnes Hall Switchgear Replacement (DB)
See “Other Disruptions” Slide for Assigned Project Manger Initial List
![Page 5: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/5.jpg)
Northwest Campus
Construction Projects
Jervey
McFadden
2 5
6
8.1
1
7
8
1. Electrical Duct Bank 7. West Campus Satellite Parking
2. Hwy 93 Sanitary Sewer 8. Ravenel Rd Stormwater
5. Little John Renovation 8.1 Ave of Champs Closure (1-2days)
6. West Campus Energy Plant N
NW
![Page 6: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/6.jpg)
Northeast Campus
Construction Projects
10
9 1410 10
1
1. Electrical Duct Bank 9. Core Campus 10. Douthit Hills / Hwy 93 14. East Campus Parking Lot N
NE
![Page 7: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/7.jpg)
Southeast Campus
Construction Projects
4. Not Used 11. Watt 4th Flr Completion 12. Central Campus Paving 13. Barnes Student Activity Center
11 12 12 1315 18
16
15. Jordan Hall Various 16. Lee I & III Various 18. Byrnes Switchgear Replacement SE N
![Page 8: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/8.jpg)
Southwest Campus
3
Construction Projects 3. Football Operations Facility/Parking
NSW
![Page 9: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/9.jpg)
Core Campus Summer Road Work/Site Work
1
Core Campus Site
Shoeboxes
Facilities
Holmes/McCabe
Fort Hill St
Union Drive/Holmes
Quad
Alpha Beta/Klugh
Fort Hill
Facilities
Dillard
4
Note: 1. Alpha Beta/Klugh • 5/16 – 5/22 – Single Lane NO
TRUCKS • 6/27 – 7/22 – Klugh/Alpha Beta
CLOSED • 6/27 – 7/29 – SIDEWALK CLOSED 2. University Facilities • 5/23 – 6/17 - East main floor
EXTERIOR DOORS CLOSED. Use west exterior doors.
3. Dillard Hall • 6/15 – 7/29 – Dillard Level 1
EXTERIOR DOORS CLOSED. 1st
Summer Semester class will take place in Dillard (Ends 6/14). Exams (6/16-6/17) at alternate location.
4. Union Drive/Holmes • 6/27 – 7/22 – Holmes Level 0 west
EXTERIOR DOORS CLOSED. ROAD CLOSED.
• Fire Department Access will be provided on Core Campus Site.
5. Fort Hill • 7/4 – 7/22 – SINGLE LANE CLOSED • 7/25 – 7/29 – ROAD CLOSED
Pave All Areas 7/20 to 7/22
2
3
5
N
All dates are subject to weather delays
![Page 10: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/10.jpg)
Core Campus Summer Road Work/Site Work Schedule
5/1 6/1 7/1 8/1 5/
17
Sing
le L
ane
5/23
5/
22
6/17
Fort Hill 5
6/15
7/4
7/22
Facilities 2
7/22
7/
22
7/25
Road
Clo
sed
7/29
7/
29
Dillard 3
4
1
6/27
Road Closed
Alpha Beta/Klugh
1st Floor West Access Closed
1st Floor Access Closed
6/27
Road Closed Union Drive
Single Lane
All dates are subject to weather delays
![Page 11: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/11.jpg)
Core Campus - Alpha Beta/Union Closure Plan Housing to
Flagman
Barricade
Remove/Replace Bollards Daily.
Quad
Access around Quad for Emergency, Service Vehicle, and Deliveries Only.
Housing to Remove/Replace Bollards Daily
Core Campus
Site
Harcombe
No Service Vehicle Parking at Loading Dock
Note: 1. Signage will be in place along Heisman, Klugh, and Quad access Rd. 2. Housing will remove Quad access road bollards during the Alpha Beta Closure 3. EMERGENCY, SERVICE, & SPECIAL PERMIT VEHICLES ONLY. No Personal Vehicles allowed beyond the flagman located east of the Fike parking lot access drive. Special access Permits are available. 4. All authorized vehicles should use extreme caution when using the Quad access rd.
Alpha Beta/Union Closed 6/27 to 7/22
N All dates are subject to
weather delays
![Page 12: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/12.jpg)
Core Campus Fort Hill Closure Plan
Core Campus Site
Shoeboxes
Facilities
Holmes/McCabe
Calhoun Mansion
Flagman
Barricade
Flagman Barricade
N
Fort Hill St
1
2
33
4
Cable
Note: 1. Emergency, Delivery, ADA,
Special Permit ,& Service Vehicle Only Beyond Barricade at Fort Hill St/Williamson Dr.
2. Fort Hill sidewalks at work site will be closed.
3. Parking along Fort Hill between work site and Calhoun Dr will be open. A turnaround will be established near worksite.
4. The barricade west of Brackett along Calhoun Dr will be open allowing two way traffic.
Ft. Hill Closures Single Lane Closure
7/4 to 7/22
Full Road Closure 7/25 to 7/29
All dates are subject to weather delays
![Page 13: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/13.jpg)
Douthit Hills Hwy 93 Improvements
Clemson House
Martin St
Bradley St
Newman Rd
Cherry Rd
Summer ’16 Road work begins at Hwy 93/ Cherry & Hwy 93/Newman Intersections
TENTATIVE
N
![Page 14: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/14.jpg)
Douthit Hills Hwy 93 Improvements
Cher
ry R
d
Hwy 93
Hwy 93
New
man
Rd
Hwy 93 / Cherry Rd Hwy 93 / Newman Rd
N
![Page 15: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/15.jpg)
Electrical Deferred Maintenance Scope of Work: Replace electrical infrastructure that has reached the end of its useful life.
• Some short(hours) and long (days) power outages will be required.
• Roadway Disruptions will also be encountered
1. Electrical Duct Bank
![Page 16: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/16.jpg)
Electrical Duct Bank N
A
B
A. Mid April – Mid May B. Early Summer
![Page 17: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/17.jpg)
Upcoming Electrical Outages • Godfrey (3-5 days) • Fike (3-5 days) • Holtzendorff (1 day) • Mell Hall (1 day) • Wannamaker/Donaldson (1 hr) • Norris/Bradley/Bowen (1 day) • Soccer Stadium (1 day) • Sloan Tennis Center (1 day) • Football Stadium/Police Station (2 hr)
• Note: Short outages will take place at nights or weekends. Specific schedule and details will be coordinated by project managers to Building Security Coordinators.
![Page 18: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/18.jpg)
Central Campus Paving
4
2
3 1
7/1 – 7/15 - Engineering Service Dr.
7/9 – 8/7 - S. Palmetto Blvd. (Fernow Street & Civil Service Dr)
7/25 – 8/6 - Delta Epsilon Ct.
7/25 – 8/6 - Lambda St.
Paved Areas
Affected Areas
1
2
3
4 N
All dates are subject to weather delays
![Page 19: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/19.jpg)
Other Disruptions Buildings w/ Extensive work • Jordan Hall – Roof, Window Caulk, Elevator,
Commissioning (Various, MS) • Lee Hall – Window Caulk, Solar Fins, Air Handler,
Exterior Doors (Various, MS) • Steam Outage – Early August – 1-2 days (BK)
Roofs/Windows/Envelope • Apparel Research Roof Replacement (BT) • Barre Hall Windows (AG) • Earle Hall Roof & Gutters (BT) • Holtzendorf Windows (RO) • Hunter Hall Brick Repair (RO) • Jordan Hall Roof (AG) • Jordan Hall Window Caulk (RO) • Lee Hall Window Caulk & Solar Fins (RO) • Martin Hall Caulk (RO) • Lehotsky Window Caulk (AG) • Olin Hall Caulk Windows (RO) • P&A Partial Roof Replacement (BT) • Rhodes Annex Roof Replacement (TM) • Tillman Gutter Repair (RO)
Mechanical/Electrical/Plumbing • BRC Generator Upgrade (DB) • CETL Sprinkler Head Replacement (TM) • Freeman Hall HVAC Unit Replacement (BH) • Godley Snell Chiller Replacement (TM) • Hunter Hall VFDs (BH) • Jordan Hall Elevator Replacement (SB) • Jordan Retro Commission (BH) • Lee Hall Air Handlers (BH) • Rich Lab Boiler (TM) • STI Upgrade Fire Alarm (SB) • Strode Hall Elevator Doors (SB) • Tillman Replace Elevators (SB) • Flour Daniel VFD (BH) • Edwards Water Fountains (BH) • Cooper Library Dampers (TM) • CUFD Generator Replacement (DB) • Hendrix Fire Alarm Replacement (SB) • BRC Fire Alarm Upgrade (SB) • South Chiller Plant Fire Alarm (SB)
![Page 20: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/20.jpg)
Other Disruptions Sitework / Roadwork • Cooper Library Bridge Repairs (PA) • Hendrix Paver Repair (BT) • Martin Concrete Repair (PA) • McAdams Replace Exterior Stairs (BT) • S. Palmetto Paving (BT) • Engineering Drive Renovation (BT)
Space Renewal / Interior • Fike Flooring (PA) • Holtzendorff Door/Hardware Replacement (RO) • Lehotsky Exterior Hardware (BT) • Lee Hall Exterior Doors (RO) • Various Classroom Improvements (Various, MS)
All scheduled work will be coordinated by the project manager through Building Security Coordinators & other stakeholders
Project Manager List AG Alan Garret BH Bill Hurst BM Bill Muth BrM Bret McCarley BK Brian Kauer BT Bryson Thomas CC Channon Chambers DB Dan Byers DF Dwayne Fennell JG John Gambrell KM Kevin McDonough MP Mike Parker MS Mike Smith PM Paul Borick PA Phillip Addington RO Rick Owen SZ Sam Zanca SB Steve Black TM Tom Minor TJ Tommi Jones
![Page 21: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/21.jpg)
Parking & Transportation Update Current Projects 1. Football Operations Center Parking Lot 2. Hwy 76 (R-6) Parking Lot 3. Snow Family Recreation Parking Lot 4. Core Campus Parking Spaces 5. Central Campus Parking Spaces 6. R01 (Kite Hill) Parking Spaces 7. E21 (Cherry Rd) Parking Spaces
Future Projects 1. Feasibility Study for a Solar Powered Covered Bike Shelter Near
Lowry and the Watt Innovation Center 2. Ravenel Satellite Parking Lot 3. Bike Share Program
![Page 22: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/22.jpg)
Football Operations Parking
Indoor Track
Football Operations
Facility
Completion Time Frame 2017 200 + parking spaces
N
![Page 23: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/23.jpg)
Hwy 76 Lot (R-6) N
123
1
Completion Time Frame
Phase 1 (6/2016) 200+ spaces w. resident overflow
Phase 2 (est. 6/2017) 250 student spaces
Phase 3 (est. 6/2018) 200 student spaces
2
3
Total of 650+ for Douthit Hills student residents
![Page 24: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/24.jpg)
Snow Family Recreation Center Parking Completion Time frame Phase I - 152 spaces (est 9/16) Phase 2 – 200 spaces (est ?) Total of 350+ spaces
N
![Page 25: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/25.jpg)
Core Campus Parking N
Adding back 15 Metered Spaces N
Completion Time Frame July 2016
![Page 26: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/26.jpg)
Central Campus Parking
2
1
2
3 1
3
East Library Parking (R15)
Lambda Street
Strom Thurmond
1
2
3
N
![Page 27: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/27.jpg)
Central Campus Parking
East Library (E15) +3 Employee Spaces, LED Lighting and an EV Charging Station
Lambda Street + 14 Student Commuter Spaces
1 2
3 STI – Add 25 Employee Spaces
Phase 2
Phase 1
![Page 28: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/28.jpg)
Kite Hill (R1)Parking N
Add 130 Resident Spaces
![Page 29: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/29.jpg)
E-21 (Cherry Rd) Parking N
Convert to Employee
![Page 30: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/30.jpg)
Barnes Student Center Parking
Construction Zone
NLosing 30 Employee Spaces
![Page 31: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/31.jpg)
Future Parking InitiativesLowry Covered Bike Shelter
![Page 32: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/32.jpg)
Future Parking Initiatives NRavenel Satellite Parking
650 +/- Parking Spaces
![Page 33: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/33.jpg)
Future Parking InitiativesBike Share
![Page 34: 2014 Campus Construction - Clemson Universitycufacilities.sites.clemson.edu/documents/maintenance/2016... · 2019-03-17 · Construction Projects 4. NW NE SW SE N . 2 5 6 7 15 1 9](https://reader034.vdocuments.us/reader034/viewer/2022050506/5f97d4c1a1b1b415ad421b76/html5/thumbnails/34.jpg)
Thank You