2014 Solicitation DGS Request for Proposals &
ADGS Request for Information Conference
July 1, 2014
![Page 2: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/2.jpg)
Page: 2
Introduction Conference Agenda
DGS and ADGS Overview
RFP/RFI Schedule
The DGS RFP Product Sought by SCE
Process for Submitting a Proposal
Evaluation Process
Pro Forma DGS Contracts Distributed Generation Solution Agreement
Designated Load Agreement
Added Facilities Agreement
Interconnection Interconnection Requirements
Where To Go For More Information
ADGS RFI Information Sought by SCE
Process & Schedule
Questions & Answers
Overview of the Conference
![Page 3: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/3.jpg)
Page: 3
• Objective
Using distributed generation as an alternative to building distribution upgrades to accommodate forecasted load growth on the distribution system.
• What is DGS?
– The Distributed Generation Solution (DGS) Request for Proposal (RFP), will solicit proposals from owners and operators of distributed generation facilities (Distributed Generators) and designated load customers (DLC) to reduce a specified amount of load in the identified distribution system area.
• What is ADGS?
– The Alternative Distributed Generation Solutions (ADGS) Request for Information (RFI), will solicit informational proposals from interested parties, including owners and operators of distributed generation facilities and/or load customers (Participants) on solutions for providing distribution grid reliability using distributed energy resources (DERs).
DGS & ADGS Overview (1 of 2)
![Page 4: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/4.jpg)
Page: 4
• DGS and ADGS are not:
– Energy Procurement Solicitation
o Local Capacity Requirements (LCR) RFO
o Solar Photovoltaic Program (SPVP) RFO
o Renewable Market Adjusting Tariff (ReMAT)
– Net Energy Metering (NEM) Program
– Preferred Resource Pilot (PRP)
For more information on these programs visit:
Energy Procurement: www.sce.com/energyprocurement
Net Energy Metering: www.sce.com/nem
Preferred Resource Pilot: www.sce.com/wps/portal/home/about-us/reliability/meeting-demand/our-preferred-resources-pilot
DGS & ADGS Overview (2 of 2)
![Page 5: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/5.jpg)
Page: 5
DGS & ADGS Overview
2014 DGS & ADGS Schedule
Date Event
May 13 SCE Notifies Commission Service Lists
June 13 SCE releases DGS RFP & ADGS RFI
July 1 SCE hosts a Proposal Conference
August 15 Deadline for Submission of Proposals
September 15* Deadline for SCE to advise Distributed Generators on the status of their Proposals relative to SCE’s short list
October 30* Deadline for SCE and short-listed Distributed Generators to complete negotiation of the Final Agreements
November 14* Deadline for SCE and Distributed Generators (and Designated Load Customer, as applicable) to execute Final Agreements
December 12* Deadline to submit report on the results of the Pilot DGS RFP to the CPUC
* These dates apply only to the DGS RFP, and are subject to change
![Page 6: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/6.jpg)
Page: 6
• Distributed Generation
– Any viable electricity generation technology (i.e. currently in commercial operation)
– Rancho Cucamonga area
– Minimum capacity = 1.9 MW
– Commercial Operation by June 1, 2016
• Physical Assurance
– Ability to automatically disconnect Distributed Generator and Designated Load Customer from the distribution system if net load exceeds a certain threshold (Firm Service Level)
– Proposal must identify Designated Load Customer
– Minimum load-reduction capacity = 1.9 MW
– Must be in operation during Peak Hours (i.e. 1-7 PM) in Peak Months (June 1st to September 30th)
DGS RFP – Products Sought by SCE
![Page 7: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/7.jpg)
Page: 7
[TAL: Can we get another map
that zooms out to show Rancho
Cucamonga in Greater Los
Angeles Area?]
Products Sought by SCE - Location
![Page 8: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/8.jpg)
Page: 8
• Automatic Load Reduction Scheme (ALRS) Operation
– Monitor the Electric Net Demand (Load – Generation)
– Disconnected all Load and Generation if the Electric Net Demand exceeds a predetermined amount (FSL)*
– The breaker will be reset automatically after 5 minutes
– If Electric Net Demand still exceed FSL the ALRS will disconnect the generation and load again and will remain open until customer contacts Grid Operations.
• The ALRS will be operational during certain conditions
– Summer months: June 1st – September 30th
– Peak daytime hours: 1:00 pm – 7:00 pm
• The RFP includes a Customer Installed ALRS Option
– The customer installed option must be reviewed and approved by SCE as described in section 2.02 of the DGS RFP Instructions
*Firm Service Level (FSL) = On Peak Load – Contract Capacity
Products Sought by SCE – Physical Assurance
![Page 9: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/9.jpg)
Page: 9
• Cost per ALRS
– ALRS Cost = ~$255k
– Salvage Value = ~ <$60k>
– Removal Labor = ~$35k
– Total Customer Cost (excluding civil) = $230k
• Added Facilities Monthly Charge per ALRS
– $800 (assuming $255k ALRS Cost)
• Customer Work Required
– Conduits
– 3 – Padmount Structures
o 8’ x 10’
o 6’ x 8’6”
o 5’ x 10’6”
• Location of ALRS
– Electrically before Generator and Designated Load
ALRS Specifics
![Page 10: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/10.jpg)
Page: 10
57
57.5
58
58.5
59
59.5
60Historical Load and Generation Profile
Peak Hours
Substation Loading Limit (Example)
Add slides before to show
just the contract capacity
Contract
Capacity
Peak Forecasted Substation
Load (Example)
MW
DGS Example – Qualifying Proposal (1 of 3) M
W
![Page 11: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/11.jpg)
Page: 11
57
57.5
58
58.5
59
59.5
60Historical Load and Generation Profile
Generation
Peak Hours Add slides before to show
just the contract capacity
Contract
Capacity
0
MW
DGS Example – Qualifying Proposal (2 of 3)
1.9
Substation Loading Limit (Example)
Peak Forecasted Substation
Load (Example)
MW
![Page 12: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/12.jpg)
Page: 12
57
57.5
58
58.5
59
59.5
60Historical Load and Generation Profile
Generation Load
Peak Hours Add slides before to show
just the contract capacity
Contract
Capacity
MW
DGS Example – Qualifying Proposal (3 of 3)
0
1.9
Substation Loading Limit (Example)
Peak Forecasted Substation
Load (Example)
MW
![Page 13: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/13.jpg)
Page: 13
57
57.5
58
58.5
59
59.5
60Historical Load and Generation Profile
Generation Load
Peak Hours Add slides before to show
just the contract capacity
Contract
Capacity
MW
DGS Example – Non-Qualifying Proposal (Gen)
0
1.9
MW
Substation Loading Limit (Example)
Peak Forecasted Substation
Load (Example)
![Page 14: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/14.jpg)
Page: 14
57
57.5
58
58.5
59
59.5
60Historical Load and Generation Profile
Generation Load
Peak Hours Add slides before to show
just the contract capacity
Contract
Capacity
MW
DGS Example – Non Qualifying Proposal (Load)
0
1.9
MW
Substation Loading Limit (Example)
Peak Forecasted Substation
Load (Example)
![Page 15: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/15.jpg)
Page: 15
• When to Submit a Proposal • Distributed Generators must submit Proposals no later than August 15, 2014
• List of Documents to include in a Proposal 1. Proposal Structure Letter 2. DGS Proposal Template 3. Distributed Generator Facility Description and One line diagram 4. Designated Load Description 5. Proposed Changes to the Applicable Agreements 6. Site Description 7. Site Map
• How to Submit a Proposal
– Save documents to a USB Flash Drive – Submit USB Flash Drive with Proposal in the required format to:
3 Innovation Way, Pomona, CA 91768
Attention: Christopher Ohlheiser
Transmission & Distribution
Update Me
DGS RFP Process
![Page 16: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/16.jpg)
Page: 16
• Proposal Selection Process
• After the Proposal Due Date:
• SCE will check all proposals for conformity & completeness
• Evaluate & rank proposals
• Select a Short-List
• Notify participants
• Open negotiations
• Final Selection
• Agreement Execution
DGS RFP Proposal Selection Process
![Page 17: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/17.jpg)
Page: 17
• How should I price my bid?
– The bid will be in the form of a monthly payment amount for the duration of the contract term (36 months)
• How will the bid be evaluated?
– The bid amount must be less than SCE’s expected savings for deferring the project
• How will the bid be shortlisted?
– SCE will shortlist the lowest cost bids
DGS RFP Proposal Evaluation
![Page 18: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/18.jpg)
Page: 18
• Non-Disclosure Agreement (NDA)
– Distributed Generator and Designated Load Customer must electronically accept the terms and conditions of this Non-Disclosure Agreement by no later than the Proposal due date by selecting “Yes” to the input field contained in Section E of the DGS Proposal Template.
– The form of the NDA is attached to the DGS RFP Instructions as Exhibit C
– The NDA is non-negotiable
SCE’s Pro Forma Contracts
![Page 19: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/19.jpg)
Page: 19
• DGS Agreement
– DGS In-Service Date: The date by which the Project must be in full commercial operation (i.e. June 1, 2016)
– Project specifications: location, technology type, contract capacity, point of interconnection, project development milestone schedule, generating facility description, etc.
– Collateral Amount: Distributed Generator must post collateral (cash or LOC) in the amount of $20/kW of Contract Capacity
If Distributed Generator fails to achieve Commercial Operation by the DGS In-Service Date, SCE can terminate the DGS Agreement and will keep the Collateral Amount
SCE’s Pro Forma Contracts
![Page 20: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/20.jpg)
Page: 20
• DGS Agreement (cont.)
– Payment Terms: Contract price will be fixed monthly payments ($/mo.) for the 36 months that the Project must be in operation
– ALRS: The ALRS stays in effect until the earlier of (i) one year after an early termination of the DGS Agreement, or (ii) the end of the original Term of the Agreement
– Insurance: Must be in effect as of the Effective Date (i.e. the date the DGS Agreement is signed
– Designated Load Agreement (DLA) and Added Facilities Agreement (AFA) incorporated as exhibits to the DGS Agreement
SCE’s Pro Forma Contracts
![Page 21: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/21.jpg)
Page: 21
• Designated Load Agreement (DLA)
– Three-way agreement between SCE, Distributed Generator and Designated Load Customer
– Specifies the requirements for Physical Assurance
– No Payment Terms
o SCE does not pay designated load customer
SCE’s Pro Forma Contracts
![Page 22: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/22.jpg)
Page: 22
• Added Facilities Agreement (AFA)
– Agreement between SCE and the Distributed Generator
– Contract Length - 20 years
o For DGS RFP contract will be terminated after 3 years
o Distributed Generator pays for Removal less Salvage Value
– Not an Interconnection Facilities Agreement
SCE’s Pro Forma Contracts
![Page 23: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/23.jpg)
Page: 23
• There are various Generation Interconnections Agreements
• The Interconnection process can vary from 3 months – 24 months
Generation Interconnection Map
Rule 21
Non- Export Export
WDAT
Export
Generation Interconnection Information
![Page 24: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/24.jpg)
Page: 24
Generation Interconnection Questions?
• Website: www.SCE.com/wps/portal/home/regulatory/open-access-information
• Email: [email protected]
![Page 25: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/25.jpg)
Page: 25
ADGS RFI – SCE Reliability Overview
• Reliability Requirements for Resolving Distribution System Needs
1. The solution must satisfy the peak load at the time a projected facility overload occurs
• Contract Capacity and Peak Hour Requirements
2. The solution must do so for the duration of the projected overload
• Contract Length
3. The solution must be located so that the peak loading of the target asset will be decreased and reliability and operability of the grid is not reduced.
• Physical Assurance
![Page 26: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/26.jpg)
Page: 26
• Option 1 – Customer Owned ALRS – SCE recognizes that other methods may exist that could provide a similar level of grid reliability
without the use of a utility-owned Automated Load Reduction Scheme. As an alternative, Participants may provide one or more Proposals based upon other physical load reduction assurance options.
– Participant proposals for physical load reduction assurance could utilize customer-owned equipment and control schemes, devices, technologies, arrangements, and methodologies that would reduce, limit or disconnect the load as needed to assure grid reliability.
• Option 2 – Physical Assurance Alternative – Participants may provide proposals that could eliminate the need for physical load reduction
assurance. This alternative could include, for example, combining multiple DERs to reach the target load reduction amount.
ADGS RFI – Proposal Options
![Page 27: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/27.jpg)
Page: 27
• The graph below gives an example of one possible load offset requirements that could be satisfied by sufficient generation or load reductions, shown in 30 minute increments, required over the peak loading period of 2PM to 6PM during the summer months of June through September.
ADGS: Example Reliability Requirements
![Page 28: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/28.jpg)
Page: 28
• When to Submit a Proposal • Distributed Generators must submit Proposals no later than August 15, 2014
• How to Submit a Proposal – Save documents to a USB Flash Drive – Submit USB Flash Drive with Proposal in the required format to:
3 Innovation Way, Pomona, CA 91768
Attention: Christopher Ohlheiser
Transmission & Distribution
ADGS RFI Process
Update Me
![Page 29: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/29.jpg)
Page: 29
For Questions regarding the Distributed Generation Solutions RFP please email us at:
For Questions regarding the Alternative Distributed Generation Solutions RFI please email us at:
For additional information regarding these solicitations, please visit us at:
• On.sce.com/dgs
Contact Information
![Page 30: 2013 DGS Solicitation Request for Proposals Request for … · 2020-01-24 · Page: 5 DGS & ADGS Overview 2014 DGS & ADGS Schedule Date Event May 13 SCE Notifies Commission Service](https://reader036.vdocuments.us/reader036/viewer/2022070901/5f4d171d03923d5c3a49c4c5/html5/thumbnails/30.jpg)
Page: 30
Questions and Answers