Eng M 530 Engineering Project Management
Laboratory Development Project
In-Class Assignment: Risk Register
Team Members:
Luke Glistak Sean Hodgson
Shannon MacDonaldMk NimeshAnand Rohit
-
8/7/2019 10 Risk Register
2/4
Risk Register
# Risks Risk Type ProbabilityLevel Impact RatingProbability
RatingCost
ImpactSchedule
ImpactRisk
OwnerRisk
Response
1Physical injury(during movingor installation)
Safety 0.10 0.80 8.0% Medium $10,000 2 days
RogerMarchand /
MikeLipsett
Call 911
2 Late arrivingfurniture Equipment 0.30 0.05 1.5% Low $0 7 daysMike
Lipsett Call vendors
3
Power failureduring labequipment
commissioning
Equipment 0.10 0.05 0.5% Low $0 1 day RogerMarchandReschedule
move
4 Failure of UWSconnectivity Equipment 0.10 0.05 0.5% Low $200 4 days AICT
Contact ITdepartment forplacement of
wireless router
5Damagingequipment
during moveEquipment 0.10 0.20 2.0% Low $1,000 14 days RogerMarchand
Orderreplacementsfrom Vendors
(informStudents too)
6Movers are
absent Personnel 0.10 0.10 1.0% Low $500 2 daysRoger
MarchandReschedule
move
7 Damagingexperiments Research 0.10 0.05 0.5% Low $1,000 7 daysMike
Lipsett
Orderreplacementsfrom Vendors
(informStudents too)
8 Failed drainage Facility 0.10 0.05 0.5% Low $4,000 21 days RogerMarchand
Reschedulemove, assess
damage
9 Explodingequipment Facility 0.10 0.80 8.0% Medium $20,000 31 daysMike
LipsettCall 911,evacuate
-
8/7/2019 10 Risk Register
3/4
-
8/7/2019 10 Risk Register
4/4
Team #1 Personnel Listing
Shannon MacDonaldProject ManagerMec E
Luke Glistak Team MemberMec E
Sean HodgsonTeam MemberECE
Mk NimeshDevils Advocate
Eng. Mgmt.
Anand RohitTeam MemberECE