Gateway Pacific Terminal EIS Scoping Process
Successes, Catastrophes and Lessons Learned
![Page 2: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/2.jpg)
Copyright [insert date set by system] by [CH2M HILL entity] • Company Confidential
What I’ll cover
What we did
What went well
What we learned
Photos from CrossCut and Bellingham Herald
![Page 3: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/3.jpg)
Copyright [insert date set by system] by [CH2M HILL entity] • Company Confidential
Gateway Pacific Terminal EIS overview
CH2M HILL is conducting
the NEPA/SEPA process
for the Army Corps of
Engineers, Whatcom
County and the
Washington State
Department of Ecology
Proposal would construct a
deep water export terminal
north of Bellingham at
Cherry Point
![Page 4: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/4.jpg)
Copyright [insert date set by system] by [CH2M HILL entity] • Company Confidential
Scoping process
Conducted seven in person scoping meetings
Included a robust online meeting
Purpose of scoping is to understand issues and concerns to
inform EIS
Community members could participate: online, in person or by
submitting written comments
![Page 5: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/5.jpg)
Copyright [insert date set by system] by [CH2M HILL entity] • Company Confidential
Scoping participation outcomes
Location
Approximate No. of
Attendees
Bellingham 1,800
Friday Harbor 450
Mount Vernon 1,000
Ferndale 1,300
Spokane 850
Vancouver 900
Seattle 2,400
Photos from CrossCut
![Page 6: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/6.jpg)
Copyright [insert date set by system] by [CH2M HILL entity] • Company Confidential
Scoping participation outcomes
Website:
– More than 64,000 visits
More than 124,000 comments
Public meetings were civil and
verbal comments were taken
throughout each meeting
![Page 7: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/7.jpg)
Copyright [insert date set by system] by [CH2M HILL entity] • Company Confidential
Most comments from Washington State
![Page 8: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/8.jpg)
Lessons learned
![Page 9: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/9.jpg)
1
Stakeholder interviews lay the groundwork for a
equitable, fair public process.
![Page 10: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/10.jpg)
2Put the web to work for you to reduce data
entry and increase transparency.
![Page 11: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/11.jpg)
Copyright [insert date set by system] by [CH2M HILL entity] • Company Confidential
Comment management: self tagging
![Page 12: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/12.jpg)
3
Create convenient ways for people to
participate who don’t want or need the public
meeting experience.
![Page 13: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/13.jpg)
Plan for your meeting from start to finish!
4
![Page 14: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/14.jpg)
5
Provide plenty of
space.
![Page 15: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/15.jpg)
6
Manage verbal comment very carefully.
Photos from CrossCut and Bellingham Herald
![Page 16: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/16.jpg)
7
Refine as you go and communicate
changes to participants.
![Page 17: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/17.jpg)
Copyright [insert date set by system] by [CH2M HILL entity] • Company Confidential
Communicating change during the process
![Page 18: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/18.jpg)
8
Decide how
comments will
be collected
and analyzed
ahead of time.
![Page 19: 10-2-13 PI Network: Gateway Pacific Terminal EIS Scoping P2 by Kristin Hull](https://reader035.vdocuments.us/reader035/viewer/2022070322/55909e941a28ab7f148b4771/html5/thumbnails/19.jpg)
9