8th Central and Eastern European Software Engineering Conference in Russia - CEE-SECR 2012November 1 - 2, Moscow
Mikhail GedzbergSr. Project Manager
Agile implementation in investment banking projects
![Page 2: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/2.jpg)
Why Agile?
Preconditions:Long release cycleFast requirements changesHeavy weight featuresLow delivery progress transparencyMany incidents on production
![Page 3: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/3.jpg)
Case: What Scrum Is
Agile means: everything is changed. Right?Individual understanding what Scrum is.PO vs Team: who is winner
![Page 4: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/4.jpg)
Case: Distributive Stakeholders
•Identify all persons & roles•Involve in discussion loop•Get rapid feedback
![Page 5: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/5.jpg)
Case: Feature Sign Off
Get business sign off in advance
![Page 6: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/6.jpg)
Case: Roadmap To The Future
Get key things:Features/priorities Dead linesDependencies
![Page 7: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/7.jpg)
Case: Scope Negotiation Time
StepsAll Sprint-> 1 Week1 Week -> 3 Days3 Days -> 0 Days
![Page 8: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/8.jpg)
Case: Human Resource Pool
Focus on Full Functional TeamFreeze team on Sprint/ReleaseMinimize team member sharing between projects
![Page 9: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/9.jpg)
Case: Maximum Task Duration
Steps:Infinite -> 3 Days3 Days -> 2 Days2 Days -> 1 Day
![Page 10: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/10.jpg)
Case: Team Capacity
Commit on 80% of team capacity on sprintAnalyze worst task estimation Automate everything possible
![Page 11: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/11.jpg)
Case: Business vs IT
Sprint scope: 80% business / 20% technical tasksPeriodically announce sprint with technical goalDon’t miss sprint!
![Page 12: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/12.jpg)
Case: Show What Team Did
Each release demo is a must (Live or Record)
![Page 13: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/13.jpg)
Achievements
Time To Market: 3 weeksTransparent, predictable & stable projectExtra positive feedback from customersNo incident on productionHigh team spiritISO 9001:2008 certification
![Page 14: Внедрение Agile в проектах инвестиционного банкинга](https://reader033.vdocuments.us/reader033/viewer/2022051515/54c7e26a4a795999488b467e/html5/thumbnails/14.jpg)
Hints
Document process highlightsCare your processSale your demoRetro with action plan is a mustKeep in mind product roadmap
Have fun