double slip joint - winddays...2018/06/13  · cranefree gravity foundation ( seatower) (undisclosed...

45
Westpoint Building 2 | De Brauwweg 60 | 3125 AE Schiedam | The Netherlands | www.kci.nl | [email protected] Schiedam, 2015 WindDays - 13 th June 2018 Double Slip Joint Innovative Pile Connection

Upload: others

Post on 20-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Westpoint Building 2 | De Brauwweg 60 | 3125 AE Schiedam | The Netherlands | www.kci.nl | [email protected]

Schiedam, 2015WindDays - 13thJune 2018

Double Slip Joint Innovative Pile Connection

Page 2: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets
Page 3: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

About KCI

• Oil & Gas

• Renewables

• Equipment

• Wheels

Page 4: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

1.3 Substations

Riffgat (Basic Design (2nd BSH), Detailed Design (3rd BSH)) DanTysk (Basic & Detailed Design) Luchterduinen (Owners engineering) Horns Rev C (Detailed engineering) Offshore Switch Yard (Elia, Belgium, Basic Design) Wikinger (Iberdrola, Germany:

Concept Design, Basic Design, Detailed Design, Fabrication support) Meerwind (WindMW, Germany, Basic Design, Detailed Design) Gemini (Iemants, The Netherlands, all jacket calculations) Riffgat (Hollandia Strukton, Germany, Basic Design, Detailed Design) DanTysk (Hollandia Strukton, Germany, Basic Design, Detailed Design) Offshore Switch Yard (Elia, Belgium, Basic Design)

Page 5: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Wind Turbine Foundations

GBFs Blyth Offshore Wind

Demonstrator Secondarysteel design

Further development of transition piece design Cranefree Gravity Foundation (Seatower) (undisclosed project)

Monopiles Bearing Solution MP-TP Double Slip Joint (patented)

Jackets Three legged Jacket Light Transition Piece Double boatlanding

Page 6: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

About KCI

135 m

London Paris

324 m

Wheels – Ain Dubai(under construction)

Page 7: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets
Page 8: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Special relations

R&D Consortium

Installation Fabrication

Design

SIEMENS

Valuable feed-back

Page 9: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets
Page 10: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Question

“What do you think can be improved for TP connections ?”

Page 11: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

8 Monopile connections (left 4 concepts are based on presentation for event Smulders 1000 TP)

Dowec ‘03

Page 12: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets
Page 13: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

How it works

Foundation pile

Conical rings Taper angle ≈ 2⁰

ICCP anode

Transition Piece

Page 14: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

4 m

2⁰

How it works - Sketch

• Material: St355

• Minimum machining

• Tolerance angle ± 0.1°

Page 15: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

How it works - vertical self settling

Load

Slip

Storm 1(SW)

Storm 2(W)

Storm 3(NW)

time

locked

≈ 150mm

Pile

Self-tightened/lockedSteel on steel contact

Page 16: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

How it works – roundness settling

Page 17: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

How it works – roundness settling

100% settled(100% contact)

5% settled(75% contact)

Before settling(contact at 3 points)

Well defined contact between rings

Page 18: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Tapered rings

Bending moment is fully transferred by friction- connected as if welded

MF

How it works – Load transfer by friction

Page 19: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Settling by natural turbine loads- no special tools required

Tapered rings

How it works – Settling by natural loadsF

M

Page 20: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Attractiveproperties

Page 21: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Benefits – 1 of 5

Tapered rings

1) Simple, no grout or bolts, contact at conical steel surfaces

Page 22: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Fast: TP installation cycle 30% shorter:

• Smaller installation vessel spread

• Short offshore campaign

• Logistics of entire project speeding up

Tapered rings

2) Fast installation

1) Simple, no grout or bolts, contact at conical steel surfaces

Benefits – 2 of 5

Page 23: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Safe:

• The DSJ avoids the awkward unstable moment of pin-point placement of the TP on the pile

Tapered rings

2) Fast installation

3) TP instantly stable after placing it on the pile

1) Simple, no grout or bolts, contact at conical steel surfaces

Benefits – 3 of 5

Page 24: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Safe:

• No access to the TP required

Tapered rings

2) Fast installation3) TP instantly stable after placing it on the pile

4) Personnel access and manual work on the TP not required

1) Simple, no grout or bolts, contact at conical steel surfaces

Benefits – 4 of 5

Page 25: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

5) Connection can be deep under water

2) Fast installation

Why is this important ?Tapered rings

3) TP instantly stable after placing it on the pile 4) Personnel access and manual work on the TP not required

1) Simple, no grout or bolts, contact at conical steel surfaces

Benefits – 5 of 5

Page 26: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Weight split 50%

200 ton25 m

1200 ton80 m

Typical foundation for 8 MW turbine

Bolted TP

flanges

groutskirt

40m

20m

With DSJ

700 ton45 m

700 ton55 m

Relevant for building future turbines ! 10-15 MW

Page 27: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Future XL foundation for 15 MW

1500 ton

1500 ton

TP installation

Tower installation

Page 28: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Future XL foundation for 15 MW

Page 29: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

1. Simple connection, no grout or bolts

2. Fast installation

3. TP instantly stable on the pile

4. Personnel access and manual work on TP are not required

5. Connection can be deep under water (weight split 50%)

Five Benefits - summarized

“Plug & Go”

Page 30: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets
Page 31: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Test set-up

F

EquivalentMoment & force

MP clamped

TP neutral weight

M

Page 32: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Prototype SIF

Length 15m + 6mWeight 12t + 5 t

Scale 1:5 for 8 MW(or full scale 500 kW)

Page 33: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Test set-up WMC

6 ton6 ton

Page 34: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Test results – cyclic bending

Limit 8 mm

Limit 12 mm

125 cycles

125 cycles

Page 35: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Test results - irregular loads

Page 36: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets
Page 37: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Various rings manufacturing methods

1) Rollingconical strips 800x130 mm

2) Forging and final machining

3) Expansion first cylindrical rolling

Tolerances• wedge angle • Circumference • Ring flatness • Ring distance

Manufacturing costs

Tolerances• wedge angle • Circumference • Ring flatness • Ring distance

Manufacturing costs

Tolerances• wedge angle • Circumference • Ring flatness • Ring distance

Manufacturing costs ?

Page 38: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets
Page 39: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Business case – main conclusions

1. The most appealing properties: simple, robust and stable connection

2. Costs of installation are 30% lower

3. Costs manufacturing are also lower (especially with future larger turbines)

4. The installation is faster and safer, reducing the project schedule and project risks

5. No investments in the organization, supply chain or installation equipment

6. More flexibility in the employability of the installation fleet for future XL foundations.

Page 40: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets
Page 41: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Time line for Double Slip Joint development

Feasibility

Mini-testsWoZ medium-tests

Full scale demo

Ready for commercial use

WoZ award

1:30

1:5

1:1

futureJan 2014 (graduation TUD)

Jan 2015-2016(graduation TUD)

2017(consortium)

• Our product: foundation & connection concept

• Offshore wind farm - 2019 ?

Page 42: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Time line for Double Slip Joint development

Actual & Perceived risksJudging risks and returns

Use proven technologyUse the Double Slip Joint – “risks”: Returns: Use the Double Slip Joint – “risks”:• Does it work ?• Failure modes, corrosion ?• Time risks ?• Unknown risks ?

Returns:• Lower costs supply & installation• Shorter installation schedule• Lower O&M costs• No risks of bolt/grout failure

Page 43: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Question

• Dynamic Strength

• TP Installation speed

• Low Risk, Safety

• Cost Efficiency

“What do you think can be improved for TP connections ?”

Page 44: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Questions ?

Page 45: Double Slip Joint - WindDays...2018/06/13  · Cranefree Gravity Foundation ( Seatower) (undisclosed project) Monopiles Bearing Solution MP -TP Double Slip Joint (patented) Jackets

Boudewijn van [email protected]

Thank you !