double quarter wave crab cavity helium vessel

33
HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014 Work partly supported by the EU FP7 HiLumi LHC grant agreement No. 284404 and by the US DOE through Brookhaven Science Associates, LLC under contract No. DE-AC02- 98CH10886 with the US LHC Accelerator Research Program (LARP). This research used resources of the National Energy Research Scientific Computing Center, which is supported by the US DOE under contract No. DE-AC02-05CH11231. Double Quarter Wave Crab Cavity Helium Vessel Silvia Verdú-Andrés on behalf of the DQWCC team May 5, 2014

Upload: tevy

Post on 23-Feb-2016

46 views

Category:

Documents


0 download

DESCRIPTION

Double Quarter Wave Crab Cavity Helium Vessel. Silvia Verdú -Andrés o n behalf of the DQWCC team May 5, 2014. Outline. Conceptual design of the helium vessel and tuning system for the SPS DQWCC Overview: dimensions, weight, He volume Cavity stiffening, pre-tuning and tuning systems - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

Work partly supported by the EU FP7 HiLumi LHC grant agreement No. 284404 and by the US DOE through Brookhaven Science Associates, LLC under contract No. DE-AC02-98CH10886 with the US LHC Accelerator Research Program (LARP). This research used resources of the National Energy Research Scientific Computing Center, which is supported by the US DOE under contract No. DE-AC02-

05CH11231.

Double Quarter Wave Crab CavityHelium Vessel

Silvia Verdú-Andréson behalf of the DQWCC team

May 5, 2014

Page 2: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

2

Outline• Conceptual design of the helium vessel and tuning system for the SPS

DQWCC– Overview: dimensions, weight, He volume– Cavity stiffening, pre-tuning and tuning systems – Helium vessel and tuning system: assembly sequence, connections and

interfaces, materials and joints

• Engineering studies– Pre-tuning and tuning range– Mechanical stresses– Thermal loads

• Summary

Page 3: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

3

• PoP helium vessel to introduce smoothly the conceptual design

Page 4: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

4

Cryo jumper

Tuner +

stiffening

Adjacent beam pipe through the vessel

beam

FPC

HOM

HOM

Helium vessel - concept

• Titanium and Niobium similar thermal expansion coefficient rigid connections for all ports• Piezo outside vessel larger tuning

range• Prep rings for eventual disassembly• All liquid helium – vacuum interfaces

welded for best vacuum tightness• Clearance to access to ports

PUPU

Ribs for additional stiffening

Can CERN provide drawing of tuning system with piezo part?

Page 5: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

5

Pre-tuning and tuning systems

Combined function: tuning + stiffening

H-field

Tuning by actuation on the central plates

E-field

Silvia: PoP SPS

Page 6: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

6

Nicer cross-section to show pre-tuning with bolts to be fixed onto helium vessel top plate??

Pre-tuning system

pre-tuning

• Pre-tuning ~ 1.6 MHz/mm(during assembly of cavity-vessel)for machining tolerances

Put Qiong’s table with machining tolerances

Page 7: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

7

Tuning system

Symmetric actuation onto both

central plates

Can CERN provide drawing with piezo location???

tuning

• Tuning(after installation) push-pull ~ 1.6 MHz/mm(during operation) piezo ~ 30 mmfor Lorentz detuning and microphonics

Page 8: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

8

Lorentz detuning

Lorentz detuning: 0.17 Hz/ (10J) – best case scenario

E-field H-field

Fixed all ports and central plates (best case scenario)

𝑃=14 (−𝜀0|�⃗�|2+𝜇0|⃗𝐻|2)

Page 9: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

9

Combined function: tuning + stiffening

on central plates

Stiffening during cooling down and pressure changes

All port connections are rigid but PU

Stiffening for cavity and helium vessel

Ribs Any additional stiffening for the cavity????

Page 10: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

10

Helium vessel - dimensions

660mm

470mm

390m

m

He capacity: ??Weight: ??

Integration into cryomodule

Page 11: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

11

Cavity assembly1

Page 12: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

12

Cavity assembly1 316LN SS

DN63CFFlanges for FPC and BP; others are NbTi

SS flange, Nb tube, Ti ring/adaptor

Ti

brazedwelded

HOM: NbTi flange welded to Ti adaptor and Nb tube

Page 13: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

13

Tuning system assembly1 2

Ti rod

brazedwelded

Page 14: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

14

Tuning system assembly1 2

3Ti

housing

brazedwelded

Page 15: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

15

1

2

3

4

Helium vessel assembly

brazedwelded

Ti prep ring

Ti prep ring

Ti vessel

Grade 2 titanium.

Integrated section of adjacent beam pipe in which material??

Cryo tube in SS brazed to prep tube in Ti. SS – H ; Ti-V

Page 16: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

16

Helium – vacuum interfaces

• All liquid helium – vacuum interfaces welded

No flow! Find another word

Page 17: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

17

Cooling and heat-stationing

Helium chamberfor HOM filter

Heat-stationing for tuning frame

Heat-stationing for tuning tube

He

Page 18: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

18

Heat loads – tuning system • Picture with temperature to show gradients• Picture of simulation result

CERN: heat load for tuning system

Page 19: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

19

Total heat load

To be updated: Skaritka

Page 20: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

20

Mechanical stresses1. Helium pressure2. 300 K 2K3. Actuation of tuning system

Page 21: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

21

Mechanical stresses1. Helium pressure2. 300 K 2K3. Actuation of tuning system

Helium

Page 22: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

22

Mechanical stresses due to helium pressure

• Constrains (fixed boundaries, etc)• Load(s) and number of cycles (if applies)• Max. stress allowed• Picture of mesh• Picture of initial constrains and loads• Picture of stress value and deformation arrows• Design elements incorporated to counter-act load effects• Young modulus and Poisson’s ratio

Page 23: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

23

Mechanical stresses1. Helium pressure2. 300 K 2K3. Actuation of tuning system

Page 24: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

24

Mechanical stresses due to thermal contraction (300K 2K)

• Constrains (fixed boundaries, etc)• Load(s) and number of cycles (if applies)• Max. stress allowed• Picture of mesh • Picture of initial constrains and loads• Picture of stress value and deformation arrows• Design elements incorporated to counter-act load effects• Thermal expansion coefficient for Niobium and Titanium,

Young modulus and Poisson’s ratio

Page 25: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

25

Mechanical stresses1. Helium pressure2. 300 K 2K3. Actuation of tuning system

Page 26: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

26

Mechanical stresses due to tuning system actuation

• Constrains (fixed boundaries, etc)• Load(s) and number of cycles (if applies)• Max. stress allowed• Picture of initial constrains and loads• Picture of mesh• Picture of stress value and deformation arrows• Design elements incorporated to counter-act load effects• Young modulus and Poisson’s ratio

Page 27: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

27

Integration into cryomodule

Tomorrow’s presentation by John Skaritka

Page 28: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

28

Summary• Compact vessel for compact cavity• Dedicated vessel design to:

– minimize liquid helium leak chances (all helium-vacuum interfaces welded)

– ease assembly, particularly the access to cavity ports– ease disassembly (prep rings)

• Robust vessel design?? • Appropriate stiffening of the cavity provided by rigid connection

of cavity ports to vessel and tuning system• Manifold tuning : pre-tuning + push-pull + piezo• Optimized design for reduced heat load??

Page 29: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

29

BNLSergey Belomestnykh, Ilan Ben-Zvi, John Skaritka, Silvia Verdú-Andrés, Binping Xiao, Qiong Wu

CERNLuis Alberty, Rama Calaga, Ofelia Capatina, Federico Carra, Giuseppe Foffano, Norbert Kuder, Raphael Leuxe, Thierry Renaglia

SLACZenghai Li

Page 30: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

30

Thanks for your attention

Long Island Blue Claw Crabs

Page 31: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

31

Cavity mounting

Page 32: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

32

Page 33: Double Quarter Wave Crab Cavity Helium Vessel

HiLumi-LHC/LARP Crab Cavity System External Review – May 5-6 2014

33

Integration into cryomodule