    Handling of Bell mounted OLTCs during VPD & Tanking at Trafo end

    Correct method:

    Diverter switch should be fitted on OLTC

    with Headonly.

    Head

    Wrong method:

    Diverter switch should not be fitted on

    Aluminium Bell mounting Top flange

    without OLTC Head.

    Alu. Bell Mounting Flange.

    If the diverter switch was mounted on the

    OLTC head then the gap will be achieved

    in between Nylon numbering disc gear

    and Diverter Fixed Contact Shell(DFCA)

    Gap 4 mm.

    If the diverter switch was mounted on the

    Bell mounting flange with out OLTC head

    then the Diverter Fixed Contact Shell(DFCA) will foul on the numbering disc

    Nylon gear resulting damage in

    numbering disc gear.

    Fouling area.

    Diverter

    switch

  • 8/7/2019 Dos and Donts During VPD

    2/2

    Handling of Bell mounted OLTCs during VPD & Tanking at Trafo end

    Fouling of Diverter will led to damage of

    Numbering disc Nylon gear teeth.

    Fouling of Diverter will also lead to

    damage the center stem of Numbering

    disc Nylon gear.

    Two types of gear damage due to

    improper handling of OLTCs during VPD

    and Tanking process.

    a) Teeth broken.b) Stem broken.

    Conclusion:

    Diverter switch should not be inserted without OLTC Aluminium / Fabricated Head.