dor and precom 11 okt.xlsx

43
EPCI MILA- A ASTI D Date October 11 th, 2015 Number 11/DOR-CNO/RPE/X/ASTI Period from 6.00 October 11 th, 2015 to 6.00 October 12 th, 2015 Location ASTI-A, CNOOC area 1. WORKING PROGRESS 1.1.MAIN No Job Description 1 Anchor Job and Barge Setup 1.1 Anchor Job and Barge Setup at Asti A P/F 1.2 TRA-2 and Simop 2 Preparation 2.1 Transfer equipment to Asti - A P/F 2.2 Line Mapping (Mechanical and E & I) 2.3 Install Scaffolding 3 Mechanical Work 3.1 Install Support and Mechanical Equipment 3.2 Structure reinstatement 3.3 Install sum caisson 3.4 Install pump caisson 3.5 Install riser cable I-tube 4 Piping 4.1 Piping valve and fitting reinstatement 4.2 Piping Field weld 4.3 Riser and subsea spool installation 4.4 Painting and Touch-up 5 Installation Electrical 5.1 Continuity and insulation test cable 5.2 Install cable ladder, tray and support 5.3 Pulling cable 5.4 Glanding 5.5 Install electric Equipment 5.6 Termination 6 Installation Instrument 6.1 Continuity and insulation test cable 6.2 Install cable ladder, tray and support 6.3 Pulling cable 6.4 Glanding 6.5 Running tubing 6.6 Install Instrument equipment 6.7 Termination 7 Precomissioning 7.1 Piping 7.2 Hydrotest piping 7.3 Mechanical 7.4 Riser Pipeline 7.5 Electrical

Upload: isfhahan-achmad-dzulqarnain

Post on 14-Apr-2016

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Dor and precom 11 okt.xlsx

EPCI MILA- A ASTI PLATFORM AND PIPELINE 2nd CAMPAIGN

DAILY OPERATION REPORT

Date October 11 th, 2015Number 11/DOR-CNO/RPE/X/ASTIPeriod from 6.00 October 11 th, 2015 to 6.00 October 12 th, 2015Location ASTI-A, CNOOC area

1. WORKING PROGRESS1.1.MAIN

No Job Description

1 Anchor Job and Barge Setup1.1 Anchor Job and Barge Setup at Asti A P/F1.2 TRA-2 and Simop2 Preparation

2.1 Transfer equipment to Asti - A P/F2.2 Line Mapping (Mechanical and E & I)2.3 Install Scaffolding3 Mechanical Work

3.1 Install Support and Mechanical Equipment3.2 Structure reinstatement3.3 Install sum caisson3.4 Install pump caisson3.5 Install riser cable I-tube4 Piping

4.1 Piping valve and fitting reinstatement4.2 Piping Field weld4.3 Riser and subsea spool installation4.4 Painting and Touch-up5 Installation Electrical

5.1 Continuity and insulation test cable5.2 Install cable ladder, tray and support5.3 Pulling cable5.4 Glanding5.5 Install electric Equipment5.6 Termination6 Installation Instrument

6.1 Continuity and insulation test cable6.2 Install cable ladder, tray and support6.3 Pulling cable

6.4 Glanding6.5 Running tubing6.6 Install Instrument equipment6.7 Termination7 Precomissioning

7.1 Piping7.2 Hydrotest piping7.3 Mechanical7.4 Riser Pipeline7.5 Electrical

Page 2: Dor and precom 11 okt.xlsx

7.6 Instrument7.7 Precomissioning completed8 Demob

8.1 Demob

TOTAL

Note:

1.2. ADDITIONAL WORK 1

No Item Qty

1 Riser 35% 12 Subsea Spool A (fixed) 25% 13 Subsea Spool A (metrology) 40% 1

Total

1.3 ADDITIONAL WORK 2

No Item Qty Unit

1 38 Ea

2 38 Ea

Total

1.4 ADDITIONAL WORK 3 (FABRICATION AND INSTALL SAFETY EQUIPMENT)

No Description

1 Support for Carbon Dioxide Portable Extinguisher2 Support for Dry Chemical Portable Extinguisher 3 Support for Wheelded Dry Chemical Extinguisher4 Support for Self Contained Eye Wash Unit5 Support for Safety Equipment Cabinet6 Support for Emergency rescue kit7 Support for Life Buoy8 Support for Life Raft

Total

3460-AST-61015 Telecomunication tower modify ladder

3460-MLA-61015 Telecomunication tower modify ladder

Page 3: Dor and precom 11 okt.xlsx

2. HSE RECORD

Issue Date WP No. Description of Work

10/11/15 PGF/HW/BC/15/208 Fabrication support at main deck BC

10/11/15 PGF/CW/BC/15/209 Lifting and transfer material

10/11/15 PGF/CW/AST/15/111 Install and dismantle scaffolding

10/11/15 PGF/HW/AST/15/052 Fabriction, fit-up, welding, pipe riser 10" and support

10/11/15 PGF/CW/AST/15/109 Pulling cable and termination

10/11/15 PGF/CW/AST/15/110 Hydrotest preparation and bolting

10/11/15 PGF/CW/AST/15/086 Radiography activity for line pipe 10"

Description Previous Today

- Unsafe action / unsafe condition 0 0- Near Miss 0 0- Incident / Accident 0 0

- Medical Treatment 0 0

3. MANHOURS

Safety Man-hours POB Previous Today

RPE 67 29604 804Consortium RPE 7 3924 84TIMAS 0 2688 0Patra Dinamika 22 10404 264Bayu Maritim 22 18456 264TAU 17 9300 204Geoservices 21 3636 252Lekom Maras 3 1008 36Mesco 7 1776 84CNOOC Reps 1 348 12Hydra Asia 1 1224 12Gardatama 1 588 12Pageo 2 1176 24Other 0 108 0

Total 171 84240 2052

4. PROJECT DOWNTIME ISSUE

TotalWeather Down Time Client Activities Insertion

Prev. Today Cum. Prev.(hours) 2 0 2 0

5. GENERAL ACTIVITY

Time Location Job Description

6:00 - 6:30 BC Toolbox meeting on main deck Bayu Construction

Piping, Structure and Mechanical6:30 - 17:00 ASTI ѻ Complete joining Water sea line (GRE) at subcellar deck, 2 joint

ASTI ѻ Continue touch-up painting at all area ASTI ѻ Continue SAT ICS by vendor at mezzanine deckASTI ѻ Continue setting Multi Phase Flow Meter by vendor at cellar deck

ElectricalASTI ѻ Install cable ladder cover, 16 lines at mezzanine deck

Page 4: Dor and precom 11 okt.xlsx

ASTI ѻ Install cable ladder clamps, 28 setsASTI ѻ Install and modify cable cover elbow, 2 eaASTI ѻ Install tagging marker cable electical JB and equipment field at all area

InstrumentASTI ѻ Modify additional support on pump injection MEG inside MEG skid at mezzanineASTI ѻ Re-location MEG pump position at mezanine deckASTI ѻ Install tagging marker cable instrument at all area

17:30 - 18:00 BC Break and crew change18:00 - 18:30 BC Toolbox meeting on main deck Bayu Construction

Piping, Structure and Mechanical18:30 - 5.30 ASTI ѻ Assist diver bolt tighting riser guard

BC ѻ Prepare and arrange filling pumps in preperation for pipline hydrotestASTI ѻ Continue cleaning all areaASTI ѻ Modifiy chemical sampling support

Page 5: Dor and precom 11 okt.xlsx

6. PLANNING NEXT 24 HOURS

Discipline Description

Piping - Continue spool preparation for hydrotesting - Install subsea spool (metrology)

7. ACTUAL PROGRESS WORK FOR 24 HOURS

A. Mechanical Work

B. Piping Work

C. Electric work

8. MATERIAL AND GAS CONSUMABLE

MATERIAL

Consumable gas send From Bayu Construction to Petro Charlie:ѻ Oxygen = 1 botlѻ Acetylene = 1 botl

10. MAN POWER BREAKDOWN

RPE CONSORTIUM RPE

Position Qty PositionConstruction Manager 1 Piping Eng.Superitendent 0 Electrical Eng.Doctor 1 Instrument Eng.Electrical & Instrument 16 Material ManFitter 4 Mechanical Eng.Grinder 5 Structure Eng.HSE 3 QA/QCHydrotest Operator 1 SafetyMechanic 2 Project EngNDT 0Painter 0Paramedic 1Planner 1QA/QC 4Rigger 6Scaffolder 6Store man 2

Page 6: Dor and precom 11 okt.xlsx

Supervisor 2Welder 6Technician 3Other 3

Total 67 Total

9. CONSTRAINT, HIGHLIGHT, AND ASK FOR HELP

A. CONSTRAINT

ѻ Modification washdown pump connection ѻ Modification Air compressor piping to get space for maintenanceѻ Need to maintenance jib crane after 2 year storage (change oil, grease, ect)ѻ Modification Corrosion inhibitor tubing line ѻ Modification Chemical injection tubing line

B. HIGHLIGHT

ѻ Outstanding duplex spool 6" to Carbon steel flange that fabrication at Jakarta(o/s 1 joint and Hydrotest)

ѻ Outstanding material for thermocouple that machining at Jakartaѻ Outstanding horn, swing limiter switch for Jib Craneѻ Outstanding enclosure seal for pig launcher

RPE GROUP - B.CON (CONSORTIUM)Prepared by : Checked by :

Didik Sudaryono Reza AjiputraConstruction Manager PT. RPE Engineer

Page 7: Dor and precom 11 okt.xlsx

EPCI MILA- A ASTI PLATFORM AND PIPELINE 2nd CAMPAIGN

DAILY OPERATION REPORT

Period Weather Wind Sea Picth06.00 to 08.00 Clear 15 - 16 moderate 0.5 - 1

12.00 to 13.00 Clear 15 - 16 rought 1 - 2

18.00 to 19.00 Clear 14 - 16 rought 1 - 2

24.00 to 01.00 Clear 14 - 16 rought 1 - 2

Weight factor (%) previous today to date

2.00% 2.0% 0.00% 2.00%

1.00% 100.0% 0.0% 100.0%

1.00% 100.0% 0.0% 100.0%

4.00% 3.97% 0.00% 3.97%

1.00% 97.0% 0.0% 97.0%

1.00% 100.0% 0.0% 100.0%

2.00% 100.0% 0.0% 100.0%

25.00% 24.2% 0.75% 24.98%

5.00% 84.6% 15.0% 99.6%

8.00% 100.0% 0.0% 100.0%

4.00% 100.0% 0.0% 100.0%

4.00% 100.0% 0.0% 100.0%

4.00% 100.0% 0.0% 100.0%

20.00% 17.75% 0.00% 17.75%

4.00% 98.8% 0.0% 98.8%

8.00% 98.1% 0.0% 98.1%

6.00% 92.6% 0.0% 92.6%

2.00% 19.8% 0.0% 19.8%

17.00% 16.44% 0.00% 16.44%

1.00% 100.0% 0.0% 100.0%

3.00% 99.1% 0.0% 99.1%

5.00% 98.4% 0.0% 98.4%

2.00% 91.6% 0.0% 91.6%

4.00% 100.0% 0.0% 100.0%

2.00% 85.9% 0.0% 85.9%

19.00% 17.66% 0.06% 17.72%

1.00% 84.0% 0.0% 84.0%

3.00% 98.8% 0.0% 98.8%

4.00% 97.6% 0.0% 97.6%

2.00% 91.5% 0.0% 91.5%

4.00% 90.1% 0.0% 90.1%

4.00% 91.6% 1.5% 93.1%

1.00% 85.4% 0.0% 85.4%

11.00% 5.8% 1.22% 7.05%

2.00% 74.1% 0.0% 74.1%

1.00% 92.1% 0.0% 92.1%

1.00% 20.0% 0.0% 20.0%

2.00% 100.0% 0.0% 100.0%

2.00% 52.0% 34.0% 86.0%

Page 8: Dor and precom 11 okt.xlsx

2.00% 9.8% 2.7% 12.5%

1.00% 0.0% 48.1% 48.1%

2.00% 0.0% 0.00% 0.00%

2.00% 0.0% 0.0% 0.0%

100% 87.89% 2.03% 89.92%

UnitNDT Precomm Progress

20% 70% 5% 5%

EA 100% 100% none 100% 95.5%

EA 100% 100% none 0% 90.0%

EA 100% 95% 100% 0% 91.5%

92.6%

Cut bevelFit Up Welding NDT Lift - Install Progress

20% 50% 5% 15%

100% 100% 100% 100% 100% 100.0%

100% 100% 100% 100% 0% 85.0%

93%

Total QtyCut & Fit-up Welding Painting Installation

25% 55% 10% 10%

4 EA 0.0% 0.0% 0.0% 0.0%7 EA 0.0% 0.0% 0.0% 0.0%2 EA 0.0% 0.0% 0.0% 0.0%1 EA none none none 100.0%1 EA 100.0% 100.0% 100.0% 100.0%1 EA 100.0% 100.0% 100.0% 100.0%12 EA 100.0% 100.0% 100.0% 100.0%2 EA 100.0% 100.0% 100.0% 100.0%30

11/DOR-CNO/RPE/X/ASTI

Lifting & positioning

Fit-up & welding or Bolting

Page 9: Dor and precom 11 okt.xlsx

Description of Work Location Permit authority Open Close

Bayu Construction Yudi 6:00

Bayu Construction Parlindungan 6:00

ASTI-A Baharudin 8:05

Fabriction, fit-up, welding, pipe riser 10" and support ASTI-A Yusran 8:05

ASTI-A Wahsidin 7:05

ASTI-A Yudi 7:05

ASTI-A Yudi 7:05

To date Description Previous Today

0 - Safety Induction 0 00 - Inspection 0 00 - Toolbox meeting 38 20 - General safety meeting 4 1

Today Overtime Cumulative Lost Time Accident

0 30408 00 4008 00 2688 00 10668 00 18720 00 9504 00 3888 00 1044 00 1860 00 360 00 1236 00 600 00 1200 00 108 00 86292 0

Client Activities Insertion Equipment DowntimeTotal Downtime

Today Cum. Prev. Today Cum.0 0 0 0 0 2

Job Description

Toolbox meeting on main deck Bayu Construction

Complete joining Water sea line (GRE) at subcellar deck, 2 jointContinue touch-up painting at all area Continue SAT ICS by vendor at mezzanine deckContinue setting Multi Phase Flow Meter by vendor at cellar deck

Install cable ladder cover, 16 lines at mezzanine deck

Page 10: Dor and precom 11 okt.xlsx

Install cable ladder clamps, 28 setsInstall and modify cable cover elbow, 2 eaInstall tagging marker cable electical JB and equipment field at all area

Modify additional support on pump injection MEG inside MEG skid at mezzanineRe-location MEG pump position at mezanine deckInstall tagging marker cable instrument at all area

Toolbox meeting on main deck Bayu Construction

Assist diver bolt tighting riser guardPrepare and arrange filling pumps in preperation for pipline hydrotestContinue cleaning all areaModifiy chemical sampling support

11/DOR-CNO/RPE/X/ASTI

Page 11: Dor and precom 11 okt.xlsx

Discipline Description

E&I - Continue cable termination - Continue glanding cable

A. Mechanical Work D. Instrument Work

B. Piping Work E. Precomissioning

C. Electric work F. Comissioning

11/DOR-CNO/RPE/X/ASTI

MATERIAL Content Total Empty

Oxygen 16 10Acetylene 6 3LPG 8 2Nitrogen 10 8Argon UHP 99.999% 25 13

CONSORTIUM RPE TIMAS PATRA DINAMIKA

Qty Position Qty Position1 Tecnician 0 Supervisor1 QC 0 Ass. Supervisor1 QC Supervisor 0 Diver1 Engineer 0 Mechanic1 Tech/Hydrotest 0 Opt tensioning0 FE 0110

Page 12: Dor and precom 11 okt.xlsx

7 Total 0 Total

A. CONSTRAINT

B. HIGHLIGHT C. ASK FOR HELP

RPE GROUP - B.CON (CONSORTIUM) CNOOCChecked by : Approved by:

Reza Ajiputra Alexander SutrisnoPT. RPE Engineer Company Representative

11/DOR-CNO/RPE/X/ASTI

Page 13: Dor and precom 11 okt.xlsx

Roll0.5 - 1

1 - 2

1 - 2

1 - 2

Page 14: Dor and precom 11 okt.xlsx

Progress

0.0%0.0%0.0%

100.0%100.0%100.0%100.0%100.0%61.0%

page 1 of 3

Page 15: Dor and precom 11 okt.xlsx

Continue

To date

00

40

5

Lost Time Accident

Total Downtime

2

Job Description

Page 16: Dor and precom 11 okt.xlsx

page 2 of 3

Page 17: Dor and precom 11 okt.xlsx

Description

D. Instrument Work

E. Precomissioning

F. Comissioning

page 2 of 3

Full

6362

12

PATRA DINAMIKA

Qty22

1512

Page 18: Dor and precom 11 okt.xlsx

22

A. CONSTRAINT

C. ASK FOR HELP

CNOOCApproved by:

Alexander SutrisnoCompany Representative

page 3 of 3

Page 19: Dor and precom 11 okt.xlsx

1.FABRICATION

1.1 Piping

No Item Qty

1 Carbon Steel (CS) 149 2 Galvanize 583 1/43 Stainless Stell (SS) 4 4 Duplex 97 1/45 GRE 34

Total 867 1/2

1.2 Structure

No Item Qty

1 Main deck Flooring 582 Subcellar deck Framing 423 Cellar deck Flooring 274 SUMP CAISSON (AST-80001) 85 PUMP CAISSON 2

Total 137

2. PRECOMM

No Item Qty

1 TP-AST-001 12 TP-AST-002 13 TP-AST-003 14 TP-AST-004 15 TP-AST-005 16 TP-AST-006 17 TP-AST-007 18 TP-AST-008 19 TP-AST-008A 110 TP-AST-009 111 TP-AST-010 112 TP-AST-010A 113 TP-AST-011 114 TP-AST-012 115 TP-AST-013 116 TP-AST-014 117 TP-AST-015 1

Page 20: Dor and precom 11 okt.xlsx

18 TP-AST-016 119 TP-AST-017 120 TP-AST-018 121 TP-AST-019 122 TP-AST-019A 123 TP-AST-020 124 TP-AST-021 125 TP-AST-022 126 TP-AST-023 127 TP-AST-024 128 TP-AST-025 129 TP-AST-026 130 TP-AST-027 131 TP-AST-028 132 TP-AST-029 133 TP-AST-029A 134 TP-AST-030 135 TP-AST-031 136 TP-AST-032 1

Total 36

3. INSTALLATION

No Item Qty

1 Riser 12 Spool A 13 Spool B (Metrology) 1

Total

4. HOOK-UP PIPING

No Item Qty

1 Wellhead piping. 32 Pipeline from riser to SDV 203 Sump caisson, pump caisson, cable i-tube 3

TOTAL

5. TOUCH-UP PAINTING

Page 21: Dor and precom 11 okt.xlsx

No Item Qty

1 Riser above water 0.582 Piping 8.913 Structure 95.5

Total 104.99

Page 22: Dor and precom 11 okt.xlsx

October 11 th, 2015

Unit Fit-up Welding NDT PrecommProgress

30% 60% 5% 5%DB 100% 100% 100% 74.1% 98.7%DB 100% 100% 100% 74.1% 98.7%DB 100% 100% 100% 74.1% 98.7%DB 100% 94% 92% 74.1% 94.6%DB 100% 100% none 0.0% 95.0%

98.1%

UnitFit-up Welding NDT Precomm

Progress25% 70% 5%

jts 100% 100% 100% none 100.0%jts 100% 100% 100% none 100.0%jts 100% 100% 100% none 100.0%jts 100% 100% 100% none 100.0%jts 100% 100% 100% none 100.0%

100.0%

Unit Progress

TP 88.5%TP 84.0%TP 88.5%TP 88.5%TP 88.5%TP 88.5%TP 88.5%TP 88.5%TP 88.5%TP 75.0%TP 88.5%TP 20.0%TP 88.5%TP 88.5%TP 88.5%TP 88.5%TP 88.5%

Page 23: Dor and precom 11 okt.xlsx

TP 88.5%TP 75.0%TP 75.0%TP 90.0%TP 75.0%TP 88.5%TP 88.5%TP 88.5%TP 88.5%TP 90.0%TP 90.0%TP 90.0%TP 90.0%TP 90.0%TP 90.0%TP 90.0%TP 90.0%TP 15.0%TP 90.0%

74.1%

UnitNDT Precomm

Progress

20% 70% 5% 5%

EA 100% 100% none 10% 95.5%EA 100% 100% none 0% 90.0%EA 100% 95% 100% 0% 91.5%

92.6%

Unit Fit-up Welding NDT PrecommProgress

30% 60% 5% 5%

well 50.00% 50.00% 0.00% 0.00% 45.00%DB 100.00% 100.00% 100.00% 100.00% 100.00%EA 100.00% 100.00% 100.00%

59.95%

Lifting & positioning

Fit-up & welding or

Bolting

Page 24: Dor and precom 11 okt.xlsx

UnitBlasting Primer coat Second coat Top coat

Progress40% 20% 20% 20%

m2 100.0% 100.0% 100.0% 100.0% 100.00%m2 4.0% 4.0% 4.0% 4.0% 4.00%m2 30.0% 30.0% 7.0% 7.0% 20.80%

19.8%

Page 25: Dor and precom 11 okt.xlsx
Page 26: Dor and precom 11 okt.xlsx
Page 27: Dor and precom 11 okt.xlsx
Page 28: Dor and precom 11 okt.xlsx

ELECTRICAL WORKOctober 11 th, 2015

1 Support tray, Cable Tray and Cable Ladder

No Item Qty Unit WF Install Progress

1 Cabble tray support 20 EA 10% 20 100.0%

2 Cable Tray 25 Line 45% 24.5 98.0%

3 Cable Ladder 52 Line 45% 52 100.0%

TOTAL 97 100% 99.1%

2 Cable Work

No Description Qty Unit WF Install Progress

1 Pulling 31 Pull 50.0% 30.5 98.4%2 Glanding 262 EA 20.0% 240 91.6%3 Termination 262 Point 30.0% 225 85.9%

TOTAL 555 100% 93.3%

3 Electrical Equipment

No Item Qty Unit WF Install Progress

1 Navigation Aids Lantern (NAL) 2 EA 10.0% 2 100.0%

2 Obstruction Light 1 EA 10.0% 1 100.0%

3 Radar Beacon 1 EA 10.0% 1 100.0%

4 Lighting 36 EA 60.0% 36 100.0%

5 Trafo Lighting (TR) 1 EA 10.0% 1 100.0%

Total 41.0 100.0% 100.0%

INSTRUMENT WORK

1 Support tray, Cable Tray and Cable Ladder

No Item Qty Unit WFInstall Progress

1 Cabble tray support 50 EA 20% 49 98.00%

2 Cable Tray 25 Line 40% 24.5 98.00%

3 Cable Ladder 28 Line 40% 28 100.00%

TOTAL 103 100% 101.5 98.8%

2 Cable Work

No Description Qty Unit WF Installed Progress

1 Pulling 82 Pull 50.0% 80 97.6% 82 152 Glanding 164 EA 20.0% 150 91.5%3 Termination 164 Point 30.0% 140 85.4%

TOTAL 410 100% 370 92.7%

3 Tubing Work

No Description Qty Unit WF Installed Progress

1 3/8" 220 feet 16% 220 100.0%2 1/4" 119 feet 9% 119 100.0%3 1/2" 1050 feet 76% 912 86.9%

TOTAL 1389 100% 1251 90.1%

4 Instrument Equipment

No Item Qty Unit WF Installed Progress

1 Temprature indicator (TI) 6 EA 5.0% 4 100%2 Pressure Indicator (PI) 14 EA 5.0% 10 100%3 Level Gauge (LG) 1 EA 5.0% 1 100%4 MPFM cw Accessories 1 EA 10.0% 0 100%6 2 EA 5.0% 1 50% 120 - ok (at BC), 121 flange change to #600 (at jakarta)7 Pressure Indicator Transmitter (PIT) 14 EA 5.0% 14 100%8 Level Indicator Transmitter (LIT) 3 EA 5.0% 3 100%9 Temperature Indicator Transmitter (TIT) 2 EA 5.0% 2 100%

10 Flow Transmitter & Orifice Plate (FIT) 1 EA 5.0% 1 100%11 Restriction Orifice 8 EA 5.0% 1 13% at Jakarta,12 WHCP 1 EA 10.0% 1 100%13 PSV 5 EA 5.0% 5 100%14 Gas Detector (GD) 8 EA 5.0% 8 100%15 ESP Push Button 10 EA 5.0% 10 100%16 Regulator (PCV) 6 EA 5.0% 5 100%17 3 EA 15.0% 3 100%

Total 85 100.0% 69 93.1%

Pig Signaller (ZIS-120), (ZIS-121)

SDV - BDV - XV

Page 29: Dor and precom 11 okt.xlsx

MECHANICAL EQUIPMENT ASTI-A

No Description Qty Unit

1 Chemical Injection Set (U-715, T-175, P-715 A/B) 1 Set

2 Chemical Injection Set (U-725, T-725, P-725 A/B) 1 Set3 Wash Down Pump P-615 1 Pcs4 Closed Drain Pump P-415 1 Pcs5 Open Drain Pump P-510 1 Pcs

6 Jib Crane Equipment Y-905 E&I Cable 1 Pcs

7 Jib Crane Equipment Y-905 Lighting Lamp 1 Pcs

TOTAL 7

October 11 th, 2015

Page 30: Dor and precom 11 okt.xlsx

MECHANICAL EQUIPMENT ASTI-A

Installed Progress Remark

100.0% 100.0% installed100.0% 100.0% installed100.0% 100.0% installed100.0% 100.0% installed100.0% 100.0% installed

95.0% 95.0%

100.0% 100.0%99.63%

need scaffolding, prerequirement: comissioning trafo/FLBS/SWGR

need scaffolding, prerequirement: comissioning trafo/FLBS/SWGR

Page 31: Dor and precom 11 okt.xlsx

Planning to install

23 sept (tentative)23 sept (tentative)

installed20-Sep22-Sep

Page 32: Dor and precom 11 okt.xlsx

PRECOMISSIONING PIPING ASTI-A PLATFORM

TEST PACKAGE LINE CHECK

10% 5%

TP-AST-001 9 100.0% 100.0%TP-AST-002 10 100.0% 100.0%TP-AST-003 12 100.0% 100.0%TP-AST-004 3 100.0% 100.0%TP-AST-005 4 100.0% 100.0%TP-AST-006 1 100.0% 100.0%TP-AST-007 1 100.0% 100.0%TP-AST-008 3 100.0% 100.0%TP-AST-008A 1 100.0% 100.0%TP-AST-009 1 100.0% 100.0%TP-AST-010 3 100.0% 100.0%TP-AST-010A 3 100.0% 100.0%TP-AST-011 9 100.0% 100.0%TP-AST-012 2 100.0% 100.0%TP-AST-013 5 100.0% 100.0%TP-AST-014 1 100.0% 100.0%TP-AST-015 5 100.0% 100.0%TP-AST-016 17 100.0% 100.0%TP-AST-017 4 100.0% 100.0%TP-AST-018 33 100.0% 100.0%TP-AST-019 1 100.0% 100.0%TP-AST-019A 2 100.0% 100.0%TP-AST-020 2 100.0% 100.0%TP-AST-021 4 100.0% 100.0%TP-AST-022 8 100.0% 100.0%TP-AST-023 11 100.0% 100.0%TP-AST-024 2 100.0% 100.0%TP-AST-025 1 100.0% 100.0%TP-AST-026 1 100.0% 100.0%TP-AST-027 1 100.0% 100.0%TP-AST-028 1 100.0% 100.0%TP-AST-029 1 100.0% 100.0%TP-AST-029A 4 100.0% 100.0%TP-AST-030 8 100.0% 100.0%TP-AST-031 6 100.0% 50.0%TP-AST-032 1 100.0% 100.0%

36 181 100.0% 97.6%Hydrotest complete 33 of 36Progress Precomm at B-con 30%

PRECOMISSIONING ELECTRIC ASTI-A PLATFORM (INTERNAL)

QTY LINE PER TEST

PAGKAGE

MATR' TRACE AND NDE

CLEARENCE

Page 33: Dor and precom 11 okt.xlsx

NO TEST SHEET

1 Low Voltage Switchgear and Motor Control Center2 Power Transformer3 Navigation Aid and Radar Beacon4 Battery charger5 Power, Control and Earthing Cable6 Low Voltage Induction Motor7 Lighting and Small Power Transformer8 High Resistance Grounding (HRG) Panel and Resistor9 Medium Voltage Fused Load Break Switch (FLBS)

10 Distribution Board (DB)11 Continuity and Megger Test12 Earhting Cable Resistance Test

Page 34: Dor and precom 11 okt.xlsx

PRECOMISSIONING ISTRUMENT ASTI-A PLATFORM

NO. TEST SHEET

CI-00 MiscellaneaousCI-01 ThermowellCI-02 Local Gauge (LG PG TG)CI-03 Transmitter (LT PT TT)CI-04 Orifice Plate and Restriction OrificeCI-05 Analyzer Indicating Transmitter (AIT)

CI-06 Pressure Safety/Relief Valve (PSV/PRV)CI-07 On/Off Valve Pneumatic Type (SDV BDV XV)CI-08 Self Actuated Pressure Regulator Valve (PCV)CI-09 Pig SignalCI-10 Instrument TubingCI-11 Fusible LoopCI-12 Gas DetectorsCI-13 ESD Push ButtonCI-14 Junction Box (JB)CI-15 Choke ValveCI-16 Instrument CableCI-17 Multivariable Flow TransmitterCI-18 Multiphase Flow Meter (MPFM)TI-01 General PurposeTI-02 Actuated On/Off Valve (XV, BDV,SDV)TI-03 Relief ValveTI-04 Instrument Analog O/PTI-05 Instrument Switched O/PTI-06 Instrument Tube/PipeTI-07 Oriface PlateTI-08 Instrument Cable

TI-09 Multipair Instrument Cable

TOTAL

PRECOMISSIONING MECHANICAL ASTI-A PLATFORM

No Categories

1 Chemical Injection Skid (U-715)2 Chemical Injection Tank (T-175)3 Chemical Injection (P-175)4 Chemical Injection Skid (U-725)5 Chemical Injection Tank (T-725)6 Chemical Injection Tank (T-725)7 Submersible Pump/Wash down pump8 Closed Drain Pump9 Closed Drain Vessel10 Open Drain Pump11 Air instrument Vessel12 Jib Crane Equipment Y-905 (Cable)

Page 35: Dor and precom 11 okt.xlsx

13 Jib Crane Equipment Y-905 (Lighting)

Total

PRECOMISSIONING COMPLETED

No Categories

1 PIPING2 ELECTRIC3 INSTRUMENT4 MECHANICAL

TOTAL

Page 36: Dor and precom 11 okt.xlsx

FLUSHING PRESSURE TEST DRYNG

5% 10% 40% 5% 15% 10%

100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 90.0% 90.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 0.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 0.0% 0.0% 0.0% 0.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 0.0% 0.0%100.0% 100.0% 100.0% 100.0% 0.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%100.0% 100.0% 100.0% 100.0% 0.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 90.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%100.0% 100.0% 100.0% 100.0% 100.0% 0.0%50.0% 0.0% 0.0% 0.0% 0.0% 0.0%

100.0% 100.0% 100.0% 100.0% 100.0% 0.0%

97.6% 92.9% 92.1% 92.1% 66.8% 0.0%TP

PUNCHLIS CATEGORY A

RE-INSTATEMENT

BOLT TIGHTENING

Page 37: Dor and precom 11 okt.xlsx

WF VISUAL TEST PHISYCAL TEST PROGRESS

20% 30% 50%

6.0% 100.0% 100.0% 100.0% 100.0%6.0% 100.0% 100.0% 100.0% 100.0%5.0% 100.0% 100.0% 100.0% 100.0%5.0% 100.0% 100.0% 100.0% 100.0%8.0% 100.0% 100.0% 100.0% 100.0%6.0% 100.0% 100.0% 100.0% 100.0%6.0% 100.0% 100.0% 100.0% 100.0%8.0% 100.0% 100.0% 100.0% 100.0%8.0% 100.0% 100.0% 100.0% 100.0%8.0% 100.0% 100.0% 100.0% 100.0%20.0% 100.0% 100.0% 100.0% 100.0%14.0% 0.0% 0.0% 0.0% 0.0%

100.0% 86.0%

ELECTRICAL TEST

Page 38: Dor and precom 11 okt.xlsx

PROGRESS

0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%

100.0% 8 60.0%0.0%0.0%0.0%0.0%0.0%0.0%50.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%

100.0%100.0%12.5%

PROGRESS

0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%60.0%0.0%50.0%75.0%

Page 39: Dor and precom 11 okt.xlsx

75.0%

20.0%

PROGRESS

74.1%86.0%12.5%20.0%

48.1%

Page 40: Dor and precom 11 okt.xlsx

October 11 th, 2015

WF PROGRESS

100%

5.0% 88.5%5.5% 84.0% o/s flange6.6% 88.5%1.7% 88.5%2.2% 88.5%0.6% 88.5%0.6% 88.5%1.7% 88.5%0.6% 88.5%0.6% 75.0%1.7% 88.5%1.7% 20.0% vendor5.0% 88.5%1.1% 88.5%2.8% 88.5%0.6% 88.5%2.8% 88.5%9.4% 88.5%2.2% 75.0%18.2% 75.0%0.6% 90.0%1.1% 75.0%1.1% 88.5%2.2% 88.5%4.4% 88.5%6.1% 88.5%1.1% 90.0%0.6% 90.0%0.6% 90.0%0.6% 90.0%0.6% 90.0%0.6% 90.0%2.2% 90.0%4.4% 90.0%3.3% 15.0%0.6% 90.0%

100.0% 74.1%

Page 41: Dor and precom 11 okt.xlsx
Page 42: Dor and precom 11 okt.xlsx
Page 43: Dor and precom 11 okt.xlsx