doosan skoda experience

18
Mexico and Latin America Doosan Škoda Power David Zeman 30.3.2016

Upload: phamtruc

Post on 30-Dec-2016

250 views

Category:

Documents


2 download

TRANSCRIPT

Mexico and Latin America

Doosan Škoda Power

David Zeman30.3.2016

Parní turbíny vyrábíme již 111 let

2

Doosan Skoda Power Business Line

Doosan Skoda Power provides total solutions for various power generation application, ranging from design of trurbogenerator equipment to supply, erection and post-project services.

Fossil fuel

Cogeneration

Combined cycle

Nuclear

Waste incineration

Biomass

Solar

Steam turbine &Generator

Completemachine hall

IndustrialSteam

Turbines(<50 MW)

New Build(>50 MW)

Service

1

2

3

3

Steam Turbine Experience

Through worldwide presence Doosan represents a rich tradition, long experience and professional knowledge, with innovative approaches to project management.

Total Records ~ 115 GW = 594 UnitsMW

Unit

Europe42 GW

325 Units

Asia55,5 GW

126 UnitsMiddle East8,4 GW

28 Units

India3,5 GW

62 Units

Africa1,3 GW

16 Units

America3,7 GW

37 Units

4

Igarape3x125 MW

Lujan de Cuyo120 MW

Latin America – selected installations and SERVICES

more then 45 years provides Doosan Skoda modern energy solutions for Latin America countries

Punta del Tigre200 MW

Termotasajero200 MW

Paco Panam2x160 MW

Boca de Jaruco200 MW

Mejillones2x165 MW

Kelar180 MW

Felton2x275 MW

Hermosillo88 MW

El Sauz145 MW

Selected References

Empalme I & II2x 300 MW

Tula revamp2x100 MW

Red Dragon375 MW

Atacama I& II110 MW

AG2 Martinique45 MW

NEW BUILD projects

MODERNIZATION projects

SERVICES and maintenance

Mexico – Doosan Skoda experience

2004

2004

HERMOSILLO - 90MW

2005

SAUZ- 145 MW

2017

TULA – 2x 100 MW

2 units installed in past 2002 - 2005

4 new units under execution in 2014 - 2018

Wide knowledge of local site managing and supervising

2018

EMPALME 1x 300

2005

Experience in seismic active zones in Latin America

2014 2015

2019

EMPALME II 1x 300

2015

Mexico – Doosan Skoda experience

International tenders by CFE

Cooperation with developers - Spanish, Korean, American

Spanish language – critical for communication and documentation

Local Service / Local supplies

Strong - Labor Unions

Permanent establishment

8

MEXICO – new projects

EMPALME I – 280 MW- Final client - CFE

- Direct client – consorcium OHL + SENER- Combined cycle power plant

EMPALME II – 300 MW- Final client - CFE

- Direct client – consorcium DURO FELGUERA + ELECNOR- Combined cycle power plant

TULA – 2 x 100 MW - RETROFIT- Final client - CFE

- Direct client – consorcium INITEC + COBRA + AVANZIA- Modernization of existing power plant

9

Mexico – Doosan Skoda experience

NEW BUILD projects

MODERNIZATION projects

SERVICES and maintenance

MODERNIZATION – Doosan Skoda experience

3D scanning in Mexico

Temporary import – via ATA KARNET

Hi-tech technology demonstration to client

Higher investment costs

… led to new project and new market

Project TULA – 3D scanning in Mexico

Project TULA – 3D scanning in Mexico

5 boxes and two pallets

Total weight more than 850 KG

Special packing sheets separately for each shipment

Dangerous goods according to IATA

Control of temperature and humidity during transport

3D scanning - PACKAGING for transport

NEW BUILD projects

MODERNIZATION projects

SERVICES and maintenance

SERVICES – Doosan Skoda experience

Supply of spare parts, maintenance and overhauls on existing units

LOCAL PARTNER – critical for success

SKODA cooperates since 2009 with ENERGY CORPORATION

CFE - state owned client – advantage / disadvantage

Complicated administration