Meeting #19
Wednesday 27 November, Seasons Botanic Gardens
DOMAIN COMMUNITY REFERENCE GROUP
1
![Page 2: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/2.jpg)
A LOOK BACK AT 2019
2
![Page 3: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/3.jpg)
3
![Page 4: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/4.jpg)
ST KILDA ROAD REALIGNMENT
4
Over 13 days:
• 1,390 metres of new tram tracks laid
• 3,400 tonnes of new asphalt laid
• 7,500 cubic metres of ground excavated
• 1,415 cubic metres of concrete poured
• 10,500 tonnes of crushed rock used
• 7,000 cubic metres of concrete and asphalt
demolished
![Page 5: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/5.jpg)
WORKS UPDATE
5
![Page 6: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/6.jpg)
ANZAC STATION PROGRAM
6
Look ahead for 2019/20
![Page 7: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/7.jpg)
CURRENT AND UPCOMING WORKS
• Excavation through the void
• Base slab construction
(Steel fixing and concreting)
• Shed construction
• Diaphragm wall construction
• Tunnel boring machine (TBM)
deliveries
Under the roof slab7
![Page 8: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/8.jpg)
8
NORTH BOX EXCAVATION
• Excavating through the
void in the station roof
• All material transported
via St Kilda Road
• North box excavation to
be complete in December
![Page 9: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/9.jpg)
9
NORTH BOX EXCAVATION
![Page 10: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/10.jpg)
BASE SLAB CONSTRUCTION
10
• Steel fixing currently operating
24/7 under the station roof
• 2 of 6 major concrete pours
completed
• Once complete, tunnelling
team will commence
preparation for the TBM
installation
![Page 11: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/11.jpg)
BASE SLAB CONSTRUCTION
11
![Page 12: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/12.jpg)
SHED CONSTRUCTION
12
• Panel installation continuing until
end of the year
• Two gantry cranes now installed
• Internal fit-out works to continue into 2020
![Page 13: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/13.jpg)
DIAPHRAGM WALL CONSTRUCTION
MIDDLE BOX
13
• First pile completed Friday 22
November
• Piling and D-wall construction to
be completed March 2020
![Page 14: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/14.jpg)
TBM DELIVERIES
14
• First TBM parts have now been delivered
• Some overnight closures of St Kilda
Road will be required for the remaining
TBM part deliveries. These closures will
all occur between 1am-5am
• Parts will continue to arrive to site until
April 2020
• Preparation work for the TBM assembly
will begin in December
![Page 15: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/15.jpg)
GROUND CONDITION INVESTIGATIONS
• Boreholes are required at the site of one
of the tunnel cross passages directly
under Toorak Road West
• From 8pm Friday 6 December to 6am
Monday 9 December, Toorak Road West
will be closed to traffic at the corner of
Toorak Road West and Arnold Street
• Works Involve:
• Asphalt cutting
• Non-destructive digging using a vacuum truck
• Drill to bore and take soil samples.
• Backfilling and reinstatement works
• To minimise the duration of the Toorak
Road closure, works will be carried out
24/7
15
![Page 16: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/16.jpg)
ENVIRONMENT UPDATE
16
![Page 17: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/17.jpg)
NOISE MONITORING – OOH TBM DELIVERIES
17
• Attended monitoring undertaken for TBM deliveries
• Environmental resource available at night to monitor works post 10pm
Building RIMG Noise Guideline
LAeq – 1 hour
Measured (Night) dB
The Domain
64
58
The Botanica50
Hallmark Apartments52
Domain Hill54
![Page 18: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/18.jpg)
NOISE MONITORING – OOH TBM DELIVERIES
18
TBM Delivery 25/11 – 2:20am TBM Delivery 25/11– 3:20am
![Page 19: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/19.jpg)
UPCOMING OOH WORKS
19
• Continuation of TBM deliveries
• Base slab works currently ongoing –
24/7
• TBM assembly works coming up
• Concrete pours associated with middle
box and base slab
Working with tunnels team to review
process and out of hours works required
![Page 20: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/20.jpg)
ENVIRONMENTAL MONITORING – AIR QUALITY
20
St Kilda Rd Air Quality
(PM10)
St Kilda Rd Air Quality
(PM2.5)
![Page 21: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/21.jpg)
DOMAIN PRECINCT UPDATE
21
![Page 22: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/22.jpg)
MAJOR EVENTS
• CYP work with local Council in coordinating
any potential interface between major events
and the Metro Tunnel Project
• In the Domain Precinct this includes events
such as:
o Anzac Day services
o Australian Grand Prix
o Melbourne Marathon
![Page 23: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/23.jpg)
DOMAIN ROAD POP-UP PARK UPDATE
• Installation of the pop-up park
begins 2 December
• Involves the installation of pre-
fabricated sections
• This is expected to be completed
within two weeks
• Planting will take one week,
following installation
![Page 24: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete](https://reader036.vdocuments.us/reader036/viewer/2022071010/5fc78a8a8ebc59737f1f8ef5/html5/thumbnails/24.jpg)
CHRISTMAS SHUTDOWN
24
• Works finish on 20 December
2019, and return 6 January 2020
• We wish you all a Merry
Christmas, and a happy and
healthy New Year
• See you in 2020!