document of the world bank...report no: icr00004624 implementation completion and results report...

67
Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00004624 IMPLEMENTATION COMPLETION AND RESULTS REPORT 4771‐KE, 5034‐KE and 5367‐KE ON A CREDIT IN THE AMOUNT OF SDR 128.8 MILLION (US$198 MILLION EQUIVALENT) AND ON A GRANT MULTI DONOR TRUST FUND FOR HEALTH RESULTS INNOVATION (TF016027) IN THE AMOUNT OF US$20 MILLION TO THE REPUBLIC OF KENYA FOR A HEALTH SECTOR SUPPORT PROJECT (P074091) April 29, 2019 Health, Nutrition & Population Global Practice Africa Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 26-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

Document of 

The World Bank 

FOR OFFICIAL USE ONLY  

 Report No: ICR00004624 

  

 

IMPLEMENTATION COMPLETION AND RESULTS REPORT 

4771‐KE, 5034‐KE and 5367‐KE  

ON A 

CREDIT  

IN THE AMOUNT OF SDR 128.8 MILLION 

(US$198 MILLION EQUIVALENT) 

 

AND ON A  

GRANT 

MULTI DONOR TRUST FUND FOR HEALTH RESULTS INNOVATION (TF016027) 

IN THE AMOUNT OF US$20 MILLION 

 

TO THE 

 REPUBLIC OF KENYA   

FOR A 

HEALTH SECTOR SUPPORT PROJECT (P074091)  April 29, 2019 

 Health, Nutrition & Population Global Practice 

Africa Region 

   

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

 CURRENCY EQUIVALENTS  

 

(Exchange Rate Effective {October 30, 2018}) 

 

Currency Unit  =    Kshs 

Kshs 102.05 =  US$1 

US$1.38 =  SDR 1  

 FISCAL YEAR 

July 1 ‐ June 30    

                 

Regional Vice President:  Hafez M. H. Ghanem 

Country Director:  Carlos Felipe Jaramillo 

Senior Global Practice Director:  Timothy Grant Evans 

Practice Manager:  Magnus Lindelow 

Task Team Leader(s):  Gandham N.V. Ramana, Jane Chuma 

ICR Main Contributor:  Peter Okwero 

    

Page 3: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

ABBREVIATIONS AND ACRONYMS  

 AF  Additional Financing 

AMREF  African Medical Research and Education Foundation 

AOP  Annual Operational Plan 

CPF  Country Partnership Framework 

DARE   Decentralized Reproductive Health and HIV/AIDS Project 

DHIS2  District Health Information System 2 

DHS  Demographic and Health Survey 

EMMS  Essential Medicines and Medical Supplies 

GAVI  Global Alliance for Vaccines and Immunization 

GFATM  Global Fund to Fight AIDS, Tuberculosis and Malaria 

GoK  Government of Kenya 

HFMCs  Health Facility Management Committees 

HIA  Health in Africa Initiative 

HISP  Health Insurance Subsidy Program 

HIV/AIDS  Human Immunodeficiency Virus/Acquired Immune Deficiency Syndrome 

HRITF  Multi Donor Trust Fund for Health Results Innovation  

HSSF  Health Sector Services Fund 

IIFRA  Independent Integrated Fiduciary Agent 

IPPF  Indigenous Peoples Planning Framework  

ISR  Implementation Status and Results Reports  

JFA  Joint Financing Agreement 

KEMSA  Kenya Medical Supplies Authority 

KEPH  Kenya Essential Package for Health 

KMTC  Kenya Medical Training College 

LMIS  Logistic Management Information system 

MoH  Ministry of Health 

M+E  Monitoring and Evaluation 

MDGs  Millennium Development Goals 

NEMA  National Environment Management Authority 

NHIF  National Hospital Insurance Fund 

NHSSP  National Health Sector Strategic Plan  

OVC  Orphan and Vulnerable Children 

PDO  Project Development Objective 

RBF  Results‐Based Financing 

SWAp  Sector‐Wide Approach  

UHC  Universal Health Coverage 

UNICEF  United Nations International Children's Emergency Fund 

USAID  United States Agency for International Development 

    

Page 4: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198
Page 5: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

 

TABLE OF CONTENTS  

DATA SHEET ............................................................................................................................ 1 

I.  PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ........................................................ 5 

A. CONTEXT AT APPRAISAL ........................................................................................................... 5 

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) ...................................... 10 

II.  OUTCOME ...................................................................................................................... 14 

A. RELEVANCE OF PDOs .............................................................................................................. 14 

B. ACHIEVEMENT OF PDOs (EFFICACY) ........................................................................................ 15 

C. EFFICIENCY ............................................................................................................................. 21 

D. JUSTIFICATION OF OVERALL OUTCOME RATING ..................................................................... 22 

E. OTHER OUTCOMES AND IMPACTS (IF ANY) ............................................................................. 22 

III.  KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ................................ 23 

A. KEY FACTORS DURING PREPARATION..................................................................................... 23 

B. KEY FACTORS DURING IMPLEMENTATION .............................................................................. 24 

IV.  BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME .. 26 

A. QUALITY OF MONITORING AND EVALUATION (M&E) ............................................................. 26 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ..................................................... 27 

C. BANK PERFORMANCE ............................................................................................................. 29 

D. RISK TO DEVELOPMENT OUTCOME ........................................................................................ 30 

V.  LESSONS AND RECOMMENDATIONS .............................................................................. 30 

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ............................................................ 32 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ......................... 45 

ANNEX 3. PROJECT COST BY COMPONENT............................................................................. 47 

ANNEX 4. EFFICIENCY ANALYSIS ............................................................................................ 48 

ANNEX 5. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS ... 51 

ANNEX 6. SUPPORTING DOCUMENTS (IF ANY) ...................................................................... 61 

   

Page 6: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198
Page 7: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

1

        

DATA SHEET 

  

BASIC INFORMATION  Product Information 

Project ID  Project Name 

P074091  Health Sector Support 

Country  Financing Instrument 

Kenya  Investment Project Financing 

Original EA Category  Revised EA Category 

Partial Assessment (B)  Partial Assessment (B) 

Organizations 

Borrower  Implementing Agency 

Ministry of Health  Ministry Of Health 

Project Development Objective (PDO)  Original PDO 

The objectives of the Project are to support the Program and improve: (i) the delivery of essential health services in theRecipient's territory, especially for the poor; and (ii) the effectiveness of planning, financing and procurement ofpharmaceuticals and medical supplies.  Revised PDO 

The objectives of the Project are to improve (i) the delivery of quality essential health and nutrition services and utilizationbywomen and children especially among the poor and drought affected populations; and (ii) the effectiveness of planning, financing,and procurement of pharmaceutical and medical supplies.  PDO as stated in the legal agreement 

The objectives of the Project are to support the Program and improve: (i) the delivery of essential health services in the Recipient’s territory, especially for the poor; and (ii) the effectiveness of planning, financing, procurement of pharmaceuticals and medical supplies.  

Page 8: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

2

FINANCING 

 

  Original Amount (US$)   Revised Amount (US$)  Actual Disbursed (US$) 

World Bank Financing        TF‐90490 

1,218,875  950,828  950,828 

 IDA‐47710 

100,000,000  99,192,565  100,907,491 

 IDA‐50340 

56,800,000  56,569,559  52,730,084 

 IDA‐53670 

41,000,000  36,686,797  33,168,854 

 TF‐16027 

20,000,000  20,000,000  20,000,000 

Total    219,018,875  213,399,749  207,757,257 

Non‐World Bank Financing         0  0  0 

Borrower/Recipient     0     0     0 

Total     0     0     0 

Total Project Cost  219,018,875  213,399,749  207,757,256  

  KEY DATES 

   

Approval  Effectiveness  MTR Review  Original Closing  Actual Closing 

29‐Jun‐2010  07‐May‐2009  12‐Feb‐2013  31‐Mar‐2015  30‐Jun‐2018 

   RESTRUCTURING AND/OR ADDITIONAL FINANCING 

 

 

Date(s)  Amount Disbursed (US$M)  Key Revisions 

20‐Dec‐2011  33.06  Additional Financing 

31‐Dec‐2013  113.48  Additional Financing 

08‐Sep‐2016  158.94  Change in Loan Closing Date(s) 

07‐Feb‐2017  181.08  Reallocation between Disbursement Categories 

06‐Dec‐2017  198.37  Reallocation between Disbursement Categories 

29‐Jun‐2018  208.56  Cancellation of Financing Reallocation between Disbursement Categories 

  

Page 9: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

3

KEY RATINGS  

 

Outcome  Bank Performance  M&E Quality 

Moderately Satisfactory  Moderately Satisfactory  Modest 

 

RATINGS OF PROJECT PERFORMANCE IN ISRs  

 

No.  Date ISR Archived  DO Rating  IP Rating Actual 

Disbursements (US$M) 

01  22‐Feb‐2011  Satisfactory  Satisfactory  8.64 

02  12‐Sep‐2011  Satisfactory  Satisfactory  8.92 

03  15‐Apr‐2012  Satisfactory  Satisfactory  33.56 

04  14‐Oct‐2012  Satisfactory  Satisfactory  68.26 

05  22‐Apr‐2013  Satisfactory  Satisfactory  83.96 

06  05‐Jan‐2014  Satisfactory  Satisfactory  113.90 

07  30‐Jun‐2014  Satisfactory  Moderately Satisfactory  126.03 

08  16‐Dec‐2014  Moderately Satisfactory  Moderately Unsatisfactory  130.99 

09  27‐May‐2015  Moderately Satisfactory  Moderately Unsatisfactory  136.84 

10  01‐Dec‐2015  Moderately Satisfactory  Moderately Satisfactory  145.98 

11  30‐May‐2016  Moderately Satisfactory  Moderately Satisfactory  159.12 

12  30‐Nov‐2016  Moderately Satisfactory  Moderately Satisfactory  181.50 

13  23‐Jun‐2017  Moderately Satisfactory  Moderately Unsatisfactory  181.50 

14  21‐Dec‐2017  Moderately Satisfactory  Moderately Unsatisfactory  198.79 

15  30‐Jun‐2018  Moderately Satisfactory  Moderately Unsatisfactory  208.99 

 

Page 10: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

4

SECTORS AND THEMES  

 Sectors 

Major Sector/Sector  (%) 

 

Health   100 

Public Administration ‐ Health  6 

Health  94 

  Themes   

Major Theme/ Theme (Level 2)/ Theme (Level 3)  (%)  Private Sector Development  10  

Public Private Partnerships  10  

   Human Development and Gender  67  

Disease Control  17  

HIV/AIDS  17    

Health Systems and Policies  50  

Health System Strengthening  17   

Reproductive and Maternal Health  16   

Child Health  17  

   

ADM STAFF  

Role  At Approval  At ICR 

Regional Vice President:  Obiageli Katryn Ezekwesili  Hafez M. H. Ghanem 

Country Director:  Johannes C.M. Zutt  Carlos Felipe Jaramillo 

Senior Global Practice Director:  Yaw Ansu  Timothy Grant Evans 

Practice Manager:  Eva Jarawan  Magnus Lindelow 

Task Team Leader(s):  Michael Mills Gandham N.V. Ramana, Jane Chuma 

ICR Contributing Author:    Peter Okwero 

       

Page 11: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

5

 

I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES 

 

A. CONTEXT AT APPRAISAL  

Context  1. The preparation of  the project spanned several years and took place  in a complex environment1. The performance and track record of the health sector had been inadequate and previous attempts at reforming the sector unsuccessful. The Kenyan economy was experiencing a slowdown in growth. After peaking at 6.9 percent in 2007, economic growth contracted to 1.7 percent  in 2008 before  increasing slightly  to 2.5 percent  in 2009, which was  still  below  the population  growth  rate.  A  combination of  factors,  including:  (a)  2008 post‐election violence; (b)  impact of the international financial crisis; and (c) reduced farm production arising from the 2009 drought were said to be responsible for the economic downturn. Persistent high levels of poverty and inequality were reported. Between 1981 and 2009, the poverty rate dropped from 48 percent to 47 percent. The Gini index2 was estimated at 0.693, with most of the poor reported living in rural areas.   2. Project preparation coincided with declines in infant and child mortality.  According to the Demographic and Health Survey (DHS, 2008), Kenya recorded remarkable declines in infant and under‐five mortality rates (from 77 to 52, and from 115 to 74, per 1,000 live births, respectively) between 2003 and 2007. However, progress in reproductive, maternal and neonatal  indicators, as well as, nutrition was  limited. Maternal mortality ratio was estimated at 414 per 100,000 live births; six of out ten infant deaths were reported to occur in the first 28 days of life; and 35 percent of children were reported stunted with 14 percent severely wasted,  in 2007.   Despite the relative improvement, disparities persisted.  Stunting varied from 29 percent in Nairobi to 42 percent in Eastern Province.    Progress with  respect  to  the Millennium Development Goals  (MDGs) was mixed. While  Kenya was poised  to  achieve  three  out  of  the  eight  MDGs:  universal  primary  education,  gender  equality  and  women empowerment and combating major communicable diseases, the health MDGs on child and maternal health were considered unachievable.  Similarly, Kenya was not likely to achieve the MDG on eradication of extreme poverty and hunger.  3. At appraisal, the health sector faced several health systems challenges.  The effects of the challenges were more pronounced at the lower level facilities where the poor mainly seek care.  The low level of overall public spending was compounded by inappropriate resource allocation, with relatively high proportion of spending going to regional and central hospitals coupled with irregular and untimely disbursement of funds.  As a result, the lower level health facilities received insufficient operational funds for day‐to‐day operations.  Inefficiency was noted in the procurement and supply chain management system for health commodities causing wastage and leading to insufficient supplies of medicines and other commodities. There was shortage of health staff, especially  in the rural areas, due to poor incentives and weaknesses in deployment and management of staff.  4. In addition, the health sector previously had experienced several governance challenges.    In 2006 the Bank suspended the grants component of the Decentralized Reproductive Health and HIV/AIDS Project  (DARE, P066486) due to accounting and reporting deficiencies.  A forensic audit and a detailed Implementation Review in 

1 Project preparation started in the early 2000s and its concept note reviewed in 2005. The delay was caused by the prevailing challenges including the 2007 post‐election violence. 2 The Gini index is used as a gauge of economic inequality, to measure income or wealth distribution in a population. 

Page 12: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

6

2006 revealed evidence of corruption in the health sector.  As part of the creation of the Coalition Government in 2008,  the Ministry of Health was split  into  the Ministry of Medical Services and Ministry of Public Health and Sanitation. While government instituted steps to strengthen coordination between the two Ministries, the split further compounded the existing governance challenges in the sector.  Several actions were undertaken to address the  governance  challenges,  including:  development  and  implementation  of  a  new  procurement  policy; strengthening Audit, Finance and Facilities Management Committees; improving efficiency of internal audit; and public dissemination and monitoring of performance contracts, but the challenges persisted. At the time, it was considered  that,  for  Kenya  to  improve quality  of  health  services,  it  needed  to  increase  investments  in  health systems strengthening for lower level services, improve regional equity and targeting of the poor, and enhance coordination with non‐state actors.  5. Health services  in Kenya were provided by a wide range of actors and operated under a Sector‐Wide Approach (SWAp).  The actors included government, faith‐based organizations, other not‐for‐profit organizations, for‐profit  service providers and traditional healers. The overall  sector  framework was outlined  in  the National Health Sector Strategic Plan (NHSSP II, 2005‐2012), whose goal was to reduce health inequities and reverse the downward trend in the health status of the Kenyan people.  The NHSSP defined the Kenya Essential Package for Health (KEPH) for all levels.  The package of services by population cohort is included in Annex 1 Part D. As part of the SWAp arrangement, the government and partners signed a Code of Conduct and specified the mechanisms for the implementation of the Joint Program of Work and Funding in the Joint Financing Agreement (JFA). The project was meant to support two out of the five JFA baskets: Health Sector Support Fund (HSSF) 3 and for Essential Medicines and Medical Supplies.  The other baskets were for: human resources for health, capacity and systems development, and the hospital management services fund, and as further explained in Annex 1 Part F, these other baskets did not materialize as originally envisaged. 

 6. The Letter of Sectoral Policy prepared in respect of the project outlined the proposed reform agenda4.  The  proposed  reforms  included:  (a)  implementation  of  the  Kenya  Essential  Package  for  Health  (KEPH);  (b) establishment  and  implementation  of  the  HSSF;  (c)  strengthening  human  resource  management;  (d) implementation of reforms in the proposed Healthcare Financing Policy and Strategy; (e) reforming supply chain management  and  strengthening  governance  of  Kenya  Medical  Supplies  Authority  (KEMSA);  and  (f) implementation  of  the  community  strategy  to  empower  communities  and  enhance  their  participation  in  the provision of health services.  The project implemented through the SWAp modality, would focus on two reform areas: (a) development and implementation of the HSSF with the aim of increasing capacity for health services delivery and funding to the frontline service providers using existing transfer mechanisms and performance based grants; and (b) strengthening capacity for procurement and supply chain management of essential medicines and medical supplies by providing predictable financing for medicines, allocating budgets for medicines to individual facilities,  establishing  a  pull  system  and  creation  of  buffer  stock.    In  addition,  the  project was  to  support  (a) development  and  implementation  of  the Healthcare  Financing  Policy  and  Strategy  giving  priority  to  financing health care for the poor and vulnerable through subsidies; (b) innovative projects on public private partnerships 

3 The HSSF (co‐financed initially by the Bank and DANIDA before DANIDA later pulled out) was an innovative scheme established by the Government  of  Kenya  to  disburse  funds  directly  to  the  health  facilities  to  enable  them  improve  health  service  delivery  to  the communities.  It  had  two main objectives:  (i)  generating  and providing  sufficient  resources  for  implementing each  facility’s Annual Operational Plan (AOP) to address preventive, promotive and curative services at level 1,2 and 3; and (ii) supporting capacity building in management of health facilities; supporting and empowering rural communities to take charge of improving their health; Providing grants for strengthening of the faith based health facilities through their respective secretariats; and Improving the quality of health services in the health facilities.  4 Dated May 10, 2010 

Page 13: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

7

and activities to strengthen voice and accountability within the HSSF framework; and (c) activities to strengthen the referral system.  

 The Rationale for Bank Involvement  7. The project was aligned with the two goals of Country Partnership Strategy (2010‐2013)5, which included: (i) improved social service delivery for vulnerable groups, particularly women, and (ii) better provision of health and sanitation services by the counties.  In addition, the project was aligned with the Bank’s Health, Population and  Nutrition  for  Africa  and  the  Bank’s  Health,  Nutrition  and  population  Global  Strategy  (2007):  specifically, strategic direction 2 on supporting country efforts to strengthen and realize well‐organized and sustainable health systems for HNP results. All these strategies sought to strengthen health systems and to improve health outcomes, especially for the poor.  8. The project  design built  upon  the Bank’s past  involvement  in  the health  sector.  The Bank  in  the past supported  various  projects  including:  (a)  Sexually  Transmitted  Infections  Project  (Cr.  2686);  (b)  Decentralized Reproductive Health and HIV/AIDS Project (Cr. 3440); Kenya HIV/AIDS Disaster Response (Cr. 3415); and Total War Against HIV/AIDS (Cr. 4336).  In addition, the Bank has contributed to development of the health sector in Kenya through: (a) policy dialogue; (b) donor coordination; (c) technical assistance in a range of areas including strategic planning, financing, procurement and monitoring and evaluation; and economic and sector work.   9. The project in its design focused on the areas where the Bank had comparative advantage.   At the time, the  Bank  had  a  solid  track  record  in  Kenya  supporting  health  systems  strengthening,  health  financing  and procurement.    Based  on  the  division  of  labor,  the  Bank was  delegated  as  the  lead  partner  for  the  HSSF  and procurement.  Other development partners were to provide complementary support in other relevant areas by committing, for example, to provide harmonized support for human resources for health.  Theory of Change (Results Chain)  10. The  project  at  appraisal  did  not  prepare  a  comprehensive  Theory  of  Change.  However,  a  conceptual framework  for  the  HSSF  and  a  results  chain were  developed  to  explain  the  causal  pathways  of  the  project’s contribution  towards  strengthening  delivery  of  health  services  at  the  primary  level.    Building  on  the  two conceptual frameworks and the Theory of Change (Annex 1 Part E) prepared by the project team during project implementation, the author prepared the Theory of Change in Figure 1.   The Theory of Change is premised on rolling out HSSF  and providing  grants  (HSSF  and Results‐Based  Financing, RBF)  to  front  line  service  providers, building  institutional  capacity  for  improved  health  service  delivery  at  the  sub  national  level,  supporting implementation  of  central  level  governance  and  stewardship  initiatives,  and  strengthening  supply  chain management to ensure delivery of the package of essential health services.   A key assumption was that other partners operating under a SWAP arrangement would support other complementary reforms; for example, the areas of human resources for health reforms and the implementation of the community strategy.  

      

5 Report Number 52521‐KE 

Page 14: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

8

Figure 1. Theory of Change 

 

Strategies/Activities  

Outputs   Outcomes  Long‐Term Outcomes 

Rollout HSSF countrywide to the primary HFs. Key activities would involve: (i) HSSF grants; (ii) Introduction and rollout of RBF; (iii) Building capacity of HFs to plan and implement AOPs; (iv) Strengthening Counties to support HFs; (ii) Promotion of social accountability for health service delivery; and (iii) Piloting innovative Public Private Partnership for Health (PPPH) approaches  

Number of HFs meeting the required standards for the level (HFMCs, EMMS, staffing, equipment, financing etc.)   Number of HFs delivering the package of essential health services for the level   Increased share of reported complaints acted upon   Number of PPPH initiatives piloted 

Improved access to essential health services  Increased utilization of the essential health services especially by the poor   Increased coverage of the population to essential health services  Client Satisfaction     

   Reduction in Morbidity and Mortality   Reduced Burden of diseases 

 

Support implementation of Health Sector Governance and Stewardship initiatives: SWAP Secretariat; Pilot approaches to reach the poor; Management and performance of district hospitals; Referral system; and Health care waste management 

Increased number of poor households enrolled for health insurance subsidies  HFs meeting health care waste management standards  Increased number of cases referred and treated at the hospitals 

Increased utilization of the essential health services by the poor households  Reduced OOP among the poor 

Implementation of initiatives to strengthen the Supply Chain Management for Essential Health Commodities through (i) increased funding for essential commodities and (ii) supporting reforms in KEMSA    

Improved availability of essential health commodities at the HFs  Improved capacity at KEMSA to procure and distribute essential commodities in a timely fashion  

Reduced stockouts of essential health commodities at KEMSA and the HFs   

 Project Development Objectives (PDOs)  11. The original objectives of the Project are to support the Program and improve: (PDO 1) the delivery of essential  health  services  in  the Recipient’s  territory,  especially  for  the poor;  and  (PDO 2)  the effectiveness of planning, financing, procurement of pharmaceuticals and medical supplies6. 

6 The PDO  is  taken  from the Financing Agreement  (dated  July 5, 2010) as  the PDO statement  in  the PAD excluded mention of  the Program.  The PDO in the PAD was stated as follows: “The Project development objectives are to improve: (i) the delivery of essential 

Page 15: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

9

 Key Expected Outcomes and Outcome Indicators  12. Six project outcome indicators and fourteen intermediate outcome indicators were identified to monitor project implementation.  The following indicators below were the project outcome indicators: 

 a. Direct project beneficiaries (number) of which female (percent) b. Health facilities that experience essential drugs stock‐outs for more than two weeks (percent) c. Children immunized (number, disaggregated for Northeast Province)  d. HSSF facilities meeting core financial management requirements of the fund (percent)  e. Timely payment to suppliers by KEMSA based on agreed procurement contract  f. Facilities displaying quarterly information on funds received and availability of drugs at facility‐level (levels 2 

and 3) (percent) 

Components  13. The project comprised two components.  14. Component  1:    Effective  and  transparent  implementation  of  the  KEPH  through  HSSF  grants  and performance strengthening (total estimated cost US46 million). This component was aimed at providing direct cash transfers through the HSSF to primary health care facilities (Levels 1, 2 and 3)7 and strengthening governance and stewardship functions to enhance delivery of essential health services.  Levels 1, 2 and 3 of the health system were the focus of the HSSF. In addition, the HSSF was an important initiative to empower communities to take charge of  improving their health by providing direct cash transfers to Health Facility Management Committees (HFMCs) through enhanced transfers and performance‐based incentives.  15. Sub Component 1.1: Health Sector Services Fund (US$34 million): The project under the subcomponent was to support effective implementation of the KEPH, through HSSF grants targeted at health service delivery levels (Levels 1, 2 and 3) and capacity building  in  the management of health  facilities.   The recipients could use  the resources for: (a) employment of casual workers, operational costs including facility maintenance; (b) outreach activities; (c) strengthening management and coordination of health services delivery; and (d) supporting activities to  strengthen  voice  and  accountability.    It was  envisaged  that  innovative  activities  to  improve  private  public partnerships would be piloted under the subcomponent.  16. Sub  Component  1.2:    Health  Sector  Governance  and  Stewardship  (US$12 million):  The  project  was  to support selected activities to strengthen governance and stewardship functions of the two ministries for enhanced service  delivery.    Specific  activities were  to  support:  (a)  implementation  of  health  financing  reforms  through selective pilots, capacity building and evaluations with focus on developing and piloting approaches for reaching the poor with health insurance cover; (b) KEPH referral system through capacity building of district hospitals and establishment of five model referral sites; (c) health care waste management; and (d) the SWAp Secretariat. 

health services for Kenyans, especially the poor; and (ii) the effectiveness of planning, financing and procurement of pharmaceuticals and medical supplies”. 7 Level 1 is the community for which there is no HF. Level 2 HFs are dispensaries. They are at the lowest level of the public health system and the first point of contact with patients. They provide outpatient services for simple ailments and are staffed by enrolled nurses, public health technicians, and dressers. Level 3 are health Centers.  They are staffed with clinical officers as the team leaders and provide a range of services, such as basic curative and preventive services for adults and children, as well as reproductive health services. They also provide minor surgical services such as incision and drainage.   

Page 16: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

10

 17. Component 2: Availability of essential health commodities and supply chain management reform (US$54 million).   The project was to provide financing towards essential medicines and support reforms to strengthen supply chain management for essential medicines.  This was in light of the fact that the strengthening of levels 1, 2 and 3 above would not have been sufficient without parallel investments in essential commodities to ensure that the quality of services is improved.  18. Sub Component 2.1: Commodities (US$48 million): This component was aimed at improving availability of commodities at the lower levels of the public health system through: (a) financing the budget for commodities and building up a buffer stock of essential medicines; (b) reforming the procurement and supply chain system to become more efficient and effective; and (c) establishment of a commercial window to supply commodities to facilities on a cost recovery basis.   19. Sub Component 2.2:  Strengthening governance and  institutional  reforms  to enhance  the efficiency and transparency of KEMSA (US$6 million).  The project was to support capacity building for KEMSA and the health ministries in the key functions of forecasting, planning, procuring and managing critical commodities with a focus on reforms in the flow of funds to KEMSA, definition of the EMMS list, billing system of the KEMSA, development of supplementary commodity services for hospitals, and to address the key constraints affecting the availability of essential medicines in the public health facilities. 

 20. Independent  Integrated  Fiduciary  Review Agency  (IIFRA).  To  ensure  transparency  and  effectiveness  in carrying  out  the  implementation  of  the  project  components,  in  particular  with  regard  to  the  HSSF  and  the procurement  through  KEMSA,  an  IIFRA  was  to  be  recruited  to  undertake:  (i)  compliance  verification,  (ii) procurement monitoring;  (iii)  performance  auditing  of  the  project;  and  (iv)  continuous  financial  audits  of  the project with the objective of ensuring that any systemic governance problems and accountability issues are noted early and corrective measures taken. 

 B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE)  

Revised PDOs and Outcome Targets   21. The PDOs were revised twice during the project lifespan as part of Additional Financing (AF) in November 2011  and  December  2013,  respectively8.    The  project  in  2011  obtained  AF  to  support  the  government’s humanitarian response to the needs of the drought affected populations and scale up project interventions.  More than 3.7 million people in arid and semi‐arid regions of Kenya were directly affected by the drought with around 385,000 children and 90,000 pregnant women estimated to be suffering from acute malnutrition in the affected areas. The 2011 revision changed the PDOs to ‐ “support the Program and  improve:  (i)  the delivery of essential health services in the Recipient’s territory, especially for the poor and the drought affected populations; and (ii) the effectiveness of planning, financing, procurement of pharmaceuticals and medical supplies”.  The revision of PDO 1 in 2011 was intended to reflect the emergency response to deliver essential health and nutrition services to drought affected populations in arid and semi‐arid regions of Kenya.  22. The second revision in 2013 modified the PDOs to ‐ “improve (i) the delivery of quality essential health and nutrition services and utilization by women and children among the poor and drought affected populations; and (ii) 

8 The first AF (U$56.8 million) was financed through the IDA Crisis Response Window; while the second AF was financed through an IDA Credit (USS$41 million) and the Multi Donor Trust Fund for Health Results Innovation (HRITF, US$20 million). 

Page 17: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

11

the effectiveness of planning, financing, procurement of pharmaceuticals and medical supplies.” – The revision was meant  to  enhance  the  project  focus  on  improving  utilization  of  health  and  nutrition  services  by  women  and children. The results framework was revised to reflect changes to the project ‐ adding new indicators, dropping others and revising targets9.  In addition to specifying the beneficiary population groups, a key change in the PDOs was the addition of the quality dimension to PDO 1. The full list of project indicators is included under Annex 1 C. 

Revised PDO Indicators  23. The following were the revised project outcome indicators in 2011:  

a. Direct Project Beneficiaries (Number of outpatient visits to levels 2 and 3 disaggregated by females and drought affected areas, new) 

b. Children fully immunized (number, disaggregated for Northeast Province) c. Value fill rate for commodities on KEMSA Essential Drug List (Percent, revised) d. HSSF facilities meeting the core financial management requirements of the fund (Percent) e. Fiduciary irregularities reported from HSSF and KEMSA acted upon during the previous quarter (Percent) f. Level 2 and 3 HSSF facilities displaying information as per Government of Kenya (GoK) guidelines (Percent) g. Severely malnourished children under five receiving treatment recovered (Percent, new) 

 24. The revised project outcome indicators in 2013 were as follows: 

a. Direct project beneficiaries (Number of outpatient visits to levels 2 and 3) (i) Female Beneficiaries (ii) Beneficiaries from drought affected areas (Number) 

b. Children immunized (number, disaggregated for Northeast Province) c. Value fill rate of orders for commodities for Primary Health Care facilities received by KEMSA either from 

counties or facilities (Percent) d. Severely malnourished children under five receiving treatment recovered (Percent) e. Share of planned procurement from Essential Medicines and Medical Supplies (EMMS) pool completed by 

KEMSA in the financial year as per GoK guidelines (Percent, new) f. Women receiving free delivery services meeting the quality norms at public health facilities (Number, new) g. Poor households receiving health insurance subsidies (Number, new) 

 Revised Components  25. Component 1 of the project was revised during the 2011 AF.  The AF was to support the emergency response in  the  drought  affected  arid  and  semiarid  regions  of  the  country.  In  2011,  a  new  activity  was  added  under Component 1 (US$12.8 million) to deliver essential health and nutrition services to populations affected by drought, focusing on the supply of nutrition commodities to manage malnutrition among children under five years, pregnant and  lactating women,  and Component  2  (US$44 million)  scaled  up  to  supply  essential  health  commodities  for drought affected areas and strengthened to deepen the on‐going reforms to move towards the “pull” system of supply chain management. The nutrition Interventions focused on infant feeding, micronutrient supplementation and management of acute malnutrition.  

9 In 2011, one new PDO indicator was added. Meanwhile, for intermediate outcome indicators, two new ones were added and seven dropped. In 2013, three PDO indicators were added and three were dropped. 

Page 18: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

12

26. Component 1 was again revised during the 2013 AF. The AF was to finance the cost of the scale‐up activities and restructuring of the project to respond to devolution10 process, scale‐up RBF to further enhance the impact of the project and join government’s efforts towards achieving universal health coverage specifically targeting the poor. The changes included: (a) scaling‐up support to the HSSF (IDA, US$11 million); (b) scaling‐up of RBF (Multi Donor Trust Fund for Health Results Innovation, HRITF, US$14 million) to 21 counties in arid and semiarid regions; (c) supporting implementation of the government policy on free maternity services11 and phase one of the Health Insurance  Subsidies  for  the  Poor  (HISP,  US$20 million  –  IDA US$14 million  and HIRTF US$6 million)12;  and  (d) capacity building of counties to plan, budget and monitor delivery of health services within the new devolution arrangement, specifically targeting county health teams, health facility in‐charges and members of the HFMCs (IDA, US$16 million).  A comprehensive impact evaluation to assess the RBF and health insurance subsidies was envisaged to inform government decision making on future scale‐up.  Other Changes 

 27. The project underwent restructuring as  further explained below  to better reflect  the project’s  focus on women and children, ensure the project’s implementation arrangements are aligned with the ongoing devolution reforms, and allow adequate time to complete implementation of project activities.  

a) Extension of the Project Closing Date. The project closing date was extended twice. The first extension during the AF in 2013 extended the closing date to December 31, 2016 to facilitate implementation of RBF and HISP and completion of impact evaluation to inform future scale‐up of RBF and health insurance subsidies for the poor. The second extension during a Level 2 restructuring (October 2016) extended the closing date to June 30, 2018 to allow for full implementation of remaining project activities: (a) RBF scale‐up; (b) scale‐up of Phase 1 of the HISP; and (c) training 400 enrolled community nurses13; and to enable the project to fully disburse the remaining project proceeds (IDA Credit of US$ 45. 6 million and US$ 10 million grant). 

a) Reallocation  between  Disbursement  Categories.  The  second  Level  2  restructuring  (December  2017) reallocated unspent funds for RBF from the IDA Credit (about US$44 million) to finance the procurement of  essential medical  equipment  to  fill  the  critical  gaps  in  the  delivery  of  primary  health  services  and nutritional commodities to respond to the prolonged drought in the country.   

b) Revision  of  the  Implementation  Arrangements.  In  2011,  United  Nations  International  Children's Emergency Fund (UNICEF) was chosen as the specialized procurement agency to be contracted to supply 

10 Kenya promulgated a new constitution in 2010, which ushered devolution. Under the devolution framework newly created Counties assumed overall responsibility for the coordination and delivery of health services, while the national government remained with the responsibility for stewardship, health policy, technical assistance to counties, and management of national referral health facilities. The Counties took over ownership of the health facilities and became responsible for staff recruitment and deployment, and procurement of equipment as well as medical supplies. Besides KEMSA, Counties could procure drugs from any other source. With devolution, funds to Counties were transferred as conditional grants through the respective County Revenue Fund (CRF) Accounts before being channeled to a County Special Purpose Account for Health for onward disbursement to the beneficiary facilities. 11 The Government of Kenya (GoK) abolished user fees for delivery services in all public hospitals (June 1, 2013) through a presidential directive with the aim of promoting health facility delivery and reducing pregnancy related mortality in the country. The project however did not finance free maternity services. The activity was financed by government. 12 HISP was intended to provide comprehensive health insurance cover for outpatient and inpatient services to five beneficiaries from each enrolled household. 13 The students enrolled to the Kenya Enrolled Community Health Nursing Program run by the Kenya Medical Training College (KMTC) were selected from poor households from the arid and semiarid counties and were expected to return to serve their communities upon completion of the course. 

Page 19: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

13

the nutrition commodities. In 2013, the overall responsibility for the project implementation was placed under  the  newly  created Directorate  for  Policy,  Planning  and Healthcare  Financing  in  the Ministry  of Health after  the merger of the previous two ministries created by the coalition government. With the advent  of  the devolution policy,  the  county  governments  became  responsible  for  delivering  essential health services including overseeing project related activities in the counties. The government budget for health services  including essential health commodities was devolved to the county governments.   The project  implementation  arrangements  including  the  financial  management  arrangements  and procurements were updated to reflect  the new mandate of  the counties to approve workplans, verify performance and report results as well as statement of expenditures14.  At the same time, Kenya School of Government was  identified  to  lead capacity building of  the Counties  in  financial management; and African Medical Research and Education Foundation (AMREF) to train HFMCs on their new roles.  

c) Revision of the Results Framework. The results framework underwent major revisions during the AF to enhance  the project  focus on  improving  the delivery and utilization of health  services by women and children  and  to  reflect  changes  to  the  project  (nutrition  and  devolution).    Some  indicators  were revised/dropped specifically for lack of relevance in view of the devolution process.  Four indicators were dropped, and two new ones added in 2011; meanwhile, five indicators were dropped, and three new ones added in 2013.  In the end the project remained with seven PDO outcome indicators, five under PDO 1 and two under PDO 2.   

Rationale for Changes and Their Implication on the Original Theory of Change  28. The  changes were  intended  to:  (a)  scale‐up  ongoing  activities  to  deepen  the  impact  of  the  project;  (b) support the government to respond to the health needs of the population severely stricken by drought; and (c) ensure the project is compliant and supportive of the devolution program adopted by the GoK.  Considering the implied original Theory of Change, the changes added the quality dimension to the PDO, added nutrition as a core project  activity,  better  clarified  the  poor  and  vulnerable  populations  targeted  by  the  project,  and  deepened implementation impact of the project in terms of utilization. While changes to the results matrix were meant to strengthen  the  results  chain,  the  dropping  of  some  indicators weakened  the  causal  pathways  of  the  project’s interventions to attain its objectives.  The indicator, “health facilities experiencing drug stockouts” was replaced with “value fill rate of commodities on KEMSA Essential Drug list,” which was considered to better capture the new accountability relationship between KEMSA and the health facilities under the pull system ‐ the main reform agenda said to be supported by the project. The indicator, “health facilities meeting staffing norms” was dropped because Counties were taking over the responsibility for staffing at levels 2 and 3 facilities. Finally, devolution made County Local Government significant stakeholders in the delivery of health services, which was unanticipated in the original implied Theory of Change.   

14 The devolution process in Kenya was very ambitious and fast‐tracked devolution of responsibilities to the newly created counties in an environment where the building blocks for devolution were still evolving, including intergovernmental structures and mechanisms for intergovernmental cooperation and transfer of resources to deliver on policy priorities.  This resulted in the project mainly playing a catchup or firefighting role. 

Page 20: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

14

II. OUTCOME 

 

A. RELEVANCE OF PDOs 

 Assessment of Relevance of PDOs and Rating  29. The relevance of the PDOs  is High. The PDOs are aligned with  the current national development plans: National Health Policy (2012‐2030), Health Sector and Strategic Plan (2013‐2017), and Vision 2030.  The PDOs are aligned with the Social Pillar of Vision 2030 which prioritizes improving the livelihoods of Kenyans by providing efficient,  integrated,  high  quality  and  affordable  health  care  through  a  devolved  system  of  governance,  and relevant for the current initiatives on Universal Health Coverage (UHC) premised on provision of quality health services  and  financial  risk  protection  to  all  Kenyan  citizens.  The  PDOs  are  also  aligned with  two out  of  three domains of engagement in the Country Partnership Framework15 (CPF): human resource development for shared prosperity and delivering a devolution dividend, and specifically  two goals of  the CPF:  improved social  service delivery for vulnerable groups, particularly women, and better provision of health and sanitation services by the counties.   30. The PDOs focus on priority interventions.  The PDO 1 objectives of improving delivery of quality essential health and nutrition  services and utilization of essential health and nutrition  services by women and  children among the poor and drought affected populations are highly  relevant. Women and children represent a  large share of the population and at the same time bear a disproportionate burden of disease. The semi‐arid and arid regions of Kenya periodically experience episodes of severe drought and the drought affected population need to be provided with the necessary food supplementation.  Kenya, like other countries is faced with the challenge of delivering  quality  health  services  commensurate  with  the  needs  of  the  population,  and  as  it  embarks  on implementing the various health initiatives for the attainment of UHC, it will need to systematically address the quality  gaps  in  health  service  delivery.  Similarly,  the  PDO  2  objective  of  improving  effectiveness  of  planning, financing and procurement of essential health commodities is relevant. While capacity of KEMSA was enhanced, insufficient  budgetary  allocation  for  drugs  still  poses  a major  challenge  for  ensuring  sustainable  financing  of essential medicines. Furthermore, with the transfer of responsibility for delivery of essential health services to the counties,  the  need  for  continued  capacity  building  for  health  services  delivery,  and  especially  supply  chain management of health commodities remain of paramount  importance.  It  is necessary that the capacity of  the county governments is continually enhanced for them to perform their new roles and mandates within the new devolution dispensation.   

15 Kenya Country Partnership Strategy 2014‐2018, 88940 v2 

Page 21: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

15

B. ACHIEVEMENT OF PDOs (EFFICACY) 

Assessment of Achievement of Each Objective/Outcome  31. Rationale for assessment.  The PDO includes two main parts (PDO1 and PDO2), each of which are broken down further into separate parts which this ICR analyzes individually, per ICR Guidelines.  PDO 1 has two parts: (a) improve the delivery of quality essential health and nutrition services and (b) improve utilization of essential health and nutrition services by women and children among the poor and drought affected populations. PDO 2 on the other  hand  has  three  parts  ‐  improve  effectiveness  of:  (a)  planning,  (b)  financing  and  (c)  procurement  of pharmaceuticals  and  medical  supplies.    Each  of  these  five  PDO  parts  are  assessed  against  the  PDO  outcome indicators, including those dropped or replaced in 2013, given over 70 percent of credit proceeds were disbursed by November 201316.  However, as all targets were revised upwards and the scope of the PDOs expanded, this ICR does not use a split rating methodology.  The assessment also reviewed the extent of execution of the core reforms supported by the project and the main elements implied in the PDOs and compared utilization of core services in RBF counties against the rest of the country.  32. Overall  achievement  of  project  indicators.    The  project  RF  includes  13  indicators,  of  which  seven  are outcome  indicators  and  six  are  Intermediate  Outcome  (IO)  Indicators.  The  project  achieved  11  out  of  the  13 indicators  (Figure 2).    Four of  the  five PDO 1 outcome  indicators and  the  two PDO 2 outcome  indicators were achieved.  The status of achievement of project indicators is captured in the updated table in the results framework, Annex 1 C.  

Figure 2. Overall Project Achievement 

Rating  PDO Indicators  

Intermediate Outcome Indicators 

Total  PDO/IO Indicators achieved 

Total 

PDO 1  PDO 2  PDO 1  PDO 2  PDO 1  PDO 2 

Achieved   4  2  4  1  8  3  11 

Not Achieved   1  0  1  0  2  0  2 

Total   5  2  5  1  10  3  13 

33. Assessment  of  Indicators  dropped  at  2013  AF.  Three  PDO  indicators  and  five  intermediate  outcome indicators dropped during the 2013 AF were assessed against the original targets.  Most of the dropped indicators were under PDO 2. All three PDO outcome indicators had been achieved: two under PDO 1 and one under PDO 2. Regarding the Intermediate Outcome Indicators, the annual targets for two indicators were achieved against the 2013 targets.   Assessment of achievement of PDO 1, Part One: improve the delivery of quality essential health and nutrition services – Rating: Substantial  34. The project thrust was on delivering quality health services based on the KEPH. The package comprised cost‐effective interventions that address the major causes of disease burden in Kenya.  As further explained below, in addition to improving direct financing to front‐line health facilities (Levels 2 and 3) through the RBF and HSSF to procure necessary inputs in a timely manner, the project improved the supply of the essential medical and health supplies.    The  project  achieved  the  two  PDO  indicators  on  quality  (see  Figure  3  below).    The  delivery  of  free 

16 The indicators dropped or replaced in 2011 were excluded from assessment 

Page 22: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

16

maternity services was based on standard norms promoting delivery of quality services.    In total, over 600,000 women delivered under the free maternity program compared with the original target of 550,000.  The women received a benefit package which included both outpatient and inpatient services for the mother and newborn for a period of one year as well  as antenatal  care, delivery, postnatal  care and emergency  referrals  for pregnancy related conditions and complications.  This was one of the flagship programs instituted by government in its quest to  achieve  universal  health  coverage.    Improvement  in  the  care  of malnourished  children  was  also  recorded. According to the nutrition surveillance and reporting system, over 80 percent of malnourished children treated recovered compared to a target of 60 percent.  The number of admissions of children suffering from severe acute malnutrition was also reported to have declined to around 3000 per month in 2013 compared to over 5000 per month  in 2011.    In  addition, over 19,000 health personnel were  trained  in  various disciplines over  the project duration.   35. Based on achievement of the two PDO indicators, improvement in the delivery of quality essential health and nutrition services is rated Substantial.   Assessment of achievement of PDO 1, Part Two: improve utilization of essential health and nutrition services by women and children among the poor and drought affected populations – Rating: Modest  

 36. Increased  utilization  of  essential  health  and  nutrition  services  (Figure  3).  The  utilization  of  health  and nutrition services increased as demonstrated by the increase in direct project beneficiaries based on outpatient visits. Women and  the drought affected population  registered a  significant  increase  in utilization of outpatient services which more than doubled the baseline figures.  Although not directly financed by the project, a significant increase was also registered in the utilization of free delivery services offered as part of the free maternity program as  explained  above.    However,  immunization  rate  remained  persistently  low.  The  annual  immunization  rate remained  low  throughout  the project duration,  and  the end project  rate achieved was  lower  than  the original baseline.  This is confirmed by the GAVI Country Fact Sheet on Kenya (2018), which shows DPT 3 coverage had been slowly  sliding  downwards  since  2012/13  and  in  2017  was  estimated  at  71  percent  based  on  official  country estimate.  The same report noted that only 15 out of 47 counties achieved a DPT3 coverage of 80 percent or more. While immunization data was meant to be disaggregated for the North East region, the information was not tracked and was therefore unavailable.    

Figure 3. Achievement of PDO 1 Indicators   

PDO 1 Indicators  

Baseline  Target  Actual  Status 

Part 1. Delivery of quality essential health and nutrition services  

Severely malnourished children under five receiving treatment recovered ‐ New 2011 

0%  60%  84%  Achieved 

Women receiving free delivery services meeting quality norms at public facilities – New 2013 

453,857  550,000  604,521  Achieved  

Part 2. Utilization of essential health and nutrition services by women and children among the poor and drought affected populations 

Direct project beneficiaries Number Female (55%) Number from drought affected areas 

25,896,000 14,299,363 0 

35,000,000 17,500,100 5,500,000 

50,949,459 34,447,148 15,088,032 

Achieved 

Page 23: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

17

Children immunized – National From North East 

1,188,698 32,800 

1,298,058 65,000 

1,105,234 NA 

Not Achieved 

Poor households receiving health insurance subsidies – New 2013 

0  30,000   181,315  Achieved  

  

37. The increase in utilization at the facilities was however not registered at the population level. According to the preliminary findings of the 2018 Household Health Expenditure and Utilization Survey17, there was no change in the total number of outpatient visits made  in the four weeks preceding the survey between 2013 and 2018, which remained about 9.1 million visits.  Annual per capita utilization dropped from 3.1 in 2013 to 2.5 visits in 2018 with the rate for the lowest wealth quintile dropping from 2.7 to 2.2 visits18.  The same scenario was reported in the RBF counties. Out of the 18 RBF counties with data for the 2013 survey, 10 registered a drop  in per capita utilization rate, 5 an increase and 3 witnessed no change in the per capita utilization rates between 2013 and 2018.  While the project used national outpatient data to estimate number of project beneficiaries, and assuming that the preliminary survey findings are valid, it can be deduced that the sum total of the initiatives undertaken during the period were not able to positively impact on the per capita utilization rate.  38. Emergency Nutrition Support to Drought Affected Areas.  While Kenya remains prone to drought and its effects, the project contributed towards the government’s humanitarian nutrition response in the drought affected areas. Over 15 million people (moderately malnourished children under five and pregnant and lactating women) in the  drought  affected  areas  received  health  care  services  and  the  relevant  food  supplements.    Because  of  the persistent household food insecurity in the arid and semiarid regions of Kenya, severe acute malnutrition remains a challenge. In 2017 admissions for children with severe acute malnutrition spiked from 3,000 in the previous years to about 6,000 cases per month in early part of the year. The total number of children 6 to 59 months and pregnant and lactating women requiring treatment for acute malnutrition in the arid and semiarid counties were estimated at 420,674 and 39,068, respectively19. In light of this, the unutilized RBF funds as explained below were reallocated to procure additional food supplements.   39. Health Insurance Subsidy for the Poor Program (HISP). The project, through the National Hospital Insurance Fund (NHIF), successfully supported the HISP20, the government’s flagship program under Vision 2030 to provide the  poor  and  vulnerable  households  with  health  insurance  cover  reaching  181,315  of  the  181,968  targeted households21, representing about 50 percent of orphan and vulnerable children (OVC) households countrywide. This is consistent with the increase in health insurance coverage, which increased from 17.1 percent to 19.9 percent between 2013 and 2018, representing coverage of 9.5 million Kenyans out of the estimated 47.8 million population.  An  impact evaluation of  the HISP concluded that despite challenges encountered  in  its  implementation, health insurance subsidies for the poor increased utilization of health services22, especially services provided by the private 

17 These was one of main studies financed under the project in part to assess its impact on the delivery health services 18 Ministry of Health, Draft Report, Kenya Household Health Expenditure and Utilization Survey, 2018 19 Ministry of Health. Nutrition Situation Report for Arid and Semiarid Areas, August 2017 20 The Health in Africa Initiative (HIA) Kenya program in collaboration with the project provided the technical support towards the design of HISP both the pre‐test and scale up, as well as implementation through community mobilization and sensitization under the Africa Health Markets for Equity program. In addition, HIA conducted three rounds of process evaluation during the lifetime of HISP. 21 The target households were beneficiaries of the orphan and vulnerable children cash transfer program. 22  The  average  number  of  hospitalizations  per  household  per  annum  increased  in  the  intervention  group  (from  1.4  to  1.6), while declining in the control group (from 1.6 to 1.3). In addition, there was an overall reduction in outpatient OOP of Kshs 3488.81 and a similar decrease in inpatient expenditure of Kshs 4828.99, which is estimated to have resulted in an annual decrease in mean direct medical  costs  of  Kshs  6,320.08.  In  addition,  at  end‐line,  levels  of  spending  declined  among  intervention  households  to  7.1%,  and increased  among  control  households  (14.4%).  The HISP  intervention was  thus  estimated  to  be  responsible  for  a  reduction  by  6.8 absolute percentage points in the share of household expenditure spent on treatment. 

Page 24: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

18

sector,  and  reduced out  of  pocket health expenditure  as  a  share of  the overall  household expenditure23.    The incidence of  catastrophic  health expenditure was estimated at  4.9 percent  (using 40 percent  threshold)  and 8 percent (using 10 percent threshold). This was a significant improvement from 2013 rates of 6.21 percent and 12.7 percent,  respectively.    Furthermore,  the  project  used  a  combination  of  approaches  to  target  the  poor  and vulnerable to enhance equitable access to health and nutrition services. The HSSF grants whose allocations were based on equity targeted the primary health facilities predominantly used by the poor. Both the RBF program and nutrition humanitarian support targeted the arid and semi‐arid areas, where most of the poor reside.  40. Implementation of the HSSF reform.  The project facilitated reforms to directly transfer funds to primary health facilities by rolling out HSSF grants to all primary health facilities and strengthening community engagement in health service delivery.  Project support was instrumental in increasing the operational budgets for lower level health facilities, capacity building for health service delivery at the county level and establishment of Health Facility Management  Committees  (HFMCs).    According  to  the  Independent  Integrated  Fiduciary  Agent  (IIFRA)  report, irregular use of grants by health facilities reduced from 21 percent to 5 percent and the health facilities maintaining proper cash books increased from 53 percent to 78 percent between 2011/12 and 2017/18, respectively.  IIFRA at midterm confirmed that overall quality of service, waiting time, cleanliness and the state of health centers had also improved.  Another independent evaluation24 revealed that direct cash transfers to peripheral health facilities led to improved quality of care, staff motivation and patient satisfaction, even though such funds represented less than 1 percent of the total health sector budget, and increased involvement of community members in the running of facilities as part of HFMCs, which strengthened accountability.  However, with devolution, the original fund flow arrangements under the HSSF to the health facilities were severely disrupted and curtailed implementation of the essential activities25 previously financed through the HSSF grants.  The capacity created through project support, as explained below, continues to partly benefit the devolution program in the health sector; however, because of the severe disruption of the fund flow arrangements to primary health facilities the original principles – especially timely  transfers  of  funds  to  the  HFs  ‐  that  underpinned  the  HSSF  were  no  longer  tenable  under  the  new arrangements through the counties.      41. Results  Based  Financing.    The  project  facilitated  the  introduction  of  performance‐based  financing approaches  in  the health  sector by piloting and  rolling out RBF  to 21 arid and  semi‐arid  counties.   Because of devolution the program experienced considerable challenges with funds flow and reporting requirements, which constrained  implementation  of  the  RBF  activities  and  undermined  the  program’s  potential  contribution  to improving performance of the health sector.  RBF activities started late in 2015/16 and only two transfers were made to the counties in 2015/16 and 2016/1726.  Absorption of RBF funds by the facilities remained low and many counties  did  not  procure  equipment.    Slow  implementation of  RBF was  attributed  to  funds  flow  challenges  to counties, delays in internal clearances in MoH and protracted health worker’s strikes and national elections. The individual  counties  experienced  diverse  challenges  and  their  overall  performance was mixed.    In  the  end,  the project  was  restructured  to  reallocate  the  savings  from  the  Credit  (about  US$  44  million)  due  to  slow implementation of RBF activities to procure essential equipment and nutrition commodities. In addition, the US$ 10 million transferred to counties that remained unspent/unaccounted and of which half remained in the County Revenue Fund were absorbed through re‐costing which involved the upward revision of the RBF indicator payment 

23 Ministry of Health, A Report of the Impact Evaluation of the Health Insurance Subsidy Program Pilot in Kenya, November 2017 24 Carried out by the Kenya Medical Research Institute Welcome Trust (2014). 25 Basic repairs and maintenance, installation of water tanks, printing patient treatment log cards, and payment for utility bills and casual staff. 26 Shs 508 million in 2015/16 and Shs 1,167 million in 2016/17, equivalent to US$16.75 million. The second release include funds for equipment. 

Page 25: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

19

rates. Despite these efforts, about US$ 4 million of the project proceeds had to be cancelled after reconciliation of project expenditures.  42. Capacity Building.  In  support of  the HSSF under  component 1,  the project  included a  set of activities  to strengthen the governance and stewardship functions of the Ministry of Health at the national level and health teams at  the county  level  to enhance service delivery.   The activities  included strengthening the Directorate of Policy Planning and Healthcare Financing and County Departments of Health including creation of strategic planning and management  units.    The project  supported  capacity  building  of  county  health  teams  through  provision of technical assistance before and after devolution: (a) training County teams in financial management and (b) training health facility management committees. In addition, DANIDA in parallel supported the training of HSSF Accountants who were deployed to the Counties. In addition, the project supported the scale up of training midwives under the Kenya Enrolled Community Health Nursing Program.  A total of 400 students from poor counties sponsored by the project were in their final year into the course during the ICR mission and upon completion of the studies would return  to  serve  in  their  respective  counties27.    Another  800  students  sponsored  through  other  financing arrangements are currently enrolled in year 1 and 2 of the course and are also expected to return to serve in their communities.  On  the  other  hand,  innovative  projects  to  improve  public  private  partnership  and  activities  on strengthening the referral system were not carried out. 

Assessment  of  achievement  of  PDO  2,  Part One:  Effectiveness  of  planning  for  pharmaceuticals  and medical supplies – Rating: Modest 

 43. Effectiveness of Planning.  While there were no specific indicators to monitor effectiveness of planning, the project contributed to reforming the supply chain management system for medicines and medical supplies and making KEMSA become autonomous and more effective and efficient as well as transparent in its operations. With the reforms, all  the previous vertical supply chains were  integrated  into one system under KEMSA. The project among others supported establishment of an electronic record keeping system, and development of an electronic Logistic Management Information system (LMIS), which has improved KEMSA’s ability to monitor and manage the supply chain system for medicines in Kenya.  KEMSA is now the medical logistics provider with the widest national coverage of 4,100 health facilities in the country.  By 2013, 95 percent of health facilities were able to place orders under pull system the previous quarter28. These reforms were largely focused on KEMSA and did not involve the counties, yet counties with devolution became responsible  for overall planning and management of  the supply chain system under their jurisdiction. While overall management capacity improved at KEMSA, this was not the case with the counties. Furthermore, the advent of devolution adversely affected the capacity of the counties in areas of quantification, forecasting, execution of orders and ensuring timely payments for commodities. Without capacity for planning and forecasting drug needs at the counties, KEMSA runs a risk of eroding its current level of buffer stock especially if counties fail to make timely payments for orders. Besides, KEMSA still needs to strengthen its administrative processes.  Assessment of  achievement of PDO 2,  Part  Two:  Effectiveness of  financing  for pharmaceuticals  and medical supplies – Rating: Substantial  

27 The training of enrolled community health nurses over a period of three (3) years was conceived in response to the severe shortage of frontline health workers, especially nurses in the arid and semiarid counties.  The students are selected from marginalized communities, minority groups and orphans and upon completion of the studies return to their communities. 28 This indicator was dropped in 2013 

Page 26: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

20

44. Effectiveness of Financing. The project, among others, supported KEMSA’s transformation from an agency that was previously dependent on government resources to an adequately resourced independent procurement agency able to respond to the needs of 47 counties, the national government and other key stakeholders including bilateral and multilateral partners in the country.  The timely reimbursement of KEMSA by the MoH also allowed KEMSA to operate a drug revolving arrangement29.  KEMSA created a buffer stock and reformed the supply chain management system from a “push” to a “pull” system. Using the new structure, KEMSA now sells medicines and medical supplies to county governments and faith‐based institutions using a not‐for‐profit revolving fund system30. KEMSA  is  also able  to procure  commodities  for  key donor  support projects  including United States Agency  for International  Development  (USAID),  Global  Fund  to  Fight  AIDS,  Tuberculosis  and Malaria  (GFATM)  and  Global Alliance for Vaccines and Immunization (GAVI). In 2015, the US government signed a five‐year US$ 650M contract with KEMSA to procure commodities for its programs.  According to the UNICEF publication, KEMSA managed to procure and distribute essential medicines and health supplies valued at about US$900 million over a seven‐year period.  

 Figure 4. Achievement of PDO 2, Part Three Indicators – On Procurement 

 PDO 2 Indicators  Baseline  Target  Actual  Status 

Share of planned procurements from EMMS pool completed by KEMSA in the FY per GoK guidelines – New 2013 

0  60%  100%  Achieved 

Value fill rate of orders for commodities for primary health care received by KEMSA either from counties or facilities – Revised 2013 

73%  80% (2013) 

83% (2018)  Achieved 

 Assessment of achievement of PDO 2, Part Three: Effectiveness of procurement of pharmaceuticals and medical supplies – Rating: Substantial  45. Effectiveness of  Procurement  (Figure 4). The project  achieved  the  targets  for  the  two PDO 2  indicators assessed under the PDO, both of which were related to effectiveness of procurement (Figure 5). KEMSA attained 100 percent completion rate of the planned procurements, against the end target of 60 percent. Over the period, KEMSA improved on the handling of orders from the HFs, and by the end of the project, had achieved a value fill rate of 83 percent against a target of 80 percent.  The PDO 2 indicator on health facilities that experience essential drugs stock‐outs for more than two weeks was dropped in 2011; however, it would have provided a better picture of the performance of the entire drug supply chain management system31.  The indicator was replaced with the indicator  “value  fill  rate  for  commodities  for  primary  health  care  received  by  KEMSA  from  either  counties  or facilities” to ensure that the project would be better aligned with the devolved health system where counties would have resources and flexibility to place orders.  According to the IIFRA report, after devolution many counties failed to order and pay for essential medicines from KEMSA on time, which increased stock‐outs of commodities at the health  facilities  in  2013/14  and  2014/15.  The  shortages  were  confirmed  by  the  Kenya  Household  Health 

29 The indicator Timely reimbursement to KEMSA documented claims by MoH was dropped in 2013 30 UNICEF Publication. KEMSA after the devolution: Financial sustainability through a supply chain strategy with a strong focus on human resources and leadership 31 The following three PDO 2 indicators dropped in 2011 were not assessed: health facilities that experience essential drugs stock‐outs for more than two weeks, timely payment to suppliers by KEMSA based on agreed procurement contract, and facilities displaying quarterly information on funds received and availability of drugs.

Page 27: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

21

Expenditure and Utilization Survey, 2018, which reported 21 percent (similar to 2013) of patients had bypassed the nearest and lowest level health facility for lack of drugs.  Justification of Overall Efficacy Rating  

 46. Overall rating for efficacy is Substantial. This is based on the following ratings for the five parts of the project.   

Figure 5. Rating of Efficacy 

PDO Parts  Rating 

PDO1, Part One: improve the delivery of quality essential health and nutrition services 

Substantial 

PDO1, Part Two: improve utilization of essential health and nutrition services by women and children among the poor and drought affected populations  

Modest 

PDO2, Part One: Effectiveness of Planning   Modest 

PDO2, Part Two: Effectiveness of Financing  Substantial 

PDO2, Part Three: Effectiveness of Procurement  Substantial 

 

  

C. EFFICIENCY 

 Assessment of Efficiency and Rating 

 47. Cost Benefit. Project specific economic evaluation was not undertaken for the project during appraisal.  The ICRR, however, includes an economic analysis at the end of the project to estimate the extent to which the project was  able  to  yield  economic  and  financial  returns  to  Kenya  by  supporting  the  delivery  of  the  basic  package  of essential  health  services.   Given net  estimated  cash  flow  in  terms of  income of  lives  saved  from mothers,  the estimated internal rate of return stands at 9.9 percent. At the given discount rate of 3 percent and the net present value of US$$60,912,114.67 the benefits outweigh the costs. Further, the project has a benefit‐cost ratio of 1.74:1. Sensitivity analysis was conducted by  increasing the discount rate to 5 percent still yielding a positive return at US$3,410,258.54 or a benefit‐cost ratio of 1.04:1. This analysis only focused on the reduction of maternal mortality and excluded child health and nutrition. The project contribution to improvements in child health were considered minimal.  Nutrition data was unavailable. It is important to note that, while data on the costs and cost‐effectiveness of humanitarian feeding programs are generally lacking, there are concerns regarding the cost‐effectiveness of the programs. A few studies carried out reveal that evidence regarding cost effectiveness of supplementary feeding programs are context specific and cannot be generalized32.  Further, the gains realized from increased efficiency in 

32 Emergency, Nutrition Network; The impact and effectiveness of emergency nutrition and nutrition‐related interventions: a review of published evidence 2004‐2010; 2011 

 

Page 28: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

22

KEMSA’s  operation  were  not  considered  as  separate  outcomes  by  themselves  and  were  treated  as  inputs  to increased access and utilization of basic package and the resultant improvement in maternal health outcomes. 

 Implementation efficiency 

 48. Design: The project in its design was meant to support implementation of the KEPH.  The package consisting of cost‐effective interventions aimed at addressing the major causes of disease burden in Kenya.  Analysis of the package reveals the interventions are consistent with Kenya’s disease burden and the World Health Organization recommended  list  of  cost‐effective  interventions.  In  addition,  the  project  provided  nutrition  supplements  to populations  affected  by  drought,  focusing  on  children  under  five  years,  pregnant  and  lactating women. While provision  of  food  supplements  is  generally  considered  less  cost‐effective  and  unsustainable,  they  are  often distributed during emergencies as part of the humanitarian response, which was the case with the project.  49. Implementation:  The  project was  designed  to  use  the HSSF  as  its main  implementation  platform.    As explained above and in the sections below, both the HSSF and RBF mechanisms suffered major implementation setbacks with the onset of devolution, the effects of which to a large extent were never fully resolved up to the end of the project, despite several measures put in place as well as the capacity building initiatives undertaken by the project.    The  project  was  restructured  in  2016  extending  the  closing  date  to  allow  for  RBF  implementation; however, even with the additional time, the problems remained largely unresolved.    In addition to the delayed disbursements  to  the  counties,  there  were  significant  disbursement  delays  to  virtually  all  the  other  major implementing entities including KEMSA, UNICEF, AMREF and KMTC.  Furthermore, the changes as result of project restructuring added to the complexity of the project.  Finally, while IIFRA diligently conducted reviews, the reports were not shared with stakeholders and could not therefore inform project implementation. 

 50. Efficiency is rated as Modest. This is based on the fact that while the project based on the economic analysis yielded  a  positive  return,  the  rate  was  borderline.  Secondly,  the  analysis  did  not  factor  the  implementation challenges which beset the project with the advent of devolution. 

 D. JUSTIFICATION OF OVERALL OUTCOME RATING 

 51. Overall project outcome is rated Moderately Satisfactory. This is based on the High rating for relevance of the PDOs, Substantial rating for efficacy, and Modest rating for efficiency.  

E. OTHER OUTCOMES AND IMPACTS (IF ANY) 

 Gender  

52. The project  directly  targeted women providing  a  range  of  essential  reproductive  and maternal  health services. In doing so, the project contributed to improving access to health services for the poor and, particularly, poor women. In addition to the 34,447,148 women beneficiaries, the project supported over 600,000 women to receive free delivery services that met the quality norms at public health facilities.   Institutional Strengthening  53. The  project  supported  various  institutional  strengthening  initiatives.    These  include  the  accountants recruited to facilitate HSSF implementation and the HFMCs established with project support in the 21 Counties.  As 

Page 29: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

23

explained earlier, the accountants were absorbed to continue serving in the counties. While devolution disrupted the project’s  fund flow arrangements,  the project contributed to building capacity of counties to manage fiscal transfers  from  the  government.    The  reforms of  the  supply  chain management  system were  to  a  large  extent supported by the project which have enhanced KEMSA’s  institutional capacity. With support of the project and other  partners,  KEMSA  successfully  adopted  and  is  currently  using  the  Enterprise  Resource  Planning  System, Logistics Management Information System and an e‐filing system, which have boosted its capacity to procure and supply medical supplies and commodities in the country.   

Mobilizing Private Sector Financing 

54. The HIA Kenya program in collaboration with the project provided technical support to the NHIF towards the design  and  implementation  of  HISP.  In  addition,  HIA  supported  NHIF  to  develop  instruments  to  enhance recruitment of informal sector employees into the health insurance scheme. 

Poverty Reduction and Shared Prosperity 

55. The  project  was  pro‐poor.  It  (a)  supported  lower  level  health  facilities  utilized mainly  by  the  poor,  (b) targeted drought affected populations supplying nutrition commodities to manage malnutrition among children under five years, pregnant and lactating women, and (c) supported the rollout of the government flagship program providing  health  insurance  subsidies  to  the  poor.  Furthermore,  the  RBF  program was  implemented  in  the  21 semiarid and arid counties where poverty levels are highest in Kenya.  Other Unintended Outcomes and Impacts 

56. Not applicable. 

III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME 

 A. KEY FACTORS DURING PREPARATION 

57. Project preparation was protracted33, was participatory and involved major stakeholders of the health sector. The preparation took account of the country and sectoral context as well as the contribution of other development  partners  including  experience  of  the  Bank’s  past  involvement  in  the  health  sector  in  Kenya, especially  the DARE project.   Project preparation benefited from several diagnostic studies and assessments including a comprehensive pharmaceutical study which informed the design of Component 2.  Careful attention was given to effectiveness conditions, which enabled the operation to become effective on October 1, 2010 shortly after approval in June 2010.  The HSSF, a major reform supported under the project was designed based on the model successfully piloted in two provinces.   58. The PDOs while broad and complex were aligned with national and sectoral priorities.  PDO 1 referred to “delivery of essential health services” without specifying actual services.  PDO 1 also referred to the poor in terms of level of health service delivery (Level 1‐3), but the design did not describe mechanisms to target the poor as the project was designed to support a national program and project beneficiaries were not explicitly mentioned in the appraisal document.  PDO 2 on the other hand was more transactional in its description.  To ensure clarity, PDO 1 was later revised during the AF to exclude reference to the Program and to specify project 

33 The concept note for the project was reviewed in 2005, and by 2007 a full package of documentation was prepared for a Decision Meeting. However, due to governance concerns about the outbreak of post‐election violence, the split of the MOH as part of the political agreement relating to the establishment of the Coalition Government, and the subsequent institutional problems facing the MOMS and MOPHS, World Bank management decided to suspend Project processing throughout 2008.     

Page 30: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

24

beneficiaries; and in the process the quality dimension was added.  The results framework was designed to use the regular government information system which eased the collection of the data.  The intermediate outcome indicators were quite many, and some could have been excluded as was later done during the restructuring of the project.  59. The project was designed as part of  the SWAp to support  the government’s program to reform the health  sector.    This  was  meant  to  ensure  synergy  and  complementarity  with  other  partner  programs. Coordination mechanisms were put in place such as a SWAp secretariat which ensured improved collaboration and information sharing across key actors thereby avoiding duplication of interventions and allowing for a more overall  strategic engagement.   However,  the scope of project activities was broad, and the  institutional and implementation arrangements complex given the governance arrangements between the two Ministries and large number of entities involved in project implementation.   60. A  comprehensive  risk  assessment was  conducted  during  project  preparation  and  a mitigation  plan adopted.  This  included a  governance assessment of  the overall  health  sector,  and both  components of  the project were  designed  to  include  specific  activities  that  address  governance  and  corruption  concerns.    The project was essentially ready for implementation by Bank approval. Its implementation arrangements were in place and it was declared effective within two months of approval. 

 B. KEY FACTORS DURING IMPLEMENTATION  

Factors subject to Govt/implementing agency control.  61. The introduction and rollout of the HSSF. The HSSF was rolled out successfully. The HSSF was a home‐grown reform program developed and piloted before national scale‐up. It marked the first‐time direct transfers of funds were made to frontline health facilities to meet day‐day operational and maintenance costs. The HSSF was successful and by 2013 the funds allocated to the HSSF were almost fully disbursed.   62. Strong commitment and political will to reform the supply chain management system for medicines and medical supplies. While KEMSA experienced operational challenges, because of the strong support from government and development partners, it was able to transform into an autonomous agency, establish a buffer stock, and establish more efficient and effective systems for the planning and management of the supply chain system for medicines and medical supplies. The reforms enabled KEMSA to effectively carry out its mandate in the supply chain management of medicines.  63. Planned  and  targeted  capacity  building  activities. While  there were  delays with  disbursements,  and disruptions with the transfer of funds to the health facilities, the institutions contracted to carry out targeted capacity building activities under  the project were successful  in enhancing capacity of  the sub‐national  level entities.  Kenya  School  of  Government  trained  over  2,900  County  officers  out  of  4,000  in  public  financial management. AMREF  trained members of  the Health Facility Management Committees  in 21 RBF Counties. Most of the trained officials continue to support the various departments in the counties including the health department. In addition, most of the district accountants were absorbed by the counties. 

 64. The  government  decision  to  abolish  user  fees  at  primary  level  health  facilities  and  introduce  free maternity services. In support of the two reforms, the government increased the budget to the health sector. The abolition of user fees contributed to the increased utilization of health services including maternity services. 

Page 31: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

25

While a statistically significant increase in the number of facility‐based deliveries was identified, there were no significant changes in the ratio of maternal mortality and the rate of neonatal mortality34. 

 65. Impact  of  devolution  on  transfer  of  funds  to  the  health  facilities.    The  devolution  process  greatly impacted project implementation, especially the HSSF and RBF fund flow arrangements to the health facilities.  Prior  to  devolution  HSSF  and  RBF  grants  were  directly  transferred  from  the  center  to  the  health  facilities.  However,  following  devolution,  conditional  grants  and  project  disbursements  were  channeled  through  the respective County Revenue Fund  (CRF) Accounts. The grants were  then  transferred  from the respective CRF Account to a County Special Purpose Account for Health for onward disbursement to the beneficiary facilities.  This  resulted  in  delays  of  between  3‐6 months  in  releasing  the RBF  and  conditional  grants  to  the  facilities.  According to the IIFRA, the main causes for the delay were diversion of funds and slow processing and approval of funds by the counties.  Secondly, because of the changes, RBF disbursements to counties were made based on the County Allocation of Revenue Act provisions rather than performance.  Attempts to ensure the transfers were based  on performance were unsuccessful,  as  it was  deemed  that  performance‐based  transfers would contravene  the existing Act.    The  introduction of devolution also greatly disrupted  the  supply of medicines. Counties  were  no  longer  obliged  to  source  medicines  from  the  government‐run  KEMSA,  which  led  to mismanagement and scarcity of drugs at health facilities.  It is reported that nearly all counties are faced with challenges  ranging  from  capacity  gaps,  human  resource  deficiency,  lack  of  critical  legal  and  institutional infrastructure, and a conflictual relationship with the national government, the net effect of which has led to stagnation and in some cases a reversal of some of the previous gains in the sector35. Originally, devolution was planned to be rolled out over a three‐year period; instead the pace was hastened. Besides some of the enabling policy frameworks were not in place.  66. Merger of the Ministry of Medical Services and Ministry of Public Health and Sanitation. The decision to merge the two ministries resulted in changes to the project’s institutional and implementation arrangements. New coordination and implementation arrangements for the project had to be established.  Partly, as a result, there was a high turnover of staff responsible for coordination of project implementation and loss of institutional memory.  Furthermore, the changes impacted on the execution and follow‐up of some core tasks necessary for project implementation leading to delays in: (a) release of funds by the MoH to implementing entities; and (b) signing/extension of  key  agreements/memorandum of  understanding with  KEMSA, AMREF,  KSG,  KMTC  and UNICEF.  

 67. Delayed disbursements of funds.  While delay with disbursement of funds was most pronounced at the health  facilities,  especially  after  the  advent  of  devolution,  all  other  entities  including  KEMSA,  KMTC,  NHIF, AMREF and Kenya School of Government suffered major disbursement delays.  The implementation of activities by these entities not only started late due to delay with signing memoranda of understanding, implementation was further slowed down by the delayed disbursements by the MoH.  After devolution, the Counties through the  Council  of  Governors,  took  a  long  time  in  the  2013/14  and  2014/15  financial  years  before  signing  the memorandum of understanding (MOU) for the KHSSP conditional grants. This adversely affected the release of conditional grants and led to non‐implementation of some planned activities by the health facilities. 

34 C. M. Gitobu, P. B. Gichangi, and W. O. Mwanda. The effect of Kenya’s free maternal health care policy on the utilization of health facility delivery services and maternal and neonatal mortality in public health facilities. BMC Pregnancy and Childbirth. 27 March 2018. 35 Leah Kimathi, Challenges of the Devolved Health Sector in Kenya: Teething Problems or Systemic Contradictions? Africa Development, Volume XLII, No. 1, 2017, pp. 55‐77 © Council for the Development of Social Science Research in Africa, 2017 (ISSN: 0850 3907) 

Page 32: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

26

 Factors outside Govt/implementing agency control  68. Industrial action by health workers.  The doctors 100‐day strike in 2016 and nurses’ industrial action of 2017 which lasted over 5 months severely disrupted delivery of health services. The impact of the industrial action  was  particularly  severe  for  front  line  services  supported  by  the  project.    The  nurses’  strike  gravely impacted  the  provision  of  health  and  nutrition  services  country‐wide.    Over  50  percent  of  primary  health facilities were closed in six drought‐affected Counties.  Analysis of District Health Information System 2 (DHIS2) data  for Turkana and Garissa  counties  revealed dramatic declines  in  immunization  rates  from 80 percent  in January ‐ May 2017 to 30 percent in June – July.  Similarly, Ante‐natal Care attendance dropped from 40 percent to 10 percent and Skilled Birth Attendance dropped from 60 percent to 30 percent36.  69. Drought. Kenya experienced severe drought which affected the most impoverished areas of the country populated by nomadic and semi‐nomadic pastoralists and subsistence farmers. As part of the support towards the  government’s  response  the project obtained AF  to help Kenya address more effectively  the emergency health  and  nutrition  needs  of  most  vulnerable  populations,  especially  pregnant  and  lactating  women  and children under five in the drought affected northern arid and semi‐arid regions. 

Factors subject to WB control  70. Additional Financing and project restructuring. Through the AF in 2011 and 2013 the project supported the government’s humanitarian response to drought affected populations; supported the free maternity care following abolition of user fees for delivery services; and expanded the supply of medicines and other medical supplies through KEMSA. The restructuring (a) refocused the PDO to support the drought affected populations; (b) targeted women and children as project beneficiaries; (c) adapted the implementation arrangements to the ongoing reforms in the country; and (d) provided time for implementation of delayed project activities. But in the process, the new initiatives added made the project more complex.  71. The Bank team’s proactivity and resilience. The project was implemented in a complex environment amid many challenges; but  the  task team remained proactive  in  their engagement with government and partners which enabled the project to undergo restructuring and receive the AF to address the adverse effects of drought and scale‐up project interventions.  

 

IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME 

 A. QUALITY OF MONITORING AND EVALUATION (M&E)  

M&E Design  72. Quality of M&E design is rated modest.  The project’s results framework was designed with the majority of indicators collected from routine data sources and complemented by surveys where appropriate. All the indicators had baseline data and the expected targets to be achieved. The intermediate outcome indicators were many. Owing to the SWAp approach, the results framework was designed to measure national level implementation, although the indicator on immunization was disaggregated to the North East Province for equity consideration.  The design 

36 UNICEF, Kenya Humanitarian Situation Report – 1 September 2017 

Page 33: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

27

included the use of IIFRA to monitor the execution of the project.  A major shortcoming of the results framework was that the design did not include the appropriate PDO indicators to adequately measure the delivery of essential health  services. With exception of  immunization,  the  results  framework  consisted of mainly  input and process indicators. Indicators on coverage of specific program interventions or targeting specific population groups were lacking.   This was however partly rectified during the AF with incorporation of  indicators targeting children and women and utilization of nutrition services.    M&E Implementation  73. Quality of M&E implementation is rated modest.  The results framework was regularly populated and the Implementation Status and Results Reports (ISRs) updated. The ISR ratings were realistic and generally reflected the implementation status of the project.  The results framework was revised to reflect changes to the project and to  take account of  implementation experience with devolution. With counties becoming  responsible  for health services  delivery,  the monitoring  of  such  indicators would  be  difficult  from  the  center.    The  changes  included dropping some indicators, adding new indicators and revision of the targets with the aim of simplifying the results framework and ensuring that it is aligned with the revised project objectives. However, in the process, the project became more  complex.    Furthermore,  these  efforts  did  not  rectify  the weaknesses  around  the  PDO  outcome indicators.  Instead  relevant  PDO  indicators  (staffing  norms  and  drug  shortages)  were  dropped.    In  addition, immunization data for the North East region were not reported.  Two major studies were conducted during project implementation: household expenditure and utilization survey and the service delivery indicator survey.  Owing to delays,  both  studies  had  not  been  concluded  by  project  closing  and  as  such  could  not  directly  inform project implementation. It is, however, envisaged that the findings will inform future developments of the overall health sector program in Kenya. IIFRA on its part conducted periodic reviews of the project and issued the reports.  In addition,  the  project  contributed  towards  the  Kenya  Demographic  Health  Survey  and  STEPwise  approach  to Surveillance for non‐communicable diseases and the evaluation of the HISP.  M&E Utilization  74. Quality of M&E utilization was modest.  The project generated a considerable volume of data.  The use of the data was however mixed.   KEMSA built an effective electronic management information system, which was used  to monitor  execution  of  its  programs  and  to  drive  the  reform  agenda  towards  the  “pull”  system.   With devolution, the quality of reporting by the counties deteriorated considerably.  For various reasons, many of the counties failed to provide timely progress and financial reports to the Ministry of Health.  In addition, while IIFRA submitted its reports to the Ministry of Health, the reports were not shared with the key stakeholders including the Bank team.  As a result, use of the IIFRA findings was limited. This was a missed opportunity since IIFRA was responsible  for assessing compliance with approved work plans; verifying activities  in the approved work plans were executed and planned results achieved, and linking the expenditures incurred to successful achievement of the envisaged results.   

Justification of Overall Rating of Quality of M&E  75. Overall rating for quality of M&E is modest. This is based on the modest quality of M&E design, modest quality of M&E implementation and modest quality of M&E utilization. 

 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE  

Page 34: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

28

76. Environmental  safeguards.  The  project  triggered  Operational  Policy  4.01  relating  to  Environmental Assessment and was classified as environmental Category B. The environmental safeguard policy issue related to handling and disposal of medical waste generated by the health facilities. The project procured incinerators for five hospitals  and  supported  the  training  of  health  providers  on  the  handling  and  disposal  of  medical  waste  and infection  control.    The project overall was  compliant with  the  environmental  safeguard policy. Health  facilities segregated medical waste using color coded bins. The environmental and social audit report on the installation of the incinerators was approved by National Environment Management Authority (NEMA). By the time of project closure, the Ministry of Health was following up on the implementation of the audit findings and recommendations by NEMA  on  decommissioning  of  old  incinerators  and  ensuring  that  hospitals  obtain  a  license  from NEMA  to operate the incinerators.   77. Social  safeguards. The project was designed  to address  inequities  in access  to, and utilization of, health services, which was a central goal of the NHSSP II. The project triggered OP 4.10 on Indigenous Peoples, and for which an Indigenous Peoples Planning Framework (IPPF) was prepared at appraisal. During implementation, and especially after the AF, attention was paid to increasing access and utilization of health services by the poor and the vulnerable populations. Emphasis was made to target drought affected population, and women and children from the arid and semiarid regions of Kenya. The poor were also targeted through HISP.  It is important to note that deliberate efforts were made to enhance the inclusion and participation of the vulnerable and marginalized groups through community empowerment, promotion of good and desirable health practices, making services affordable, and ensuring the health facilities serving the vulnerable and marginalized groups obtained sufficient medicines.  The HFMCs served as a key link with the communities to channel their grievances.  Service charters were translated into local languages.  Facilities also kept locked feedback boxes, where grievances can be submitted anonymously.  In addition, the NHIF implementing the Health Insurance Subsidies for the Poor (HISP) operated a 24‐hour toll‐free hotline and a dedicated email address to handle client complaints.  78. Financial management. At midterm review (August 2013), financial management arrangements at the MoH central  level  (Health  SWAp  and  HSSF  Secretariats)  and  counties  were  reported  as  adequate.  There  were  no outstanding audit issues and interim financial reports were submitted in a timely manner and in a form acceptable to the Bank. However, the advent of devolution severely disrupted the HSSF financial management arrangements and adversely affected the transfer of grants to the health facilities.   Many counties were no longer submitting financial returns despite repeated follow up by the Ministry of Health.  By project closure, several issues raised in the audit reports and other reviews had not been addressed including ineligible expenditures of Kshs 295,785,262 and potential ineligible expenditure of Kshs 1,166,120,469.  The audit report for the period ending June 30, 2018 also noted that the statement of financial assets and liabilities reflected a bank balance of Kshs 1,029,248,879 as at 30 June 2018. Included in this balance was Kshs 657,875,266 in respect of bank balances from 47 counties that were  not  supported  with  bank  confirmation  certificates,  bank  reconciliation  statements  and  cashbook. Furthermore, the National Hospital Insurance Fund implementing the HISP did not submit quarterly reports to the MoH as required. As reported above, while IIFRA diligently conducted the reviews, the reports were not shared with stakeholders and could not therefore inform project implementation.  The FM issues are being followed up under the new follow‐on Project.  79. Procurement. The bulk of procurements under the project were carried under component two by KEMSA. Prior to the project, procurements by KEMSA experienced major shortcomings, but with support of the project, KEMSA  made  substantial  progress  in  the  procurement  of  essential  medicines  and  implementation  of  the procurement plan.  Improvements were noticed with respect to compliance in terms of procurement planning, bid preparation, publication of contracts and filing and records management.  However, KEMSA needs to improve the 

Page 35: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

29

quality  of  bid  evaluation  reports,  strengthen  contract  administration  and management,  and  pay  suppliers  in  a timely manner. While  few,  procurements  by  the MoH were  slow  and  experienced  considerable  delays.  In  the project design, health facilities were meant to handle small procurements. Because of the changes brought about by devolution, these procurements, including those for essential medical equipment could not go ahead and were abandoned.   

C. BANK PERFORMANCE  

Quality at Entry 

 80. The Bank’s performance with respect to quality at entry is rated moderately satisfactory.  The project was aligned with the strategic development objectives of the sector and country as described  in the HSSIP  II  (2005‐2012) and Vison 2030.  The preparation and design of the project involved broad stakeholder consultations and several analytics, took cognizance of the Bank’s prior experience with the health sector, and reflected the country and sectoral context. Great attention was paid to assessment of the governance environment including fiduciary arrangements and putting in place appropriate mitigation measures.  The majority of the QER recommendations were incorporated during the project design.  The project had robust implementation arrangements and was able to become effective two months after Board approval. The long project preparation duration meant team members kept changing, but the overall team composition remained comprehensive. The major shortcomings were with the broad  scope and  complex design of  the project.  The project  apart  from mentioning  the poor did not explicitly identify its beneficiaries, nor were the actual services to be delivered mentioned.  These as explained earlier were only partly addressed during the restructuring of the project. Besides the broad PDOs and complex nature of the project,  the  project  design  did  not  include  appropriate  PDO  indicators  to  adequately measure  the  delivery  of essential health services.   Quality of Supervision  81. The Bank’s performance with respect to quality of supervision is rated satisfactory. The majority of the task team members including the task team leader were based in the Kenya Country Office and had been involved in project preparation. The team leader during Board approval stayed throughout the project duration as team leader. The  team  jointly with  other  partners  and  the MoH held  regular  biannual  implementation  support missions.  In addition to assessing progress with project implementation and achievement of the project objectives, the missions assessed compliance with  fiduciary and  safeguards policies as well  as  the  legal  covenants. The outcomes were captured and adequately reflected in the aide memoires and ISRs. The ISR ratings were generally consistent with the mission findings and reflected the status of project implementation.   82. The team was proactive in addressing the project’s shortcomings and responding to the changing country dynamics. This was demonstrated by the team’s effort in obtaining AF and restructuring the project. The team was proactive  and  established  strong  rapport with  partners  and  government  officials which  provided  them a  good opportunity to access MoH and other government agencies and to understand the changing country context and dynamics. Their understanding of the local context helped them to effectively supervise the project and respond to the changing dynamics around project implementation.  Despite the team’s efforts, the disruptions to the fund flow arrangements persisted and severely impacted the implementation of RBF activities. As noted above (M+E section),  the weaknesses  around  the PDO outcome  indicators were only partially  addressed.  Furthermore,  the opportunity to use IFRAA findings to monitor project execution were missed. 

Page 36: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

30

 Justification of Overall Rating of Bank Performance  83. Overall Bank performance is rated moderately satisfactory. 

 

D. RISK TO DEVELOPMENT OUTCOME  84. Overall risk to development outcome is moderate. The Project was executed using country systems, did not finance new health infrastructure outside the existing health facilities and focused on building institutional capacity at county and facility levels.  Most staff (technical officers in financial management and HFMCs) trained under the project continue to serve in their respective capacities.  The 400 nurses who were under training during the mission were expected  to  return  and  serve  in  their  communities.   With  the  systems  for procurement  and  supply  chain management using automated Enterprise Resource Planning Program, KEMSA has become more successful as a public‐sector procurement agency.  While KEMSA’s reliance on release of funds by the MoH has reduced there is the  increased  risk  of  fragmentation  of  the  budget  for medicines with  the  onset  of  devolution.  The  devolution disrupted the RBF and HSSF fund flow arrangements, but created a new mechanism for intergovernmental fiscal transfers, which provides a good opportunity for government and partners to make direct transfer of funds to health facilities.  However, this will require the Ministry of Health to proactively engage in the ongoing discussions on the devolution process.  Building on the project, the Bank prepared a follow‐on project “Transforming Health Systems for Universal Care Project”  (P152394, $191.1 m)  to  continue  support  to  the Kenya Health  system. With project closing, the government has taken over the funding of the HISP.  The new project is also using a performance‐based approach to allocate resources to the counties based on improved PHC results. 

 

V. LESSONS AND RECOMMENDATIONS 

 85. The challenge of projects responding to major government reforms.   The devolution process in Kenya was very ambitious, fast‐tracked and unfolded in an environment where the building blocks for devolution were still evolving. For such major reforms, like the Kenya one, while flexibility was needed, it is necessary to exercise caution, otherwise, the project risks losing focus and playing a catchup and/or firefighting role.   86. Direct  funding  of  health  facilities.  Initiatives  and  programs  aimed  at  directly  transferring  funds  to  health facilities  like  the  HSSF  and  RBF  can  potentially  improve  service  delivery  and  promote  transparency  as  well  as accountability.  Implementation of both the HSSF and RBF programs faltered in Kenya. To ensure success of such initiatives, it is necessary to ensure: (a) proactive and continuous dialogue between the central and county levels of the Ministry of Health to clarify respective roles and responsibilities: (b) a supportive regulatory framework is  in place  anchored  within  an  appropriate  legal  instrument;  (c)  fund  flow  arrangements  are  clarified  and  clearly enshrined in the devolution framework; and (d) health facilities are adequately capacitated to perform the necessary fiduciary roles. 

 87. The reforms undertaken by KEMSA were successful and demonstrate the importance of: (a) a comprehensive diagnostic  assessment  conducted  in  a  consultative  manner;  (b)  securing  consensus  among  partners  and  with government  on  the  proposed  reforms,  (c)  ensuring  the  reforms  are  institutionalized within  a  clear  institutional framework; and (d) provision of the necessary technical assistance and adequate resources to support the reform process.  

Page 37: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

31

88. In‐country presence of the Task Team. The project was a complex one implemented in a challenging context. The continuity and  in‐country presence of  the  task  team and especially  the  task  team  leader was critical  in  the context of the fast‐tracked devolution which introduced complex reforms in the health sector.   This allowed the project to address implementation gaps as they arose and to work together with central and county government towards effective solutions.  89. The  importance  of  supporting  home  grown  initiatives.  The  HSSF  was  a  home‐grown  reform  program developed  and  piloted  before  national  scale‐up.  While  its  implementation  suffered  with  devolution,  it  was  a successful program, demonstrating the value of building on home grown initiatives, piloted and executed within the government institutions. On the other hand, the HISP, a government flagship program, supported by the project in the first phase is now fully funded under the UHC umbrella through the National Treasury after the closure of the project. 

 90. The use of government institutions to implement capacity building activities. The project used established GOK institutions to implement key capacity building activities in many areas, which has enabled continuity. Financial management training was undertaken by Kenya School of Government.  The Enrolled Community Nursing Program by KMTC, has ensured continuity in provision of the curriculum and courses offered by the institution to date. .

Page 38: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

32

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS 

       A. RESULTS INDICATORS  A.1 PDO Indicators       

 Objective/Outcome: The delivery of essential health services in the Recipient’s territory, especially for the poor; 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Direct project beneficiaries  Number  25896000.00  29300000.00  35000000.00  50949459.00 

  05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018  

Female beneficiaries  Percentage  14229369.00  16100100.00  17500000.00  34447148.00 

  05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018    

Beneficiaries from drought affected areas 

Number  0.00  332500.00  5500000.00  15088032.00 

  05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018  

 

Comments (achievements against targets): Target Achieved    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Children immunized  Number  1188698.00  1800000.00  1298058.00  1105234.00 

Page 39: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

33

 

(number)    05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  29‐Mar‐2018  

Comments (achievements against targets): Target Not Achieved    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Severely malnourished children under five receiving treatment recovered 

Percentage  0.00  60.00  60.00  84.00 

  30‐Jun‐2011  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018  

Comments (achievements against targets): Target Achieved    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Women receiving free delivery services meeting the quality norms at public health facilities 

Number  453857.00  550000.00  550000.00  604521.00 

  01‐Jul‐2013  30‐Dec‐2016  29‐Jun‐2018  29‐Jun‐2018 

 

Comments (achievements against targets): Target Achieved    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Poor households receiving health insurance subsidies 

Number  0.00  30000.00  30000.00  181689.00 

  01‐Jul‐2013  30‐Dec‐2016  29‐Jun‐2018  29‐Jun‐2018 

Page 40: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

34

   

Comments (achievements against targets): Target Achieved. In total, 6 out of 7 PDO Outcomes were Achieved      

 Objective/Outcome: The effectiveness of planning, financing, procurement of pharmaceuticals and medical supplies 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Value fill rate of orders for commodities for Primary Health Care facilities received by KEMSA either from counties or facilities 

Percentage  73.00  90.00  80.00  83.00 

  05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018 

 

Comments (achievements against targets): Target Achieved    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Share of planned procurement from EMMS pool completed by KEMSA in the financial year as per GoK guidelines 

Percentage  0.00  60.00  60.00  100.00 

  31‐Dec‐2013  30‐Dec‐2016  29‐Jun‐2018  29‐Jun‐2018 

 

Comments (achievements against targets): Target Achieved  

 

 A.2 Intermediate Results Indicators      

 Component: The delivery of essential health services in the Recipient’s territory, especially for the poor 

Page 41: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

35

 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

People with access to a basic package of health, nutrition, or reproductive health services (number) 

Number  0.00  30495000.00  39400000.00  47143791.00 

  05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018 

 

Comments (achievements against targets): Target Achieved    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Facility management committees having quarterly meetings with minutes of meetings (levels 2 and 3) (percent) 

Percentage  27.00  90.00  90.00  83.00 

  05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018 

 

Comments (achievements against targets): The Target was Substantially Achieved (92%)    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Health personnel receiving training (number) 

Number  0.00  35120.00  14899.00  19271.00 

  05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018  

Comments (achievements against targets): Target Achieved    

Page 42: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

36

 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Level 2‐3 facilities implementing results based financing initiatives (number) 

Number  0.00  250.00  1331.00  1770.00 

  05‐Jul‐2010  31‐Mar‐2015  29‐Jun‐2018  30‐Mar‐2018  

Comments (achievements against targets): Target Achieved    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of beneficiaries receiving supplementary feeding in the drought affected areas. (Moderately malnourished children under five and moderately malnourished pregnant and lactating women) 

Number  157413.00  285210.00  285210.00  450582.00 

  01‐Jul‐2011  31‐Mar‐2015  29‐Jun‐2018  29‐Jun‐2018 

 

Comments (achievements against targets): Target Achieved      

 Component: The effectiveness of planning, financing, procurement of pharmaceuticals and medical supplies 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Counties placing orders for Essential Medicines and Medical Supplies with KEMSA 

Number  16.00  30.00  30.00  47.00 

  31‐Jan‐2014  29‐Jun‐2018  29‐Jun‐2018  30‐Mar‐2018 

Page 43: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

37

   

Comments (achievements against targets): Target Achieved In total, 5 out of 6 Intermediate Outcome Indicators were Achieved.  

           

Page 44: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

38

B. KEY OUTPUTS BY COMPONENT   

Objective/Outcome 1: Effective and transparent implementation of the KEPH through HSSF grants and performance strengthening (total estimated cost US119.68 million) 

 Outcome Indicators 

1. Direct project beneficiaries (Number of outpatient visits to levels 2 and 3) Female Beneficiaries Beneficiaries from drought affected areas (Number) 

2. Children immunized (number, disaggregated for Northeast Province) 3. Value fill rate of orders for commodities for Primary Health Care facilities received by KEMSA either from counties or facilities (Percent) 4. Severely malnourished children under five receiving treatment recovered (Percent) 5. Share of planned procurement from Essential Medicines and Medical Supplies (EMMS) pool completed by KEMSA in the financial year as per GoK guidelines (Percent) 6. Women receiving free delivery services meeting the quality norms at public health facilities (Number) 7. Poor households receiving health insurance subsidies (Number)  

Intermediate Results Indicators 

1.  People with access to a basic package of health, nutrition and reproductive health services 2.  Facility management committees having quarterly meetings with minutes of meetings 3.  Health personnel receiving training 4.  Level 2‐3 facilities implementing results‐based financing initiatives 5.  Number of beneficiaries receiving supplementary feeding in drought affected areas 6. Counties placing orders for essential medicines and supplies with KEMSA 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 1) 

1.  Contributed to the delivery of primary health care services to 50 million direct project beneficiaries, including 34.4 million women, 0.6 million women receiving free delivery services and 15 million beneficiaries from the drought affected regions; 2.  Provided health insurance cover to 181,968 poor households ‐ included outpatient and inpatient services; 3.  Improved treatment outcome for children severely malnourished, achieving 84 percent recovery rate; 4.  Rolled out HSSF to all public health facilities and RBF to 21 counties reaching 1,771 primary health facilities; 

Page 45: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

39

5.  Supported training of 19,271 beneficiaries, including training 400 students as enrolled community health nurses with focus on midwifery to address human resource shortages in underserved counties; 6.  Trained Health Facility Management Committees (HFMCs) in 21 RBF counties; 7.  Trained 2,994 county executives, administrative and technical officers in financial management; 8. Supported the service delivery indicators survey targeting 3,281 health facilities and a new round of household expenditure and utilization survey (HHEUS) targeting 37,500 households 

Objective/Outcome 2: Availability of essential health commodities and supply chain management reform (US$98.11 million) 

 Outcome Indicators 1.  Share of planned procurements from EMMS pool completed by KEMSA in the FY per GoK guidelines 2.  Value fill rate for commodities on KEMSA Essential Drug List 3.  Fiduciary irregularities reported from HSSF and KEMSA acted upon 

Intermediate Results Indicators 

1.  Number of beneficiaries receiving supplementary feeding in drought affected areas 2.  Facilities under pull system sending orders in previous quarter 3.  Timely reimbursement to KEMSA documented claims by MoH 4.  Counties placing orders for essential medicines and supplies with KEMSA 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 2) 

1. Supplied essential health and nutrition commodities, cold chain equipment and basic equipment to the 21 RBF counties;  2.  Improved KEMSA’s performance to achieve 100 percent execution of planned procurement for the FY; 3.  Supported establishment of an electronic record keeping system, development of a procurement manual and an electronic Logistic Management Information system; 4.  Supported KEMSA’s transformation from an agency that was dependent only on government resources to an adequately resourced independent procurement agency responding to the needs of 47 counties and the national government; 5. Supported KEMSA to create a buffer stock and to reform the supply chain management system from a “push” to a “pull” system. 

Page 46: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

40

C. Author’s Results Framework – Kenya Health Sector Support Project: Reflects original and revised baselines and targets from 2011 and 2013 AF  Indicators  Original 

Baseline 2011 Baseline 

2013 Baseline 

Original Target  2011 Target  2013 Target  Achieved 

Project Outcome Indicators               

PDO 1               

Direct project beneficiaries Number Female (55%) Number from drought affected areas 

25,896,000 14,299,369 

  0 

  29,300,000 16,100,100  

  332,500 

35,000,000 17,500,100 5,500,000 

50,949,459 34,447,148 15,088,032 

Children immunized From North East 

1,188,698 32,800 

    1,800,000 65,000 

1,298,058    1,105,234  

HSSF facilities meeting core financial management requirements of the fund – Dropped 2013 

0%      90%    85%  97% (2013) 

Level 2 and 3 HSSF facilities displaying information as per GoK guidelines ‐ Dropped 2013 

  0%    90%  90%  80% (2013)  77% (2013) 

Severely malnourished children under five receiving treatment recovered ‐ New 2011 

  ‐      60%     84% 

Women receiving free delivery services meeting quality norms at public facilities – New 2013 

    453,857      550,000  604,521 

Poor households receiving health insurance subsidies – New 2013 

    0      30,000  181,968 

PDO 2               

Health facilities that experience essential drugs stock‐outs for more than two weeks ‐ Replaced 2011 

18%      5%       Not Assessed 

Timely payment to suppliers by KEMSA based on agreed procurement contract – Replaced 2011 

60%      80%       Not Assessed 

Facilities displaying quarterly information on funds received and availability of drugs – Replaced 2011 

0%      90%      Not Assessed 

Share of planned procurements from EMMS pool completed by KEMSA in the FY per GoK guidelines – New 2013 

    0%      60%  100% 

Value fill rate of orders for commodities for primary health care facilities received by KEMSA either from counties or facilities – New 2011and revised in 2013 

  73%      90%  80% (2013)  83% (2018) 

Fiduciary irregularities reported from HSSF and KEMSA acted upon (last quarter) – new 2011 and Dropped 2013 

  0%      100%  90% (2013)  100% 

Intermediate Outcome Indicators (PDO 1)               

People with access to a basic package of health, nutrition and population services 

0      30,495,000    39,400,000  47,143,791 

Page 47: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

41

Facilities receiving HSSF Funds within 15 days of the beginning of the quarter – Dropped 2013 

0%      90%    60% (2013)  0 

Facility management committees having quarterly meetings with minutes of meetings 

Level 2 27% Level 3 46% 

    90%      83% 

Health personnel receiving training  0      35,120  6,500   14,899  19,271 

Level 2 and 3 facilities meeting staffing norms – Dropped 2013 

Level 2 3% Level 3 34% 

    40%    40% (2013)  Not Available 

Level 2 and 3 facilities providing reports on services to OVCs ‐Dropped 2011 

0%      50%  

Dropped     Not Assessed 

Successful completion of innovative initiatives to improve referral to district hospitals and for improved health financing – Dropped 2011 

0      5  

Dropped     Not Assessed 

Level 2‐3 facilities implementing results‐based financing initiatives 

0      40%  

250  1,331  1,770 

Number of beneficiaries receiving supplementary feeding in drought affected areas – New 2011 

  157,413      285,210    450,582 

Intermediate Outcome Indicators (PDO 2)               

Performance contract between KEMSA and MOMS, and a client service agreement between KEMSA and MOPHS, established and monitored on a quarterly basis ‐ Dropped 2013 

N0      Yes     Dropped  Draft 

Complaints reported, and actions taken through an accessible complaints mechanism on service delivery, fraud and corruption on a quarterly basis – Dropped/Replaced 2011 

Level 2 8% Level 3 10% 

    70%      Not Assessed 

Tenders and awarded contracts advertised on the KEMSA website and meeting the national and international standards for dissemination – Dropped 2011 

70%      90%      Not Assessed 

On‐time delivery of drugs and medical supplies to level 2 and 3 facilities ‐ Dropped 2011 

      80%      Not Assessed 

Availability of pre‐shipment inspection certificate within KEMSA ‐ Dropped 2011 

60%      80%      Not Assessed 

Timely completion of the Annual Procurement Plan – Dropped 2011 

No       Yes       Not Assessed 

Facilities under pull system sending orders in previous quarter – New 2011 and Dropped 2013 

  TBD      TBD  TBD  95% 

Timely reimbursement to KEMSA documented claims by MoH –New 2011 and Dropped 2013 

  ‐      100%  75%  75% 

Counties placing orders for essential medicines and supplies with KEMSA 

    16      30  47 

Page 48: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

42

D.  The Kenya Essential Package for Health  Cohort  Service package 

Cohort 1  Pregnancy and newborn (up to 2 weeks of age)  

ANC and nutritional care, IPT, TT2. Use of skilled birth attendants, clean delivery, BCG. Postnatal care, breast feeding support, supplementary feeding. Family planning services. ITN promotion and use. IPT and indoor spraying. PMTCT. Micro‐nutrient supplements (iron). Hygiene, water and sanitation. 

Cohort 2  Early childhood  (2 weeks to 5 years)  

Community IMCI, ITN promotion and use. Appropriate nutrition, extended breastfeeding, growth monitoring, EPI, provision of vitamin A, zinc. Psychological stimulation, physical / cognitive development. Exercise and recreation. 

Cohort 3 Late childhood (6 ‐ 12 years)  

Essential school health program.  Adequate nutritional care. ITN promotion and use. Exercise and recreation. 

Cohort 4 Adolescents (13 ‐ 24 years)  

TT2 in schools. RH and HIV/AIDS/STI counseling. Substance abuse counseling. Adequate nutritional care. Accident prevention. RH/FP services. Exercise and recreation. 

Cohort 5 Adults (25 ‐ 59 years)  

Annual screening and medical examinations. Accident prevention. FP/RH services. Healthy lifestyles (exercise, recreation, nutrition, etc.). 

Cohort 6 Elderly  

Annual screening and medical examinations. Exercise and the promotion of general hygiene. Social/emotional/community support. 

Page 49: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

43

 E.  Theory of Change Prepared by Project Team During Implementation 

Activities  Outputs  PDOs/Outcomes  Long‐Term 

Outcomes 

Component 1: Delivery of quality essential health and nutrition services and utilization by women and children especially among poor and drought affected populations 

                     Reduction in Maternal and Child Mortality  Reduced Burden of diseases Universal Health Coverage  

HSSF grants to primary health facilities (US$ 34 M)  

Primary health facilities receiving HSSF grants in time 

Effective delivery of essential health services 

Health Sector Governance and Stewardship (US$ 12 M) 

Facility management committees in place and meeting regularly  Health personnel trained 

Health facilities meeting core staffing and financial management requirements   

Supply of Nutrition Commodities in Drought affected districts (US$ 12.8 M) 

Delivery of nutrition services to malnourished children and pregnant mothers 

Severely malnourished children receiving treatment recovered 

Introduction of Results Based Financing in Arid and Semi‐Arid Counties (US$ 25 M) 

Facilities implementing RBF initiatives  

Improved Outpatient attendance; Institutional deliveries; Immunization coverage  Women receiving free delivery services meeting the quality norms at public health facilities  

Piloting Health Insurance Subsidy Program (HISP, US$ 36 M) 

Poor households enrolled for health insurance subsidies  

Poor households receiving health insurance subsidies 

Component 2: Effectives of planning, financing and procurement of pharmaceutical and medical supplies 

Improved availability of Essential Health Commodities (US$ 48 M)  

Timely reimbursement to KEMSA documented claims by Ministries of health 

Primary health facilities placing orders during previous quarter   

Strengthening reforms to enhance efficiency and transparency of KEMSA US$ 6 M 

KEMSA signs Performance contract  Reforms in KEMSA – Procurement Manual; On‐line LMIS 

Share of planned procurement completed by KEMSA in the financial year  

Increased availability of essential health commodities to drought affected areas (US$ 44 M) 

On‐time delivery of drugs and medical supplies to primary health care facilities  

Value fill rate of orders for commodities for Primary Health Care facilities received by KEMSA either from Counties or facilities 

 

Page 50: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

44

F. HSSP SWAp Arrangements 

 The project was designed for implementation under a Sector‐Wide Approach (SWAp) arrangement.  As part of the arrangement, the government and partners signed a Code of Conduct and specified the mechanisms  for  the  implementation  of  the  Joint  Program of Work  and  Funding  in  the  Joint Financing Agreement  (JFA).   The JFA established the  joint provisions and procedures  for  financial support  through pooling of  resources  from partners  and  the GOK  for  the  implementation of  the NHSSP II. It also served as a coordination framework for consultation between Signatories. The main partners were: World Bank, USAID, DANIDA, JICA, the German Development Cooperation and the UN Agencies.   The SWAp coordination structures included the Joint Interagency Coordinating Committee (JICC) at the Ministers’ level, the Health Sector Coordinating Committee (HSCC) at the Permanent Secretaries’ level, and the HSCC Steering Committee (HSCC‐SC). The day‐to‐day work was coordinated by a SWAP Secretariat  supported  by  different  Interagency  Coordination  Committees  (ICCs)  established  as technical‐level and systems‐support forums for discussions of programs in various areas including: Procurement and Supply Chain Management  ICC, Community Services  ICC, Human Resources  for Health ICC, Health Sector Financing ICC, and Public‐Private Partnership ICC.   Under the framework partners were to pool funding using any of the five JFA baskets: Health Sector Support Fund, Essential Medicines and Medical Supplies, Human Resources for Health, Capacity and Systems Development, and the Hospital Management Services Fund. While several partners signed the code of conduct, only the World Bank and DANIDA signed the JFA. The project was meant to support  two  out  of  the  five  JFA  baskets:  Health  Sector  Support  Fund  (HSSF)  and  for  Essential Medicines and Medical Supplies. USAID on the hand had committed to: (i) strengthening of KEMSA, through:  (a)  leadership,  management  and  governance,  (b)  infrastructure  and  systems,  including LMIS,  (c)  technical  capacity  for  commodity  management  and  coordination  with  programs,  (d) operational  financing  for  distribution  and  warehousing;  (ii)  strengthening  of  MOH  commodity management,  through  (a)  technical  capacity  at  national  level,  (b)  coordination  for  commodity management at national level, (c) technical capacity at provincial (supervision), district (supervision and  management),  and  facility  level  (management);  and  (iii)  strengthened  pharmaceutical regulation.  Apart from the HSSF and essential medicines and medical supplies baskets, the other baskets: human resources for health, capacity and systems development, and the hospital management services fund did not materialize as originally envisaged. With the onset of devolution DANIDA also pulled out of the HSSF leaving the Bank as the sole partner financing the HSSF. Many of the other SWAp structures were equally affected and could not operate as previously envisioned.

Page 51: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

45

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION 

 

A. TASK TEAM MEMBERS 

 

Name  Role 

Preparation 

Supervision/ICR 

Gandham N.V. Ramana, Jane Chuma  Task Team Leader(s) 

Grace Nakuya Musoke Munanura, Dahir Elmi Warsame, Joel Buku Munyori 

Procurement Specialist(s) 

Josphine Kabura Kamau  Financial Management Specialist 

Lucie Muchekehu  Team Member 

Eva K. Ngegba  Team Member 

Suryanarayana Satish  Social Safeguards Specialist 

Yi‐Kyoung Lee  Team Member 

Kimberly Vilar  Team Member 

Joyce Cheruto Bett  Team Member 

Racheal Njeri Mwaura  Team Member 

Ocheng Kenneth Kaunda Odek  Team Member 

Toni Lee Kuguru  Team Member 

Angelina Darini Musera  Team Member 

Lilian Wambui Kahindo  Social Safeguards Specialist 

Diana Jemutai Sirma  Environmental Safeguards Specialist 

   

   

Page 52: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

46

    

B. STAFF TIME AND COST 

Stage of Project Cycle Staff Time and Cost 

No. of staff weeks  US$ (including travel and consultant costs) 

Preparation 

FY04  0  11,060.00 

FY05  13.425  77,635.56 

FY06  67.885  396,156.72 

FY07  87.232  430,310.45 

FY08  94.990  494,722.31 

FY09  43.255  202,695.43 

FY10  35.847  220,508.91 

FY11  0  2,980.47 

FY12  0  7,500.00 

Total  342.63  1,843,569.85  Supervision/ICR 

FY08  0     0.00 

FY11  37.997  214,688.28 

FY12  33.496  245,494.34 

FY13  21.613  250,544.53 

FY14  54.278  344,981.42 

FY15  63.625  450,324.13 

FY16  33.952  314,242.50 

FY17  35.156  220,074.24 

FY18  29.833  312,184.22 

FY19  10.150  71,422.23 

Total  320.10  2,423,955.89     

  

Page 53: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

47

ANNEX 3. PROJECT COST BY COMPONENT 

 

Components Amount at Approval  

(US$M) Actual at Project Closing (US$M) 

Percentage of Approval (US$M) 

Effective and transparent implementation of the Kenya Essential Package for Health (KEPH) through HSSF grants and performance streng thening. 

46  109.66  237 

Availability of essential health commodities and supply chain management reform 

54  98.10  181 

Total     100.00   207.76     207 

  

   

Page 54: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

48

ANNEX 4. EFFICIENCY ANALYSIS 

 Implementation Efficiency    1. Essential  Package  of  Cost‐Effective  Interventions.  The  project  was  designed  to  support implementation of the KEPH, a package consisting of cost‐effective interventions aimed at addressing the major causes of disease burden in Kenya.  The interventions were consistent with Kenya’s disease burden and  the World Health Organization  recommended  list  of  cost‐effective  interventions.  In  addition,  the 

project was  later  restructured  to  provide  nutrition  supplements  to  populations  affected  by  drought, 

focusing  on  children  under  five  years,  pregnant  and  lactating  women.  While  provision  of  food supplements is generally considered less cost‐effective and unsustainable, their provision is often justified during emergencies as part of the humanitarian response, which was the case with the project. Finally, the KEPH was designed as a national package, and as such, did not specify the category of services to be delivered by the different HF levels.   2. Equity. The  project was  designed  to  support  service  provision  at  Levels  2  and  3  HFs, where  the majority of  the poor  received  care, but did not  specify  the actual  target beneficiaries.    This was  later 

rectified when the project implementation was restructured to focus on children under five and women 

as well as the drought affected populations.  Furthermore, through the National Hospital Insurance Fund, the project supported the HISP, the government’s flagship program under Vision 2030 to provide the poor and  vulnerable  households  with  health  insurance  cover  reaching  181,315  of  the  181,968  targeted households,  representing  about  50  percent  of  orphan  and  vulnerable  children  (OVC)  households countrywide.   3. Use of existing systems. The project was designed  to operate under a SWAp and  to use existing 

national health systems including both public and private providers.  Unfortunately, the SWAp did not materialize as originally envisaged.  DANIDA and the Bank were the two partners to pool funds under the HSSF window. The arrangement however was short‐lived as DANIDA pulled out  in 2014. Similarly,  the initiatives to promote public private partnership did not take off and as such faith‐based providers were not brought on board.  4. Significant  Implementation  Delays.  The  project  experienced  significant  disbursement  delays  of 

funds. While was most pronounced at the health facilities, especially after the advent of devolution, all other entities  including KEMSA, KMTC, NHIF, AMREF and Kenya School of Government suffered major disbursement delays.  The implementation of activities by these entities not only started late due to delay with  signing memoranda of understanding,  implementation was  further  slowed down by  the delayed disbursements by the MoH.  After devolution, the Counties through the Council of Governors, took a long time  in  the  2013/14  and  2014/15  financial  years  before  signing  the memorandum  of  understanding (MOU) for the RBF and KHSSP conditional grants. These adversely affected the release of grants and led to non‐implementation of planned activities by the health facilities. While the project closing date was extended  twice,  implementation  of  the  RBF  continued  to  be  marred  by  challenges,  which  led  to reallocation of a significant share of funding ($44 million) originally earmarked for RBF for procurement of  essential  equipment  to  fill  critical  gaps  in  the  delivery  of  primary  health  services  and  nutrition commodities to respond to the protracted drought.   

Page 55: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

49

5. HSSF and RBF Implementation Challenges.  The two reforms were the hallmarks of the project. The 

devolution process greatly impacted implementation of the HSSF and RBF causing significant delays of between 3‐6 months in the release of the RBF and conditional grants to the facilities.  Attempts to ensure the  transfers  were  based  on  performance  were  unsuccessful.  The  introduction  of  devolution  also disrupted  the  supply  of  medicines.  Counties  were  no  longer  obliged  to  source  medicines  from  the government‐run KEMSA, which led to mismanagement and scarcity of drugs at health facilities.  Cost benefit analysis  6. Project specific economic evaluation was not undertaken for the project during appraisal. The ICRR however  includes an economic analysis at  the end of  the project  to estimate  the extent  to which  the project was able to yield economic and financial returns to Kenya by supporting the delivery of the basic package of essential health services. Since the major focus of the project was maternal health, the analysis assessed  the  extent  to  which  the  project  could  potentially  have  averted  maternal  deaths  over  its implementation  duration.    The  interventions  related  to  management  and  availability  of  essential medicines and supplies were assessed among the inputs towards reducing maternal mortality. Reduction in child mortality was excluded because the project’s contribution was considered minimal. Similarly, the provision of food supplements was excluded from the analysis for lack of data and the fact the rationale for the provision of supplements was mainly based on humanitarian concerns. The assumptions guiding the analysis are included in the Table below. 

Assumptions Guiding the CBA

1. Discount rate 3% 2 Sensitivity analysis (discount rate) 5%

3 constant relative rate of reduction of

maternal mortality per year 7%

4 Probability of deliveries with twins live births

14/1000

5 Annual per capita for the bottom 50%

US$1200

6 Real wage growth 5.85%

7. To estimate the number of deaths averted, the analysis compared maternal deaths between 2010 and  2018. The  base  case  scenario  of  the  number  of maternal  deaths without  new  interventions was compared against number of deaths upon instituting new interventions. Without any new interventions, it  is  estimated  that  about  64,096  maternal  deaths  would  have  occurred  between  2010  and  2018. However, with the new interventions implemented since 2010, it is estimated that only 48,625 maternal deaths could have occurred during the period thus saving 15,470 women.  This is however only partially attributable  to  the  project,  given  other  financing mechanisms  including  from  government  and  other donors. Attribution was estimated at 7.1 percent, or the project’s share in total public reproductive and maternal health expenditures as per 2016 national health accounts estimate.  

 8. Lives saved from these interventions were put into monetary value to be able to compare to total project cost and arrive at an internal rate of return and a benefit‐cost ratio. The average age of women giving birth in Kenya is 22 years. Women who survived were expected to earn an annual income of USD 

Page 56: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

50

1,200 which is the average income of the bottom 50 percent which is associated to the project target group rather than per capita GDP or GNI. Real wage growth was estimated to be 5.85 percent annually, or  at  the  rate  of  long‐term  economic  growth.  Furthermore,  it  is  about  half  the  value  of  the  official minimum  hourly  wage  at  1.15  (which  would  result  in  an  annual  income  of  USD  2,208). Women  are expected  to  earn  this  income until  their  life  expectancy  of  67  years.  This  figure was  discounted  by  3 percent to arrive at a net present value.  

9. Given the estimated net cash flow in terms of income of lives of mothers whose lives would have been saved, the estimated internal rate of return stands at 9.9 percent. At the given discount rate of 3 

percent, the net present value of the total investment equals to USD $60,912,114.67 or a benefit cost 

ratio of 1.74:1. Sensitivity analysis was conducted by elevating  the discount rate even  further up to 5 percent, which still yields a positive return at USD$3,410,258.54 or a benefit cost ratio of 1.04:1.   Sustainability  10. The Project was executed using country systems, did not finance new health infrastructure outside 

the existing health facilities and focused on building institutional capacity at county and facility levels.  Most staff (technical officers in financial management and HFMCs) trained under the project continue to serve in their respective capacities.   With the systems for procurement and supply chain management using automated Enterprise Resource Planning Program, KEMSA has become more successful as a public‐sector procurement agency.   The devolution disrupted the RBF and HSSF fund flow arrangements, but created a new mechanism for intergovernmental fiscal transfers, which provides a good opportunity for government  and  partners  to make  direct  transfer  of  funds  to  health  facilities.    It was  noted  that  the government and partners are continuing to engage in discussions on how best to support the health sector in the current decentralized context.    11. GoK has  substantially  increased  funding  to  the  health  sector  to  support  the  flagship  programs under the UHC agenda. This is reflected in the share of the budget allocated to health by the Counties, which has increased from an average of 13 percent in FY2013/14 to 25.2 percent in FY2014/1537.  Building 

on the project, the Bank prepared a follow‐on project “Transforming Health Systems for Universal Care Project” (P152394, $191.1 m) to continue support to the Kenya Health system. To obtain funding from the new Project, counties are required to allocate at least 20 percent of the county budget to health and maintain sustained increases in budgetary allocations to the health sector in the subsequent years. 

       

   

37 MoH. 2017. 2016/2017 National and County Health Budget Analysis Report. 

Page 57: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

51

   

ANNEX 5. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS 

 The Client’s Report 

Project Development Objectives 

1. The objective of the project was to improve: (i) the delivery of essential health services for Kenyans, especially  the  poor;  and  (ii)  the  effectiveness  of  planning,  financing,  procurement  and  logistics  of pharmaceuticals and medical supplies.   Key Expected Outcomes and Outcome Indicators  2. The project  identified seven key performance/outcome  indicators and five  intermediate outcome (IO) indicators. The key project indicators were:  (i) direct project beneficiaries (number) of which female 

(percent); (ii) health facilities (level 2‐4) without one of 14 tracer drugs at any point between delivery intervals  (percent);  (iii)  children  immunized  (number, disaggregated  for Northeast Province);  (iv) HSSF facilities meeting core FM requirements of the fund (percent); (v) timely payment to suppliers by KEMSA, based  on  agreed  procurement  contracts;  and  (vi)  facilities  displaying  quarterly  information  on  funds received and availability of drugs at facility level (levels 2 and 3) (percent).  The expected outcomes were primarily improved maternal, neonatal and child care as well as health systems strengthening.   Project Components  3. The project consisted of two components:  

a) Effective and transparent implementation of the Kenya Essential Package for Health (KEPH) through HSSF  grants  (US$32.6 million)  and  performance  strengthening  (US$11.8 million)  totaling  US$44.4 million for Component 1; main activities supported were generating and providing sufficient resources for implementing each facility’s AOP to address preventive, promotive and curative services at levels 1,2  and 3,  and  to  account  for  them  in  an  efficient,  and  transparent manner  according  to  current government  systems;  supporting  capacity  building  in  the  management  of  health  facilities; Strengthening voice and accountability, linked especially to the HSSF; Supporting the KEPH through the phased implementation of health financing reforms through selective pilots, capacity building and evaluations; Supporting the KEPH referral system; Strengthening environmental standards through support to waste management; and Strengthening sector governance structures through support to the SWAp Secretariat.   

b) Availability  of  essential  health  commodities  US$48 million  and  supply  chain management  reform US$7.6  million  totaling  US$55.6  million  for  component  2.  Main  activities  were  to  support implementation  of  initiatives  to  strengthen  the  Supply  Chain  Management  for  Essential  Health Commodities through (i) increased funding for essential commodities and (ii) supporting reforms in KEMSA. 

 Status of implementation at completion  

Page 58: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

52

4. Most of the scheduled activities had been completed by June 2018 and no new activities have since been  initiated.  The Ministry  has  focused  on  finalizing  payments  and  continues  to  implement  priority activities using government resources as the project objectives remain relevant to date. The following key 

outputs have been attained: Primary health facilities receiving HSSF grants on time, Facility management 

committees  in place and meeting  regularly, Health personnel  trained, delivery of nutrition  services  to malnourished children and pregnant mothers,  facilities  implementing RBF  initiatives, poor households enrolled for health insurance subsidies, timely reimbursement to KEMSA documented claims by MOH, on time delivery of drugs and medical supplies to primary health care facilities and reforms in KEMSA.  Achievement of Project Development Objectives and Analysis of the Results Framework  5. 6 out of the 7 Project Development Objective indicators surpassed the end‐of‐target and 4 out of 5 Intermediate objective  indicators  surpassed  the  targets.  Two  indicators  that did not achieve  target:  i) 

number of children immunized; and ii) Facility management committees having quarterly meetings with 

minutes  of  meetings  (levels  2  and  3)  (percent)  never  achieved  the  target  due  to  issues  relating  to governance and management  in a devolved system resulting  inequities  in access and distribution. The detailed Results Framework (RF) is presented separately below.  

Project Development Objective Indicators  

Indicator Name  Baseline  2013‐2014  2014‐2015 

2015‐2016  2016–2017 

2017–2018 

End Target 

Direct  Project beneficiaries 

25,896,000  38,327,054 

39,499,288 

34,670,439  44,275,435 

50,949,459 

35,000,000 

(a) Female beneficiaries 

14,229,369  21,263,422 

22,076,154 

24,065,319  18,356,514 

34,447,148 

17,500,100 

(b) Beneficiaries from  drought affected areas 

0  7,820,890  5,806,659 

9,359,722  

14, 365,881  

15,088,032  

5,500,000 

 Children  Fully immunized 

1,188,698  1,090,751  1,110,212 

1,142,374  1,107,604 

1,105,234 

1,298,058 

Value  order  fill  rate  of orders  for  commodities from Primary Health Care facilities  received  by KEMSA  

73%  95%  87%  90%  87%  83%  80% 

Severely  malnourished children  under  five receiving  treatment recovered 

60%  79%  67%  58%  56%  

84%  60% 

Share  of  planned procurement  from EMMS  pool  completed by KEMSA in the financial 

0%    75%  100%  100%  100%  60% 

Page 59: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

53

year  as  per  GoK guidelines 

Women  receiving  free delivery services meeting the  quality  norms  at public health facilities  

453,857  630,355   717,442  784,846  670,575     

604,521  

550,000 

Poor  households receiving  health insurance subsidies 

0    Indicator introduced in 2014 

21,546  158,925  

181,968  30,000 

Key Intermediate Results Indicators 

Indicator Name  Baseline  2013/2014  2014‐2015 

2015‐2016  2016  –2017 

2017–2018 

End Target 

People  with  access  to  a basic  package  of  health, nutrition,  or reproductive  health services 

0  38,935,800 

41,800,000 

41,800,000  47,114,397 

47,848,479 

39,495,000 

Facility  management committees  having quarterly  meetings  with minutes of meetings 

27%  92%  90.1%  90%  88%  

83%  90% 

Health  personnel receiving  training (number) 

0  9,884  10,431  15,284  18,655  

19,271  

14,899 

Level  2‐3  facilities implementing  results‐based  financing initiatives  

0  89  89  1,627         1,770  

1,990   1,331 

Beneficiaries  receiving supplementary  feeding in  drought  affected areas.  

157,413  337,346  450,582  Support  on this ceased  

Support on  this ceased  

Support on  this ceased 

285,210 

Counties  placing  orders for  Essential  Medicines and Medical supplies  

16  16  47  47  47  47  30 

 

KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME  

A. KEY FACTORS DURING PREPARATION  

6. The project set realistic objectives for improving maternal, neonatal and children services along with 

health systems strengthening and improving planning, financing and procurement of pharmaceutical & 

medical supplies aligned with the national priorities. This was fully aligned with the MOH’s strategic plans (NHSSP II) as well as the sectoral context during appraisal which ensured smooth implementation of the 

Page 60: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

54

PDO. The clear and compelling rationale for Bank involvement was adequately reflected in the Project Appraisal Document. The project used national systems for monitoring, which ensured regular updates and sustainability.  

 B. KEY FACTORS DURING IMPLEMENTATION 

 7. Several  factors  affected  project  implementation.  These  factors  are  sub‐divided  into  five  main 

sections: (i) factors that positively affected project implementation; (ii) factors within MOH control that 

adversely  affected  implementation;  (iii)  factors  beyond  MOH’s  control;  and  (iv)  factors  beyond government’s control.  8. Factors that positively affected project implementation: 

a. The  domiciling  of  project  implementation  responsibility  under  the  HSSF/SWAp  Secretariat helped in mainstreaming administrative and coordination processes.  

b. The  deployment  of  a  project  coordinator  and  other  key  staff  (which  was  a  legal  covenant), ensured adequate attention, administration, supervision and monitoring of the project;  

c. The  Bank’s  independent  audits  helped  establish  credibility  and  ensure  greater  accountability, while Bank support for fiduciary functions helped strengthen capacity; 

d. MOH’s proactive disclosure of information (for example, disclosing the names of the people who received  scholarships  and  naming  the  suppliers  providing  defective  equipment)  promoted transparency and accountability; 

e. The  project  financed  procurement  of  vehicles  and medical  equipment  along  with  training  of relevant technicians. This greatly benefitted the project as it avoided the need for the equipment to be transported to the manufacturer/supplier and then taken back after repair; 

f. Use  of  SWAp  coordination  mechanisms,  particularly  the  thematic  technical  working  groups, ensured greater collaboration amongst  the stakeholders, avoided duplication of  interventions, resolved implementation bottlenecks, and promoted greater harmonization; 

g. Recruitment  of  HSSF  and  KHSSP  accountants  increased  accountability  for  funds  reaching  the primary health facilities and the District Health Management Team; 

h. The bi‐annual review missions carried out by the Bank jointly with the MOH, helped to establish credibility, enhance accountability and address any implementation gaps and issues at an early stage, while Bank support for fiduciary functions helped strengthen capacity; 

i. The  direct  cash  transfers  to  level  2  and  3  primary  health  facilities  through  the  Health  Sector Services Fund (HSSF) for employment of casual workers (clerks, guards, etc.), operational costs, and the maintenance and improvement (e.g. small repairs), and the provision of EMMs through the  “drawing  rights”  system  (leading  to  full  “pull”  system  for  EMMS)  helped  significantly  to improve overall functionality, general cleanliness and service delivery at the facilities; 

j. The active involvement of the beneficiary communities through quarterly HFMCs meetings and annual  meeting  of  stakeholders  to  review  past  performance,  identify  and  analyze  current problems, identify priorities, and plan (i.e. AOP) for outputs and activities to be undertaken during the next financial year ensured project ownership (making sure the project delivered on actual needs of the communities) and helped monitor progress; 

Page 61: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

55

k. Citizen engagement through committees linked to Health Facilities ensured ownership (making sure the project delivered on actual needs of the communities) and helped monitor progress; 

l. The project’s social accountability interventions and MOH’s proactive disclosure of information (such as the requirement for health facilities to display quarterly information on funds received and availability of drugs at facility level, i.e. levels 2 and 3 helped in promoting transparency and accountability; 

m. Efficient  and  prudent  use  of  project  proceeds.  Cost  savings  realized  from  project  activities, especially at KEMSA, were reallocated to other critical and relevant project activities, for example, the reallocation of funds for hire of a pre‐shipment inspection firm for quality assurance testing and  development  of  a Marketing  Plan  for  Supplementary  Services  Division  (SSD)  (which  was developed with the support of USAID); 

9. Factors within MOH control that adversely affected implementation:  

a. (a) inadequate planning for project activities, which led to delays and cost overruns, eventually resulting to the project not disbursing fully  

b. (b) Weak plans for procurement, due to inadequate specifications and insufficient participation of  the  user  departments  meant  that  equipment  supplied  to  some  of  the  facilities  were  not needed.  Due  to  limited  capacity  in  the  MOH,  particularly  for  preparing  comprehensive  cost estimates some of the supplies had awards given despite the contract price being high. The lack of a proper distribution plan as well as the need to do pre‐installation work at the facilities meant distribution  and  commissioning  was  almost  always  delayed  and  worsened  by  the  weak coordination in the devolved system  

c. (c) Greater efforts were needed to strengthen the health facility inventory systems, train staff in the use of new equipment procured, and to continue the mentorship program of health workers in the areas of Financial management  

d. (d) Frequent change for social safeguards officer in the project led to limited implementation of the VMPP 

e. (e) Absence of a communication officer in the Ministry/Project led to limited updates to the public about the project  

f. (f) Implementation of the two components was particularly hampered by devolution of the health system leading to delays in funds transfer to health facilities and stock‐out of essential medicines and commodities  

g. (g)  Inadequate  capacity  and  under‐staffing  for  the  unit  coordinating  KHSSP  procurements  for KHSSP caused the slow start to the rolling out of the HSSF, late disbursement of Project funds and lengthy delays in the implementation of the planned procurement activities, especially at the start of the project and  

h. (h) Inadequate management and coordination of the M&E functions as the hiring of a Technical Assistance to strengthen M&E capacity of KHSS Project was delayed and later dropped. 

10. Factors  beyond  MOH’s  control:  Lack  of  collaboration  between  MoH  and  Council  of  Governors resulted  to  reduced  allocation  and  transfer  of  funds  to  County  Governments  as  accountability  and utilization of funds could not be assured.   

Page 62: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

56

11. Factors beyond government’s control: unusual rain patterns disrupted implementation and delayed 

completion of some activities e.g. surveys and distribution of equipment that resulted to contracts being amended.   EVALUATION OF PERFORMANCE AND COMPLIANCE ISSUES  COMPONENT 1: EFFECTIVE AND TRANSPARENT IMPLEMENTATION OF THE KENYA ESSENTIAL PACKAGE FOR  HEALTH  (KEPH)  THROUGH  HSSF  GRANTS  AND  PERFORMANCE  STRENGTHENING  (US$44.4 MILLION).    12. Health  Sector  Services  Fund:    The  Project  supported  the  effective  implementation  of  the  KEPH, through  financing  the HSSF  targeted at health service delivery  levels 1, 2 and 3. The Government has 

established the HSSF as part of its efforts to delegate power and responsibility for health service provision to  the  community,  as envisaged by  the NHSSP  II.  The HSSF  improved  the delivery of quality essential services,  especially  at  the  sub‐district  and  community  levels,  in  an  equitable  and  efficient  manner, through:  (i) generating and providing sufficient resources for implementing each facility’s AOP to address preventive, promotive and curative services at levels 1,2 and 3, and to account for them in an efficient, and  transparent  manner  according  to  the  current  government  systems;  and  (ii)  supporting  capacity building in the management of health facilities.     13. The Results Based Financing was  implemented  in 20 ASAL Counties plus Migori. Overall, Counties 

reported  an  increase  in  utilization of  the  10  key maternal  and  child  health  services with  progressive improvement in quality of health services. Further, the project procured medical equipment to ensure Health Facilities are ready to provide the essential health services as per the KEPH.   14. Through additional financing and project restructuring, the project procured nutritional commodities that reduced significantly the effects of drought through prevention and management of malnutrition. The support provided since 2013 has significantly averted child deaths in the affected areas.     15. HSSF and Health Sector Governance and Stewardship:  The two health ministries were strengthened 

selectively in some of their main governance and stewardship functions, especially at the district level, to enhance service delivery and ensure a strong poverty focus.  This was done in conjunction with other DPs through:   16. Strengthening voice and accountability, linked especially to the HSSF.  This included various activities, 

such as  information dissemination and use of  report  cards;  the  close monitoring of  the demand  side 

indicators in the results framework, including for the performance of the KEMSA; the establishment of effective complaints mechanisms; and independent external monitoring and auditing of performance and results.  An  independent  integrated  fiduciary  implementation  review  agent  to  check  compliance  with procedures, monitor procurement and carry out performance audits throughout the project life mitigated several  fiduciary  risks  especially where  internal  controls  lacked  and  the  high  turnover  of  government officers where handover was not properly done.   17. Supporting the KEPH through (i) The phased  implementation of health  financing reforms through piloting and scale‐up of Health Insurance Subsidy Program for the Poor that resulted to at least 177,815 Households accessing outpatient and inpatient services in accredited public and private health providers. In addition, pre‐screening  for various ailments was  introduced as a  result of  the  support  and  is being applied  in  all  insurance  schemes  provided  by  the  NHIF  to  ‐date;  (ii)  selected  capacity  building  and 

Page 63: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

57

evaluations  related  to:  (a)  training  for  Kenya  Enrolled  Community  Health  Nursing  that  provided  full 

scholarship for 400 students from ASAL counties and marginalized populations to address critical service delivery gap; (b) training of Health Facility Management Committees initially planned for in 47 Counties but due to logistical challenges and budget constraints, the project focused on the 21 RBF Counties that saw an increased knowledge and skills on various areas and processes in running of a Health Facility in the selected Counties; and (c) Capacity building of health financing institutions in the provision of Financial Management  course  in  the  wake  of  devolved  functions.  This  enabled  for  better  accountability  and transparency  in  the  administration  of  resources  in  the  Health  Sector.      These  also  included  activities related  to analytical  studies  to support  the detailed planning and  initial  implementation of  the health financing strategy as well as the collection of data on expenditure to inform utilization of health services.  COMPONENT  II:  AVAILABILITY  OF  ESSENTIAL  HEALTH  COMMODITIES  AND  SUPPLY  CHAIN MANAGEMENT REFORM (US$55.6 MILLION)  18. This  component  was  implemented  in  parallel  with  the  HSSF.  Generally,  there  was  improved 

availability of commodities at  the  lower  levels of  the public health system. This  further enhanced the quality  of  care  provided  as  frequent  shortages  and  stock‐outs  have  been minimized.  The  constraints related to flow of funds from MoH have reduced significantly with KEMSA being capitalized at over Kshs 6 Billion. The order fill rate received from counties constantly remained above 85% and all 47 Counties are now using Logistic Management Information System to place orders on‐line. The order turnaround time for primary health care facilities is now around 8 days.  19. KEMSA has sustained key reforms implemented as part of KHSSP. The KEMSA Board continues to have  independent  members  and  institutional  integrity  mechanisms  put  in  place.  To  support  the procurement of EMMS commodities and the reform process, the Project will further strengthen KEMSA and the Ministry of Health in the key functions of planning, procuring and managing critical commodities, in conjunction with other DPs.    20. Environmental: The project was classified as environment category “B” and it triggered one of the World Bank’s Operational Policies, 4.01 relating to Environmental Assessment due to the potential impact caused  by  medical  waste.  The  project  complied  with  the  World  Bank’s  environmental  and  social 

safeguards requirements. The MOH prepared an HCWM plan to guide health facilities to manage medical 

waste effectively. While most of the health facilities segregated medical waste using color‐coded bins as required, final disposal was mainly carried out using open burning by the health centers as incinerators are only  located  in  the hospitals. However,  the  inadequate  capacity at  the health  facilities means  the HCWM plan is not being adhered to. More support is needed to ensure the HCWM plan is adequately implemented and monitored.   21. Social  accountability:  Client  charters  were  developed  and  translation  into  Kiswahili  and  local vernacular done. The printing of the service charters by the graphic designer was not done due to long procurement procedures against limited time. Guidance notes on translating client charters were issued to county VMG focal persons, the health facility in charges and the primary school teachers from adjacent 

schools  who  use  the  language  as  they  teach.  Focal  persons  were  invited  for  client  charters  who coordinated these activities conducted in three concurrent workshops held in Nakuru, Kilifi and Marsabit.  Besides, civil society organizations were engaged to strengthen citizen participation and engagement as they could also participate  in activities  like RBF community verification of  results. The monthly health 

Page 64: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

58

facility meeting of HFMC were also used for grievance redressal as suggestion boxes contents could be checked and discussed. In some HFs the MOH set‐up a helpdesk (customer Service desk) for Triage which have also capacity to serve as a “call center” for grievance redressal and client referral services. At present, the system has not developed adequate capability to record complaints and direct them to the relevant people and do not regularly inform the aggrieved of the action(s) taken.  22. Financial management (FM):   Quarterly  interim unaudited FM reports of acceptable quality were submitted in a timely manner. The external audit reports, to a large extent, have been clean. However, there were delays in processing payments mainly due to under‐staffing of the MOH’s accounting unit. Per agreements under the project, annual audits were undertaken by the Office of the Auditor General (OAG). Largely,  the  audit  reports  related  to  the  HSSF  have  been  questionable  as  potential  ineligibles  and disclaimer of opinion have been expressed. This mostly arising due to lack of human capacity by the office of the Auditor General to carry out audits in the Counties, while expecting MOH to have all the returns in the wake  of  devolved  health  functions  and  compounded  further  by  the  lack  of  HSSF  accountants  to 

provide  returns  as  most  of  them  had  either  been  absorbed  by  the  Counties  or  terminated  after devolution.  Under  RBF,  disbursements  to  counties  were  based  on  County  Allocation  of  Revenue  Act (CARA) provisions rather than performance. The initial disbursement to counties in February 2016 for RBF was based on estimates. Subsequent disbursements were to be based on output; however, the MOH was not able to do this as it was considered non‐compliance with the CARA. The NHIF implementing the HISP program  failed  to  share  quarterly  reports  with  MoH  as  required  by  the  program’s  monitoring  and evaluation  framework and plan. This ultimately affected transfer of  funds  to  the  institution. The NHIF should reconcile the HISP claims payment data per the operations cash book and the utilization data. The payments  for all  the  inpatient and special benefits package claims should be made and accounted for through the HISP operations account.  Issues raised in audit reports and other reviews were addressed especially ineligible expenditure amounting to KShs 229,785,262 and potentially ineligible expenditure of Kshs 1,166,120,469.  Further, MoH was unable  to  substantiate and  thus  refunded  the US$ 802,888.37 being outstanding undocumented advances under IDA Credit 4771.   

23. Procurement:  There were overall delays in procurement throughout the life of the project. By the end of the project, all procurement contracts signed both goods and consultancies were fully executed despite  the MOH  having  to  amend  several  contracts  towards  the  project  closure  date  as  a  result  of challenges of either failure to deliver consignment to final destinations due to flooding in hard to reach areas or delayed manufacturing that would result in equipment reaching final destinations after project closure date. The MOH has ensured the quality of goods received.   LESSONS   24. The project provides important lessons that are considered good practices, most of which have been incorporated in follow‐on operations:  

a. Ensure use of SMART indicators for which regular updates are available. Wherever possible, the RF should include indicators that are already being tracked by the government to avoid the need to  rely  on  additional  player(s)  for  reporting on  project’s  outcomes.  These  help  in  project monitoring and decision‐making. 

Page 65: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

59

b. Continuity and  in‐country presence of  the  task team aids project  implementation and ensures supportive supervision. The World Bank’s implementation support used independent validation, which ensured project efficiency and helped the MOH be on track. 

c. Embedding new initiatives within the existing government structure, helps ensure continuity and broad‐based ownership. In the case of HISP, the project helped advocate for allocation of funds under the UHC umbrella through the National Treasury after the closure of the project.  

 RECOMMENDATIONS  25. Effective planning and ensuring adequate capacity of the implementation unit to deliver on project activities early on can accelerate implementation. During fiduciary assessment of the project, attention should  be  paid  to  the  client’s  performance  and  capabilities  in  implementing  the  activities  and interventions and include appropriate mitigation in the project design, for example, provision of technical support early on  to help with planning, design and  realistic  costing. Similarly,  focal persons should be identified early, and adequate capacity put in place to deal with social and environmental issues. 

26. When  significant  investments  in  equipment  are  made,  adequate  budgetary  provisions—from 

government—should be made available for maintenance and incremental costs. Similarly, government should make provisions for the required HR to be trained in handling the equipment. This would ensure optimal  use  as  well  as  longer‐term  sustainability  and  continue  with  development  impacts  of  project interventions.  27. Subsequent projects should collaborate and work closely with the Council of Governors since the health sector is devolved and implementation of the KEPH is mainly by the county Governments.  ARRANGEMENTS FOR SUSTAINABILITY OF RESULTS  28. The preparation, design and implementation of the new project with related development objectives 

that have potential to propagate the roll out of the best practices e.g. THS‐UCP is using the Performance 

Based Financing approach to allocate resources to County Governments.  29. Riding  and  use  of  established  GOK  institutions  to  run  components  of  the  program  like  capacity building in Financial Management done by Kenya School of Government, Enrolled Community Nursing by KMTC has ensured continuity  in provision of  the curriculum and courses offered by the  institutions  to date.  30. The health interventions financed by the project are the Government of Kenya priorities which have 

some existing budgetary support e.g. Health Insurance Subsidy Program for the Poor. 

 

31. The  use  of  the  in‐Country  systems  and  staff  for  implementation  and monitoring  of  the  project 

enables  for system strengthening and capacity building e.g. hosting of  the new  innovations  in existing established portal e.g. the Web portal for RBF in the MOH DHIS and use of same staff for managing.  32. One of the Health Financing Strategies being employed under strategic purchasing towards achieving universal health care is Results Based Financing. This strategy will improve the quality of health services provided.

Page 66: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

60

The Government Comments on the ICRR 

 

1. The  GoK  appreciates  the  assessment  review  of  the  extent  of  execution  of  the  core  reforms 

supported by the project. 

2. The ICRR rating of Moderately unsatisfactory is unacceptable for a project whose performance 

throughout  the  course  of  its  implementation  has  mostly  been  satisfactory  /  moderately 

satisfactory. Further, the banks performance rating is satisfactory while M&E quality is modest. 

How is that possible? The Project disbursed up to 98%. How is the ICRR rating determined? The 

Governments view is that the rating is not consistent, it’s unfair despite most results having been 

achieved as per the Results Framework. 

3. The Project was implemented in a devolved system. What was the effect of devolution on the 

rating, performance etc.? An analysis of these should be provided to GoK. 

4. Use of  the  IIFRA  findings being  limited  is  agreeable especially  in  the devolved Health System. 

However, the IIFRA only towards the end of the project closure did exit meetings with County 

Governments. 

5. Involvement  of  Council  of  Governors  was  not  as  effective  as  the  County  Government 

representatives then did not appreciate the activities implemented under the Project which was 

ongoing. The reason being the Project was designed and Implemented before devolution hence 

County Engagement was minimal. 

6. GoK/MoH team in force at closure could be annexed 

7. Replace KEHP with KEPH (Kenya Essential Package for Health) in all areas in the document. 

8. Elaborate further on the effect of data quality issues and lack of data on the cost benefit analysis 

9. Considering the initiatives undertaken during the period were not able to positively impact on the 

per capita utilization rate, what measures were instituted to the follow‐on project (THS‐UCP) to 

ensure that increased access and utilization is registered at population level (vis a vis reporting on 

merely coverage of essential health services). 

Page 67: Document of The World Bank...report no: icr00004624 implementation completion and results report 4771‐ke, 5034‐ke and 5367‐ke on a credit in the amount of sdr 128.8 million (us$198

The World Bank Health Sector Support (P074091)

61

ANNEX 6. SUPPORTING DOCUMENTS (IF ANY)