document of the world bank · 12/15/2017 · 2015 budget law date achieved 12/31/2013 12/31/2016...
TRANSCRIPT
i
Document of
The World Bank
Report No: ICR00004366
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-H9370 AND IDA-D0830)
FOR AN
ECONOMIC GOVERNANCE REFORM OPERATION
(US$3.8 MILLION)
AND A
SECOND ECONOMIC GOVERNANCE REFORM OPERATION
(US$3.0 MILLION)
TO THE
UNION OF THE COMOROS
December 15, 2017
Macroeconomics and Fiscal Management Global Practice
Comoros Country Management Unit
Africa Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
ii
THE UNION OF THE COMOROS
GOVERNMENT FISCAL YEAR
January 1 – December 31
CURRENCY EQUIVALENT
(Exchange Rate as of November 30, 2017 Currency Unit = Comorian Franc (KMF)
US$1 = KMF 418
ABBREVIATIONS AND ACRONYMS
BCC Central Bank of the Comoros
CPS Country Partnership Strategy
CREF Economic and Financial Reforms Unit
DGCPT Direction Générale de la Comptabilité Publique et du Trésor
(Office of Public Accounting and Treasury)
DGRH Direction Générale des Resources Halieutiques
DeMPA Debt Management Performance Assessment
DPO Development Policy Operation
DSA Debt Sustainability Analysis
ECP Economic Citizenship Program
EDA Electricité de Anjouan (Electricity Company of Anjouan)
EGRG Economic Governance Reform Grant
ERDPG Economic Reform Development Policy Grant
ESRP Electricity Sector Recovery Project
GB Gigabyte
GDP Gross Domestic Product
HIPC Heavily Indebted Poor Countries
ICT Information and Communications Technologies
IDA International Development Association
IFC International Finance Corporation
IMF International Monetary Fund
INSEED National Institute of Statistics and Economic Studies and Demographic
MA-MWE Gestion de l’Eau et l’Electricité aux Comores (Water and Power Utility in Comoros)
MOF Ministry of Finance
PDOs Program Development Objectives
PFM Public Financial Management
RCIP-4 Fourth Phase of the Regional Communication Infrastructure Program
SCADD Sustainable Accelerated Growth and Development Strategy
TSA Treasury Single Account
Vice President: Makhtar Diop
Country Director: Resident Representative:
Mark R. Lundell Rasit Pertev
Global Practice Senior Director: Carlos Felipe Jaramillo Practice Manager: Mathew Verghis ICR Team Leader:
ICR Author: Shireen Mahdi Ana Lucia Armijos
iii
UNION OF THE COMOROS
Economic Governance Reform Operation
(P131688)
Second Economic Governance Reform Operation
(P150924)
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Program Performance in ISRs
H. Restructuring
1. Program Context, Development Objectives and Design ........................................................ 1
2. Key Factors Affecting Implementation and Outcomes .......................................................... 8
3. Assessment of Outcomes ...................................................................................................... 14 4. Assessment of Risk to Development Outcome ..................................................................... 25 5. Assessment of Bank and Borrower Performance ................................................................. 25
6. Lessons Learned.................................................................................................................... 28 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners....................... 29
Annex 1. Policy and Result Matrix …………………………………………………...………31
Annex 2 Bank Lending and Implementation Support/Supervision Processes.......................... 35 Annex 3. Borrower's Comments ............................................................................................... 37 Annex 4. Comments of Cofinanciers and Other Partners/Stakeholders ................................... 38
Annex 5. List of Supporting Documents .................................................................................. 39
MAP
iv
A. BASIC INFORMATION
Program 1
Country Comoros Program Name:
Comoros Economic
Governance Reform
Grant
Program ID: P131688 L/C/TF Number(s) IDA-H9370
ICR Date: 12/15/2017 ICR Type: 12/15/2017
Financing Instrument: DPL Borrower GOVERNMENT OF
COMOROS
Original Total
Commitment USD 3.80M Disbursed Amount USD 3.85M
Implementing Agencies: Vice-Presidency in charge of Finance of the Union of the Comoros.
Co-financiers and Other External Partners:
Program 2
Country Comoros Program Name: Comoros Second Economic
Governance Reform Grant
Program ID: P150924 L/C/TF Number(s) IDA-D0830
ICR Date: 12/15/2017 ICR Type: 12/15/2017
Financing Instrument: DPL Borrower GOVERNMENT OF
COMOROS
Original Total
Commitment USD 3.00M Disbursed Amount USD 3.09M
Implementing Agencies: Vice-Presidency in charge of Finance of the Union of the Comoros.
Co-financiers and Other External Partners:
B. KEY DATES
Comoros Economic Governance Reform Grant P131688
Process Date Process Original Date Revised / Actual Date(s)
Concept Review: 11/06/2013 Effectiveness: 05/16/2014
Appraisal: 02/10/2014 Restructuring(s):
Approval: 04/29/2014 Mid-term Review:
Closing: 12/30/2014 12/30/2014
Comoros Second Economic Governance Reform Grant P150924
Process Date Process Original Date Revised / Actual Date(s)
Concept Review: 09/02/2014 Effectiveness: 06/12/2015 06/16/2015
Appraisal: 03/16/2015 Restructuring(s):
Approval: 06/02/2015 Mid-term Review:
Closing: 12/31/2016 12/31/2016
C. RATINGS SUMMARY
C.1 Performance Rating by ICR
Overall Program Rating
Outcomes Moderately Satisfactory
v
Risk to Development Outcome Substantial
Bank Performance Satisfactory
Borrower Performance Moderately Satisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Overall Program Rating
Bank Ratings Borrower Ratings
Quality at Entry Satisfactory Government: Moderately Satisfactory
Quality of Supervision: Satisfactory Implementing
Agency/Agencies:
Overall Bank Performance Satisfactory Overall Borrower
Performance Moderately Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Comoros Economic Governance Reform Grant P131688
Implementation
Performance Indicators QAG Assessments (if any) Rating
Potential Problem Program
at any time (Yes/No): No Quality at Entry (QEA) None
Problem Program at any
time (Yes/No): No
Quality of Supervision
(QSA) None
DO rating before
Closing/Inactive status Moderately Satisfactory
Comoros Second Economic Governance Reform Grant P150924
Implementation
Performance Indicators QAG Assessments (if any) Rating
Potential Problem Program
at any time (Yes/No): No Quality at Entry (QEA) None
Problem Program at any
time (Yes/No): No
Quality of Supervision
(QSA) None
DO rating before
Closing/Inactive status
D. SECTOR AND THEME CODES
Comoros Economic Governance Reform Grant P131688
Original Actual
Major Sector
Agriculture, Fishing and Forestry
Livestock 6 6
Fisheries 6 6
Public Administration
Central Government (Central Agencies) 66 66
Information and Communications Technologies
vi
ICT Infrastructure 11 11
Energy and Extractives
Other Energy and Extractives 11 11
Major Theme/Theme/Sub Theme
Economic Policy 6 6
Fiscal Policy 6 6
Fiscal sustainability 6 6
Private Sector Development 4 4
Jobs 4 4
Job Creation 4 4
Public Sector Management 84 84
Public Administration 50 50
State-owned Enterprise Reform and Privatization 11 11
Transparency, Accountability and Good Governance 39 39
Public Finance Management 34 34
Debt Management 6 6
Public Expenditure Management 28 28
Urban and Rural Development 8 8
Rural Development 4 4
Rural Infrastructure and service delivery 4 4
Urban Development 4 4
Urban Infrastructure and Service Delivery 4 4
Comoros Second Economic Governance Reform Grant P150924
Original Actual
Major Sector
Public Administration
Central Government (Central Agencies) 78 78
Information and Communications Technologies
ICT Infrastructure 11 11
Energy and Extractives
Other Energy and Extractives 11 11
Major Theme/Theme/Sub Theme
Economic Policy 6 6
Fiscal Policy 6 6
Fiscal sustainability 6 6
Public Sector Management 84 84
Public Administration 50 50
Administrative and Civil Service Reform 11 11
E-Government, incl. e-services 11 11
Transparency, Accountability and Good Governance 39 39
Public Finance Management 34 34
Debt Management 6 6
Public Expenditure Management 28 28
vii
E. BANK STAFF
Comoros Economic Governance Reform Grant P131688
Positions At ICR At Approval
Vice President: Makhtar Diop Makhtar Diop
Country Director: Mark R. Lundell Mark R. Lundell
Practice Manager/Manager: Mathew A. Verghis John Panzer
Task Team Leader: Shireen Mahdi Rafael Munoz Moreno
ICR Team Leader: Shireen Mahdi
ICR Primary Author: Ana Lucia Armijos
Comoros Second Economic Governance Reform Grant P150924
Positions At ICR At Approval
Vice President: Makhtar Diop Makhtar Diop
Country Director: Mark R. Lundell Mark R. Lundell
Practice Manager/Manager: Mathew A. Verghis Mark Roland Thomas
Task Team Leader: Shireen Mahdi Shireen Mahdi
ICR Team Leader: Shireen Mahdi
ICR Primary Author: Ana Lucia Armijos
F. RESULTS FRAMEWORK ANALYSIS
Program Development Objectives (from Program Document)
The Development Objective of this DPO series is to strengthen economic management, promote transparency, and
enhance performance in the electricity and ICT sectors. The operation is designed around three pillars: (i)
strengthening economic management; (ii) improving transparency in economic management; and (iii) improving
competition and management in key infrastructure sectors.
Indicator(s)
P131688 - Comoros Economic Governance Reform Grant
P150924 Comoros Second Economic Governance Reform Grant
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally Revised
Target Values
Actual Value Achieved at
Completion or Target Years
Indicator 1: Cash management plans integrating the Union and island treasuries are operational
Value
quantitative or
Qualitative
No integrated plans
Integrated plan
updated
Cash management plans
integrating the Union and
Island Treasuries are
operational and have been
incorporated to the budget
law.
Date achieved 12/31/2013 12/31/2016 12/31/2016
viii
Comments
(incl. %
achievement)
Achieved (100%) Treasury cash management plans are in place. The computerization of
public finances is a recent reality (2017) through the Integrated Financial Management
Information System (IFMIS) rollout with the accounting software SIMBA used since mid-
2016 for implementation by the Union and Island Governments of automate budget
execution, accounting, and reporting.
Indicator 2: Number of non-project central government bank accounts outside of the single account
framework reduced
Value
quantitative or
Qualitative
64 accounts
Less than 10
accounts
Starting in 2016 there are no
central government accounts
outside the Treasury Single
Account (TSA)
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Achieved (100%). The Memorandum of Understanding signed between the Ministry of
Finance and the Central Bank in November 2014, prohibited the opening and operating of
new bank accounts unless prior authorization from the vice-president responsible for
finances has been given. The implementation of this agreement played an important role
towards the elimination of accounts
Indicator 3: A computerized wage management system that integrates union and island civil service
operational
Value
quantitative or
Qualitative
Separate systems
operated for the
Union and Islands
An integrated
system that
consolidates
union and islands
civil service
operational
An integrated civil service
wage management system
for the Union and Islands is
operational
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Achieved (100%). The integrated personnel and payroll management system for the Union
and Island Governments is functioning since January 2016 through the operationalization
of the Government Human Resource Management Information System (GISE). However,
the gains in efficiency have not been fully obtained yet. As of March 2017, more than 95
percent of civil servants are paid through the automated payroll system.
Indicator 4: Public budget that includes detailed information on investment and recurrent expenditures
adopted
Value
quantitative or
Qualitative
There is no public
budget with
detailed
information on
investment and
recurrent
expenditures
Public budget
with detailed
information on
investment and
recurrent
expenditures
adopted
The Public Investment Plan
(PIP) is included in the
budget law starting with
2015 budget law
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Achieved (100%)The Public Investment Plan (PIP) is annexed in the budget law, starting
with the 2015 budget law
Indicator 5: Transparency and accountability of debt management has improved.
ix
Value
quantitative or
Qualitative
No regular debt
reports produced
and debt
management
framework
incomplete
Annual debt
reports produced
& all new loans,
guarantees/loan
renegotiations
conducted in line
with debt
management law
No self-standing debt
reports have been published
but an annual debt report
has been included in the
budget law since 2015.
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Partially achieved . The debt management bill was not adopted by the parliament. Since the
debt management bill was prepared and submitted to the National Assembly on October
13, 2014, an annual debt report has been prepared and included in the annual budget laws
of 2015, 2016 and 2017.
Indicator 6: National Accounts prepared using the 1993 methodology and National Statistics Institute
operational.
Value
quantitative or
Qualitative
Draft national
accounts for year
2007 using the
1993 methodology
prepared
National accounts
for 2013 using
the 1993
methodology
adopted
National Statistics Institute
is operational and has
completed the GDP
database for 2007-2015
using the SNA 93 in 2016
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Achieved (100%) The National Accounts until 2015 have been validated and adopted by
the Government in September 2017. INSEED has also delivered the preliminary NA for
2016 with the SNA 93 methodology.
Indicator 7: Number of cases completed by the anti-corruption commission and brought to court.
Value
quantitative or
Qualitative
15 cases
20 cases The anti-corruption
commission was dissolved
in September 2016
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Not achieved (0%) The new President that assumed power in May 2016 eliminated the
Anti-Corruption Commission on the grounds of inefficiency. However, the government has
not put in place a credible system for pursuing the fight against corruption nor has taken
specific measures to combat corruption. Indicator 8: Information on access granted for fishing activities systematically disclosed, with revenue
and its use
Value
quantitative or
Qualitative
Information not
systematically
available
Access to
information on
revenue and its
use regularly
documented and
disclosed
Information on fishing
activities is systematically
prepared and disclosed
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Achieved (100%) The Direction Generale des Ressources Halieutiques (DGRH)
systematically prepares the fishing activities information that is sent to the Economic and
Financial Refor Unit (CREF) for disclosure. The revenue generated by the fishing activities
is included in the budget law of 2015 and 2016
x
Indicator 9: Increase in the number of Telecom operators with a service license and reduction in the
monthly price per 1 GB of mobile data
Value
quantitative or
Qualitative
1 Telecom operator
and KMF 10,000
price
At least 2
Telecom
operators and
KMF 7,500 price
There are two telecom
operators: Comores
Telecom (national) and
Telma (private).
Telma’s price per 1GB per
month is 5000 KMF while
the Comores Telecom price
is 5250 KMF p/month for
1GB
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Achieved (100%) Telma Comores (private company) was awarded a license in December
2015 and began operations in 2016. Telecom was opened to the new operator but the
process was quite complicated and delayed.
Indicator 10: Increase in MA-MWE collection rates
Value
quantitative or
Qualitative
55 percent
65 percent The collection rate reached
79 percent and represents
the total amount collected
for electricity sales billed in
2016
Date achieved 12/31/2013 12/31/2016 12/31/2016
Comments
(incl. %
achievement)
Achieved (100%). The collection rate of the Electricity Company surpassed the expected at
end 2016, despite the low pace of reform. However, to make the gains sustainable, the
government, , is working with the World Bank and African Development Bank on a
longer-term strategy to strengthen the technical, management, and commercial capacity of
the entity.
G. RATINGS OF PROJECT PERFORMANCE IN ISRs
Comoros Economic Governance Reform Grant P131688
No. Date ISR
Archived DO IP
Actual Disbursements
(USD millions)
1 10/13/2014 Moderately Satisfactory Satisfactory 3.85
H. RESTRUCTURING (IF ANY)
Not Applicable
1
1. Program Context, Development Objectives and Design
1.1 Context at Appraisal
Country context
Comoros had been undergoing a prolonged period of political instability since its independence
from France in 1974, defined by struggles for political power and strained relations between the
national and island governments. Dialogue and constitutional reforms in the 2000s paved the way
for a gradual move to political stability, allowing three democratic transitions of power to occur in
the last decade. The return of political stability had been instrumental for building more stable
institutions and opened a window of opportunity for reform. Thus, since 2009, Comoros has
implemented a series of macro-stabilization and structural reform programs with support from
development partners, securing gains in fiscal consolidation and macroeconomic stability and
making advances in public financial and debt management reforms. These measures enabled the
country to reach the Heavily Indebted Poor Countries Initiative (HIPC) completion point in
December 2012 and allowed it to benefit from debt cancellation.
However, Comoros continued to be a poor and fragile island state with substantial coordination
challenges between the Union government and the three islands’ governments, a delicate political
context and significant political economy constraints. Also, the economy began stabilizing but has
weak growth due to its limited sources of growth, weak fiscal footing: low revenues, high recurrent
costs, a rising public wage bill, fiscal risks from weak public utilities and infrastructure
deficiencies. Poverty was, and still is, widespread and was estimated at 42.3 percent in 2014. The
narrow economic base and the low institutional capacity are major challenges to poverty reduction.
Much of the poverty problem lies in high unemployment, exacerbated by a high prevalence of
informality and low productivity of the economy, centered primarily on the export of a few
agricultural commodities, subject to terms of trade and price shocks associated with global market
fluctuation.
It was against this backdrop that the World Bank’s support to economic governance reforms was
conceived through a programmatic series of two development policy operations (DPO) aimed at
improving economic management and transparency and enhancing performance in key
infrastructure sectors. This was the first programmatic DPO for Comoros and followed a stand-
alone DPO approved in November 2012.
This Implementation Completion and Results Report (ICR) assesses the achievements of the
expected results of the programmatic series of Economic Governance Reform Development Policy
Operations to the Union of the Comoros. The DPO series intended to support the Government of
Comoros to strengthen economic management, improve transparency and improve competition
and management in key infrastructure sectors. The first operation (DPO1) of US$3.8 million was
approved by the World Bank’s Board of Directors on April 29, 2014 and disbursed upon loan
effectiveness on May 16, 2014. The second operation (DPO2) of US$3.0 million was approved on
June 2, 2015 and disbursed upon loan effectiveness on June 12, 2015. The second and last
operation in the series closed on December 31, 2016.
2
Macroeconomic context
At the inception of the DPO series, economic activity in Comoros had improved slowly since
bottoming out in 2009 and real GDP growth reached 3.5 percent in 2013 mainly driven by a good
agricultural harvest and increased investments in infrastructure and construction (Table 1).
However, the fiscal position continued to be fragile with limited room for maneuver, weak public
finance management systems, while transparency and accountability remained key constraints to
the development agenda. Fiscal performance remained too dependent on non-tax revenues and
grants, and the lack of a broader improvement in reducing major public expenses such as the wage
bill and in collecting taxes did not ensure fiscal sustainability in the medium term. Moreover,
growth and job creation continued to be held back by a high cost environment, particularly in
relation to securing reliable access to electricity and connectivity through modern
telecommunication services. Pressures relating to these factors, particularly difficulties in the
electricity sector, reduced the rate of economic growth to 2 percent in 2014.
Growth, deteriorated even further to 1 percent in 2015 due to electricity shortages and cuts to
investment when the non-tax revenues from the Economic Citizenship Program (ECP)1 declined,
placing further pressure on the overall envelope. The weak fiscal management and over reliance
on non-tax revenue from the economic citizenship program, the growing wage bill, added to the
ongoing crisis in the electricity sector and the slower-than expected implementation of the public
investment program, were the main factors behind the growth deceleration in 2015, below the
annual population growth rate of 2.5 percent. The government also started accumulating civil
service salary arrears as the public-sector wage and salary bill continued its upward trend reaching
9.1 percent in 2015. An unforeseen disbursement of a Saudi budget support grant of €40 million
by mid-December 2015, changed the fiscal picture for the year. It enabled the authorities to clear
the wage and salary arrears before the end of the year and record an overall fiscal surplus of 2.9
percent of GDP. This was a one-off disbursement; a fiscal deficit driven by underlying revenue
and expenditure pressures was expected in the subsequent years.
Following presidential elections in April 2016, a new president of the Union of Comoros was
sworn in late May. President Azali had been previously head of state during 1999-2006 and had
repeatedly declared that poor revenue collections, a high public sector wage bill, and corruption
are major challenges for his administration, thus, highlighting some of the challenges that the
economic governance DPO series had been seeking to tackle. He has also declared that he was
aware that persistent electricity shortages were significant obstacles to economic growth and
development in Comoros and that his administration was determined to overcome them as soon as
possible.
1 The Economic Citizenship Program (ECP) allows Comoros to offer citizenship to foreigners who reside
in partner countries. The partner government selects the candidates following a background check
conducted by the partner government. In exchange, Comoros receives a fee for each passport issued. In the
years, before the Economic Governance Reform DPOs were implemented, the revenue from the ECP had
become significant in relation to Comoros’ GDP. In 2012 it reached an impressive 5.6 percent of GDP.
3
Table 1: Comoros Main Economic Indicators and Central Government Operations 2013–2019
Main Economic Indicators (% of GDP)
2013 2014 2015 2016 2017 2018 2019
Actuals Projections
National Income and Prices
Real GDP growth (% change) 3.5 2.0 1.0 2.2 3.3 4.0 4.0
Real GDP per capita (% change) 1.0 -0.3 -1.3 -0.1 1.0 1.7 1.7
Inflation (% change, annual average) 1.6 0.0 2.0 2.0 2.0 2.0 2.0
Public Finance
Domestic Revenue (excl. grants) 15.4 14.5 16.5 14.4 16.0 16.5 17.0
Grants 27.4 9.4 15.1 8.4 8.3 7.8 7.7
Total expenditures (incl. net lending) 26.2 24.4 27.3 29.9 30.8 28.1 28.5
Domestic primary balance -1.5 -2.0 -1.4 -3.5 -2.9 -1.4 -1.3
Overall balance (incl. grants) 15.1 -0.8 2.9 -6.4 -7.3 -3.8 -3.8
External Sector
Current account balance -8.1 -8.6 0.6 -9.3 -10.1 -10.6 -10.8
Exports of goods and services 14.9 16.3 17.1 17.3 17.4 17.4 17.4
Imports of goods and services 57.0 49.7 45.5 47.4 47.8 46.9 46.0
Remittances 25.3 21.6 18.4 18.0 17.6 17.1 16.6
Gross reserves (months of imports) 5.4 6.6 9.1 7.2 6.6 6.3 6.1
External debt
External debt (in percent of GDP) 16.1 20.2 24.2 25.4 27.7 27.3 26.9
External debt service (in % of exports) 2.0 0.5 0.3 1.8 2.0 2.4 2.6
Central Government Operations (% of GDP)
Revenue and grants 42.8 23.9 31.6 22.7 24.3 24.3 24.7
Revenue 15.4 14.5 16.5 14.4 16.0 16.5 17.0
Tax revenue 12.0 11.8 11.1 12.0 12.9 13.4 13.9
Non-tax revenue 3.4 2.7 5.4 2.4 3.1 3.1 3.1
Grants 27.4 9.4 15.1 8.4 8.3 7.8 7.7
Of which: Budget support 1.6 1.5 9.0 0.5 0.5 0.0 0.0
Project grants 7.6 7.8 6.1 7.8 7.8 7.8 7.7
HIPC grants 18.2
Total expenditure 26.2 24.4 27.3 29.9 30.8 28.1 28.5
Current expenditure 14.8 16.4 17.3 17.4 16.1 15.8 15.6
Wages and salaries 7.6 8.5 9.1 9.0 8.4 8.1 7.9
Goods and services 3.7 4.7 4.6 4.4 3.7 3.7 3.7
Transfers and pensions 2.1 2.0 2.6 2.5 2.5 2.5 2.5
Capital expenditure and net lending 11.4 8.0 9.9 12.6 14.8 12.2 13.0
Capital expenditure 10.9 8.0 8.4 10.7 13.0 12.2 13.0
Net lending 0.5 0.0 1.5 1.9 1.8 0.0 0.0
Overall balance w/ grants
(commitment) 16.0 -0.5 4.4 -7.2 -6.5 -3.8 -3.8
Domestic primary balance -1.5 -2.0 -1.4 -3.5 -2.9 -1.4 -1.3
Change in net arrears -0.9 -0.2 -1.6 0.8 -0.7 0.0 0.0
Overall balance w/grants (cash) 15.1 -0.8 2.9 -6.4 -7.3 -3.8 -3.8
Financing -16.9 2.0 -1.4 6.4 3.1 1.3 1.4
Domestic financing (net) 1.6 1.1 -4.7 3.2 0.0 0.0 0.0
Foreign financing (net) -18.5 0.9 3.3 3.2 3.1 1.3 1.4
Drawings 0.0 0.0 3.2 4.0 3.8 2.1 2.2
Amortization -18.5 0.7 -0.1 -0.6 -0.7 -0.8 -0.8
Sources: Government of Comoros; WB and IMF staff estimates.
4
1.2 Original Program Development Objectives (PDO) and Key Indicators
The original program development objective specified in DPO1 was: to (i) improve economic
management and transparency, and (ii) enhance competition and improve development
performance in key infrastructure sectors (ICT and electricity). The operation was designed around
three pillars: (I) Strengthening economic governance; (II) improving transparency in economic
management; and (III) improving competition and management in key infrastructure sectors.
(Table 2)
1.3 Revised PDO and Key Indicators, and Reasons/Justification
There were no revisions to the PDOs. But in the second operation (DPO2), the wording of the
PDO was more specific and better aligned with the three pillars of the operation. Moreover, the
reform focus was broadened to include two new indictors aimed at better coordinating the treasury
and cash management and strengthening the wage bill management. The second operation kept
the three pillars: (I) strengthening economic management; (II) improving transparency in
economic management; and (III) improving competition and management in key infrastructure
sectors. The outcome indicators expected to be achieved by the end of DPO1 and DPO2 series
follows:
Table 2: DPO Key Outcome Indicators – Original (DPO1) and Revised (DPO2)
DPO1 Indicators DPO2 Indicators
Pillar A: Strengthening economic management
Coordinating treasury and cash management
1. Cash management plans integrating the Union and
island treasuries are operational. (Baseline: No
integrated plans (2013); Target: Integrated plan
updated monthly (2015)
1.Cash management plans integrating the Union and island
treasuries are operational. (Baseline: No integrated plans
(2013); Target: Integrated plan updated monthly (2016).
2. Number of non-project central government bank accounts
outside of the single account framework reduced. (Baseline:
64 (2013; Target: Less than 10 (2016)
Strengthening the wage bill management
3.A computerized wage management system that integrates
union and island civil service operational. (Baseline:
Separate systems operated for the Union and Islands (203);
Target: An integrated system that consolidates union and
islands civil service operational (2016)
Improving budget comprehensiveness
2.Public budget that includes detailed information on
investment and recurrent expenditures adopted.
(Baseline: No public budget with detailed
information on investment and recurrent
expenditures (2013); Target: Public budget with
detailed information on investment and recurrent
expenditures (2015)
4.Public budget that includes detailed information on
investment and recurrent expenditures adopted. (Baseline:
No public budget with detailed information on investment
and recurrent expenditures (2013); Target: Public budget
with detailed information on investment & recurrent
expenditures (2016)
5
Improving debt management
3.Transparency and accountability of debt
management has improved. (Baseline: No regular
debt reports produced and debt management
framework incomplete (2013); Target: Annual debt
reports produced & all new loans, guarantees and
loan renegotiations conducted in line with debt
management law (2015)
5.Transparency and accountability of debt management has
improved. (Baseline: No regular debt reports produced and
debt management framework incomplete (2013); Target:
Annual debt reports produced and all new loans, guarantees
and loan renegotiations conducted in line with debt
management law (2016)
Strengthening statistical system
4.National Accounts prepared using the 1993
methodology and National Statistics Institute
operational.
(Baseline: Draft NA for year 2007 using the 1993
methodology prepared (2013) and no autonomous
National Statistics Institute 0perational. Target: NA
for year 2012 using the 1993 methodology adopted
(2015) and autonomous National Statistics Institute
is operational
6.National Accounts prepared using the 1993 methodology
and National Statistics Institute operational. (Baseline: Draft
national accounts for year 2007 using the 1993 methodology
prepared (2013); Target: National accounts for year 2013
using the 1993 methodology adopted (2016)
Pillar B--- Improving transparency in economic management
Supporting the fight against corruption
5.Percentage of senior officials who filed their Asset
Declaration Form, publicly available on the CNLPC
website and/or in a national newspaper. (Baseline:
30% (2013); Target: 80 % (2015)
7.Number of cases completed by the anti-corruption
commission and brought to court. (Baseline:15 (2013);
Target: 20 (2016)
Enhancing transparency in the management of fisheries resources
6.Information on access granted for fishing activities
systematically disclosed, with revenue and its use
documented in the budget law. (Baseline:
Information not systematically available and
included in the budget law (2013); Target: Access to
information on revenue and its use regularly
documented and disclosed (2015)
8.Information on access granted for fishing activities
systematically disclosed, with revenue and its use
documented. (Baseline: Information not systematically
available (2013); Target: Access to information on revenue
and its use regularly documented and disclosed (2016)
Pillar C--- Improving competition and management in key infrastructure sectors
Enhancing competition in the ICT sector
7. Increase in the number of Telecom operators with
a service license and reduction in the monthly price
per 1 GB of mobile data (3G). Baseline: 1 Telecom
operator and US$20.81 price (2013); Target: 2
Telecom operators and US$15 price (2015)
9.Increase in the number of Telecom operators with a service
license and reduction in the monthly price per 1 GB of
mobile data (3G). Baseline: 1 Telecom operator and KMF
10,000 price (2013); Target: At least 2 Telecom operators
and KMF 7,500 price (2016)
Improving performance in the electricity sector
8.Reduction in total losses in the electricity sector.
(Baseline: 45% (2013). Target: 40% (2015)
10. Increase in MA-MWE collection rates. (Baseline: 55
percent (2013); Target: 65 percent (2016)
6
The reasons for the adjustments made to the outcome indicators under DPO2 are below:
Table 3: DPO1 and DPO2 Outcome Indicators - Reasons for the Adjustments2
2 The remaining four indicators (indicators #1, #4, #5, #6, #8 and #9 in DPO2) did not change. The language
of these indicators was amended to make them more specific or reflect the availability of the new
information on the baseline and target values (e.g., indicator #1, #6 and #8 in DPO2).
DPO1 Results Indicators DPO2 Results Indicators Notes
Pillar A: Strengthening economic management
Consolidating treasury and cash management
Number of non-project central
government bank accounts outside of the
single account framework reduced.
(Baseline: 64 (2013; Target: Less than
10 (2016)
This indicator was introduced to
measure the results of the functioning
& administration of a Treasury Single
Account (TSA) created following the
signing of a MOU between MOF and
CB in Nov 2014. This indictor
reflects a stronger policy measure for
deepening treasury coordination,
namely the TSA framework that
prohibits the opening & operating of
new bank accounts
Strengthening the wage bill management
A computerized wage management
system that integrates union and island
civil service operational. (Baseline:
Separate systems operated for the Union
and Islands (203); Target: An integrated
system that consolidates union and
islands civil service operational (2016)
The wage bill indicator was
introduced because wage bill
management was added as an area of
reform in DPO2, in response to
increased wage bill pressures
affecting the fiscal position.
Pillar B--- Improving transparency in economic management
Supporting the fight against corruption
Percentage of senior officials
who filed their Asset
Declaration Form, publicly
available on the CNLPC
website and/or in a national
newspaper. (Baseline: 30%
(2013); Target: 80 % (2015)
Number of cases completed by the anti-
corruption commission and brought to
court. (Baseline:15 (2013); Target: 20
(2016).
The corruption indicator was changed
because the original one was too
close to the actual prior action. The
revised indicator is more closely
aligned to the objective of the pillar.
Pillar C--- Improving competition and management in key infrastructure sectors
Improving performance in the electricity sector
Reduction in total losses in the
electricity sector.
(Baseline: 45% (2013).
Target: 40% (2015)
Increase in MA-MWE collection rates.
(Baseline: 55 percent (2013); Target: 65
percent (2016)
The electricity indicator was changed
to be more aligned with the expected
outcome of the reforms under the
electricity sector recovery plan, which
had a strong focus on improving
commercial management. So, the new
indicator aimed at increasing the
collection rates, linked to improved
commercial management.
7
1.4 Original Policy Areas Supported by the Program:
1. Strengthening economic management
In support of strengthening economic management under the first pillar, the DPO series sought to
support the implementation of the government’s reform program, aligned with the strategic
direction on the SCADD and other key strategies underpinning the government’s reform program
through:
Improving treasury coordination between the Union and Island governments through a
coordinating directorate for public accounts and treasury
Enabling better cash management by introducing a Treasury Single Account (TSA).
Strengthening the wage bill management by adopting harmonized computerized wage
management system for the civil services of the Union and Island governments
Improving budget comprehensiveness by integrating more information on revenues,
recurrent spending, budget execution and the public investment program in the budget
law;
Strengthening debt management through a debt management law; and
Strengthening statistical institutions and upgrading national accounts system to SNA 93.
2. Improving transparency in economic management
Under the second pillar, the DPO series sought to advance the transparency and anti-corruption
agenda by:
Publishing the list of public officials who have filed an asset declaration;
Giving more legal power to the anti-corruption commission to fight corruption by
strengthening the anti-corruption law; and
Systematizing the disclosure of fishing activities: licenses, access rights to national
waters, as well as related revenues and its allocation.
3. Improving competition and management in key infrastructure sectors
Under the third pillar, the DPO series sought to improve competition in the telecom sector and
strengthen management in the electricity sector by:
Enhancing competition in the telecommunication sector by launching a bidding process
for a second full-service license; and
Improving the performance of the electricity sectors by adopting a recovery and
development plan for the national electricity company MAMWE, that includes
commercial recovery and performance framework.
1.5 Revised Policy Areas
Policy areas were not revised
8
1.6 Other significant changes
The changes occurred are mentioned in section 1.3 under “reasons for adjustments”
2. Key Factors Affecting Implementation and Outcomes
2.1 Program Performance
The programmatic series consisted of two single-tranche Development Policy Operations
disbursed upon effectiveness, in the total amount of US$6.8. Table 4 provides key dates for the
DPO series.
Table 4. Key Dates of the DPOs
Operation Disbursed
Amount
Expected Release
Date
Actual Release
Date Release
DPO1 (P1316888) XDR 2.5 M 05/16/2014 05/16/2014 Regular
DPO2
(P150924) XDR 2.2 M 06/16/2015 06/22/2015 Regular
All the prior actions for both DPO1 and DPO2 were satisfactorily met before Board approval on
April 29, 2014 and June 2, 2015 respectively (see Table 5). The last operation of the series closed
on December 31, 2016.
As the series evolved, the changes made to the policy matrix in DPO2 were limited to two
adjustments. Out of the nine indicative triggers identified under DPO1, eight were converted into
prior actions for DPO2, one trigger was dropped and a new prior action was added. The new prior
action supported the strengthening of the wage bill management3 in response to mounting wage
bill pressures and accumulating salary arrears in 2015.
The trigger that was dropped was related to the reforms for enhancing transparency in the
management of fisheries resources. The authorities had made considerable progress towards
improved transparency of fisheries revenue based on the prior action under DPO1; further reforms
were not identified as a priority.
3 The prior actions sought to strengthen wage bill management through: (i) the integration of civil service
wages in the computerized wage management system; and (ii) the integration of biometric national ID
numbers in the computerized wage management system.
9
Table 5: DPO1 and DPO2 - Prior Actions and Implementation Status
DPO1 - Prior Actions Status
Pillar A: Strengthening economic management
Consolidating treasury and cash management:
A dedicated budget line for the Directorate of Public Accounts and Treasury is clearly identified in the
2014 Budget Law and the following key staff is appointed in accordance with the Recipient’s decree
no. 12-047/PR 29 February 2012 relating to DGCPT, including its General Manager (Directeur
Général), Coordinator (Coordonnateur), Managers of the three support services (Chefs des 3 Services
d’Appui), Treasurer of the Union (Trésorier Payeur Général) and Treasurer of each of the three
Autonomous Islands (Trésoriers Payeurs de chacune des trois Îles Autonomes).
The Recipient has included in its 2014 Budget Law four (4) previously off-budget accounts (comptes
de régies) recorded in the accounts of the Treasury, and has issued a decision (arrêté) containing a
complete list of accounts of the administrative entities of the Recipient (at the union and the
Autonomous Islands’ levels) in the Recipient’s central bank.
Completed
Completed
Improving budget comprehensiveness:
The Recipient has included in its 2014 Budget Law: (i) overall envelopes per ministry; (ii) the state of
execution of the 2013 budget until June 30, 2013 presented in the same format as the draft budget; and
(iii) data on government revenues (own resources and external resources) in the main headings of the
budget nomenclature, including data for Fiscal Year 2013
Completed
Improving debt management:
The Recipient has included in its 2014 Budget Law a detailed debt report analyzing the debt stock as
of October 31, 2013
Completed
Pillar B: Improving transparency in economic management
Enhancing transparency and efficiency on the fight against corruption:
The Anti-Corruption Commission (Commission nationale de prévention et de lutte contre la
corruption) has published, on its website and/or in a national newspaper, a list of public officials who
have filed their asset declaration, in accordance with the Recipient’s Decree no. 12-183/PR dated
September 15, 2012.
Completed
Enhancing transparency in the management of fisheries resources
The Recipient has signed and published a presidential decree to systematize disclosure of fishing
access rights to national waters attributed and related revenues as well as their allocation.
Completed
Strengthening statistical systems:
The Recipient has signed (after Cabinet review) and published a presidential decree for the
establishment of the National Council of Statistics.
Completed
Pillar C: Improving competition and management in key infrastructure sectors
Enhancing competition in the ICT sector:
The Recipient’s government has prepared and submitted to the National Assembly a draft information
and communication technology sector law that sets out a framework for market liberalization.
Completed
Improving performance in the electricity sector:
To reduce total losses in the electricity sector, the Recipient’s government has approved the terms of
reference for a recovery and development plan establishing clear objectives for results to be attained by
MA-MWE management and has initiated the procurement of the independent expert to prepare such
plan by the publication of a call for expressions of interest
Completed
10
DPO2 - Prior Actions Status
Pillar A: Strengthening economic management
Coordinating treasury and cash management:
The Recipient’s Directorate of Public Accounts and Treasury within its Ministry of Finance has become
operational through: (i) the identification of a dedicated budget line in the Recipient’s 2015 Budget
Law; and (ii) the appointment of the remaining core staff as required by the Recipient’s Decree no. No.
12-047/PR dated February 29, 2012, through the Recipient’s Arrete No.15-008/VP-MFEBICEP/CAB
dated March 28, 2015.
The Recipient’s Ministry of Finance and Central Bank have signed a memorandum of understanding
governing the functioning and administration of a Treasury Single Account at the Recipient’s Central
Bank, which memorandum of understanding, among other things, prohibits the opening and operating
of new bank accounts unless prior authorization from the Recipient’s vice-president responsible for
finance has first been obtained.
Completed
Completed
Strengthening wage bill management: The Recipient has strengthened wage bill management through: (i) the integration of civil service wages
in the computerized wage management system; and (ii) the integration of biometric national ID numbers
in the computerized wage management system.
Completed
Improving budget comprehensiveness:
The recipient has incorporated the public investment program in its 2015 budget law.
Completed
Improving debt management:
The Recipient has prepared and submitted to its National Assembly a debt management bill to
strengthen the Recipient’s debt management framework.
Completed
Strengthening statistical systems:
The Recipient, through its National Statistics Institute (L’Institut National de la Statistique et des
Etudes Economiques et Demographiques), has: (i) prepared a budgeted five year action plan that uses
the SNA 1993 methodology for the production of national accounts; and (ii) has completed data
collection for updating the Recipient’s 2011-2013 accounts.
Completed
Pillar B: Improving transparency in economic management
Supporting the fight against corruption:
The Recipient has enacted Law No.13-015/AU amending the Anti-Corruption Law, dated December
26, 2013, in order to, inter alia, strengthen the judicial powers of the Anti-Corruption Commission
(Commission nationale de prévention et de lutte contre la corruption).
Completed
Pillar C: Improving competition and management in key infrastructure sectors
Enhancing competition in the ICT sector:
The Recipient has launched a competitive bidding process to award a second full-service license in the
telecommunications sector.
Completed
Improving performance in the electricity sector:
The Recipient, through its Ministry in charge of Production, Environment, Energy, Industry and Craft,
has adopted a recovery and development plan of the MA-MWE Company that includes a commercial
recovery and performance framework.
Completed
2.2 Major Factors Affecting Implementation:
Adequacy of government’s commitment
The overall implementation of the DPO series was adequate with the Government committed to
the reform program, though there were factors that negatively affected program implementation.
11
These negative factors were: (i) the impact of the elections on the fiscal position: an increase in
spending occurred during this period; (ii) the new government changed policy focus to an
expansionary fiscal policy instead of a focus on more efficacy in spending; (iii) the new
government made extensive changes in management and technical personnel in the union and
island governments including the closure of the anti-corruption commission, which is affecting
capacity and continuity in the reform momentum; (iv) Comoros continue to present a very low
capacity for implementation: (v) Comoros has a staff-monitored program (SMP) with the IMF but
a disbursing program has not been possible partly because of the challenges listed above.
Notwithstanding the mentioned negative factors, the contribution of the DPO series to the
strengthening of economic management, improvement in transparency and improvement in
competition and management in key infrastructure sectors was positive and satisfactory, except
for two specific areas (debt management and the fight against corruption) where the intended
outcome was partially achieved or not achieved. Specifically, in debt management, the debt
management bill proposed to the National Assembly in October 2014 had not yet been adopted as
of November 2017. However, annual debt reports on central government debt management have
been regularly produced and annexed to the annual budget laws. On the fight against corruption,
the number of cases investigated and completed by the anti-corruption commission and sent to the
judiciary has not been achieved even though Comoros enacted in 2013 the Law No.13-015/AU
amending the Anti-Corruption Law, to inter alia, strengthen the judicial powers of the Anti-
Corruption Commission, enhance its independence and reinforce its authority. In September 2016,
the new President decided to dissolve the Anti-Corruption Commission on grounds of lack of
efficiency of the commission.
Soundness of background analysis
The DPO series was part of the Bank’s strategic engagement with the Government’s Program for
2012-2014 which was based on the Poverty Reduction and Growth Strategy Paper (PRGSP),
aimed at stabilizing the economy, promoting private sector growth and improving the delivery of
social services. The government strategy under the PRSP was followed by the Sustainable
Accelerated Growth and Development Strategy for 2015-19 (SCADD) that continued to support
the same themes, focusing on the productive sectors of agriculture, fisheries, trade and
infrastructure.
The DPO series also: (i) supported the Government’s Public Financial Management (PFM)
Reform Strategy for the period 2010-19 which was organized around modernizing the regulatory
framework; strengthening institutional capacity; rationalizing budget preparation; strengthening
budget execution; and increasing transparency through improved internal and external controls;
(ii) were aligned with the Government’s policy for the energy sector that lays out plans for sector
reform and recovery; (iii) supported the roadmap for the telecommunications sector reforms,
including the adoption of market-based mechanisms and good governance; and (iv) are aligned
with both strategic pillars of the Country Partnership Strategy for Comoros FY14-FY17, that is
increasing public sector capacity, growth and employment. Added to the support given by the DPO
to the country’s program, a positive factor affecting implementation was the coordination with
other WB technical assistance and investment projects, post HIPC reform momentum.
12
Relevance of the risks identified at appraisal
The factors that negatively affected program implementation are linked to the overall risks
identified under the DPO series, which although mitigated, affected the implementation of the
reforms in some form or another.
Political Risk
The electoral cycle posed significant political risks to the DPO series and the implementation of
Comoros’ broader reform program. The new administration that assumed office in May 2016,
recognized that faster reforms and urgent action on the budget were needed and adopted a set of
measures to improve revenue mobilization and reduce expenditures for the remainder of 2016.
Measures included cancellation of contracts of recently hired government employees, but as
mentioned earlier, the Government made extensive changes in management and technical
personnel in the union and island governments, affecting the capacity and continuity in the reform.
Opposition to reform risk
Some of the reforms supported by the operations stimulated stakeholder opposition in the design
and implementation stages. For instance, reform plans for the recovery of the electricity sector
required stricter enforcement of payment of bills that resulted unpopular as they were not
accompanied by an improvement in service provision.
Macroeconomic risk
Comoros’ macroeconomic and fiscal framework continues to be vulnerable to shocks that are
characteristic of small island economies. Commodity price shocks could be readily translated into
higher domestic prices given the extent to which consumption relies on imported goods,
particularly food and fuel. Global or regional economic downturns could yield a shock to
remittance flows and diminish employment opportunities abroad.
Institutional capacity risk
Weak institutional capacity affected the pace of implementation of some of the sector reforms
supported by the DPO series. Capacity constraints are typical in the case of small, fragile states
including the capacity to execute the budget. Institutions at the island level have particularly high
capacity constraints. These factors affected some of the actions supported by the programmatic
operations not allowing to be implemented as successfully as expected or in the agreed timeframe.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization:
Design
The DPO series policy matrix presented the pillars, sub-components and results indicators clearly
and these were well aligned with the PDO. Some indicators were revised during the preparation of
the second operation, as described in Section 1.3, and the adjustments enhanced the M&E
13
framework of the series. The design of the indicators to monitor DPO progress was adequate.
Overall, the indicators were well-selected, measurable, and clearly linked to the prior actions. The
result indicators identified baseline and targets in line with the expected program outcomes. They
were largely based on publicly-available data, however as the statistics system of the country is
weak. Both the policy matrix and the corresponding results indicators were prepared jointly with
the government counterparts, supporting the process of institutionalizing the monitoring and
evaluation (M&E) arrangements in the public sector.
Implementation
The Bank conducted regular supervision in collaboration with the government to ensure continued
implementation of the operations. The Bank’s supervision had great impact in the implementation
of DPO1 and DPO2 as the supervision was accompanied by technical assistance given to the
Economic and Financial Reforms Unit (CREF), responsible for monitoring reforms, reporting
progress and coordinating actions with all ministries and entities, including at the island level. The
technical assistance was intended to strengthen the monitoring and evaluation capacity of the
CREF who was expected to provide updates on progress of indicators, however this materialized
only for a few indicators and not with the expected frequency given constraints in the coordination
with the ministries and most of all with the Island entities.
Utilization
The DPO series promoted the use of the M&E arrangements. Regular monitoring and data
collection undertaken as part of the DPO series facilitated discussions with the Government on the
implementation of reforms and progress on the indicators. In particular, given that the statistics
system of the country was weak, the DPO selected readily available indicators that the government
already produced to facilitate monitoring and government decision making, Por instance, the
systematic preparation and disclosure of information of fishing activities (agreements, licenses,
revenues and its allocation) has contributed to improve the management of the fisheries resources
and accountability.
2.4 Expected Next Phase/Follow-up Operation:
Having set a foundation for economic governance reforms and a multi-sectoral approach to
development policy reforms, the economic governance reform series was followed by a stand-
alone DPO that seeks to further deepen the results. The follow-up DPO was designed as a
standalone in response to a government request to maintain the momentum for reform between the
end of the economic governance reform DPO series in mid-2015 and the expected inauguration of
a new government by mid-2016. Although the follow-on DPO underwent a concept note review
and has largely accomplished the implementation of its policy matrix, further progress has been
delayed by the weakening of the macroeconomic framework after the 2016 elections. Dialogue is
ongoing on the reforms areas supported by the economic governance DPO series through the
follow-on DPO series, technical assistance and World Bank investment projects. The country
strategy also provides for development operations to resume under a programmatic framework
from 2018 onwards.
14
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
Relevance of Objectives
Rating: Substantial
The program’s development objectives to assist the Government of Comoros to strengthen
economic management and improve its transparency; and improve competition and management
in key infrastructure sectors, continue to be as relevant today as they were when the DPO series
were designed. The key components of the DPO program were fully consistent with the
Government’s agenda and poverty reduction strategy (Accelerated Growth and Sustainable
Development Strategy 2015–2019); and with the pillars of the Country Partnership Strategy
(2014–2017). The relevance of the objectives is further highlighted by the fact that challenges in
economic management remain, especially in fiscal policy and public finance management. There
is need to further strengthen wage bill management, improve revenue collection, and improve
transparency. In addition, Comoros continues to have difficulties in increasing access to electricity,
and in advancing the development of its telecom sector – a driver of dynamism in many developing
countries. The 2016 IMF article IV report for Comoros, which includes a staff monitored program,
has been supporting the government efforts to address many of the challenges that the economic
governance DPO series was seeking to tackle. In effect, the new administration that took office in
mid-year 2016, recognizing that accelerated reforms and urgent action on the budget were needed.
adopted a set of measures to improve revenue mobilization and reduce expenditures for the
remainder of 2016, including cancellation of contract of recently hired government employees, as
well as measures to improve the supply of electricity.
Relevance of Design
Rating: High
The design was appropriate and relevant. It supported the implementation of core reforms in
Comoros’ CPS covering the period 2014-17 and in the Accelerated Growth and Sustainable
Development Strategy 2015–2019 (SCADD). The two main pillars of focus in the CPS, namely,
increasing public sector capacity to deliver results by building the capacity to mobilize and
effectively use public resources and strengthening the foundation for sustainable growth by
investing resources to address constraints to growth and job creation, particularly energy and
telecoms, are still at the center of the areas addressed by the DPO series. Similarly, the reforms
supported by the Accelerated Growth and Sustainable Development Strategy (SCADD) aimed at
addressing the productive sectors with a focus on agriculture, fisheries, trade and tourism, and
searching to enable environment through improved infrastructure are also part of the reforms
addressed in the DPO series.
In retrospect, the design could have benefited from a more active inclusion of Island government
authorities to promote faster implementation of reforms; and it would have also been good to
address revenue management in the DPO. At the initial stage when DPO1 was being designed,
Comoros still enjoyed revenue from the economic citizenship program. When this was suspended,
the weakness of the revenue base became even more clear. The Bank started doing analytical work
15
in this area to build a base of knowledge for future DPOs. Therefore, the follow-on stand-alone
DPO has a pillar on revenue.
Relevance of Implementation
Rating: High
Implementation arrangements were and continue to be relevant. As indicated earlier, the Economic
and Financial Reform Unit (CREF) was responsible for monitoring the reforms, reporting progress
and coordinating actions with all ministries and entities, including at the Island level. Although the
CREF has been instrumental in providing information, improvements could have been made to
maintain the flow of information throughout the implementation period as reporting was sporadic
and not always complete.
3.2 Achievement of Program Development Objectives
Overall Rating: Moderately Satisfactory
The overall Program Development Objective of strengthening economic management, improving
transparency in economic management and improving competition and management in key
infrastructure sectors, was overall achieved as evidenced by key results indicators. Although
economic management in Comoros continued to be weak, substantial progress has been achieved
in coordinating treasury and cash management; strengthening wage bill management; improving
budget comprehensiveness; strengthening statistical system; enhancing transparency in the
management of fisheries resources; enhancing competition in the ICT sector; and, improving
performance in the electricity sector. Meanwhile, less satisfactory progress has been achieved in
improving debt management and no progress was made in supporting the fight against corruption.
The sustainability of these achievements is supported by operational plans, such as for the treasury
and cash management; integrated management system, i.e., civil service wage management
system; the actual adoption of new methodology for the national accounts; the development plan
put in place for improving the performance of the electricity sector.
The PDO of the DPO series was evaluated using ten results indicators. Out of ten indicators, eight
were achieved (Indicators #1, #2, #3, #4, #6, #8, #9 and #10), while one indicator (#5) was partially
achieved and one indicator (#7) was not met. The results indicators and their status are discussed
in detail below.
Objective 1: Strengthening economic management
Rating: Moderately Satisfactory
16
Outcome Indicator 1: Cash management plans integrating the union and island treasuries are
operational from a baseline where no integrated plans existed (2013) to a target where
integrated plans have been developed and adopted within the budget laws (2016). Achieved
At the time when the DPO series were designed Comoros had taken important legal and
institutional steps towards improving public financial management. However, weak treasury
management continued to be a persistent challenge for the effective management of public
resources. The National Assembly had adopted the Public Financial Management Law in 2012
providing more clarity on the roles and responsibilities of the federal government and autonomous
islands for the management of public finances. The authorities had also adopted a PFM reform
plan towards strengthening the budget preparation process and improvements in revenue
administration. However, significant challenges remained pertaining to all aspects of the PFM
cycle. Key amongst these were Comoros’ fragmented four existing treasuries4 operations that
caused difficulties for the government to have a clear view of its cash position and to allocate
scarce resources strategically as it executed the budget.
Against the backdrop of not having cash management plans that integrated the Union and Island
treasuries, the DPO series supported efforts to improve treasury management by effectively
making operational the Directorate of Public Accounts and Treasury (DGCPT) that plays a key
coordinating role in consolidating (union and island) cash plans and financial statements. To that
end, a high priority was given to the preparation of a timely and accurate table of consolidated
government financial operations (TOFE), as this table is crucial for budget preparation, execution,
and monitoring, as well as for ensuring transparency in fiscal operations. Thus, the cash
management plans are there, but only since 2017. In fact, the computerization of public finances
is a recent reality through the Integrated Financial Management Information System (IFMIS)
rollout with the accounting and budget software SIMBA5 used since mid-2016 for implementation
by the Union and Island Governments of automate budget execution, accounting, and reporting.
Despite this progress, the full utilization of SIMBA is still hampered by the lack of a legal basis to
enforce the use of the system for capturing all critical budget transactions. Furthermore, a fire that
took place on March 4, 2017, in the Treasury building in Moroni interrupted the Union’s access to
the server for a few weeks, creating delays in the budget management and reporting.
Notwithstanding these constraints, the Treasury has prepared (even manually) integrated cash
balance statements that have been incorporated in the budget laws, contributing towards achieving
the PDO of a stronger economic management.
Outcome Indicator 2: The number of non-project central government bank accounts outside of
the treasury single account framework reduced from a baseline of 64 accounts (2013) to a target
of less than 10 accounts (2016). Achieved
The DPO series supported the adoption of a memorandum of understanding between the Ministry
of Finance and the Central Bank of Comoros governing the functioning and administration of a
4 The union treasury, and one for each of the three islands.
5 Installation and operationalization of the IFMIS IT solution (SIMBA) was completed in June 2016.
17
Treasury Single Account at the Central Bank in response to the tight cash position of government
throughout the fiscal year, to the growing number of bank accounts operated by government
spending agencies, and the delays in the depositing of funds collected by revenue agencies. The
implementation of the TSA framework would also result in a consolidation of the government’s
banking operations and the rationalization of the number of bank accounts. Prior to the
implementation of the TSA there were 64 government bank accounts6. This number was expected
to be reduced to less than 10 as of December, 2016. However, the number of central government
bank accounts outside of the TSA framework has been reduced to zero accounts from the baseline
value of 64 in 2013. The fact that the MOU signed between the Ministry of Finance and the Central
Bank, among other things, prohibited the opening and operating of new bank accounts unless prior
authorization from the vice-president responsible for finance had been obtained, played an
important role towards the rationalization of accounts.
Outcome Indicator 3. A computerized wage management system that integrates union and
island civil service must be operational. Baseline: Separate systems operated for the union and
islands (2013. Target: An integrated system that consolidates union and island civil service
operational (2016). Achieved
When the second operation of the DPO was designed Comoros’ civil service management
modalities were fragmented, leading to a lack of coordination and weak control in the wage bill
management. The union and islands operated separate civil service and wage management systems
and they had autonomy over recruitment rights. These arrangements had resulted in fragmented
management of the wage bill and provided incentives for hiring at the local level irrespective of
the aggregate cost of salaries to the budget. That is why the operation supported the strengthening
of wage bill management through the adoption of an integrated wage management system. With
support from the operation the Government migrated from the fragmented to a centralized wage
management system and a new computerized system allowed the integration of the union and the
island civil services databases.
The integrated personnel and payroll management system for the Union and Island Governments
has been operational since January 2016 through the operationalization of the Government Human
Resource Management Information System (GISE)7. However, the gains in efficiency have not
been fully obtained, yet. The deployment of the SIMBA/GISE interface has not been completely
materialized and therefore deployment of GISE has not yet translated in total human resources
data consolidation. As of March 2017, more than 95 percent of civil servants are paid through the
automated payroll system.
Outcome Indicator 4. Public budget that includes detailed information on investment and
recurrent expenditures adopted. Baseline: No public budget with detailed information on both
investment and recurrent expenditures (2013. Target: Public budget with detailed information
on investment and recurrent expenditures (2016) Achieved
6 Arrêté #14-029/VP-MFEBICEI/CAB dated 11 March 2014. 7 Government Human Resource Management Information System (Gestion Informatisée des Structures
des Effectifs, GISE).
18
At the time when the DPO series was designed, Comoros had made progress in widening the scope
of its budget documents. Previously, a key constraint to budget comprehensiveness and
transparency had been the narrow classification framework. A new classification established in
2013 was implemented in 2015. The DPO sought to deepen budget transparency by expanding the
coverage of the budget to include the Public Investment Program (PIP), which had been prepared
by the National Commission for Planning, under an entirely parallel process to the budget cycle
and hence had not been included in the budget law. The DPO supported the Planning Commission
and the Budget Directorate to prepare the PIP together with the budget preparation calendar, and
to present this information in the budget law. Thus, since 2015 the PIP has been appropriated by
parliament and the budget, using the institutional classification framework presents a complete
picture of domestically and externally funded investment program.
The inclusion of the public investment plan has contributed to widening the scope of the budget.
However, the low and decreasing execution ratio of the PIP is a major concern. The execution ratio
of the PIP has been on a declining trajectory in recent years, decreasing from 47 percent in 2012
to around 40 percent in 2016. The low execution ratio not only signals weaknesses in budget
credibility, but also causes the delay and even failure of ongoing projects. To increase the
execution ratio, the authorities should aim to improve infrastructure, enhancing project
management, and strengthening the communications with the donor countries.
Outcome Indicator 5. Transparency and accountability of debt management has improved.
Baseline: No regular debt reports produced and debt management framework incomplete (2013)
Target: Annual debt reports produced and all new loans, guarantees and loan renegotiations
conducted in line with debt management law (2016). Partially achieved
The debt management reforms supported by this DPO series were expected to strengthen economic
management through more transparent and strategic control of borrowing. Scrutiny of the debt
position through regular reporting and an effective legal framework were considered critical for
maintaining control of the country’s liabilities. The reforms supported by this operation had started
to yield results in this direction as access to regular debt information has been institutionalized in
the budget. However, despite improvements in debt management reporting, the target remains
short of full achievement. In fact, the annual reports on central government debt management are
currently not produced by the Debt Directorate (DD). However, as indicated in the latest Debt
Management Assessment8, the Debt Directorate (DD) prepares each year a Debt Management
Strategy (DMS) attached to the annual Budget law, which is published every year. The annual law
also contains information on statistics of external debt service expenditures, expected new external
debt disbursements, and monitoring of debt service payments arrears.
8 World Bank Debt Management Performance Assessment (DeMPA), August 2016.
The DeMPA is a methodology for assessing public debt management performance through a
comprehensive set of indicators spanning the full range of government debt management functions.
19
Furthermore, by law9 the DD is responsible for producing the debt statistical bulletin. De facto,
the latest annual debt statistical bulletin that DD produced was for fiscal year 2014. The bulletin
was published in print and distributed to relevant officials, including Minister of Finance and Vice-
president for finance and economy. It included information on: evolution of debt stock by external
creditors, types of creditors, currency composition, interest rate, annual debt service forecast and
actual payments, as well as forecast of debt service for the upcoming three years’ period.
Unfortunately, the bulletin is not available at the MOF website. In addition, DD produces quarterly
information briefs, which include data on outstanding debt stock, debt service and accumulated
external debt arrears, and are presented to management of the MOF and the BCC.
Per the 2016 IMF Art IV the government has neither contracted nor guaranteed any other external
loans apart from two concessional loans from the Export-Import Bank of India (US$33 million)
for the construction of a heavy fuel oil electricity generation plan, and from China (US$32 million)
to strengthen the telecommunications infrastructure. At the end of June 2016, total debt arrears
were estimated at USD 4.5 million, so the IMF indicated the authorities that the incurrence of
arrears on external debt service, even in small amounts, by a country, such as Comoros, that had
recently received comprehensive debt relief would send a very bad signal to the international
community. Hence, IMF explored with them possible steps to strengthen external debt
management to avoid further arrears, including the establishment of a mechanism that would
provide authority to the BCC to debit the government’s account to facilitate debt service payments.
Outcome Indicator 6: National Accounts prepared using the 1993 methodology and National
Statistics Institute operational. Baseline: Draft national accounts for year 2007 using the 1993
methodology prepared (2013) Target: National accounts for year 2013 using the 1993
methodology adopted (2016). Achieved
Comoros adopted a law to strengthen its institutional framework for statistics management in 2011.
The law established the National Council of Statistics, changed the status of the National
Directorate for Statistics from a directorate under the Planning Commission to an autonomous
agency, the National Institute of Statistics and Economic Studies and Demographic (INSEED).
Yet, despite these reforms and capacity building, outdated basic statistics and methodologies
continued to hamper policy decision. This DPO supported the modernization of Comoros’ national
accounts methodology as a key step towards improving basic statistics. In fact, until 2014 INSEED
had been preparing national account statistics using the SNA 1968 methodology. The DPO
operation supported INSEED in preparing updated national accounts based on SNA 1993, for the
period 2007-2016, aiming to reinforce economic management by providing more accurate
information for policy making.
At end 2016, INSEED has completed the cleaning up of a GDP database for the 2007-2015 using
the SNA 1993. The National Accounts until 2015 have been validated and adopted by the
Government only last September 2017. INSEED has also delivered the preliminary national
accounts for 2016 and although the updated series based on the SNA 93 methodology have not yet
been published, awaiting the green light from the Government, the full dataset was provided to the
World Bank.
9 Decree No. 12-047 / PR of 29 February 2012, Art. 20
20
Objective 2. Improving transparency in economic management
Rating: Moderately Unsatisfactory
Outcome Indicator 7. Number of cases completed by the anti-corruption commission and
brought to court should increase from a baseline: 15 (2013) to a Target: 20 (2016). Not achieved
Corruption is recognized as one of the main governance challenges facing Comoros. In 2014,
Comoros ranked 142 out of 175 countries in the Transparency International corruption perceptions
index, indicating the depth of the accountability and transparency deficit. In recognition of the
need to tackle this situation, the government adopted in 2012 an anti-corruption strategy that
included the issue of a decree that required asset and income declarations by high ranked public
officials to increase transparency and avoid conflict of interests. The first DPO supported this effort
by requiring the Anti-Corruption Commission to begin publishing a list of compliant and non-
compliant public officials who have filed their asset declaration. But major challenges remained,
particularly in terms of the limited capacity of the anti-corruption commission. Hence, the second
DPO sought to enhance the country’s capacity to combat corruption by supporting the
strengthening of the legal and institutional framework. The government adopted a set of
amendments to the anti-corruption legislation, empowering the Commission by giving its officers
the legal powers to investigate perceived corruption cases, and to prepare and submit those cases
to the judiciary, thus enhancing the independence of the Anti-Corruption Commission and
reinforcing its authority. It was expected that these reforms would foster an environment of
increased accountability.
As of 2013 the anti-corruption commission had submitted 15 cases to the judiciary, and under the
operation it was expected to increase the number of completed cases to 20 by 2016. However,
three months after the new President took office (mid-year 2016) the Anti-Corruption Commission
was dissolved in the grounds of lack of efficiency and efficacy. The government has not put in
place an alternative credible system for pursuing the fight against corruption nor has it taken
specific measures to combat corruption.
Outcome Indicator 8. Information on access granted for fishing activities systematically
disclosed, with revenue and its use documented. Baseline: Information not systematically
available (2013). Target: Access to information on revenue and its use regularly documented
and disclosed (2016) Achieved
The first DPO supported transparency efforts in the fisheries sector, namely, the disclosure of
information related to fishing agreements. In March 2014, the government signed and published a
presidential decree 10 that mandated full systematic disclosure of fishing agreements, license
information and budget revenues from this source. The disclosure of this information through
government sites and local newspapers had contributed to improved transparency and
accountability for the sector. Hence, the second DPO continued to support the systematic
10 Decree No. 14-034 of March 2014
21
disclosure of information of fishing activities including revenue and its allocation as it would also
contribute to improve the management of the fisheries resources where all sectors involved
(stakeholders, fishing agreement signatories and neighboring coastal countries) would get the same
information. The DGRH 11support efforts to enhance transparency in the management of the
fisheries resources through the systematic preparation of the information that is sent to the CREF12
twice a year for its publication13.This met the target of having the information available to the
public through the CREF website and is updated at least once a year. Furthermore, the amount of
revenues generated by access granted to fishing activities have been included in the budget law of
2015 and 2016. However, as of December 2016, and until October 2017, the information has not
been published in newspapers due to the lack of financial resources.
Objective 3. Improving competition and management in key infrastructure sectors
Rating: Satisfactory
Outcome Indicator 9. Increase in the number of Telecom operators with a service license and
reduction in the monthly price per 1 GB of mobile data (3G) Baseline: 1 Telecom operator and
KMF 10,000 price (2013. Target: At least 2 Telecom operators and KMF 7,500 price (2016)
Achieved
Since 2013, the Government of Comoros had been committed to the liberalization of the telecoms
sector. To that end the Communications Law was approved by Parliament in March 2014 and was
signed by the President on 25 December 2014. This law, among other issues removed Comores
Telecom’s exclusive privileges, effectively providing a level playing field for new competitive
market entry.
The reforms of the telecom sector have been supported by the Bank under the fourth phase of the
Regional Communications Infrastructure Program (RCIP-4). The program aided with
strengthening the legal framework for liberalization and with technical assistance to the process of
licensing and selecting new service providers. The DPO series supported the effective opening of
the telecoms sector through the granting of a full-service license to a new operator. Specifically,
the expected result indicator was achieved as the competitive bidding process was launched in
2015 and Telma Comores (private company) was awarded a license in December 2015 and began
operations in 2016. Although telecom was opened to the new operator the process was very
complicated and prolonged. The price paid for the license was around US$16m and there were at
least three other bidders. As expected Telma’s price per 1GB per month is 5,000 KMF14 while the
Comores Telecom (national company) has a price of 5,250 KMF per month for 1GB. Telma’s unit
price is even lower if the purchase is higher (as low as 1,000 KMF per 1GB).
11 The Direction General de Resources Halieutiques (DGRH) 12 Information on fishing agreements updated until 2016 is available on the CREF website
http://www.cref.gouv.km. 13 Licenses information can be found in site: http://www.cref- comores.org/pubs/Protocoles/
14 see http://www.telma.km/offres/4?#Telma_Net
22
The introduction of competition to Comoros’ telecoms sector is expected to result in better
connectivity for Comorian businesses and households as well as allow the access to more modern
and affordable telephone and internet services, thus contributing towards achieving the PDO of an
improving competition and management in a key infrastructure sector.
Outcome Indicator 10. Increase in MA-MWE collection rates from a baseline of 55 percent
(2013) to a target of 65 percent (2016) Achieved
At the onset of the DPO series it was clear that inadequate commercial management, investment
and maintenance were major drivers of poor electricity supply in Comoros, hence the electricity
reforms under the DPO series complemented the Bank’s Electricity Sector Recovery Project
(ESRP) aimed at improving the commercial management and governance of the sector. Based on
experience with such operations, it was fundamental to develop a performance and regulatory
framework between the Government of Comoros and MA-MWE. Hence, the DPO series
supported the preparation of a recovery and development plan for the MA-MWE in the first place
and then the adoption of the plan by the Government of Comoros and MA-MWE. The framework
would hold MA-MWE management and the senior managers accountable by setting reasonable
and achievable targets for improving performance.
The recovery process supported by this DPO series was expected to place the electricity sector on
a path to improved performance that included an expected increase of the collection rates from a
baseline of 55 percent in 2013 to 65 percent in 2016, a target that was fully achieved. In fact, the
collection rate (as of end 2016) reached 79 percent and represents the total amount collected for
electricity sales billed in 2016 (KMF) as a percentage of the total amount of electricity sales billed
in 2016 (KMF). This rate concerns electricity sold to customers from both the low and medium
voltage groups using traditional meters, which require a meter reader to manually record the
information displayed on the meter and transmit it to the sales department for registration in the
commercial management information system.15 Parallel efforts are being made to improve the
utility’s recovery commercial performance through the deployment of a state-of-the-art
management information system, prepaid meters as well as targeted communication campaigns
and stakeholder engagement against electricity theft and meter fraud. MAMWE is improving
slowly but, as mentioned earlier in this report, the new government is aware that unreliable and
15 The data used to estimate the collection rate have been extracted from the recuperations database of the
sales department of the Water and Power Utility (MA-MWE. This database has been developed under the
leadership of international senior managers hired as part of the ESRP project during the second half of 2015.
The database is regularly up-dated and records the following information (from January 1, 2015 to October
2017): (i) monthly sales in kWh (based on billing date); (ii) monthly sales in KMF (based on billing date);
(iii) receipts in KMF (knowing that each receipt is now associated with an invoice); and (iv) pre-paid meters
sales/receipts (pre-paid meters is excluded from the indicator). The collection results are always reported
to the billing period: Examples: 1) If a July 2015 bill is canceled in January 2017, the July 2015 billing rate
is impacted (downward); 2) If a January 2017 bill is paid in August 2017, it is the January 2017 collection
rate that is impacted (upward)
23
low quality supply of electricity represents a significant obstacle to economic growth, while the
high cost of diesel-based generation puts a considerable strain on public finances by making the
sector dependent on continuous provision of fuel subsidies. The government is therefore working
with the World Bank and African Development Bank on a longer-term strategy to strengthen the
technical, management, and commercial capacity of the entity in compliance with the PDO of
improving management in this key infrastructure sector.
3.3 Justification of Overall Outcome Rating
Rating: Moderately Satisfactory
The rating of the achievement of development outcomes of DPO series is moderately satisfactory.
The overall rating of moderately satisfactory reflects, conservatively, the moderately satisfactory
rating of pillar 1, the moderately unsatisfactory rating of pillar 2 and the satisfactory rating of pillar
3. The overall assessment is on balance positive, both because the reform program was significant
and relevant, eight of ten indicators were achieved while one was partially achieved. However,
one of the supported measures has been reversed (the fight against corruption). The main reason
why it is rated moderately satisfactory is because the elimination, in September 2016, of the Anti-
Corruption Commission represents a risk to the sustainability of the program development
objective “promoting transparency” given that, the fight against corruption and transparency, is a
cornerstone of the DPO series.
3.4 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
The three pillars of the DPO series are expected to have a positive impact on poverty reduction
and social development in the medium and long term. In effect, improving public financial
management and transparency indirectly contributes to improved poverty and social outcomes as
(i) an effectively executed budget allows the allocation of resources to development priorities; (ii)
effective treasury and wage bill management support the system’s ability to maximize the use of
scarce resources; (iii) an improved governance framework, driven by transparency measures,
supports openness and helps limit the leakage of funds.
The third pillar of the DPO directed to improving competition and management of the ICT and
electricity sectors is also expected to have a positive social impact by increasing the reliability of
access to electricity services available in Comoros. This will particularly be the case for households,
businesses, health facilities and schools in rural areas that still have low levels of supply and cannot
afford to run individual generators. Finally, the reforms in the telecoms sector has already
improved access to ICT services and to lower communication costs which are of social benefit in
the Comoros context given the important role that connections with family members and
remittances from abroad play in the economic welfare of households.
Notwithstanding progress made under the DPO series regarding integration between the Union
government and the islands, coordination remains to be improved. Meanwhile, problems with
revenue collection and service delivery persist resulting in limited improvements in living
24
standards and poverty rates. Per the latest Poverty Assessment prepared by the World Bank16
using the new household survey data from 2014, around four out of ten Comorians live below the
national poverty line and nearly one fourth of the population is in a state of extreme poverty. In
2014, 42.4 percent of the population lived below the basic needs poverty line of KMF 25,341 per
capita per month and about 23.5 percent of the population is in extreme poverty. However, using
the international poverty line of US$1.9 per capita per day only two out of ten Comorians would
be classified as poor, a rate that puts Comoros ahead of other Low Income (LIC) and Sub-Saharan
African (SSA) countries by up to 30 percentage points. ES.3). However, compared to some of the
richer Island Nations in the region, such as Mauritius or Seychelles, Comoros’ poverty rate is
significantly higher.
(b) Institutional Change/Strengthening
The Bank’s assistance to Comoros under the DPO series supported several reforms aimed at
institutional strengthening across the pillars of the operation. In effect, the DPO reforms in debt
management were also linked to the institutional strengthening of the debt management office that
the Bank supported through targeted capacity building, including a program of technical trainings
of a Comorian debt manager. The capacity of the Public Debt Directorate has been strengthened,
including their role in managing regular debt reporting and supporting timely debt service
payments. The 2016 Debt Management Performance Assessment (DeMPA)17 noted that the Debt
Directorate has made remarkable improvements since the last evaluation conducted in 2011.
Furthermore, through the telecom and energy investment lending – the DPO could help accelerate
the reform agenda and institutional strengthening of the Electricity and the telecom institutions.
Complementary advisory activities under the umbrella of DPO series have had a direct impact on
institutional change. Most probably, one of the most significant underpinnings included the
statistical strengthening reforms that are expected to reinforce economic management by providing
more accurate information for policy making. Improved national accounts will provide critical
information on the actual size and structure of the economy, and guide policy makers in designing
economic reforms. The institutional strengthening of INSEED allowed the institution to regularly
produce national accounts data based on an updated methodology (SNA 93) from 2015 onwards.
Furthermore, the DPO supported institutional reform mainly through public financial management,
making operational the Directorate of Public Accounts and Treasury (DGCPT) that plays a key
coordinating role in consolidating (union and island) cash plans and strengthening the functioning
of the Single Treasury Account. Finally, but not less important is the support given to wage bill
management through the operationalization of an integrated system that consolidated union and
island civil service.
(c) Other Unintended Outcomes and Impacts
No unintended negative effects have been identified by the team or the Government.
16 World Bank Comoros Poverty Assessment -- P156542 April 2017 17 World Bank, “Union of the Comoros: Debt Management Performance Assessment,” August 2016
25
3.5 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
There were no beneficiary survey and/or stakeholder workshop.
4. Assessment of Risk to Development Outcome
Overall Rating: Substantial
The risk of either policy reversals or not maintaining the outcomes in the areas supported by the
DPO series was substantial. It is mostly associated with the country’s potential political difficulties
to implement reforms, the vulnerability to external shocks, high risk of debt distress and weak
institutional capacity that could affect the pace of implementation of some of the sector reforms
supported by the operation.
In particular, the risks identified in the DPO relating to electoral cycle were well identified and
have had an important effect on the results of the program in the areas of debt management
(adoption of the debt management bill) and the anti-corruption reforms (disbanding of the anti-
corruption commission). These risks, which were well acknowledged, have also affected the PDO
to the extent that the changes brought about by the new government in economic management,
including looser fiscal policy, have weakened economic management after the DPO series
concluded.
Historically, difficult inter-islands relations over the use of public resources, within the context of
weak governance, structural weaknesses in public financial management and high politicization,
have been at the root of the country's fragility. This has been reflected in the impact of some of the
reforms and the pace at which others were implemented. Currently, although the DPO series
addressed reforms that were endorsed by the Union and Island governments, providing technical
assistance to facilitate the consensus, it has not completely created sufficient trust among the
parties despite improving transparency in the use of public resources. This is reflected in the fact
that the TSA does not include the island own revenues, which fortunately do not amount to more
than 5 or 6 percent of total revenues, due to lack of confidence that the Union government would
not revert to the islands their own revenues.
Furthermore, the country is highly vulnerable to external shocks (natural disasters, increases in
international fuel and food prices, and slowdown in remittances), that could affect continuing
implementing the reforms. As mentioned earlier in this ICR, Comoros’ macroeconomic and fiscal
framework continues to be vulnerable to shocks that are characteristic of small island economies.
Commodity price shocks could be translated into higher domestic prices given the extent to which
consumption relies on imported goods, particularly food and fuel, and global or regional economic
downturns could yield a shock to remittance flows and diminish employment opportunities abroad.
Hence, government finances remain fragile, limiting the capacity of the authorities to respond to
external shocks and maintain the country on a steady macroeconomic path.
5. Assessment of Bank and Borrower Performance
26
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Ratings: Satisfactory
Bank performance during the preparation of the operation was satisfactory. The design of the
operation was appropriate, timely and responded to the country’s priorities. It built on lessons
learned from previous DPOs in Comoros and the Bank’s experience with DPOs in low income
countries. The operations’ identification and appraisal drew from existing analytical work in areas
such as treasury and cash management, budget comprehensiveness, or debt management. In the
cash management area, the DPO benefited from the PEFA18 report that highlighted the key
weaknesses relating to treasury operations, including the fragmentation in treasury and cash
management. In budget comprehensiveness, the PEFA report as well as the analysis of the
Comoros public investment program19 made by the WB identified several gaps relating to budget
comprehensiveness and supported the recommendation to integrate all investment projects in the
budget. With regards to improving debt management the DPO benefited from the DeMPA20 that
highlighted the need to strengthen the legal and strategic framework underpinning debt
management, and this recommendation was taken-up in the operation’s plan.
Furthermore, the DPO series was underpinned by technical assistance and a frank policy dialogue.
The work was well-coordinated within the Bank’s multi-sectoral team. The results framework
established a clear mapping from PDO to prior actions to results indicators. During the preparation
of DPO2, the prior actions supported a broader reform scope relative to the triggers originally
envisioned in DPO1. Moreover, in preparing for the DPO series, the Bank consulted and
coordinated with major development partners and the sector reforms supported by the operation
were discussed with stakeholders as part of the preparation of sector operations (i.e. ICT and
electricity).
The DPO was designed to leverage the TA and investment projects in the portfolio. This helped
ensure (i) there was sufficient dialogue and consultations at the sectoral level, (ii) that there was
analytical work done, and (iii) that there was support on the ground for monitoring and
implementation. In areas, such as PFM, the World Bank Economic Governance Technical
Assistance Grant supported the implementation of PFM reforms, with a focus on budget execution
and wage bill management. The policy reforms on anti-corruption build on a dialogue stemming
from a Governance and Anti-Corruption Technical Assistance, which supported the government
in redefining the governance and anti-corruption action plan. However, the change of government,
which involved a change in political party, widespread institutional and personnel changes, were
key factors behind the closing of the anti-corruption commission. With regards to key
infrastructure sectors, the reforms towards the liberalization of the telecoms sector were supported
by the World Bank under the fourth phase of the Regional Communications Infrastructure Program
(RCIP-4), that provided technical assistance to the process of licensing and selecting new service
18 Comoros Public Expenditure and Financial Accountability (PEFA) Report (2013) 19 Policy Note on the Comoros Public Investment Program (2013) 20 Debt Management Performance Assessment (DeMPA) (2011)
27
providers. Finally, the electricity component reflects the ongoing reform supported by the
Electricity Sector Recovery Project Grant which helped the authorities in improving the
commercial performance of MA-MWE.
(b) Quality of Supervision
Ratings: Satisfactory
Bank performance in the supervision of the operation was satisfactory. The Bank conducted three
supervision missions of the DPOs (May-June 2014; October-November 2014; and March 2015),
The second supervision mission was combined with the identification mission of the second
programmatic DPO. This helped assess the status of the outcome indicators and triggered the
design of the new operation. The tentative timeline for the second economic reform DPO was like
the first operation, about a year, with negotiations and board approval envisaged in March-April
and disbursement in May 2015. Follow-up and implementation support for the program started in
May 2014, one month after the approval of the first operation and continued to be on-going
throughout the period of the operation. Additional guidance was provided by the World Bank team
in key areas, for example closer Bank supervision in debt management including a DeMPA
assessment for Comoros in 2016. In addition to this, numerous supervision missions and additional
support was provided through the World Bank Governance, Telecoms and Electricity projects that
supported areas linked to the reform program.
(c) Justification of Rating for Overall Bank Performance
Ratings: Satisfactory
Given that the Bank performance for quality at entry and the quality of supervision is rated
satisfactory, the overall Bank Performance is rated satisfactory. The unstable nature of Comoros’s
political situation and the fact that a new Government would come into power by mid-2016, six
months before the closing of the second DPO posed challenges to get political support for the
reform agenda. However, the fact that the series was anchored to Government’s strategic reforms
helped to ensure the positive results of the series. The Bank maintained high quality standards in
the design and implementation of both DPOs, providing support through its analytical work and
technical assistance
5.2 Borrower Performance
(a) Government Performance
Ratings: Moderately Satisfactory
For this ICR, Government performance and implementing agency performance are considered
the same. Therefore, the above rating should be viewed as an overall rating for the Borrower.
The Government overall performance for this operation is rated moderately satisfactory. The
Government showed commitment to reform and took full ownership of the program. The CREF
played a consistent and effective role in coordinating dialogue and implementation, but when it
came to monitoring and sustaining results its role was less effective as it monitored only
28
sporadically. In its role of harmonization, CREF coordinated with other Government ministries
and agencies involved in the implementation of the DPO series, including BCC, SG-Finances,
DGCPT, INSEED, DGRH, and MA-MWE. Together with CREF, these institutions collected the
necessary data to assess implementation progress and reported to the Bank. During the collection
of data, the documentation received for preparation of this ICR was mostly timely.
The government made progress in complying with the integration of the cash management
accounts, the reduction of central government bank accounts, strengthening the management of
the wage bill and the statistical system and improving competition and management of the key
sectors of telecommunications and electricity. Section 3.2 above explains in detail the actual
achievements of the expected outcomes. It is important to note that despite the shortcomings in
institutional capacity, the Government still managed to fully or partially achieve all indicators but
one. The government was not successful in supporting the fight against corruption through the
strengthening of the judicial powers of the Anti-Corruption Commission as established in indicator
No.7. On the contrary, the government eliminated the commission and has not put in place a
credible system for pursuing the fight against corruption. As indicated below, one of the lessons
learned is that this indicator might have been too ambitious and the fact that it was revised in DPO2
could well indicate a shortcoming on the side of the Bank
(b) Implementing Agency or Agencies Performance
Not Applicable
(c) Justification of Rating for Overall Borrower Performance
Given that the Government performance is rated moderately satisfactory, and as the Government
and Implementing Agency are indistinguishable, the overall Borrower Performance is rated
moderately satisfactory
6. Lessons Learned
Experience with the Economic Governance Reform DPOs validates lessons from previous
operations but also generated new ones.
1. A key lesson learnt is that DPOs can help secure key reforms and complement
traditional investment lending even in a fragile setting. Comoros remains a difficult
implementation environment for reforms due to the limited institutional capacity, requiring
simple project design focused on policy reforms in few relevant areas that are broadly
supported by donors and with adequate technical assistance to support implementation.
The narrow focus of the DPO was a positive design feature. By joining forces with other
development partners in a systematic manner, particularly on PFM, wage management,
statistics, energy and telecom sectors, the Government ensured adequate program
implementation. In Comoros, small steady steps, and regular consultation, proved to be
more feasible than the big bang approach.
29
2. Leveraging the existing Bank project and technical assistance activities is key to
achieving results in low capacity fragile states. The implementation of the reforms was
facilitated by targeted technical assistance provided by the Bank, i.e., through the
Electricity Sector Recovery Project (ESRP) aimed at improving the commercial
management and governance of the sector, in coordination with other donors (The AfDB
provided support through a capacity building and technical assistance project and direct
budget support); or the IMF ongoing program of technical assistance designed to improve
the reliability of the national accounts and price statistics.
3. In settings, such as in Comoros, where power is shared amongst four governments, it
is critical to seek consensus as much as possible prior to the implementation of
reforms. This is even more crucial when it touches upon political economy issues such as
the power sharing between the Island governments and the Union, or coordination between
the Union and Island entities. Better understanding can also foster trust among the parties
and help move the agenda forward in a more efficient manner. Ensuring that the Islands
participate in relevant consultations so that the reforms that the government of the Union
want to pursue are understood among all stakeholders is key.
4. Given the complicated, fragile and low capacity setting, a closer Bank supervision is
needed to follow up with the Government regarding the steps towards achieving the
PDO. For example, under this DPO, the government had information for the preparation
and publishing of debt reports, but apparently, it was not totally clear to them that these
meant self-standing comprehensive reports and not only including the information in the
budget laws.
5. Strong analytical underpinnings and technical assistance can ensure an adequate
program implementation. The DPO series was grounded in strong analytical groundwork,
which, in turn, provided the rationale for the selection of policy reform areas. However, in
formulating the results framework, a more satisfactory result could have perhaps been
achieved by focusing on the objective of what needed to be achieved (fight against
corruption) rather than a specific action for achieving it (e.g., an increase in the number of
cases completed by the anti-corruption commission and transfer to the judiciary versus a
requirement to strengthen the judiciary. This could have given the incoming administration
some flexibility.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/Implementing agencies
Not yet available
(b) Co-financiers
Not Applicable
(c) Other partners and stakeholders
30
Not Applicable
31
Annex 1: Economic Governance Reform Operations- Policy and Results Matrix
Prior Actions supported by DPO 1
Prior Actions supported by DPO2
Expected Results Indicators DPO2 (end 2016)
Actual Outcome (as of end 2016)
Pillar A: Strengthening economic management 1.1 Coordinating treasury and cash management
A dedicated budget line for the Directorate of Public Accounts and Treasury is clearly identified in the 2014 Budget and the following key staff is appointed in accordance with the Recipient’s decree no. 12-047/PR 29 February 2012 relating to DGCPT, including its General Manager), Coordinator, Managers of the three support services), Treasurer of the Union and Treasurer of each of the three Autonomous Islands
The Recipient’s Directorate of Public Accounts and Treasury within its Ministry of Finance has become operational through: (i) the identification of a dedicated budget line in the Recipient’s 2015 Budget Law; and (ii) the appointment of the remaining core staff as required by the Recipient’s Decree No. 12-047/PR dated February 29, 2012, through the Recipient’s Arrêté No.15-008/VP-MFEBICEP/CAB dated March 28, 2015.
1.Cash management plans integrating the union and island treasuries are operational. Baseline: No integrated plans (2013) Target: Integrated plans developed and adopted with the budget laws (2016)
Achieved Cash management plans integrating the Union and Island Treasuries are operational and have been incorporated to the budget law starting in 2015.
The Recipient has included in its 2014 Budget Law four (4) previously off-budget accounts (comptes de régies) recorded in the accounts of the Treasury, and has issued a decision (arrêté) containing a complete list of accounts of the administrative entities of the Recipient (at the union and the Autonomous Islands’ levels) in the Recipient’s central bank.
The Recipient’s Ministry of Finance and the Central Bank have signed a memorandum of understanding governing the functioning and administration of a Treasury Single Account at the Recipient’s Central Bank, which memorandum of understanding, among other things, prohibits the opening and operating of new bank accounts unless prior authorization from the Recipient’s vice-president responsible for finance has first been obtained.
2.Number of non-project central government bank accounts outside of the single account framework reduced Baseline:64 (2013) Target: Less than 10 (2016)
Achieved The number of central government bank accounts outside of the TSA framework has been reduced to zero accounts
1.2 Strengthening wage bill management
The Recipient has strengthened wage bill management through: (i) the integration of civil service wages in the computerized wage management system; and (ii) the integration of biometric national ID numbers in the computerized wage management system.
3.A computerized wage management system that integrates union and island civil service operational. Baseline: Separate systems operated for the union and islands (2013) Target: An integrated system that consolidates union and island civil service operational (2016)
Achieved The integrated civil service wage management system for the Union and Island Governments is in place since January 2016 through the operationalization of the Government Human Resource Management Information System (GISE). More than 95 percent of civil servants are paid through the system.
32
Prior Actions supported by DPO 1
Prior Actions supported by DPO2
Expected Results Indicators DPO2 (end 2016)
Actual Outcome (as of end 2016)
1.3 Improving budget comprehensiveness
The Recipient has included in its 2014 Budget Law: (i) overall envelopes per ministry; (ii) the state of execution of the 2013 budget until June 30, 2013 presented in the same format as the draft budget; and (iii) data on government revenues (own resources and external resources) in the main headings of the budget nomenclature, including data for Fiscal Year 2013.
The recipient has integrated the public investment program in its 2015 budget law.
4.Public budget that includes detailed information on investment and recurrent expenditures adopted.
Baseline: No public budget with detailed information on both investment and recurrent expenditures (2013) Target: Public budget with detailed information on investment and recurrent expenditures (2016)
Achieved The Public Investment Plan (PIP) is included in the budget law, starting with the 2015 budget law.
1.4 Improving debt management
The Recipient has included in its 2014 Budget Law a detailed debt report analyzing the debt stock as of October 31, 2013,
The Recipient has prepared and submitted to its National Assembly a debt management bill to strengthen the Recipient’s debt management framework.
5.Transparency and accountability of debt management has improved. Baseline: No regular debt reports produced and debt management framework incomplete (2013) Target: Annual debt reports produced and all new loans, guarantees and loan renegotiations conducted in line with debt management law (2016)
Partially achieved Since the debt management bill was prepared and submitted to the National Assembly in 2014, no self-standing debt reports have been published but debt information is produced each year and included in the budget law.
1.5 Strengthening statistical system
The Recipient has signed (after Cabinet review) and published a presidential decree for the establishment of the National Council of Statistics.
The Recipient, through its National Statistics Institute (L’Institut National de la Statistique et des Etudes Economiques et Demographiques), has: (i) prepared a budgeted five-year action plan that uses the SNA 1993 methodology for the production of national accounts; and (ii) has completed data collection for updating 2011-2013 accounts.
6.National Accounts prepared using the 1993 methodology and National Statistics Institute operational.
Baseline: Draft national accounts for year 2007 using the 1993 methodology prepared (2013) Target: National accounts for year 2013 using the 1993 methodology adopted (2016)
Achieved The National Statistics Institute (INSEED) is operational and has completed the GDP database for 2007-2015 using the SNA 1993.
33
Prior Actions supported by DPO 1
Prior Actions supported by DPO2
Expected Results Indicators DPO2 (end 2016)
Actual Outcome (as of end 2016)
Pillar B--- Improving transparency in economic management
2.1 Supporting the fight against corruption
The Anti-Corruption Commission (Commission nationale de prévention et de lutte contre la corruption) has published, on its website and/or in a national newspaper, a list of public officials who have filed their asset declaration, in accordance with the Recipient’s Decree no. 12-183/PR dated September 15, 2012.
The Recipient has enacted Law No.13-015/AU amending the Anti-Corruption Law, dated December 26, 2013 in order to inter alia, strengthen the judicial powers of the Anti-Corruption Commission (Commission nationale de prévention et de lutte contre la corruption).
7.Number of cases completed by the anti-corruption commission and brought to court. Baseline:15 (2013) Target: 20 (2016)
Not Achieved The anti-corruption commission has been dissolved by the President in of the Union of Comoros in September 2016
2.2 Enhancing transparency in the management of fisheries resources
The Recipient has signed and published a presidential decree to systematize disclosure of fishing access rights to national waters attributed and related revenues as well as their allocation.
8.Information on access granted for fishing activities systematically disclosed, with revenue and its use documented. Baseline: Information not systematically available (2013) Target: Access to information on revenue and its use regularly documented and disclosed (2016)
Achieved Information on fishing activities is systematically prepared and disclosed through the Economic and Financial Reform Unit (CREF) Furthermore, the amount of revenues generated by access granted to fishing activities have been included in the budget law of 2015 and 2016
Pillar C--- Improving competition and management in key infrastructure sectors
3.1 Enhancing competition in the ICT sector
The Recipient’s government has prepared and submitted to the National Assembly a draft information and communication technology sector law that sets out a framework for market liberalization.
The Recipient has launched a competitive bidding process for a second full-service license in the telecommunications sector.
9.Increase in the number of Telecom operators with a service license and reduction in the monthly price per 1 GB of mobile data (3G) Baseline: 1 Telecom operator and KMF 10,000 price (2013) Target: At least 2 Telecom operators and KMF 7,500 price (2016)
Achieved
There are two telecom operators: Comores Telecom (national) and Telma (private).Telma’s price per 1GB per month is 5000 KMF while the Comores Telecom price is 5250 KMF per month for 1GB
34
Prior Actions supported by DPO 1
Prior Actions supported by DPO2
Expected Results Indicators DPO2 (end 2016)
Actual Outcome (as of end 2016)
3.2 Improving performance in the electricity sector
To reduce total losses in the electricity sector, the Recipient’s government has approved the terms of reference for a recovery and development plan establishing clear objectives for results to be attained by MA-MWE management and has initiated the procurement of the independent expert to prepare such plan by the publication of a call for expressions of interest.
The Recipient, through its Ministry in charge of Production, Environment, Energy, Industry and Craft, has adopted a recovery and development plan of the MA-MWE Company that includes a commercial recovery and performance framework.
10.Increase in MA-MWE collection rates Baseline: 55 percent (2013) Target: 65 percent (2016)
Achieved The collection rate (as of end 2016) reached 79 percent and represents the total amount collected for electricity sales billed in 2016
35
Annex 2 Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
P131688 - KM First Economic Governance Reform Operation
Names Title Unit Responsibility/
Speciality
Rafael Muños Moreno Program Leader LCC Task Team Leader
Noro Aina Andriamihaja Senior Financial Sector Specialist GFM01
Anne-Lucie Lefebvre Senior Public Sector Specialist GG017
Hajarivony Andriamarofara Consultant GGO13
Xavier Vincent Lead Fisheries Specialist GENDR
Dirk Bronselaer Senior Procurement Specialist AFTPE
Tim Kelly Lead ICT Policy Specialist GTI11
Mustafa Zakir Hussain Operations Adviser OPSIL
Helene Bertaud Lead Counsel LEGES
Faniry Razafimanantsoa Economist GMF13
Hugues Agossou Senior Financial Management Specialist GGO31
Joseph Byamugisha Financial Management Specialista AFTFM
Ralph Van Doorn Senior Counrty Economist GMF06
Stephan Eggli Operations Officer OPSOR
Shahrzad Mobasher Fard Consultant GMF05
Said Ali Antoissi Operations Officer AFMKM
Jean Gaspard Ayi Ntoutomane Consultant AFTP1
P150924 - KM Second Economic Governance Reform Operation
Names Title Unit Responsibility/ Specialty
Shireen Mahdi Senior Economist GMF13 Task Team Leader
Wael Mansour Senior Economist GMF08
Said Ali Antoissi Operations Officer AFMKM
Anne-Lucie Lefebvre Senior Public Sector Specialist GG017
Hajarivony Andriamarofara Consultant GGO13
Xavier Vincent Lead Fisheries Specialist GENDR
Tim Kelly Lead ICT Policy Specialist GTI11
Mustafa Zakir Hussain Operations Adviser OPSIL
Ewa Katarzyna Klimowicz Consultant GEE07
Siobhan McInerney-Lankford Senior Counsel LEGAM
Ruxandra Costache Senior Counsel LEGLE
Aissatou Diallo Senior Finance Officer WFALN
John Y.Ngwafon Senior Economist/ Statistician DECDG
Hugues Agossou Senior Financial Management Specialist GGO31
Jean Gaspard Ayi Ntoutomane Consultant AFTP1
Madeleine Chung-Kong Senior Program Assistant GMFDR
Rondro Malanto Rajaobelison Program Assistant AFMMG
36
(b) Staff Time and Cost
P131688 - KM First Economic Governance Reform Operation
Stage
Staff Time and Cost (Bank Budget Only)
No. of staff weeks
USD Thousands (including
travel
and consultant costs)
Lending 40.8 185,783.62
Supervision 0 1,104.19
P150924 - KM Second Economic Governance Reform Operation
Stage
Staff Time and Cost (Bank Budget Only)
No. of staff weeks
USD Thousands (including
travel
and consultant costs)
Lending 27.3 137,365.38
Supervision 0 0
37
Annex 3. Borrower's Comments
38
Annex 4. Comments of Cofinanciers and Other Partners/Stakeholders
N/A
39
Annex 5. List of Supporting Documents
World Bank, Program Document for Economic Governance Reform Operation, Report No.
81671-KM of March 27, 2014
World Bank, Program Document for the Second Economic Governance Reform Grant, Report
No. 95824 -KM of May 5, 2015
World Bank Policy Note on the Comoros Public Investment Program (2013)
World Bank Electricity Sector Recovery Project, Report RES25200 of September 2013
World Bank Comoros Public Expenditure and Financial Accountability (PEFA) Report (2013)
World Bank, Comoros Policy Notes Accelerating Economic Development in the Union of
Comoros, Report No: 84095-KM of February 2014.
World Bank Country Partnership Strategy for Comoros Fy2014-17, Report No. 82054-KM of
April 16, 2014
World Bank Debt Management Performance Assessment (DeMPA), August 2016.
World Bank Comoros Public Expenditure and Financial Accountability (PEFA) Report (2016)
World Bank ICR Economic Governance Technical Assistance Project, Report No. ICR00004178
of June 20, 2017
World Bank Comoros Poverty Assessment of April 2017
International Monetary Fund, 2016 Art IV Consultation, IMF Country Report No. 16/393,
December 2016
World Bank Aide-Memoirs and Back-to-Office Reports from June 2014 to March 2015
40
MAP