document of the world bankdocuments.worldbank.org/curated/en/... · approval: 12/19/2013 mid-term...
TRANSCRIPT
Document of
The World Bank
Report No: ICR00004100
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-51910, IDA-53410, IDA-57110)
ON A
SERIES OF DEVELOPMENT POLICY CREDITS
IN THE TOTAL AMOUNT OF SDR 91.4 MILLION
(US$135 MILLION EQUIVALENT)
TO THE
REPUBLIC OF SENEGAL
FOR THE
FIRST, SECOND AND THIRD
GOVERNANCE AND GROWTH SUPPORT CREDITS
July 26, 2017
Macroeconomics and Fiscal Management Global Practice
AFCF1Country Management Unit
Africa Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
SENEGAL GOVERNMENT FISCAL YEAR
January 1 to December 31
CURRENCY EQUIVALENTS
(Exchange Rate Effective March 8, 2017)
Currency Unit = CFA Franc
1.00 = US$ 0.00161
US$ 1.00 = 617
ABBREVIATIONS AND ACRONYMS
APIX Agence pour la Promotion de l’Investissement et des Grands Travaux (Agency
for Investment Promotion and Large Projects)
CPS Country Partnership Strategy
DPC Development Policy Credit
DPEE Direction de la Prévision et des Etudes Economiques (Department of Forecasting
and Economic Studies, Ministry of Economy, Finance and Planning)
GDP Gross Domestic Product
GGSC Governance and Growth Support Credit
GWH Gigawatt hours
HOGGY Hôpital Général de Grand Yoff (General Hospital of Greater Yoff)
HR Human resources
ICRR Implementation Completion Report
ICT Information and Communication Technology
IDA International Development Association
LFI Loi des Finances Initiale (initial budget law)
LFR Loi des Finances Rectificative (revised budget law)
MEFP Ministry of the Economy, Finance and Planning
M&E Monitoring and Evaluation
OFNAC Office national pour la Lutte contre la Fraude et la Corruption (National Office
for the Fight against Fraud and Corruption)
PDO Program Development Objective
PRSC Poverty Reduction Support Credit
PSI Policy Support Instrument
SAED Société nationale d’Aménagement et d’Exploitation des Terres du Delta
du Fleuve Sénégal (Company for the Development of the Senegal River
delta.) SDR Special Drawing Rights
SENELEC Société nationale d’Electricité (National Electricity Company)
TTL Task Team Leader
UEMOA/ Union Economique et Monétaire Ouest Africaine/West African Economic and
WAEMU Monetary Union
UK United Kingdom
WB The World Bank
Vice-President: Makhtar Diop
Country Director: Louise Cord
Senior Global Practice Director: Carlos Felipe Jaramillo
Practice Manager: Lars Christian Moller
Project Team Leader: Paolo Zacchia
ICR Team Leader: Julio Ricardo Loayza
ICR Primary Author: Philip English
SENEGAL
FIRST, SECOND AND THIRD
GOVERNANCE AND GROWTH SUPPORT CREDITS
P128284, P126470, P150976
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Program Performance in ISRs
H. Restructuring
1. Program Context, Development Objectives and Design ............................................ 1
2. Key Factors Affecting Implementation and Outcomes .............................................. 7
3. Assessment of Outcomes .......................................................................................... 14
4. Assessment of Risk to Development Outcome ......................................................... 19
5. Assessment of Bank and Borrower Performance ..................................................... 19
6. Lessons Learned........................................................................................................ 22
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners........... 24
Annex 1: Bank Lending and Implementation Support/Supervision Processes
Annex 2: Beneficiary Survey Results
Annex 3: Stakeholder Workshop Report and Results
Annex 4: Summary of Borrower's ICR and/or Comments on Draft ICR
Annex 5: Comments of Cofinanciers and Other Parners/Stakeholders
Annex 6: Prior Actions and their Status
Annex 7: List of Supporting Documents
MAP
A. Basic Information
Program 1
Country Senegal Program Name
SN- First Governance
and Growth Support
Project
Program ID P128284 L/C/TF Number(s) IDA-51910
ICR Date June 30, 2017 ICR Type Core ICR
Lending Instrument DPL Borrower GOVERNMENT OF
SENEGAL
Original Total
Commitment XDR 35.80M Disbursed Amount XDR 35.80M
Implementing Agencies n.a.
Cofinanciers and Other External Partners n.a.
Program 2
Country Senegal Program Name
SN- Second
Governance and
Growth Support Credit
Program ID P126470 L/C/TF Number(s) IDA-53410
ICR Date June 30, 2017 ICR Type Core ICR
Lending Instrument DPL Borrower GOVERNMENT OF
SENEGAL
Original Total
Commitment XDR 19.60M Disbursed Amount XDR 19.60M
Program 3
Country Senegal Program Name
Senegal-Third
Governance and
Growth Support Credit
Program ID P150976 L/C/TF Number(s) IDA-57110
ICR Date June 30, 2017 ICR Type Core ICR
Lending Instrument DPL Borrower GOVERNMENT OF
SENEGAL
Original Total
Commitment XDR 36.00M Disbursed Amount XDR 36.00M
B. Key Dates
SN- First Governance and Growth Support Project - P128284
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 07/24/2012 Effectiveness: 12/28/2012
Appraisal: 11/07/2012 Restructuring(s):
Approval: 12/20/2012 Mid-term Review:
Closing: 03/31/2014 03/31/2014
SN- Second Governance and Growth Support Credit - P126470
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 09/25/2013 Effectiveness: 12/23/2013
Appraisal: 10/31/2013 Restructuring(s):
Approval: 12/19/2013 Mid-term Review:
Closing: 03/31/2015 03/31/2015
Senegal-Third Governance and Growth Support Credit - P150976
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 07/16/2014 Effectiveness: 08/15/2015 07/31/2016
Appraisal: 06/09/2015 Restructuring(s):
Approval: 07/23/2015 Mid-term Review:
Closing: 07/31/2016 07/31/2016
C. Ratings Summary
C.1 Performance Rating by ICR
Overall Program Rating
Outcomes Moderately Unsatisfactory
Risk to Development Outcome Moderately Satisfactory
Bank Performance Moderately Unsatisfactory
Borrower Performance Moderately Unsatisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Overall Program Rating
Bank Ratings Borrower Ratings
Quality at Entry Moderately
unsatisfactory Government:
Moderately
unsatisfactory
Quality of Supervision: Satisfactory Implementing
Agency/Agencies: Moderately Satisfactory
Overall Bank
Performance
Moderately
unsatisfactory
Overall Borrower
Performance
Moderately
unsatisfactory
C.3 Quality at Entry and Implementation Performance Indicators
SN- First Governance and Growth Support Project - P128284
Implementation
Performance Indicators
QAG Assessments
(if any) Rating:
Potential Problem
Program at any time
(Yes/No):
No Quality at Entry
(QEA) None
Problem Program at any
time (Yes/No): No
Quality of
Supervision (QSA) None
DO rating before
Closing/Inactive status
Moderately
Satisfactory
SN- Second Governance and Growth Support Credit - P126470
Implementation
Performance Indicators
QAG Assessments
(if any) Rating:
Potential Problem
Program at any time
(Yes/No):
No Quality at Entry
(QEA) None
Problem Program at any
time (Yes/No): No
Quality of
Supervision (QSA) None
DO rating before
Closing/Inactive status n.a.
Senegal-Third Governance and Growth Support Credit - P150976
Implementation
Performance Indicators
QAG Assessments
(if any) Rating:
Potential Problem
Program at any time
(Yes/No):
No Quality at Entry
(QEA) None
Problem Program at any
time (Yes/No): No
Quality of
Supervision (QSA) None
DO rating before
Closing/Inactive status n.a.
D. Sector and Theme Codes
SN- First Governance and Growth Support Project - P128284
Original Actual
Major Sector
Public Administration
Central Government (Central Agencies) 29 29
Education
Other Education 14 14
Tertiary Education 14 14
Health
Health 14 14
Energy and Extractives
Energy Transmission and Distribution 29 29
Major Theme/Theme/Sub Theme
Human Development and Gender
Health Systems and Policies 14 14
Health System Strengthening 14 14
Private Sector Development
ICT 22 22
ICT Solutions 22 22
Public Sector Management
Public Administration 22 22
Administrative and Civil Service Reform 14 14
Transparency, Accountability and Good Governance 22 22
Public Finance Management 22 22
Public Expenditure Management 22 22
Urban and Rural Development
Rural Development 7 7
Rural Infrastructure and service delivery 7 7
SN- Second Governance and Growth Support Credit - P126470
Original Actual
Major Sector
Public Administration
Central Government (Central Agencies) 38 38
Education
Tertiary Education 12 12
Health
Health 13 13
Energy and Extractives
Other Energy and Extractives 25 25
Industry, Trade and Services
Other Industry, Trade and Services 12 12
Major Theme/Theme/Sub Theme
Human Development and Gender
Health Systems and Policies 14 14
Health System Strengthening 14 14
Private Sector Development
Business Enabling Environment 25 25
Regulation and Competition Policy 25 25
Public Sector Management
Public Administration 22 22
Administrative and Civil Service Reform 14 14
Municipal Institution Building 13 13
Transparency, Accountability and Good Governance 22 22
Public Finance Management 22 22
Public Expenditure Management 22 22
Senegal-Third Governance and Growth Support Credit - P150976
Original Actual
Major Sector
Agriculture, Fishing and Forestry
Other Agriculture, Fishing and Forestry 10 10
Public Administration
Other Public Administration 30 30
Education
Other Education 20 20
Health
Health 10 10
Industry, Trade and Services
Other Industry, Trade and Services 30 30
Major Theme/Theme/Sub Theme
Private Sector Development
Business Enabling Environment 25 25
Investment and Business Climate 30 30
ICT 22 22
ICT Solutions 22 22
Public Sector Management
Public Administration 22 22
Transparency, Accountability and Good Governance 22 22
Public Finance Management 22 22
Public Expenditure Management 22 22
E. Bank Staff
SN- First Governance and Growth Support Project - P128284
Positions At ICR At Approval
Vice President: Makhtar Diop Makhtar Diop
Country Director: Louise Cord Vera Songwe
Practice
Manager/Manager: Lars Christian Moller Miria Pigato
Task Team Leader: Paolo Zacchia Mamadou Ndione and Philip
English
ICR Team Leader: Julio Ricardo Loayza
ICR Primary Author: Philip English
SN- Second Governance and Growth Support Credit - P126470
Positions At ICR At Approval
Vice President: Makhtar Diop Makhtar Diop
Country Director: Louise Cord Vera Songwe
Practice
Manager/Manager: Lars Christian Moller Miria Pigato
Task Team Leader: Paolo Zacchia Philip English
ICR Team Leader: Julio Ricardo Loayza
ICR Primary Author: Philip English
Senegal-Third Governance and Growth Support Credit - P150976
Positions At ICR At Approval
Vice President: Makhtar Diop Makhtar Diop
Country Director: Louise Cord Vera Songwe
Practice
Manager/Manager: Lars Christian Moller Seynabou Sakho
Task Team Leader: Paolo B. Zacchia Philip English and Jean Michel
Marchat
ICR Team Leader: Julio Ricardo Loayza
ICR Primary Author: Philip English
F. Results Framework Analysis
Program Development Objectives (from Program Document)
The Program Development Objective is to support the Government’s efforts to improve
economic governance, and promote growth through private sector development.
Revised Program Development Objectives (as approved by original approving authority)
No change.
Indicator(s)
SN- First, Second and Third Governance and Growth Support Credits – P128284, P126470,
P150976
Indicator Baseline
Value
Original
Target Values
(from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
1. Percentage of holders of public
office defined in the asset
declaration law who have made a
declaration of assets
3 persons 100% 100% 52%
as of May 2016
Comment: Target 52% achieved (Source: OFNAC Annual Report). Unlikely to have exceeded
60% by end 2016.
2. Delay in the publication of the
Audit Court annual report after
the year of the report 34 months 12 months 12 months 18 months
Comment: Target 73% achieved (The 2014 report was only published in June 2016).
3. Budget Credibility for Basic
Education wage and salaries
(Ratio executed to approved
budget)
>110 100 100 108
Comment: Target only 20% achieved (The revised budget in the 2016 LFR has been used to
approximate final spending. The total operating budget has been used since disaggregated data
for wages and salaries was not available and in any case wages account for most operating
expenditures. Note that the LFR operating budget was only 2.3% above the LFI budget in 2015,
so there appears to have been some backsliding. (Source: Ministry of Economy, Finance and
Planning website)).
4. Budget Credibility for
University Education (Ratio
executed to approved budget) 133 110 <105 107.5
Comment: Target 91% achieved (Despite considerable progress. Once again, the 2016 LFR
operating budget was compared to the 2016 LFI operating budget. Investment spending is not
considered since the objective was to improve management of the operating budget. Note,
however, that the 2015 figure was 116.6. Even though the decreasing trend is appropriate, it
would be good to have one more year to confirm that the progress has been sustained. (Source:
Ministry of Economy, Finance and Planning website))
5. Share of girls in the total
number of students receiving
scholarships (percent) 35% 40% 40% 36.7%
Comment: Target 34% achieved. (Source: Education TTL and focal point, based on Ministry
of Education information)
6. Hospital efficiency index 79.54 85 85 90 (2015)
Comment: Target surpassed. (Source : Consultant’s report, Mesure de la Performance des
Ressources Humaines dans le Secteur de la Santé, Dec. 2016)
7. Percentage of assisted births 65% 70% 70% 53% (2015)
Comment: No progress made. (No progress has been made, but the decline is surprising. No
estimate for 2016 was available. (Source: Enquête de la Démographie et la Santé) )
8. Percentage of subsidized
agriculture inputs allocated
through new e-platform
0% 90% 90% 0%
Comment: No progress made. (No progress on the indicator, but work has proceeded on
designing and developing the system, which is ready to be implemented. Minister of Agriculture
received the electronic platform and is currently preparing it to upload the data on allocation
before transfer of subsidies can begin. (Source: WB Agriculture TTL and focal point))
9. Percentage of functioning
agencies with a performance
contract 0% 50% 90% 70%
Comment: Target 70% achieved (The action plan for the rationalization of agencies proposed
to reduce the number from 44 to 30. While there may now be more agencies than this, we
accepted 30 as the appropriate number of agencies needing performance contracts. By end 2015,
13 had such contracts, with another 8 planned for 2016. There should therefore be 21 out of 30
agencies covered by end 2016, or 70%. Note that another 16 organizations were expected to
finalize performance contracts by the end of 2016, and 30 more contracts were scheduled for
2017 – which should cover the remaining agencies. (Source: Technical committee for
restructuring and Directorate for the Para public Sector, Ministry of Finance)
10. The number of government
programs with results framework
approved by the M&E Unit 0 5 10 10
Comment: Achieved (Source: Technical committee for restructuring and Directorate for the Para
public Sector, Ministry of Finance)
11. Undistributed energy due to
load shedding 250GWH 10GWH 10GWH 34GWH
Comment: Target 90% achieved (Source: World Bank energy TTL and focal point)
12. Government Subsidies to the
electricity sector for tariff
compensation
CFAF105
billion
CFAF50
billion
CFAF50
billion CFAF76 bn.
Comment: Target 53% achieved. (Actual subsidies were eliminated by 2016 thanks to the fall
in oil prices. But in order to assess the progress made in reforms, an estimate has been made of
the level of subsidies that would be required if the price of oil had remained at the price of 2012
which was roughly $100/barrel. (Source: World Bank energy team))
13. SENELEC’s debt to equity
ratio 3 <1 <1 0.9
Comment: Achieved. (Source: World Bank energy team)
14. Paying taxes: Number of
payments and time required
59;
666 hours
37;
318 hours
37;
318 hours
58;
441 hours
Comment: No progress on first indicator. Second target was 65% achieved. (Source: 2017
Doing Business Report)
15. Registering Property: Time
required and cost as % of
property value
122 days;
20%
65 days;
12%
65 days;
12%
71 days;
10.2%
Comment: First target 89% achieved; second target surpassed by 22%. (Source: 2017 Doing
Business)
16. Construction permits: Time
required 210 days 150 days 150 days 202 days
Comment: Target only 13% achieved. (Source: 2017 Doing Business)
17. Number of arrivals by air 868,649 875,000 875,000 948,000
Comment: Achieved. (Source : DPEE, Point mensuel de conjoncture)
G. Ratings of Program Performance in ISRs
SN- First Governance and Growth Support Project - P128284
No. Date ISR
Archived DO IP
Actual
Disbursements
(USD millions)
1 10/28/2013 Moderately Satisfactory Satisfactory 55.18
H. Restructuring (if any)
Not applicable.
1
1. Program Context, Development Objectives and Design
1.1 Context at Appraisal
1. In the decade since 1995, Senegal enjoyed robust per capita GDP growth but,
starting in 2006, the economy was buffeted by a series of domestic and external
shocks. Real annual gross domestic product (GDP) growth stood at only 3.3 percent in
2006-11, down from an average of 4.4 percent in 2000-05. Sharp agriculture decline over
2006-7 was followed by the onset of the global financial crisis in 2008 and its deepening
in 2009. Continued electricity shortages further contributed to the general slowdown of the
country’s economic activity. Real GDP growth slowed again in 2011 to 2.6 percent, due to
energy shortages and a large contraction in agricultural output. Weaknesses in fiscal policy
and public financial management were compounded by the fiscal costs of untargeted
subsidies for electricity and food. As a result, there was a significant increase in borrowing
and the fiscal deficit was projected to rise to 8.1percent of GDP in 2012.
2. After elections judged to be free and fair, a new government under President
Macky Sall took power in April 2012 at the head of a multi-party coalition. President
Sall faced major challenges. These include restoring trust in the state, after repeated
allegations of corruption under the previous regime, as well as urgent popular demand for
action on jobs and the high cost of living. However, having run on a platform of restoring
macroeconomic balances and reinstating good governance, transparency and
accountability, the new president had limited capacity to implement programs due to a
large fiscal deficit including huge electricity subsidies.
3. In order to reduce the deficit without affecting public investment, the
government needed to rationalize recurrent spending. A number of current expenditure
components had increased substantially in past years. For instance, agencies, hospitals and
agricultural subsidies were areas in which spending was growing quickly with limited
control or accountability, and significant leakages. Similarly, education was among the
largest budget expenditure categories, and was consistently overrun during the course of
the year. This was particularly true of the university budget, which often led to delays in
salaries or scholarships, resulting in social unrest. Consequently, the government was keen
to control the growth in current spending and reduce social disturbances. Tackling these
issues would also strengthen governance.
4. The new government wished to improve the rate of economic growth and job
creation through stronger investment from the private sector. Private investment
needed to shift from residential construction and real estate to more productive, job-
creating enterprises. To this end, enhancing the investment climate was a high priority for
the government as Senegal was lowly ranked on the Doing Business scale, in 166th place.
Also, problems in the energy sector were one of the key constraints, as electricity tariffs
were among the highest in Africa – despite substantial subsidies –, and frequent power cuts
had forced many enterprises to invest in expensive generators. In effect, energy was
perceived by most entrepreneurs as one of the major restrictions to investment.
2
5. Finally, there was broad recognition that Senegalese governments have had
trouble implementing their various strategies in the past. Technical capacity did not
seem to be the problem, even if some ministers of the new government had limited
experience in the public sector. In effect, the Senegalese civil service is relatively strong
and turnover was relatively low, as senior officials tend to remain in place even under
government changes. Non-satisfactory implementation seemed to be related to a lack of
accountability which in turn was hampered by the weakness of the monitoring and
evaluation system. The new President was well aware of this shortcoming and announced
measures to promote performance and social accountability. These included enhancing the
linkages between the development strategy and the budget, as well as their transparency1.
Previous World Bank support and Rationale for Continued Intervention
6. The proposed program represented a continuation of budget support provided
over the previous six years. Most recently, a series of two poverty reduction support
credits, PRSC4 (P128284) and PRSC5 (P126470), had supported the government between
2009 and 2011. These had had mixed results but were rated moderately satisfactory in the
Implementation Completion and Results Report (ICRR). There was no Country
Partnership Strategy in place at the time this new series was designed. However, it became
an integral part of the new CPS which was approved in 2013. The new Country Partnership
Strategy (CPS) had two pillars – accelerating inclusive growth and creating employment,
and improving service delivery – and one foundation – strengthening the governance
framework and building resilience. Hence, the Operation was fully aligned with both pillars
and with the one foundation. It was felt that the democratic election of a new government
offered a crucial opportunity to break with the past and promote more ambitious reforms.
In response to the overwhelming demands from civil society for improved governance, the
new president had made important commitments. The long-standing mismanagement of
the electricity sector, the crisis in higher education and health services, the neglect of rural
areas, and the lack of jobs were other prominent themes among voters. The proposed series
would launch the adoption of several critical but overdue reforms and support the
government in the necessary follow-up over the next two years. These reforms would
underpin major projects supported by International Development Association (IDA) in the
energy, education, health and agro-business sectors. At the same time, the operation would
provide badly-needed financial support at a time when the government has been grappling
with unanticipated costs resulting from the 2011 drought.
7. The macroeconomic framework was judged to be adequate at the start of the
program and remained so throughout. After steadily rising fiscal deficits under the
previous regime, the Macky Sall government committed to reversing this trend and in 2012
the deficit was projected to fall to 5.9 percent from 6.7 percent the previous year – and
contrary to the former expectations of a higher deficit. It also continued to implement its
1 In the same sense, President Sall also invited Tony Blair to Senegal to advise him on service
delivery.
3
Policy Support Instrument with the International Monetary Fund (IMF), completing the
fourth review in October 2012. In 2013, the authorities requested an extension of the IMF
program by one year, further demonstrating their commitment to fiscal prudence. The fiscal
deficit was projected to decline to 5.4 percent. The authorities maintained this trend, with
this deficit falling to 4.9 percent in 2014, 4.7 percent in 2015 and a projected 4.2 percent
in 2016. Domestic resource mobilization was the best in the WAEMU region, with taxes
exceeding 19 percent of GDP throughout the period. Meanwhile GDP growth responded
to the improved macroeconomic management and structural reforms, rising steadily from
2.1 percent in 2011 to 4.7 percent in 2014 and a projected 5.1 percent in 2015. Inflation
remained subdued throughout the period. A summary of key economic indicators over the
course of the program, as estimated or projected at the time of appraisal of the third
operation, is provided in Table 1.
Table 1: Senegal: Selected Economic Indicators, 2011-2016
2011 2012 2013 2014
estimated
2015
projected
2016
projected
GDP growth rate (%) 2.1 3.5 3.6 4.7 5.1 5.9
Consumer inflation (%) 2.7 1.3 0.7 -1.1 -0.9 1.5
Fiscal balance/GDP -6.7 -5.9 -5.5 -4.9 -4.7 -4.2
Total revenues/GDP 22.4 23.3 22.7 24.2 24.3 24.2
- Taxes/GDP 18.9 19.2 19.2 19.2 19.3 19.5
Total expenditures/GDP 29.1 29.2 28.2 29.2 29.0 28.4
- Current/GDP 18.1 17.5 17.3 18.1 17.2 16.7
- Capital/GDP 10.5 11.4 11.0 11.1 11.8 11.7
Total public debt/GDP 40.5 43.4 46.6 53.2 55.9 57.6
Source: World Bank Program Documents for GGSC2 and GGSC3.
1.2 Original Program Development Objectives (PDO) and Key Indicators
8. The original overarching objective of the programmatic series was to support
implementation of the new government’s reform agenda. The focus of the series was
on a set of critical policy actions to support the authorities’ efforts to improve economic
governance by strengthening government transparency and accountability, increase public
sector efficiency and effectiveness, and promote growth through private sector
development.
The original PDOs and corresponding indicators were the following:
1a. To improve economic governance by strengthening Government accountability. The
key results to be achieved by 2015 were:
The percentage of holders of public office defined in the asset declaration law that
make a declaration of assets reaches 100percent.
4
Delay in the publication of the Cour des Comptes annual report after submission to
the President decreases to no more than one month.
1b. To increase public sector performance. Key results to be achieved by 2015 were:
Credibility of the budget for wages and salaries in basic education is restored as the
ratio of executed to budget spending decreases from 110 percent in 2011 to 100
percent.
The ratio of the executed university recurrent budget to the approved budget
decreases from 133 percent to 100±5 percent.
The share of girls in the total number of students receiving scholarships increases
from 35 percent in 2011 to 40 percent.
The Hospital efficiency index increases from 74 percent in 2010 to 85 percent.
The percentage of assisted births increases from 65 percent in 2011 to 70 percent.
Percentage of agencies non-compliant (without performance contract) with the
2009 law reduced from 100percent to 50percent.
The number of government programs with results framework approved by the
Monitoring and Evaluation (M&E) Unit increased from 0 to 5.
2. To promote growth through private sector development. Key results to be achieved by
2015 were:
The undistributed energy due to load shedding decreases from 250 gigawatt hours
(GWH) in 2011 to 10 GWH.
Government subsidies to the energy sector decrease from CFAF99 billion (1.4
percent of GDP) in 2012 to CFAF50 billion (0.6 percent of GDP).
SENELEC’s debt to equity ratio decreases from 3 in 2011 to 1.
Time, cost, and number of procedures in the 3 selected DB indicators reduced:
- Paying taxes: Number of payments reduced from 59 to 37
Time required reduced from 666 hours to 318 hours.
- Registering Property: Time required reduced from 122 days to 65 days.
Cost reduced from 20percent of property value to 12percent.
- Getting Electricity: Number of procedures reduced from 8 to 6.
Time required reduced from 125 days to 100 days.
Cost reduced from 5625percent of per capita income to 4500percent.
Increase in the number of hectares of land classified in the domain privé des
collectivités locales, with baseline and target to be determined.
Increase in the number of hectares provided with irrigation and drainage services,
with baseline and target to be determined.
1.3 Revised PDO and Key Indicators, and Reasons/Justification
9. The Program Development Objective in the Third Governance and Growth
Support Credit (GGSC) was modified to make it more precise and aligned with the
pillars of the operation. The PDO of the Development Policy Credit (DPC) series was as
follows: (i) to support the Government’s efforts to improve economic governance, and (ii)
promote growth through private sector development. The first PDO pillar focused on the
management of public resources and has two parts: government accountability and public
5
sector performance. The second PDO pillar concerned growth and private sector
development. More specifically, the PDO pillars were: 1a) to improve economic
governance by strengthening accountability systems; 1b) to promote better governance and
efficiency in the education, health and agriculture sectors, and within agencies, and
strengthen monitoring and evaluation; and 2) to enhance private sector development
through energy sector reforms, and improvements in the investment climate, including in
the tourism sector.
10. Minor changes in the results framework were made as summarized in Table
2. The end year for targets was pushed back to 2016 to reflect the delay in the approval of
PRSC3 to 2015.
Table 2: Changes in Indicators and Targets
Original Indicator and
Target
Final Indicator and Target Reasons for Change
Pillar 1: Government accountability and public sector performance
Delay in the publication of the
Cour des Comptes annual report
after submission to the President
decreases to no more than one
month
Delay in the publication of the
Audit Court annual report after
the year of the report reduced
from 34 months to 12 months.
The original indicator did not
capture potential delays in
submission to the President.
The Hospital efficiency index
increases from 74 percent in 2010
to 85 percent
The Hospital efficiency index
increases from 79.54 percent in
2012 to 85 percent
New data for 2012 baseline
became available.
Percentage of agencies non-
compliant (without performance
contract) with the 2009 law
reduced from 100percent to
50percent.
Percentage of agencies with a
performance contract increased
from 0 to 90percent.
Made more ambitious to reflect
the fact that the 2009 law
already called for all agencies to
have a performance contract.
The number of government
programs with results framework
approved by the M&E Unit
increased from 0 to 5.
The number of government
programs with results
framework approved by the
M&E Unit increased from 0 to
10.
Target raised to better reflect
progress in the reform.
Increase in the number of hectares
provided with irrigation and
drainage services, with baseline
and target to be determined
Dropped and replaced by:
Percentage of subsidized
agriculture inputs allocated
through new e-platform
increased from 0 to 90 percent
Focus of the World Bank
program was more on input
distribution than on irrigation
and a new prior action was
introduced in this area in
GGSC3.
Increase in the number of hectares
of land classified in the domain
privé des collectivités locales,
with baseline and target to be
determined.
Dropped. It became clear that land reform
was going to take much longer
than expected.
Pillar 2: Private sector development
Getting Electricity: Number of
procedures reduced from 8 to 6.
Time required reduced from 125
days to 100 days.
Cost reduced from 5625percent of
per capita income to 4500percent.
Construction permits: Time
required reduced from 210 days
to 150 days.
Construction permits became a
higher priority for the
government and the private
sector.
6
Number of arrivals by air
increased from 868,649 in 2012
to 875,000.
Added to reflect the addition of
tourism sector reforms in
GGSC3. The number of arrivals
had fallen to 855,602 in 2014
due to Ebola.
1.4 Original Policy Areas Supported by the Program:
11. The original policy areas supported by the DPC series were: a) improving
economic governance by strengthening Government accountability; b) increasing public
sector performance; and c) promoting growth through private sector development. All three
constituted key elements of the National Strategy for Economic and Social Development.
Improving economic governance by strengthening Government
accountability: The reforms supported by the first operation focused on a draft
transparency law consistent with the WAEMU guidelines, and a draft law
strengthening the independence of the general auditor. These were to be followed
by approval and implementation of a law on asset declaration, and further measures
to improve the effectiveness of the general auditor.
Increasing public sector performance: Reforms focused on improving financial
management in education and health, expanding in the second and third operations
to include agency reform and monitoring and evaluation. In basic education, the
emphasis was on personnel management, while in tertiary education, the focus was
on a new financial regime to capture fees being earned through external services.
In the health sector, performance contracts were supported across a growing
number of hospitals. Agency reform concentrated on a rationalization plan and
performance contracts for those not being closed. In M&E, the series supported the
creation of a unit in the President’s office to improve implementation of policy
priorities. These measures were intended to enhance the efficiency, transparency
and performance in key sectors while generating fiscal savings which could be
reallocated to more pro-poor programs and public investment.
Promoting growth through private sector development. The initial focus was
on improving the efficiency and sustainability of the energy sector, by way of a
new Sector Development Policy Letter and Action Plan, and the financial and
operational restructuring of SENELEC, the state-owned electricity company. This
was to be followed by signature and implementation of a performance contract for
SENELEC, and preparation of a new electricity law. Better energy sector
management would improve electricity service delivery and support economic
growth. Subsequent operations in the series were expected to improve the
investment climate by supporting Doing Business reforms in three areas – taxes,
property registration and access to electricity. Agriculture was to be supported
through land reform and irrigation maintenance.
7
1.5 Revised Policy Areas
12. These policy areas were largely maintained throughout the series. However,
land reform was dropped when it was realized that it was going to take much longer than
expected. It was replaced in the final operation with a measure to enhance targeting in
agricultural subsidies in order to increase efficiency in the use of fiscal resources. In the
area of the investment climate, one of the Doing Business reforms was changed from
improving access to electricity to reducing delays in obtaining construction permits, which
emerged as a higher priority for the private sector and the government. In addition, the third
operation added the removal of barriers for tourism, to help the sector cope with the Ebola
shock.
1.6 Other significant changes
13. The final operation was increased by US$20 million at the preparation stage.
This change was introduced in response to the government’s request for help in coping
with the Ebola crisis which had seriously affected the tourism sector. Consequently,
reforms were added in the tourism sector. Approval and disbursement of the third operation
was delayed by six months to allow the authorities time to complete key reforms in asset
declaration and M&E.
2. Key Factors Affecting Implementation and Outcomes
2.1 Program Performance
14. The programmatic series consisted of three single-tranche Development Policy
Credits disbursed upon effectiveness, in the total amount of SDR91.4 million or
US$135 million. GGSC3 was increased by US$20 million to help the authorities cope with
the Ebola crisis.
Table 3: Key Dates of the DPC series
Operation Approval
Date
Effectiveness
Date
Disbursed Amount
SDR millions
Closing
Date
GGSC 1 12/20/2012 12/28/2012 35.8 03/31/2014
GGSC 2 12/19/2013 12/23/2013 19.6 03/31/2015
GGSC 3 7/23/2015 08/15/2015 36.0 07/31/2016
15. Macroeconomic management and performance has improved over the time
period covered by this budget support series. The fiscal deficit fell to 4.2 percent in 2016
as projected. GDP growth exceeded expectations, rising to 6.5 percent in 2015 and
remained above 6 percent in 2016. Debt to GDP continued to rise but the rate of growth
slowed and the risk of debt distress remains low, according to the IMF-WB Debt
Sustainability Analysis. The authorities are committed to further reductions in the fiscal
deficit in order to reach the WAEMU target of 3.0percent of GDP by 2018 and to prevent
8
debt-to-GDP rising above 60 percent. In addition, efforts to control current expenditures
allowed the government to increase public investment, despite the falling overall fiscal
deficit. Governance indicators have also improved (see section 3.2).
16. The program should help control the fiscal deficit in the long-term though its
contribution in the short-term was probably minimal. Improvements in the education
human resources data base helped reallocate teachers and reduced the need for additional
recruits. However, the failure to link this data base to the payroll system at the Ministry of
Finance delayed further gains. Changes in the criteria for scholarships and the financial
regime for universities to incorporate external fee-based services helped control the growth
in the higher education budget. Agency rationalization did not result in short-term savings
due to the limited progress made and the required compensation for laid-off staff. If
pursued, it will have longer-term benefits. Similarly, the gains from the e-platform for the
distribution of subsidized agricultural inputs depend on its implementation. Reforms in the
electricity sector are slowly reducing costs, but the main factor in eliminating subsidies has
been the fall in world oil prices. In general, the IMF program played a major role in
supporting deficit reduction in the short-term.
17. There has been no slippage in the reforms supported by the three operations
so far; however, follow-up implementation has lagged. For example, the system for
managing subsidized agricultural inputs was still not being used in 2016, despite the
sector’s commitment to its eventual application. Rationalization of agencies has proceeded
more slowly than expected. The special accountants deployed in key faculties of the
University of Dakar are still not reporting to the chief financial officer of the university. In
2016, coordination between the monitoring and evaluation unit established at the
Presidency and the finance ministry was still unsatisfactory; the role of the M&E unit
probably needs to be reconsidered. The status of all the prior actions is summarized in
Annex 3 while the changes in triggers are explained in the following tables.
Table 4: Changes in Triggers for GGSC2 GGSC1 Triggers for GGSC2 GGSC2 Prior Actions Explanation
Pilar 1: Government accountability and public sector performance
Establish effective payroll and HR
control in education by linking
HR databases for contractual
agents and civil servants and the
Payroll Database.
Postponed to GGSC3 Reform taking longer than
expected.
Adopt 2013 budget for
universities and others higher
education institutions which are in
compliance with the revised
financial regime of the
universities.
Adopt 2013 budget for the two
largest universities which are in
compliance with the revised
financial regime of the
universities; and adopt new
criteria for scholarships
Limited to two largest
universities given delays in
implementation, but
strengthened to capture
scholarship reforms originally
expected in year three.
Finalize the evaluation of
100percent of the autonomous
agencies; and implement
evaluation recommendations
including closing agencies that are
not considered relevant.
Finalize the evaluation of
autonomous agencies; and
approve an action plan including
the closure and merger of some
agencies
Modified to reflect the need
for political endorsement of an
action plan after the
evaluation.
9
Pillar 2: Private sector development
Improve Doing Business
indicators in the area of paying
taxes (reduction in number of
payments and time to fill forms).
Improve business climate by i)
enacting a law simplifying
property registration procedures
and ii) revising its tax code to
reduce property taxes and reduce
the time required for other tax
payments.
Modified to clarify the tax
reform, and strengthened to
include property registration
reform.
Adoption by the Council of
Ministers of a roadmap for land
management reform.
Dropped. Land reform was going to take
much longer than expected.
Table 5: Changes in Triggers for GGSC3 GGSC2 Triggers for
GGSC3
GGSC3 Prior Actions Explanation
Pilar 1: Government accountability and public sector performance
Implementation of the asset
declaration law.
The Recipient has operationalized its asset
declaration system by: (a) approving the related
implementation decree; (b) allocating
appropriate human and financial resources to
the national office for the fight against fraud and
corruption (“Office National pour la Lutte
contre la Fraude et la Corruption”/”OFNAC”);
and (c) ensuring deposition of asset declarations
by ministers holding a portfolio to OFNAC.
Elaborated to
clarify measures
needed for
implementation.
Develop effective follow-up
of recommendations from the
Annual Report of the Audit
Court.
Dropped. Dropped to make
room for other
reforms.
Improve payroll and HR
controls in education by a)
linking databases of the
ministries of education, civil
service and finance; b)
preparing the 2014/15
recruitment plan for education
in consultation with ministry
of finance; and c) eliminating
ghost and double-counted
teachers.
The Recipient has strengthened wage bill
control and human resources in the education
sector by: (a) creating a system connecting data
bases of the ministries in charge of education
and civil service; and (b) preparing the 2015-
2016 recruitment plan for education in
collaboration with the ministry in charge of
finance.
Modified to reflect
delays in linking
database to payroll,
and consequently
also in eliminating
fictitious teachers.
Implement the Presidential
directives to improve the
utilization of own resources
generated by universities by a)
adopting an arrêté defining the
utilization of these resources;
b) preparing a manual of
procedures; and c) creating
secondary accounting offices
in key faculties and schools.
The Recipient has implemented presidential
directives on external revenues earned by
universities through: (a) adoption and
submission to Parliament for enactment of a
draft law reforming universities governance
system; (b) issuance of an Arrêté specifying
resource allocation and use of external
revenues; and (c) appointment of accountants in
key faculties and schools at the University of
Dakar, who report to the chief financial officer.
Strengthened to
include the new
governance law, but
weakened to reflect
the difficulty of
assigning secondary
accountants.
Adopt a decree defining a new
financial regime for hospitals,
along with necessary arrêtés.
The Recipient has adopted a new financial
regime for public agencies and establishments,
and has entered with five additional public
health institutions into performance contracts
whose objectives are to increase service supply,
Strengthened to
include additional
performance
contracts, but
weakened to allow
10
improve billing process and control general
costs.
more time for the
necessary arrêtés.
Adopt a new e-platform and
have 1 million farmers
registered such that at least
half of subsidized agriculture
inputs are allocated through it
to reduce leakages and
improve targeting.
The Recipient has adopted a mobile phone-
based e-platform to distribute subsidized
agricultural inputs in the 2015 crop season.
Weakened to allow
for delays in
implementing the e-
platform but
strengthened to
include an
irrigation measure
as originally
envisaged.
Preparation of a properly
costed, funded and time-
bound action plan for SAED
which clearly defines roles
and responsibilities; sign 2
multi-year maintenance
contracts.
Recipient has obtained approval allowing SAED
to enter into multi-annual maintenance contracts
of hydro-agricultural works with private
contractors and launched a call for bids.
Simplified to
streamline the
policy matrix and
reflect need for
approval from the
finance ministry.
Close and merge some
agencies; and sign a
Performance Agreement
between all remaining
agencies with a budget over
CFAF1 billion and the
Oversight Institution.
The Recipient has launched implementation of
the action plan to restructure autonomous
government-owned agencies, by: (a) merging
certain selected agencies; (b) appointing officers
responsible for the liquidation of certain
selected agencies; and (c) entering with six of
the largest agencies into performance contracts
with the objective of clarifying the financial
commitments of the Recipient’s ministry
responsible for finance and the related
performance targets of agencies concerned
Modified to better
correspond to the
government’s
reform agenda. The
six agencies
covered represented
most of those with
budgets over
CFAF1 billion.
Pillar 2: Private sector development
Approval by the Council of
Ministers of the revised
electricity investment plan for
2014-18; separation of
SENELEC’s accounts
between generation,
transmission and distribution:
and a publicly-available
financial model.
The Recipient has amended the performance
contract entered into between the Recipient and
SENELEC on June 11, 2013 to include
performance-based bonuses and sanctions, and
has amended the agreement regularizing cross-
debt entered into between the Recipient and
SENELEC dated November 16, 2012, to
determine the method for the balance allocation.
Modified to focus
on the full
implementation of
previous prior
actions in the
program.
Improve business climate
indicators in the two areas: 1)
Trading across borders
(reduce the number of days
for importing and exporting)
and 2) Dealing with
construction permits (reduce
number of days).
The Recipient has: (a) issued (i) a decree
reducing the number of days and costs to obtain
construction permits through the creation of a
single window and online processing; and (ii) a
decree determining a new fee schedule for
warehouse inspection; and (b) eliminated the
minimum capital requirement for creating a new
company.
Modified and
strengthened to
reflect the
authorities’
priorities in Doing
Business indicators.
The Recipient has offset the impact of Ebola’s
on the tourism sector by: a) removing entry
visas’ fees; b) reducing selected taxes on air
tickets; and c) suspending recovery acts initiated
against hotels with arrears in payment of
patented and land taxes in 2015.
Added to support
the authorities’
request for help in
coping with the
Ebola crisis.
11
2.2 Major Factors Affecting Implementation:
Capacity
18. The program benefited from a strong World Bank field presence and close
linkages to on-going projects and economic and sectoral work. All of the policy areas
were supported by Task Team Leaders (TTLs) in the field during most of the program,
with relatively few changes in personnel. All of the prior actions were related to and
supported by investment projects or technical assistance.
19. On the other hand, capacity limitations within the government constrained the
effectiveness of the operation. Coordination and following up of the program at the
Ministry of Economy, Finance and Planning (MEFP) did not receive full institutional
support2. The MEFP agreed to broaden the support supplying additional human resources
dedicated to monitoring different sectors and following-up on their reform agendas, but
this change did not become effective. World Bank staff were required to make significant
efforts with sector ministries and high-level authorities in order to facilitate completion of
prior actions, but last-minute scrambles still occurred for the first two operations to permit
disbursement before the end of the government’s fiscal year. This persisted over the life of
the operation, despite complaints from several partners whose operations were adversely
affected by this situation.
Design
20. The broad, ambitious design of the program was a key challenge for
implementation. It would have been easier for the MEFP to follow-up on the reform
agenda if it had been concentrated on fewer sectors, emphasizing those where ownership
was stronger, and avoiding sensitive areas where presidential intervention might be
required. Three of the reform areas were especially sensitive: asset declaration for public
servants, agency rationalization, and the establishment of a central unit to monitor policy
priorities. All three were important objectives of the government’s program. But this still
made the coordination effort more difficult for the finance ministry.
21. In at least one case, the reform appears to have design flaws, resulting in delays
and reduced impact. Following World Bank advice, the M&E unit was based in a small,
relatively independent department within the Presidency, an approach partially inspired by
the United Kingdom (UK) example. However, this was implemented with minimal input
from key internal counterparts, notably the MEFP. Then, the Presidency created a parallel
unit monitoring the implementation of the country’s new growth strategy, with an emphasis
on priority projects, which reduced the focus on developing the first unit. Furthermore, in
many sectors the proposed M&E system competed with others, overloading the limited
2 The unit responsible for following up the budget support program was severely understaffed as the task
was primarily the responsibility of a senior advisor, concurrently with other duties.
12
capacity at the ministerial level. 3 Effective systems for monitoring priorities were
implemented in at least five sector ministries, thanks to strong support from the World
Bank. However, its sustainability remains in question. In retrospect, ampler participation
of the MEFP would have helped to strengthen the program design, given its mandate and
human resources.
Background analysis
22. The program was generally well-supported by background analysis with one
notable exception. The reforms in education and health drew on a recent Public
Expenditure Review and considerable sector work. The asset declaration reform was
informed by an analysis of international experience commissioned specifically for this
program. An evaluation of agencies provided the basis for the action plan of agency
rationalization. Electricity sector reforms built on years of experience in Senegal. However,
the M&E proposal was not based on an assessment of the current situation and that may
have contributed to its weak design.
Ownership
23. Reforms could have benefited from stronger ownership in the Ministry of
Economy, Finance and Planning. For instance, application of the new finance regime for
universities was delayed for half a year until a new budget nomenclature was finalized by
the MEFP. The agreement with SENELEC on cross-debts did not come into effect for two
years due to the absence of an agreement on how to utilize the remaining balance. The link
between the education human resource data base and the payroll at the Treasury had to be
dropped from the program objectives at least in part due to delays in the payroll department.
The effectiveness of agency performance contracts was sometimes jeopardized by failure
to live up to the finance ministry’s commitments in terms of budget allocations.
24. Ownership was also an issue in the agriculture and energy sectors. In spite of
strong support from the World Bank, implementation of the new subsidized input platform
has been delayed due partly to low ownership coupled with unexpected technical
challenges. This required weakening the GGSC3 prior action and failure to make any
progress on one of the outcome indicators. The energy sector would have benefited from
stronger leadership in SENELEC, which did improve following changes in its
management.
25. In two areas, where ownership was strong and complexity of reforms was less
demanding, implementation went relatively smoothly. One of these areas was
3 ACT for Performance, Diagnostic des dispositifs de suivi-évaluation des politiques publiques au Sénégal,
June 2016.
13
investment climate reform, which was spearheaded by APIX. This agency enjoyed strong
staff and a clear mandate to improve the country’s Doing Business ranking. It also
benefited from the high profile and rigorous deadlines of the Doing Business exercise
which pushed these reforms quite independently of the budget support program. The other
area of smooth implementation was the health sector where the sector Ministry had an
incentive to complete hospital performance contracts because they received additional
investment financing in return. However, it is also true that in both cases the required
reforms were less technically complex or politically sensitive as other reforms in the
program.
26. Evolving high-level leadership further complicated coordination and
monitoring. The initial strong commitment to the reforms included in the operation
fluctuated over time due to changes of high-level authorities, including the Prime Minister,
the key Ministry of Finance and sector Ministries.
Risk identification and mitigation
27. Risks were clearly identified but mitigation options were limited. Risks
included global economic shocks, regional instability, the challenges posed by maintaining
the political coalition, vested interests and the recent history of poor governance, and
insufficient political and administrative capacity aggravated by the change in government.
It was hoped that electricity sector reforms would mitigate the impact of a spike in oil
prices, while improvements in the investment climate would help diversify the economy
and reduce its vulnerability. Vested interests would be mitigated by the government’s
commitment to a three-year program of reforms and the intensive field-based supervision
by the Bank team. Donor coordination would help maintain political support by providing
a common message to government. The M&E reform was expected to increase
accountability for reforms by focusing the President’s attention on key issues.
28. Mitigation measures were partially effective but might have been given greater
attention. Supervision, both at the technical and strategy level, was indeed intense.
Regular, frequent meetings were held with the key Ministries and communication was
generally good with the Primature and the Presidency. Donor coordination was also given
ample attention, and cooperation with the IMF was particularly useful. A joint donor effort
was made to change the modality for budget support supervision in the finance ministry.
The M&E unit in the Presidency showed initial signs of success. But ultimately the
influence of vested interests was probably underestimated. This might have been better
addressed by more focus on policy areas with high ownership, better design of the M&E
reform, and a willingness to detach disbursement from end-of-year fiscal deadlines.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization:
Design
Rating: Modest
14
29. Many of the indicators chosen were appropriate, but in some cases it would
have been better to identify output rather than outcome indicators, in order to
strengthen appropriation. This is the case, for instance, for the indicators on gender, basic
education, tourism and some related to the energy sector. In effect, these indicators had
somewhat weaker links to the corresponding reforms as they reflected the broader progress
of the sector. The two gender indicators have the weakest link. Some targets were overly
ambitious given the general pace of reform in Senegal, and the complexity of the task at
hand. This is true of the investment climate reforms. It was probably unrealistic to expect
full compliance with the asset declaration law within 18 months, considering the important
political sensibilities involved. Preparing performance contracts with all agencies was
particularly difficult since each agency was different and faced a different set of challenges.
In addition, each contract had to be negotiated with the corresponding agency. The
authorities appear determined to meet all the targets in these areas but it will take more
time than initially programmed. In other areas, such as agricultural input distribution, the
degree of ownership was lower than initially estimated.
Implementation
Rating: Substantial
30. The M&E framework remained fairly stable over the course of the program.
Of the 17 original indicators, only 3 were dropped (see Table 2). One of those dropped, a
Doing Business indicator, was replaced by a different Doing Business measure to reflect
government priorities. Another one, in agriculture, was replaced by a different agriculture
indicator more aligned with the priorities of the program. The land reform indicator was
dropped when this policy area was eliminated from the program. A tourism indicator was
added to capture the addition of this policy area in the final year. The targets also remained
stable; none were lowered, and two were raised in keeping with the ambitions of the
program.
Utilization
Rating: Negligible
31. There is no indication that the results framework was used as a decision tool.
This is not unusual for a DPC series.
2.4 Expected Next Phase/Follow-up Operation:
32. The World Bank will continue to support the Government of Senegal in some
of the areas of the DPC series. A new DPC series is under preparation with a narrower
focus on energy and ICT, partially building on the energy components of the previous
series. The first operation of the series was approved by the Board in June 2017.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
15
Objectives
Rating: Substantial
33. The program was strongly aligned to both the country’s priorities and the
Bank strategy. For the new government, it was important to improve the country’s
governance, its investment climate, and the performance of the energy sector and higher
education. The MEFP was particularly concerned by the high level of energy and
agriculture subsidies. It was also concerned by the conflictual relationship with the
universities which routinely overspent their budgets and required major supplementary
allocations late in the year, with the implicit threat of strikes and social unrest if their
demands were not met. The program addressed all these issues. The focus on
rationalization and performance of agencies supported the government’s PSI program with
the IMF. The addition of the tourism sector in the final year of the program was in direct
response to the government’s request for help to deal with the impact of the Ebola threat.
The program was closely aligned with the Bank’s investment projects and technical
assistance and with the Strategy that has been approved later, which focused on
governance, growth and service delivery.4
34. Promoting reform in the energy sector implied high risks, given past
experience, but neglecting this sector would have been worse. The Bank had worked on
this sector off and on for at least 15 years, with little success. A sector adjustment loan had
been cancelled after its first disbursement due to lack of progress. However, it was clear
that economic progress would be difficult without improvements in the energy sector,
given the importance of the sector for private activity, and the frequency of blackouts. Also,
no other donor was willing to tackle the tough reforms required. As it turned out, progress
was slow but steady, assisted by a large Bank investment project and coordination with
IFC. The eventual change in the leadership of SENELEC also helped. On balance, the
decision to support reforms in the sector seems to have been worthwhile, and the World
Bank proposes to continue this dialogue in the follow-up budget support operation.
Design
Rating: Modest
35. The chosen areas of reform corresponded closely to the Bank Group’s country
strategy, on-going operations, analytical work and technical assistance. The Bank had
projects supporting the energy, agriculture, and basic and higher education sectors, with
important components to promote reforms, including performance contracts for SENELEC
and all universities, as well as changes in financial management. There was also a public
financial management project which included support for agency reform and the creation
of an M&E/service delivery unit. Prior to the program, the Bank had conducted a public
4 The new CPS was approved in early 2013.
16
expenditure review, with a focus on education and health, and during the program’s
implementation the Bank provided technical assistance on asset declaration, and hospital
reform. Both the Bank and IFC assisted with investment climate reform, and the Bank
provided analytical support on tourism in preparation for a new project. Thus, all the prior
actions in this program were informed by and supported parallel investment operations or
technical assistance in the World Bank Group portfolio.
36. An initial choice had to be made between a one-year stand-alone operation and
a programmatic series. A decision was taken to support the new government with a
programmatic series based on the depth of the reforms outlined in the government’s
program. However, the government’s ownership of the program was not strong and seemed
to weaken over time, elements that were not fully assessed by the Bank during preparation.
The government appeared to understand that it did not need to take a more proactive role
in order to secure budget support from its partners. With less than nine months between the
inauguration of the new government and the end of the fiscal year, time was short to
establish priorities and negotiate a full three-year program. In retrospect, it probably would
have been better to start with a stand-alone one-year operation. Waiting one year would
have permitted a deeper engagement with the government on program design, based on a
more mature development strategy, thereby increasing ownership.
37. The program design did start slowly and pursued a consistent three-year logic
in each sector. Almost every sector had a sequence of reforms over the three operations
laid out in the initial program document. In some cases, there was no prior action in the
first year but rather a first procedural step to lay the foundations for deeper reform. Only
in the area of irrigation was this not the case. However, the program eventually covered a
large number of sectors and actors. This reflected the initial vision of the Bank to pursue a
wide-ranging, ambitious reform agenda. A more focused program would have facilitated
government implementation, and allowed the Bank to focus on areas where ownership was
greatest.
38. A few reforms appear to have been poorly designed. The basic education
reforms did not materialize as anticipated. The link between the education human resource
database and the payroll was pushed back from the second operation to the third one, and
even then, it was not achieved. The M&E reform has design flaws and its inclusion in the
program created additional challenges to the coordination among the Bank and the finance
ministry. The decrees produced to satisfy the prior actions did not resolve the underlying
disagreements. The agricultural input distribution platform suffered from lack of
ownership.
Implementation
Rating: Substantial
39. The prior actions remained relatively stable over time. Dropping land reform
was clearly a good idea given the complexity of the issue as borne out but subsequent
delays. This also helped to somewhat reduce the scope of the program. One reform in basic
17
education was pushed back a year to allow more time, while another reform in higher
education was moved forward from year three to reflect faster progress by the authorities.
The addition of an agriculture prior action in the final year of the program was probably
inappropriate and did not prove effective. The changes between triggers and prior actions
are summarized in Tables 4 and 5.
40. The programmatic three-year logic of the design was strengthened in the final
year in order to ensure effective implementation of earlier reforms. Thus, the third-
year governance trigger was adjusted to focus on operationalization of the asset declaration
system. Similarly, in the electricity and higher education sectors, and in M&E, the final
year looked after pending developments from the first and second year reforms. In other
cases, the third-year triggers were adjusted downward to reflect better understanding of the
pace of reform (agencies, hospitals, basic education). However, the third-year action
related to the Auditor General was dropped to provide room for measures in other sectors.
That action would have been useful to encourage implementation of recommendations in
the auditor’s report.
41. The addition of the tourism sector in the final year was justified by the need to
respond to the Ebola crisis. The government asked for extra assistance to deal with the
impact of the Ebola crisis on this sector. The amount of the operation was increased by
US$20 million, and in return it was felt that some reforms were needed. The decision to
drop the cumbersome visa system was an important one since it demonstrated that the new
government was prepared to admit when its policies were not working.
3.2 Achievement of Program Development Objectives
42. Only 5 of the 17 outcome targets were achieved. These were in the areas of
hospitals, M&E, energy, property transfer, and tourism. Another two indicators (university
budget credibility and energy load shedding) reached 90 percent of their targets. Varying
degrees of progress were made on most of the others.
Status of Outcome Targets
Achieved Not achieved Dropped Total
Pillar 1a Government accountability 2 2
Pillar 1b Public sector performance 2 6 8
Pillar 2 Private sector development 3 4 3 10
Total 5 12 3 20
PDO 1a Government accountability
Rating: Modest
43. Modest progress was made on improving economic governance by
strengthening Government accountability. The number of persons submitting an asset
declaration had risen to 52 percent of all those required to comply. As the last available
data dates from May 2016, the situation has probably improved somewhat since then. The
18
target to reduce delays in publication of the general auditor’s annual report has been 73
percent achieved. The situation looks better if we focus on the broader objective of
improved governance. Looking at the Worldwide Governance Indicators, Senegal’s
percentile ranks improved on all six criteria between 2010 and 2015. The largest increase
was for control of corruption where Senegal improved from 28 to 59. The next best was on
voice and accountability where the rank increased from 36 to 57. On the Corruption
Perception Index, Senegal’s score rose from 36 in 2012 to 45 in 2016, and its ranking
improved from 94th to 64th. Progress made on asset declaration probably contributed to
the improved scores on corruption. But many other factors also explain these
improvements.
PDO1b Public sector performance
Rating: Modest
44. Only 2 of 8 targets were achieved in the area of increasing public sector
performance. The most impressive result was achieved in hospital efficiency, though this
would have been influenced by much more than the performance contracts which were the
focus of the DPC series. The M&E target was also achieved, but the reform remains
institutionally weak and may not be sustainable. Progress varied between 20 percent (basic
education) and 91 percent (higher education) for four others. The most disappointing one
was in subsidized agricultural inputs where a new allocative mechanism was still not being
used in 2016 despite intensive support from the World Bank. The fall in assisted births was
also disappointing, though its link to the operation and indeed to the Bank’s overall
program was not strong. This indicator and the one on girl’s scholarships were added
primarily in response to the need for gender content. On the World Governance Indicator
for government effectiveness, Senegal has posted modest improvement, rising from 36 in
2010 to 39 in 2015.
PDO2 Private sector development
Rating: Modest
45. Progress was somewhat better in promoting growth through private sector
development. Three of the seven targets were achieved, a fourth was 90 percent achieved,
and significant progress was made on two others. All the reforms supported under this PDO
appear to be sustainable. Looking at the broader picture, Senegal’s ranking in Doing
Business rose from 166 in 2012 to 147 in 2016. GDP growth has improved from 2.6 percent
to 6.6 percent over the same time period. Prior actions on the investment climate helped
raise the Doing Business ranking and, together with improvements in energy sector
management, will have supported the higher GDP growth.
46. However, the link between the operation and the gains in economic growth are
tenuous. In effect, growth acceleration is linked with many factors, including a rapid
increase of agriculture production and exports (linked to good climate conditions and rising
external demand for groundnuts) or increased consumption (linked to lower oil prices and
19
gains in terms of trade). Public investment also increased, though modestly, thanks to
slightly higher fiscal space due to the cap on current expenditures and lower oil prices.
3.3 Justification of Overall Outcome Rating
Ratings: Moderately unsatisfactory.
47. Although only 30 percent of the targets were met, the operation remains
relevant and significant progress has been achieved in several key areas. It was an
ambitious, multisector nature of the program, but with modest and varying ownership. In
some cases, the choice of indicators was inappropriate choice of indicators, and some
targets were unrealistic. It is worth noting that none of the targets were weakened over the
course of the three operations, and in fact three were strengthened, reflecting the continued
emphasis on ambitious reform. Significant progress was made in some of the most difficult
areas – governance, energy and higher education. Improvements were also achieved in the
investment climate and the tourism sector. Ultimately, the program aimed high and made
some important contributions but fell short.
48. Advances in several areas – even partial – are particularly noteworthy, due to
their political sensibility, technical complexity or the existence of vested interests. For
instance, Senegal was the first WAEMU country to adopt the transparency law and put in
place an asset declaration law and process, despite mixed support from involved civil
servants. Reforms in higher education were significant given the political sensitivity of the
sector, its high conflict potential and its impact in the overall budget. The government could
initiate the process of agency rationalization and performance contracts, but additional
efforts would be needed to ensure that the action plan is fully implemented. Reforms faced
in the energy sector were highly challenging at the technical level and the involved agencies
deserves credit for achieving a number of concrete results. Similarly, reforms concerning
the M&E mechanisms require developing non trivial frameworks and coordination
mechanisms. Key ministries took the reform seriously and began developing them.
Reforms concerning subsidy distribution in agriculture faced both harsh technical
challenges and lack of commitment probably linked with vested interests.
3.4 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
49. The DPC series was expected to have a positive impact on medium-term
poverty reduction. Strengthened government accountability and institutional capabilities
would ensure greater efficiency and effectiveness of public expenditure and improve the
quality of basic services. The selected actions were expected to create fiscal space for
primary and secondary education and basic health care. The government actions to
restructure the universities and improve quality in the higher education sector and
strengthen accountability in hospitals would impact student conditions and patient care.
The e-platform for agricultural inputs would reduce leakages and help ensure that the
intended beneficiaries – poor farmers – receive seeds and fertilizers which can substantially
20
increase their productivity and incomes. Improvements in irrigation maintenance should
have similar impacts by ensuring more reliable access to water and facilitating a second
harvest during the dry season. ???All this remains true, though the failure to implement the
e-platform to date has delayed potential benefits.
50. Policy reforms on energy, higher education, and autonomous agencies might
affect selected groups. The performance contract for SENELEC may eventually lead to
some reduction in staffing, and the evaluation of agencies will result in the closure of some
agencies. However, to the extent this happens, the persons affected will be the non-poor
and will be covered by the fairly generous provisions of Senegalese law concerning
termination of public employment. The rationalization of scholarships in higher education
will focus on re-establishing the link between performance and funding, including the
removal of students who enroll simply to obtain the scholarship and never actually come
to class.
51. The proposed series was expected to have a positive impact on gender equality.
Reforms promoted in basic and higher education as well as in health care were expected to
facilitate girls’ and women’s access to social services. The hospital reform promoted by
the GGSC series was expected to improve the quality of services and save resources for
better financing of primary health clinics (centres de santé, cases de santé), particularly in
rural areas, and thus improve access to services by women. Unfortunately, the percentage
of women giving birth with professional assistance has dropped for some reason. The
improvement of the universities’ financial situation was expected to have a positive impact
on the quality of education, reducing the drop-out rate and thus encouraging female
completion rates. The application of merit-based criteria for university scholarships may
have contributed to the increased share going to women. Gender equality exists already in
primary education and improvements in secondary education were expected to reduce
girls’ dropout rates at that level. Finally, if the targeted agricultural input delivery system
is eventually introduced, this should enhance access by women farmers to essential inputs
for productivity improvement.
(b) Institutional Change/Strengthening
52. The emphasis on performance contracts, for hospitals, the energy parastatal
(SENELEC) and agencies, should have a significant impact on the performance of all
these institutions. The introduction of penalties and rewards linked to performance in
SENELEC should be particularly helpful in changing the culture of the work place. The
performance contracts for hospitals led to new investment allocations which had been
unavailable for many years. This reportedly improved morale in these institutions. The new
governance law and reforms in the financing of universities should make them more
transparent and accountable. This will be further strengthened once the specialized
accountants in key faculties begin to report to the chief financial officer as envisaged. The
governance reforms have modestly strengthened the mandates of the Cour des Comptes
and the new OFNAC institution.
21
(c) Other Unintended Outcomes and Impacts
No unintended negative effects have been identified by the team.
3.5 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
There was no beneficiary survey and/or stakeholder workshop.
4. Assessment of Risk to Development Outcome
53. Ratings: Risks are moderate as the government appears to be committed to
most, if not all, of the objectives pursued in this series. Also, the degree of progress has
been moderate, so there is less likelihood of reversals. There is a risk that the asset
declaration exercise will have limited impact if the organization responsible for receiving
and managing them (OFNAC) is weakened. The removal of their independent President in
2016 can be perceived as a move in this direction. The eventual utilization of the e-platform
for agricultural subsidies remains in doubt. Further rationalization of agencies is also
uncertain. The commitment to performance contracts seems clear, though it remains to be
seen if they will be used effectively.5
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Ratings: Moderately unsatisfactory.
54. The Bank supported the design of an ambitious program which tackled many
relevant issues, but that was too wide-ranging and paid insufficient attention to
ownership. The programmatic, three-year approach was generally well-designed, with a
systematic progression of reforms in most areas and stability in triggers. However, the
broad and ambitious scope affected monitoring and implementation. Focusing the program
on fewer key sectors, with more mature ongoing reforms, would have helped. Also, the
program could have benefited from greater attention to country ownership both with the
MEFP and sectoral ministries. As mentioned before, the design and location of the
proposed M&E unit generated frictions and inefficiencies. This M&E unit, the proposed
agricultural input distribution platform, and agency rationalization suffered from weak
ownership at the levels of implementing agencies – despite the high relevance for the
Presidency. In general, the Bank had high expectations, but it moved too quickly into a
three-year program, over-estimated the realistic pace of reform and over-estimated the
5 There was some early evidence that the finance ministry was not always budgeting the amounts indicated
in the performance contracts, giving the agencies an excuse for underperforming.
22
strength of the ownership. Starting with a one-year operation before discussing a three-year
program and focusing on fewer sectors would have been a more sensible strategy.
(b) Quality of Supervision
Ratings: Satisfactory.
55. The series benefited from close monitoring as all the relevant sector specialists
were based in the local office in Dakar, and the prior actions were integral parts of
the overall Bank program for Senegal. The World Bank supported the many reforms
with analytical work and technical assistance, and discussed the most difficult issues at the
highest level of government when necessary. The basic education reform involving
changes to the payroll system may have suffered from inadequate attention as the
difficulties seem to have been underestimated, but lack of government commitment may
have been the bigger factor. The Bank’s monitoring capacity was affected due to natural
rotation in the team leadership half way through the second year (2013), but other members
of the team stepped in to continue managing the program, including the support of the team
located in the country office.
(c) Justification of Rating for Overall Bank Performance
Ratings: Moderately unsatisfactory.
56. The Bank was overly ambitious in the variety and depth of reforms pursued,
and in the final outcomes sought. The Bank overestimated the implementation and
coordination capacity of the new government, and its ownership of the program.
Supervision was adequate, with a few exceptions, but results were disappointing. Closer
coordination with involved sectors during design and execution would have helped to
increase ownership.
5.2 Borrower Performance
(a) Government Performance
Ratings: Moderately unsatisfactory.
57. Performance was mixed across the government. The ministries of health, basic
education and higher education showed relatively good commitment, though the last two
were sometimes impeded by weak follow up from the MEFP. For example, the payroll
department in the finance ministry delayed interconnection with the basic education human
resource data base. Delays in defining a new budget nomenclature held up the preparation
of revised university budgets using the new financial regime. The agriculture ministry did
not implement the one reform under its responsibility.
58. Insufficient coordination capacity in the finance ministry due to lack of human
resources compounded the problem. In effect, the unit responsible for following up the
budget support program was severely understaffed. This led to heavy participation by Bank
23
staff; nonetheless, there was often a last-minute crisis atmosphere at the end of the
government’s fiscal year, as incomplete reforms threatened timely disbursement. The Bank
coordinated with other donors to recommend changes in the government’s arrangements
for managing budget support, but these were not implemented.
59. Several of the outcome indicators were missed because of insufficient
commitment to tackle the issue. According to the law, all asset declarations should have
been submitted within three months of approval of the decree, yet two years later only half
of them had been received. A 2009 law stipulated that all agencies should have a
performance contract, an objective still not obtained in 2017. The platform for allocating
subsidized agricultural inputs was still not used in 2017.
60. Once a prior action was met there was often insufficient attention to ensure
proper implementation. The first electricity reform was not implemented until a further
condition was introduced in the third-year operation. Special accountants were assigned to
key faculties but did not report to the chief financial officer as expected. University budgets
were being prepared using a new financial regime, but should have been negotiated before
the national budget was approved. There was little rationalization of agencies after the
action plan was agreed.
(b) Implementing Agency or Agencies Performance
Ratings: Moderately satisfactory.
61. Performance was heterogeneous across involved implementing agencies. The
main responsibility for coordination among executing agencies and tracking
implementation remained at the Ministry of Economy, Finance, and Planning, with overall
modest results. APIX, the agency managing investment climate reform, did a very good
job, demonstrating strong ownership, pursuing Doing Business reforms in a concerted
manner, and generally completing prior actions well ahead of appraisal. SENELEC, the
energy parastatal, did moderately well, implementing prior actions in a timely fashion,
heavily supported by Bank staff. These agencies were responsible for implementing
specific reforms but not the overall program, which remained the responsibility of the
finance ministry.
(c) Justification of Rating for Overall Borrower Performance
Ratings: Moderately unsatisfactory.
62. Government performance was on the whole moderately unsatisfactory, and
many outcome targets were missed. While some ministries and agencies demonstrated
commitment to reform, others did not. Inadequate coordination and cohesion between the
finance ministry and other executing units were particularly problematic both for
monitoring the program and ensuring implementation of reforms.
6. Lessons Learned
63. The trade-off between reform and disbursement needs to be acknowledged
and addressed. The necessity of disbursing before the end of Senegal’s fiscal year caused
24
considerable stress in the first two years of the program, and led to some hasty reform
measures which were not fully owned. These include the agency rationalization action plan
and the adoption of the e-platform for agricultural inputs. The program finally broke its
link to annual disbursement in the third year.
64. The Bank and the Government need to work more effectively to agree on a set
of important reforms, ensuring strong government ownership and reflecting clear
priorities. There needs to be an understanding that budget support is not inevitable but
depends on significant reforms, that success depends on government ownership, and that
ownership depends on the active participation of both parties in defining the policy matrix.
65. The Government of Senegal needs to devote more resources to ensure
adequate follow-up and timely completion of prior actions. Full ownership should be
demonstrated by a robust monitoring unit, with a clear mandate and strong leverage on
implementing ministries and agencies. Complementing this, at the sector level, reforms
need to be owned by implementing agencies. This would lead to strong coordination
mechanisms between sector and central ministries (particularly the MEFP) thus facilitating
the reform implementation.
66. Budget support series should be limited to a smaller number of sectors. This
would permit a better focus on areas of strong government ownership and facilitate
monitoring. The Senegal program covered a wide range of sectors which taxed the
supervisory capacity of the finance ministry as well as Bank staff. Basic education should
probably have been dropped as the sequence of reforms was weak and Bank staff were
focused on higher education. Agriculture could also have been excluded from this series,
as it was added only in the final year, and there was little ownership of the key reform. The
program probably provided little valued added to the investment climate reforms as they
were being driven effectively by the Doing Business process. Such rationalization would
have allowed room for further action in year three related to the Auditor General. Focusing
on fewer sectors would have allowed more comprehensive and meaningful reform
programs in each sector.
67. Both the Bank and the Government need to follow-up after prior actions are
met, to ensure that the reforms are effectively implemented. For example, the cross-
debt agreement approved with SENELEC in 2012 did not come into force until 2014
because a critical annex had not been finalized. Similarly, application of the new financial
regime for universities was delayed for months for lack of attention to the budget
nomenclature. The special accountants assigned to key faculties were still not reporting to
the chief financial officer at the university of Dakar two years after their nomination. The
commitment to use the e-platform for allocating subsidized agricultural inputs has yet to
bear fruit for lack of implementation. And once the Ministers had submitted their asset
declarations, the pressure on others appears to have reduced. The focus on implementation
in the third operation of the series was an important step in the right direction but not
sufficient.
25
68. Targets need to be set more carefully, more tightly linked to prior actions, with
greater emphasis on outputs rather than outcomes, and more attention to the timeline
for implementation. The gender targets were not well-linked to reforms supported in the
program, and the health and tourism outcomes depended on variables beyond the
associated prior actions. The targets for asset declarations and agency performance
contracts were too ambitious.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners (a) Borrower/Implementing agencies
69. The main comment from the borrower concerned the importance of
considering partial achievement of targets. This was accommodated by including the
percentage of each target achieved in the revised version.
(b) Cofinanciers: NA
(c) Other partners and stakeholders : NA
26
Annex 1 Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
P128284, P126470, P150976 - SN- First, Second and Third Governance and Growth
Support Projects
Names Title Unit Responsibility/
Specialty
Lending
Maya Abi Karam Senior Counsel LEGAM Legal
Alexandre Arrobbio Senior Governance Specialist GGO18 Governance
Eric Brintet Lead Financial Management Spec GGO25 Governance
Wolfgang M. T. Chadab Senior Finance Officer WFALA Disbursement
Matthias Cinyabuguma Senior Economist GMFDR Macroeconomics
Linda K. English Program Leader, Human Development GEDDR Education
Edward Philip English Program Leader, Macroeconomics GMFDR TTL
Maimouna Mbow Fam Sr Financial Management Specialist GGO26 Public Finance
Fatouma Toure Ibrahima Wane Operations Adviser GEEDR Energy
Christophe Lemiere Senior Health Specialist GHNDR Health
Khady Fall Lo Program Assistant AFCF1 Program Assistant
Jean Michel Noel Marchat Lead Economist GTC07 Private sector
Mamadou Ndione Senior Economist GMFDR TTL, GGSC1
Aifa Niane Ndoye Agricultural Economist GAGDR Agriculture
Demetrios Papathanasiou Program Leader, Sustainable
Development GEEDR Energy
Atou Seck Senior Education Specialist GEDDR Education
Jean-Philippe Tre Senior Agriculture Economist GFA01 Agriculture
(b) Staff Time and Cost
P128284, P126470, P150976 – Staff Time & Cost
1. SN- First Governance and Growth Support Project – P128284
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
Number of staff weeks US$, Thousands (including Travel
and Consultant Costs)
Lending
FY12 40.20 125,494
FY13 49.10 172,861
Total: 89.30 298,355
Supervision/ICR
Total: 0 0
Total lending
&Supervision 89.30 298,355
27
2. SN- Second Governance and Growth Support Credit – P126470
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
Number of staff weeks US$, Thousands (including Travel
and Consultant Costs)
Lending
FY14 11.98 95,167
FY15 1.40 7,074
FY16 0.90 6,673
Total: 14.28 108,914
Supervision/ICR
Total: 0 0
Total lending &
supervision 14.28 108,914
3. Senegal-Third Governance and Growth Support Credit – P150976
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
Number of staff weeks US$, Thousands (including Travel
and Consultant Costs)
Lending
FY15 15.10 112,966
FY16 0 186
Total: 15.10 113,151
Supervision/ICR
FY17 1.96 20,870
Total: 1.96 20,870
Total lending &
supervision 17.06 134,021
28
Annex 2. Beneficiary Survey Results
Not applicable.
29
Annex 3. Stakeholder Workshop Report and Results
Not applicable.
30
Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR
Following a meeting to revise the draft ICR prepared by the World Bank, the Borrower
proposed only a handful of minor adjustments to text, mostly related to the role of the
Government in the design and implementation of the DPO Series. They were all included
in the final text.
The Borrower also requested to better reflect the partial (and sometimes substantial)
progress in the Indicators of the Program. In effect, the ICR version revised with the
Borrower considered only two options for the results Indicators: Attained or Not
Attained. Hence, some indicators that showed important progress were marked as Not
Attained if its value did not fully reach the objective. This issue has also been discussed
at the QER meeting and the meeting accepted to reflect the degree of accomplishment of
the Indicators to better reflect partial advances.
31
Annex 5. Comments of Cofinanciers and Other Partners/Stakeholders
Not applicable.
32
Annex 6: Prior Actions and their Status
GGSC 1 Prior Actions Status
Pillar 1a: To improve economic governance by strengthening accountability systems
Enhance Budget transparency by submitting to Parliament a draft law
consistent with the WAEMU guidelines for a Code of Transparency
(Directive No1/2009/CM/UEMOA portant Code de Transparence dans
la Gestion des Finances Publiques au Sein de l’UEMOA) by the
Council of Ministers (Prior Action 1)
Done and law was
passed in 2013.
Strengthen the independence of the Audit Court by submitting to
Parliament a draft organic law (projet de loi organique abrogeant et
remplacant la loi organique No 99-70 du 17 février 1999 sur la Cour
des Comptes) (Prior Action 2)
Done and law was
passed in 2013.
Pillar 1b: To promote service delivery through better governance and efficiency in the
education, health and agriculture sectors, rationalization of agencies and strengthening
monitoring and evaluation.
Improve personnel management of the education ministry by adopting
a decree reinforcing the deconcentration process (décret abrogeant et
remplaçant le décret n° 93-789 du 25 juin 1993 portant création des
inspections d’Académie et des inspections départementales de
l’Education nationale, modifié) (Prior Action 3)
Done.
Strengthen financial management of universities by amending the
financial regime (Décret portant régime financier des universités)
(Prior Action 4)
Done.
Sign a performance contract between the HOGGY hospital, the
Ministry of Health and the Ministry of Economy and Finance (Prior
Action 5)
Done.
Pillar 2: To enhance private sector development through energy sector reforms, and
improvements in the investment climate, including in the tourism sector.
Adoption by the Government (signed by the Minister in charge of
Finance and the Minister in charge of Energy) of a new Energy Sector
Development Policy Letter (ESDPL) and action plan 2012-2016 (Prior
Action 6)
Done.
Adoption by the SENELEC Board of directors of SENELEC’s
financial and operational restructuring plan including the agreement of
cross-debts settlement as of July 31 2012 between SENELEC and State
signed by the Ministry in charge of Finance and SENELEC (Prior
Action 7)
Done, though an
annex stipulating
how the balance
would be allocated
was not finalized at
the time, which
delayed the
agreement taking
effect.
33
GGSC II Prior Actions Status
Pillar 1a: To improve economic governance by strengthening accountability systems.
Establish an Asset Declaration System by submitting to Parliament a draft
law making asset declarations mandatory for all Ministers
(Prior Action 1)
Done and law
was passed in
2014.
Publish the 2011 Annual Report on the Cour des Comptes website (Prior
Action 2) Done.
Pillar 1b: To promote service delivery through better governance and efficiency in the
education, health and agriculture sectors, rationalization of agencies and strengthening
monitoring and evaluation.
Adopt 2013 budget for the two largest universities which are in compliance
with the revised financial regime of the universities; and adopt new criteria
for scholarships (Prior Action 3)
Done, although
well after the
2013 national
budget was
approved.
Evaluate existing performance contracts and sign performance contracts
between 5 new public hospitals, the Ministry of Health and the Ministry of
Economy and Finance (Prior Action 4)
Done.
Finalize the evaluation of autonomous agencies; and approve an action plan
including the closure and merger of some agencies
(Prior Action 5)
Done, though the
action plan was
somewhat
modified
thereafter.
Establish an institutional mechanism for regular monitoring of strategic
priorities linked with the budget cycle (Prior Action 6)
Done, though it
remained fairly
vague on the role
of different
central actors.
Pillar 2: To enhance private sector development through energy sector reforms, and
improvements in the investment climate, including in the tourism sector.
Signature of a Performance Contract between the State and SENELEC
(Prior Action 7) Done.
Improve business climate by i) enacting a law simplifying property
registration procedures and ii) revising its tax code to reduce property taxes
and reduce the time required for other tax payments.
(Prior Action 8)
Done.
34
GGSC III Prior Actions Status
Pillar 1a: To improve economic governance by strengthening accountability systems.
The Recipient has operationalized its asset declaration system by: (a)
approving the related implementation decree; (b) allocating appropriate
human and financial resources to the national office for the fight
against fraud and corruption (“Office National pour la Lutte contre la
Fraude et la Corruption”/”OFNAC”); and (c) ensuring deposition of
asset declarations by ministers holding a portfolio to OFNAC.
(Prior Action 1)
Done, although the
replacement of the
President of OFNAC
may signal a
weakening of its
independence.
Pillar 1b: To promote better governance and efficiency in the education, health and agriculture
sectors, and within agencies, and strengthen monitoring and evaluation.
The Recipient has strengthened wage bill control and human resources
in the education sector by: (a) creating a system connecting data bases
of the ministries in charge of education and civil service; and (b)
preparing the 2015-2016 recruitment plan for education in collaboration
with the ministry in charge of finance. (Prior Action 2)
Done, though the
original trigger called
for the data base to be
linked to the payroll
as well.
The Recipient has implemented presidential directives on external
revenues earned by universities through: (a) adoption and submission to
Parliament for enactment of a draft law reforming universities
governance system; (b) issuance of an Arrêté specifying resource
allocation and use of external revenues; and (c) appointment of
accountants in key faculties and schools at the University of Dakar,
who report to the chief financial officer. (Prior Action 3)
Done. The law was
approved. The
accountants were
appointed but their
reporting to the chief
financial officer
remains problematic.
The Recipient has adopted a new financial regime for public agencies
and establishments, and has entered with five additional public health
institutions into performance contracts whose objectives are to increase
service supply, improve billing process and control general costs.
(Prior Action 4)
Done. This action
was strengthened with
the addition of a new
financial regime.
The Recipient has adopted a mobile phone-based e-platform to
distribute subsidized agricultural inputs in the 2015 crop season; and
obtained approval allowing SAED to enter into multiannual
maintenance contracts of hydro-agricultural works with private
contractors and launched a call for bids. (Prior Action 5)
The Minister of
Agriculture agreed in
principle to use the
new platform but it
was still not in use
one year later. The
first multi-year
contract has been
issued.
The Recipient has launched implementation of the action plan to
restructure autonomous government-owned agencies, by: (a) merging
certain selected agencies; (b) appointing officers responsible for the
liquidation of certain selected agencies; and (c) entering with six of the
largest agencies into performance contracts with the objective of
clarifying the financial commitments of the Recipient’s ministry
responsible for finance and the related performance targets of agencies
concerned. (Prior Action 6)
Done. Closure of
agencies has been
slow but additional
performance contracts
have been prepared in
the following years.
35
GGSC III Prior Actions Status
The Recipient has issued a decree establishing a comprehensive
monitoring and evaluation system for the government’s policies and
programs, defining the roles and responsibilities of all actors in the
administration. (Prior Action 7)
Done, though tensions
between the different
actors suggest that the
system may have to
be redesigned.
Pillar 2: To enhance private sector development through energy sector reforms, and
improvements in the investment climate, including in the tourism sector.
The Recipient has amended the performance contract entered into
between the Recipient and SENELEC on June 11, 2013 to include
performance-based bonuses and sanctions, and has amended the
agreement regularizing cross-debt entered into between the Recipient
and SENELEC dated November 16, 2012, to determine the method for
the balance allocation. (Prior Action 8)
Done. The cross debt-
agreement was finally
applied.
The Recipient has: (a) issued (i) a decree reducing the number of days
and costs to obtain construction permits through the creation of a single
window and online processing; and (ii) a decree determining a new fee
schedule for warehouse inspection; and (b) eliminated the minimum
capital requirement for creating a new company. (Prior Action 9)
Done.
The Recipient has offset the impact of Ebola’s on the tourism sector by:
a) removing entry visas’ fees; b) reducing selected taxes on air tickets;
and c) suspending recovery acts initiated against hotels with arrears in
payment of patented and land taxes in 2015. (Prior Action 10)
Done.
36
Annex 7. List of Supporting Documents
ACT for Performance, Diagnostic des dispositifs de suivi-évaluation des politiques
publiques au Sénégal, June 2016.
Senegal, Ministry of Economy, Finance and Planning, Direction de la Prévision et des
Etudes Economiques (DPEE), various monthly issues of the Point mensuel de
Conjoncture for 2016.
Senegal, Ministry of Economy, Finance and Planning, Direction du Secteur Parapublic,
Rapport 2014-2015 sur le Secteur Parapublic.
Senegal, Ministry of Economy, Finance and Planning, Loi des Finances 2016 and Loi des
Finances rectificative, 2016. Sur le site web www.finances.gouv.sn.
Senegal, Ministry of National Education, Rapport annuel de Performance 2015, April
2016.
Senegal, OFNAC, Rapport annuel 2016.
Sy, A.B., A.B. Diallo, and N.N. Seck. Mesure de la Performance des Ressources
Humaines dans le Secteur de la Santé, Dec. 2016.
World Bank, Doing Business 2017 – Equal Opportunity for All, Economy Profile 2017:
Senegal.
World Bank, Senegal: Program Document for the First Governance and Growth Support
Credit, November 2012.
World Bank, Senegal: Program Document for a Proposed Second Governance and
Growth Support Credit, November 2013.
World Bank, Senegal: Program Document for a Proposed Credit for the Third
Governance and Growth Support Credit, June 2015.
MAP