document name model validation report for may 16, 2014 … validation report for may 16 2014 ras...
TRANSCRIPT
![Page 1: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/1.jpg)
Document name Model Validation Report for May 16, 2014 RAS Event
Category ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy ( ) Guideline (X) Report or other ( ) Charter
Document date August 12, 2014 Adopted/approved by
M&VWG
Date adopted/approved
August 12, 2014
Custodian (entity responsible for maintenance and upkeep)
JSIS
Stored/filed Physical location:
Web URL: http://www.wecc.biz/committees/StandingCommittees/PCC/TSS/MVWG/Shared%20Documents/MVWG%20Approved%20Documents/Model%20Validation%20Report%20for%20May%2016%202014%20RAS%20Event.pdf
Previous name/number
N/A
Status (X) in effect ( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by _____________________ ( ) other _____________________________ ( ) obsolete/archived)
![Page 2: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/2.jpg)
1
WECC Joint Synchronized Information Subcommittee and WECC Modeling and Validation Work Group
Model Validation Studies for Pacific Northwest RAS Event that Occurred in the Western Interconnection at 23:18 on May 16, 2014
FINAL Report 8-12-2014
I. Conclusions and Recommendations
On May 16 2014, at 23:18:15.85, John Day - Grizzly #1 500-kV line tripped while John Day-Grizzly #2 line was out of service for construction. With both John Day – Grizzly lines out of service and COI flow at about 3,400 MW, the NW RAS operated as designed for the double line outage contingency and keyed 2,563 MW of gen drop at Grand Coulee, Wells, John Day, Biglow Canyon Wind and Dooley Wind. The Chief Joseph Braking Resistor was also inserted as designed. Kemano Unit #1 was tripped by Kemano RAS several seconds later. Springerville Unit #4 was tripped about 40 seconds later due to boiler instability.
The purpose of model validation studies is two-fold:
- Validate accuracy of power system models used in dynamic simulations - Performing “what if” sensitivity studies with respect to control actions
Based on the analysis and studies performed, the following conclusions and recommendations:
FREQUENCY RESPONSE
1. Findings: Generation tripping during May 16, 2014 event was comparable to the resource loss contingency for the Western Interconnection per NERC BAL-003-1 Reliability Standard. The interconnection frequency stayed well above 59.5 Hz level (lowest recorded dip was 59.72 Hz), and the interconnection frequency response was consistent with the historic baseline and well above the interconnection Frequency Response Obligation.
![Page 3: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/3.jpg)
2
MODELING
2. Findings: Simulated system frequency matched actual recordings quite well. Some discrepancies were observed in active power pick-up on major paths as well as responses of individual generators.
Recommendations: Analysis of individual generator responses may provide additional insight in the power pick-up discrepancies. An application has been developed by Eric Bakie at Idaho Power and MVWG to verify the generator frequency response using SCADA data. The application is available to WECC operating entities. WECC power plant frequency response has not been reviewed programmatically since 2003. WECC Power Plant Model Data Task Force will update and review the baseload flag information as needed.
3. Findings: Majority of operating West-Wide System Model is mapped to a WECC planning case, thereby greatly improving the development of a validation base case. However, major discrepancies exist in wind power plant representation between planning and operating models.
Recommendation: We encourage expedited reconciliation between planning and EMS models for wind power plants. We recommend consistent application of WECC Wind Power Plant Powerflow Modeling Guidelines for planning and operating models across WECC utilities.
4. Findings: Relatively large number of wind generators does not have dynamic models in the dynamic database. Significant amount of wind generation was on-line during May 16 event, and had to be load-netted in dynamic simulations.
Recommendation: MVWG and SRWG need to work with TPs on identifying missing wind power plant models. MVWG will develop a data request for wind and solar generation needed to produce “default” data sets. MVWG will test and provide interim “default” models to TPs until the generators owners provide unit-specific model data.
5. Findings: Reactive current compensation and cross-current compensation models are needed for sister units. This issue has been observed in 2012 and 2013 model validation studies.
Recommendation: MVWG needs to expedite the development and implementation of Cross-Current Compensation models.
![Page 4: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/4.jpg)
3
KEMANO
6. Findings: A response-based Kemano RAS operated on a power swing caused by Northwest RAS. There is no dynamic model for Kemano RAS to study potential interactions.
Recommendation: Modeling of response-based RAS schemes was identified as a top modeling priority from September 8, 2011 outage recommendations. Kemano RAS owners need to provide to MVWG information and ultimately a dynamic model for Kemano RAS scheme.
7. Findings: Studies show that the operation Kemano RAS operation may not have been necessary to preserve transient stability of Kemano – BC Hydro tie-line during May 16 event.
Recommendation: A response based scheme needs to balance reliability (operate when needed) and security (do not operate unnecessarily). Kemano RAS owners need to review the security of Kemano RAS in the context of this event.
8. Findings: Kemano generators play a very important role in dynamic behavior of the Western Interconnection. However, there is no adequate visibility of the Kemano dynamics, as the closest PMU at BCH’s Willingston 500.
Recommendation: Kemano owners to install PMUs to monitor:
- Kemano 287-kV bus frequency, bus voltage phasor, and current phasors, active and reactive power in each of Kemano power plant transformers
- Measurements used to initiate Kemano RAS
PMU data is to be streamed continuously at 30 samples per second to Peak Reliability RC, BC Hydro and neighboring utilities. Kemano owners to work with WECC JSIS and WISP and determining data requirements.
NORTHWEST RAS AND CHIEF JOSEPH BRAKING RESISTOR
9. Findings: Studies show that the operation of Chief Joseph braking resistor may not have been necessary to preserve system stability during May 16 event. Studies also indicate that Chief Joseph brake operation amplified power swing at Kemano.
Recommendation: Chief Joseph braking resistor is used to absorb accelerating energy during power swings. Operation of Chief Joseph brake may not have been needed during May 16 event.
![Page 5: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/5.jpg)
4
Chief Joseph brake is used as a safety net, and BPA needs to review security of the brake controller to minimize the unnecessary operations.
BPA also needs to provide a dynamic model for Chief Joseph controller.
SPRINGERVILLE #4 TRIP
10. Findings: Springerville unit#4 tripped on low frequency during May 16 event, although the frequency stayed well within the envelope of NERC PRC-024 Reliability Standard. System frequency for May 16 event is compared with simulated two Palo Verde outage. Two Palo Verde outage would have caused a lower system frequency than what was observed during May 16 RAS event, and therefore 2PV outage would have likely caused the trip of Springerville unit #4. Springerville#4 trip would have had minimum impact on system frequency nadir, and some impact power pick-up and voltages on California – Oregon Intertie.
Springerville #4 owners are taking steps to resolve issues that caused unit trip during May 16 event.
![Page 6: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/6.jpg)
5
II. May 16, 2014 Event Description
On May 16 2014, Friday, at 23:18:15.85, the John Day - Grizzly #1 500-kV line tripped while John Day-Grizzly #2 line was out of service for construction. With both John Day – Grizzly # 1 and #2 lines out of service, the NW RAS operated as designed for the double line outage contingency and keyed 2,563 MW of gen drop at Grand Coulee, Wells, John Day, Biglow Canyon Wind and Dooley Wind, and inserted the Chief Joseph Braking Resistor.
NW RAS generation trip included:
Plant Units MW Dropped
BIGLOW CANYON TOTAL GEN 419.4
DOOLEY WIND TOTAL GEN 183.1
GRAND_COULEE CKT2 TO G-6-9 236.5
GRAND_COULEE G20 471
GRAND_COULEE G21 508
JOHN_DAY G09 113
JOHN_DAY G12 112
JOHN_DAY G14 111
JOHN_DAY G16 114
WELLS G03 73.86
WELLS G05 73.85
WELLS G08 73.55
WELLS G09 73.75
TOTAL 2563
Kemano unit 1 tripped with approximately 110 MW. BC Hydro reported that the tripping of the Kemano unit was due to the combined frequency response of the eight Kemano generators, which were producing about 750 MW pre-disturbance with a net export into the BC Hydro system of 380 MW. The RAS on the Kemano-Kittimat 287-kV lines tripped one unit as designed (Kemano unit #1) when the net export from Kemano system to BC Hydro is greater than 420 MW.
Within approximately one minute of the NW Gen Drop, the Springerville unit #4 tripped with approximately 445 MW due to an apparent internal plant protection, although the system frequency was well within the NERC PRC-024 off-nominal frequency ride-through envelope. SRP reported that the Springerville unit #4 tripped off line due high furnace pressure and the loss of both ID Fans. SRP has identified potential “fixes” that could be applied to prevent the tripping of the unit for future frequency deviations (Springerville unit #4 also tripped during NW RAS event on January 29, 2014).
![Page 7: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/7.jpg)
6
The system frequency dropped down to 59.73 Hz during the event, which is well above the first level of the coordinated under-frequency load shedding program set at 59.5 Hz. No loss of load is reported during the event.
John Day – Grizzly #1 Line was restored at about 23:20:30, about 2 minutes after it was tripped.
Figure 1 shows a 3-minute recording of the system frequency during the event.
Figure 1: system frequency during May 16, 2014 disturbance.
59.7
59.75
59.8
59.85
59.9
59.95
60
60.05
23:18:00 23:18:15 23:18:30 23:18:45 23:19:00 23:19:15 23:19:30 23:19:45 23:20:00 23:20:15 23:20:30 23:20:45
Frequency
NW RAS = 2,563 MW
Kemano = 110 MW
Springerville = 445 MW
John Day – Grizzly #1back in service
![Page 8: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/8.jpg)
7
III. System Frequency Performance During May 16, 2014 Event
No loss of load has been reported during the event.
Figure 2: System frequency response – determining NERC Point A and Point B
Frequency response metrics are consistent the historic baseline, as highlighted in Figure 3.
Figure 3: historic frequency response baseline in the Western Interconnection: Red dots – frequency response is measured at Point B consistent with NERC BAL-003-1 methodology Blue diamonds – response is measured at frequency nadir Size of dots and diamonds is proportional to the size of the event
![Page 9: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/9.jpg)
8
Interconnection-wide frequency response performance is performed:
Frequency – Point A (initial) Hz 60.009 Frequency – Point B (settle) Hz 59.827 Frequency – Point C (nadir) Hz 59.720 Contingency (NW RAS+Kemano) MW 2,673 NERC Frequency Response Measure MW per 0.1 Hz 1,468 Nadir-based frequency response MW per 0.1 Hz 924 Western Interconnection total generation GW 97
The system frequency performance surpasses Frequency Response Obligation for Western Interconnection per NERC BAL-003-1, and consistent with historic baseline.
IV. Validation Base Case Development
2014 Light Summer WECC Operational Planning base case (planning case) is used as a starting point in the model validation studies.
Figure 4 shows a process diagram.
Figure 4: validation base case development process
WECC Modeling and Validation work group issued a data request for generation and key transmission flows prior to the event. Peak Reliability RC provided an operating West-wide System Model base case (WSM case) just prior to the disturbance. The operational information was mapped onto 2014 planning case. Regional loads were scaled to match the key tie-line flows. Also, dynamic simulation of event is performed directly using WSM and results are benchmarked against PMUs and 2014 planning case.
Planning Base Case(Bus-Brunch Representation)
Operating West-wide System Model for Event
(State Estimator Model, Breaker-Node Representation)
Planning Dynamic Database
Composite Load Model
Dynamic Simulation of an Event
WECC MVWG Data Request
Mapping Operating Data onto Planning Case
![Page 10: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/10.jpg)
9
V. Dynamic Model
2014 operational dynamic data base is used in the validation studies.
Wind Generation.
Large amount of wind generation was on-line during May 16 event. A significant number of wind generators in Tehachapi area had no dynamic models in WECC dynamic data base. Several hundred MWs of generators had to be “netted” in dynamic simulation. Wind generation models in Pacific Northwest were unstable due to model additions, and were replaced with stable data used in 2013 studies.
Reactive Current Compensation.
Reactive Current Compensation is required to maintain stability between two sister units connected to the same bus:
- XCOMP sign is changed from +0.052 to –0.052 for RI STUB, RI SOUTH, RI NORTH units - XCOMP sign is changed from +0.05 to –0.05 on MAGCORP units - XCOMP of –0.05 for Little Goose units
Cross-Current Compensation.
John Day and The Dalles generators went unstable during the simulation. John Day and The Dalles generators have Line Drop Compensation for voltage support and Cross-Current Compensation to ensure stability of sister units. Current generator models include Line Drop Compensation, but there is no Cross-Current Compensation model in PSLF. Not having CCOMP model is adequate as long as sister units are identical and have the same active and reactive power loading, as often set-up in planning cases. Operationally, units are often loaded at different levels, and therefore go unstable without CCOMP models. To mitigate the issue, John Day generators were re-dispatched to same “average” level.
SVSMO1 dynamic model is added for Keeler SVC
Composite Load Model
Composite load model records are developed using WECC Load Model Data Tool. Shoulder season hour 22 are used to estimate load composition.
![Page 11: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/11.jpg)
10
VI. Simulations
Simulated sequence of events:
Time (sec) Action 0 Open John Day – Grizzly 500-kV line #1 0.125 RAS Gendrop – Dooley, Biglow Canyon, Grand Coulee, Wells, and John Day 0.125 Close Chief Joseph braking resistor 0.64 Open Chief Joseph braking resistor 2.3 Trip Kemano unit #1 2.3 Malin MSC cap #1 tripped 2.65 Ostrander reactors are tripped 2.72 Pearl capacitors are inserted 2.88 Slatt shunt capacitors are inserted 5.3 Malin shunt reactor is inserted 32.9 Grizzly shunt reactor is inserted 40.9 Springerville Unit#4 tripped
*Initial report had Kemano tripping at about 7 seconds after the initial event. PMU data analysis and model validation indicate that the tripping occurred earlier
Figures M1 to M6 and S1show comparison between actual and simulated responses.
VII. West-Wide System Model Studies
West-Wide System Model (WSM) is a node breaker (full topology) state estimator model from Peak Reliability RC. GE PSLF version 19 has capabilities to read node-breaker power flow model and link it with the WECC dynamic database. Peak Reliability RC and WECC performed model validation studies using the state estimator snapshot taken prior to the event. Figures WSM-1 to WSM-6 compare (i) PSLF simulations done using bus-branch WECC planning model, (ii) PSLF simulations done using node-breaker WSM model, and (iii) actual PMU recordings. WSM model agrees with WECC planning model, and both capture the main features of the May 16 event reasonably well.
![Page 12: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/12.jpg)
11
VIII. Sensitivity Studies
Sensitivity “what if” studies are conducted once the system model is validated reasonably well
Kemano RAS:
Kemano RAS tripped Kemano unit #1 with 110 MW for a power swing following Pacific Northwest gen drop.
Questions:
a. Was Kemano RAS operation necessary during the May 16 conditions? b. Would the system remain stability and adequate performance if Kemano RAS did not operate on
May 16? c. Would a two Palo Verde outage trigger Kemano RAS operation?
May 16 sequence of events was simulated with and without Kemano tripping. Two Palo Verde outage was simulated on May 16 base case.
Conclusions and Recommendations:
a. There are no dynamic models to simulate Kemano RAS in dynamic simulations. Kemano owners are required to provide description of their RAS scheme and associated dynamic models.
b. Although Power swing at Kemano was relatively large, as suggested by Figure K1, Kemano RAS operation may not have been needed for the system stability during May 16 event, as seen from simulations in Figure K2.
c. Kemano RAS owners are suggested to look into improving security of their RAS scheme d. 2 Palo Verde outage caused a less severe power swing at Kemano compared to May 16 RAS
event, and not likely to initiate Kemano RAS operation (Figure K3).
Springerville #4 Trip
Springerville unit #4 tripped on May 16 due to boiler instability caused by low frequency about 40 seconds after the initiating event. The closest to Springerville PMU is one at Coronado 500-kV bus. Figure S1 shows a good agreement between actual and simulated voltages and frequencies at Coronado 500-kV substation.
Questions:
a. Would Springerville unit #4 trip for a 2 Palo Verde outage? b. What would have been the impact on California – Oregon Intertie should 2 Palo Verde outage
occurred and Springerville unit tripped after that
Studies:
Simulations of 2 Palo Verde outage were performed to compare the frequency at Springerville#4 with the frequency during May 16 RAS event.
![Page 13: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/13.jpg)
12
Simulations of 2 Palo Verde outage plus Springerville#4 trip were performed to determine any impact the additional generation would have had on the stability of California – Oregon Intertie.
Conclusions:
a. Springerville frequency would have been lower for 2 Palo Verde outage compared to system frequency during May 16 event, therefore it is very likely that Springerville unit would have tripped for 2 Palo Verde outage (Figure S3)
b. Springerville trip following 2 Palo Verde outage would have had some, but not significant, impact on the COI voltages and power pick-up (Figure S4)
Springerville#4 owners are working on resolving technical issues that resulted in the unit’s trip.
Interaction between Northwest RAS and Kemano RAS:
NW RAS dropped 2,500 MW of generation and initiated operation of Chief Joseph braking resistor, which created a power swing that resulted in the operation of Kemano RAS.
Questions:
a. Generator dropping amounts are determined based on planning studies, usually considering conservative system conditions. Given actual system conditions, was dropping of 2,500 MW of generation was necessary, or lower gen drop amount would have suffice?
b. What the impact of lower gen drop would have been on the Kemano power swing? c. What the impact of Chief Joseph braking resistor not operating would have been at Kemano
power swing?
Studies:
Simulations of May 16 event were performed without operation of Chief Joseph brake.
Simulations of May 16 event were performed with lower amount of NW RAS gen drop.
Conclusions and Recommendations:
a. Reducing amount of NW gen drop had minimum impact on Kemano power swing (Figure N1) b. Chief Joseph brake operation had observable impact on Kemano power swing (Figure N-2).
To answer whether a smaller amount of gen drop would have been sufficient under May 16 condition, a full set of contingency analysis would need to be done per NERC TPL standards, including thermal, voltage stability and dynamic simulations. The system performance must be met for line outages initiated by 3-phase faults, while May 16 event was high impedance fault with low fault current
BPA planning needs to consider improving the security of controller that operates Chief Joseph braking resistor to minimize the unnecessary operations.
![Page 14: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/14.jpg)
13
Kemano Power System Stabilizer
Kemano generators use dual-input Power System Stabilizers (PSS). The PSS synthesizes the integral of accelerating power from speed and power measurements. The calculation of PSS gain “Ks2” is dependent on generator inertia. It was observed during recent review of PSS settings conducted by Shawn Patterson and WECC JSIS that the calculations of Kemano PSS gains “Ks2” assume wrong generator inertia.
Question:
a. What would be the impact of changing the Kemano PSS gain “Ks2” to match generator inertia?
Table below shows generator inertia and associated PSS settings:
Kemano Generator Inertia, H
PSS washout ime constant, Tw
PSS Gain Ks2 to match H
PSS Gain Ks2 as is
G1 3.2 5 0.781 0.5 G2 4.74 5 0.527 0.33 G3 4.68 5 0.534 0.37 G4 3.2 5 0.781 0.5 G5 4.68 5 0.534 0.37 G6 5.25 5 0.476 0.33 G7 3.2 5 0.781 0.5 G8 5.25 5 0.476 0.33
Simulations were performed with new PSS settings. Study results are summarized in Figure KP1.
Conclusion:
a. Changing Kemano PSS gain “Ks2” would have had a slightly negative impact on Kemano power swing.
Kittimat Load Model Composition
Composite load model is used in the studies. Kittimat aluminum smelter is represented with default model, where 10% of load are induction motors driving frequency-dependent loads (pumps and fans), and 90% of load is constant resistance load. A sensitivity study is done with respect to a more demanding load characteristic, where 20% of loads are induction motors driving constant torque load, and 80% of load is constant current. No significant change in performance is observed in this study, as shown in Figure KIT1.
![Page 15: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/15.jpg)
14
Frequency Response Margin
Simulations were run where the amount of gen.drop is increased until the system frequency nadir approached 59.5 Hz, the level at which the coordinated under-frequency load shedding plan starts. We simulated up to 4,000 MW of generation dropping in Pacific Northwest, by tripping additional hydro-power generation at John Day and Chief Joseph. Figures E1 and E2 show frequency recordings in various parts of the interconnection, they all stay above 59.5 Hz level. Figure E3 shows voltages at key tie-lines which are known to be affected by gen.drop events. Voltages in Kemano area are affected the most by increased gen.drop under the studied condition. While the system frequencies stayed above 59.5 Hz, we do not suggest increasing the amount of gen.drop beyond the existing levels in the Western Interconnection.
![Page 16: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/16.jpg)
15
Figure M1: Simulated versus Actual Frequency
0 10 20 30 40 50 60 70 8059.7
59.75
59.8
59.85
59.9
59.95
60
60.05
60.1
Time (sec)
Freq
uenc
y (H
z)Malin Frequency
ActualSimulated
0 10 20 30 40 50 60 70 8059.7
59.75
59.8
59.85
59.9
59.95
60
60.05
60.1
Time (sec)
Freq
uenc
y (H
z)
Custer Frequency
ActualSimulated
![Page 17: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/17.jpg)
16
Figure M2: Simulated versus Actual Frequency
0 10 20 30 40 50 60 70 8059.7
59.75
59.8
59.85
59.9
59.95
60
60.05
60.1
Time (sec)
Freq
uenc
y (H
z)
Grand Coulee Frequency
ActualSimulated
0 10 20 30 40 50 60 70 8059.7
59.75
59.8
59.85
59.9
59.95
60
60.05
60.1
Time (sec)
Freq
uenc
y (H
z)
Sylmar Frequency
ActualSimulated
![Page 18: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/18.jpg)
17
Figure M3: Simulated versus Actual Voltages
0 10 20 30 40 50 60 70 80535
540
545
550
555
560
565
570
Time (sec)
Vol
tage
(kV
)
Malin Voltage
ActualSimulated
0 10 20 30 40 50 60 70 80530
535
540
545
550
555
560
565
570
Time (sec)
Vol
tage
(kV
)
Grizzly Voltage
ActualSimulated
![Page 19: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/19.jpg)
18
Figure M4: Simulated versus Actual Voltages
0 10 20 30 40 50 60 70 80525
530
535
540
545
550
555
560
Time (sec)
Vol
tage
(kV
)
Pearl Voltage
ActualSimulated
0 10 20 30 40 50 60 70 80532
534
536
538
540
542
544
546
548
550
Time (sec)
Vol
tage
(kV
)
Grand Coulee Voltage
ActualSimulated
![Page 20: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/20.jpg)
19
Figure M5: Simulated versus Actual Power Flows
0 10 20 30 40 50 60 70 801500
2000
2500
3000
3500
Time (sec)
Pow
er (
MW
)
COI Power
ActualSimulated
0 10 20 30 40 50 60 70 800
200
400
600
800
1000
1200
1400
Time (sec)
Pow
er (
MW
)
Custer - Ingledow Power
ActualSimulated
![Page 21: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/21.jpg)
20
Figure M6: Simulated versus Actual Phase Angles
0 10 20 30 40 50 60 70 8018
20
22
24
26
28
30
32
34
36
Time (sec)
Ang
le (D
EG)
John Day - Malin Angle
ActualSimulated
0 10 20 30 40 50 60 70 8025
30
35
40
45
50
Time (sec)
Ang
le (D
EG)
Grand Coulee - Malin Angle
ActualSimulated
![Page 22: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/22.jpg)
21
Figure WSM-1: Malin 500-kV Bus Frequency
Figure WSM-2: Custer 500-kV Bus Frequency
![Page 23: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/23.jpg)
22
Figure WSM-3: Malin 500-kV Bus Voltage
Figure WSM-4: Custer 500-kV Bus Voltage
1.06
1.07
1.08
1.09
1.1
1.11
1.12
1.13
1.14
1.15
0 10 20 30 40 50 60 70 80 90 100
MALIN VMAG PMU PSLF(Bus&Branch) PSLF(Node&Breaker)
![Page 24: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/24.jpg)
23
Figure WSM-5: Grand Coulee 500-kV Bus Voltage
Figure WSM-6: COI total power
1.06
1.065
1.07
1.075
1.08
1.085
1.09
1.095
1.1
1.105
0 10 20 30 40 50 60 70 80 90 100
G_COULEE VMAG PMU PSLF(Bus&Branch) PSLF(Node&Breaker)
0
500
1000
1500
2000
2500
3000
3500
4000
0 10 20 30 40 50 60 70 80 90 100
COI POWER PMU PSLF(Bus&Branch) PSLF(Node&Breaker)
![Page 25: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/25.jpg)
24
Figure K1: Simulated Kemano Dynamics during May 16 RAS event
0 10 20 30 40 50 60 70 80100
200
300
400
500
600
Time (sec)
Pow
er (
MW
)
Power out of Kemano
KIT-MINMIN-SKA
0 10 20 30 40 50 60 70 8059.4
59.6
59.8
60
60.2
Time (sec)
Spe
ed (
PU
)
Kemano Generator Speed
KMO3KMO7
0 10 20 30 40 50 60 70 800.9
0.95
1
1.05
1.1
1.15
Time (sec)
Vol
tage
(PU
)
Kemano Area Voltages
KMO287KIT287MIN287SKA287WSN500
![Page 26: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/26.jpg)
25
Figure K2: Comparison of Simulated Kemano Dynamics with Kemano RAS operating and not operating for May 16 condition
0 10 20 30 40 50 60 70 80100
200
300
400
500
600
Time (sec)
Pow
er (
MW
)
KIT-MIN Power Flow
KMO RAS OperatesKMO RAS Does Not Operate
0 10 20 30 40 50 60 70 800.85
0.9
0.95
1
1.05
1.1
Time (sec)
Vol
tage
(kV
)
MIN287 Voltage
KMO RAS OperatesKMO RAS Does Not Operate
![Page 27: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/27.jpg)
26
Figure K3: Comparison between May 16 RAS event and 2 Palo Verde as seen at Kemano
5 10 15 20 250.85
0.9
0.95
1
1.05
1.1
Time (sec)
Vol
tage
(kV
)
MIN-287-kV Voltage
May 16 as was2PV
5 10 15 20 25200
250
300
350
400
450
500
550
600
Time (sec)
Pow
er (
MW
)
KIT-MIN Power Flow
May 16 as was2PV
![Page 28: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/28.jpg)
27
Figure S1: Simulated versus Actual Coronado 500-kV Voltage and Frequency During May 16 Event
0 10 20 30 40 50 60 70 80525
530
535
540
545
Time (sec)
Vol
tage
(kV
)Coronado 500-kV Bus Voltage
ActualSimulated
0 10 20 30 40 50 60 70 8059.7
59.75
59.8
59.85
59.9
59.95
60
60.05
60.1
Time (sec)
Freq
uenc
y (H
z)
Coronado 500-kV Bus Frequency
ActualSimulated
![Page 29: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/29.jpg)
28
Figure S2: Simulated Springervile 4 Dynamics During May 16 RAS Event
0 10 20 30 40 50 60 70 801
1.02
1.04
1.06
Time (sec)
Vol
tage
(PU
)
Sprinerville 4 Voltages
POI 345-kVGenerator
0 10 20 30 40 50 60 70 8059.5
59.6
59.7
59.8
59.9
60
Time (sec)
Freq
uenc
y (H
z)
Sprinerville 4 Frequency
FrequencySpeed
0 10 20 30 40 50 60 70 80420
430
440
450
460
Time (sec)
Pow
er (
MW
)
Sprinerville 4 Power
ElectricalMechanical
![Page 30: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/30.jpg)
29
Figure S3: Comparison of Simulated Springervile Dynamics During May 16 RAS Event and 2 PV event
0 10 20 30 40 50 60 70 8059.65
59.7
59.75
59.8
59.85
59.9
59.95
60
60.05
Time (sec)
Freq
uenc
y (H
z)
Sprinerville 4 Frequency
RAS-2014-05-162 Palo Verde
0 10 20 30 40 50 60 70 80420
425
430
435
440
445
450
455
460
Time (sec)
Pow
er (
MW
)
Sprinerville 4 Electrical Power
RAS-2014-05-162 Palo Verde
![Page 31: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/31.jpg)
30
Figure S4: Comparison of Simulated Springervile Dynamics During May 16 RAS Event and 2 PV event
0 10 20 30 40 50 60 70 8059.6
59.7
59.8
59.9
60
Time (sec)
Freq
uenc
y (H
z)
System Frequency
2PV2PV+Springerville
0 10 20 30 40 50 60 70 80480
500
520
540
560
Time (sec)
Vol
tage
(kV
)
Malin 500-kV Bus Voltage
2PV2PV+Springerville
0 10 20 30 40 50 60 70 803000
3500
4000
4500
5000
Time (sec)
Pow
er (
MW
)
COI Power
2PV2PV+Springerville
![Page 32: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/32.jpg)
31
Figure N1: Sensitivity with respect to reducing NW RAS gen.drop
5 10 15 20 250.85
0.9
0.95
1
1.05
1.1
Time (sec)
Vol
tage
(kV
)
MIN-287-kV Voltage
OriginalReduced NW RAS
5 10 15 20 25200
250
300
350
400
450
500
550
600
Time (sec)
Pow
er (
MW
)
KIT-MIN Power Flow
OriginalReduced NW RAS
![Page 33: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/33.jpg)
32
Figure N2: Sensitivity with respect to operation of Chief Joseph braking resistor
5 10 15 20 250.85
0.9
0.95
1
1.05
1.1
Time (sec)
Vol
tage
(kV
)MIN-287-kV Voltage
OriginalNo brake
5 10 15 20 25200
250
300
350
400
450
500
550
600
Time (sec)
Pow
er (
MW
)
KIT-MIN Power Flow
OriginalNo brake
![Page 34: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/34.jpg)
33
Figure KP1: Sensitivity with respect to Kemano PSS settings
10 12 14 16 18 200.85
0.9
0.95
1
1.05
1.1
Time (sec)
Vol
tage
(kV
)MIN-287-kV Voltage
OriginalKMO PSS-Intertia Gain
10 12 14 16 18 20200
250
300
350
400
450
500
550
600
Time (sec)
Pow
er (
MW
)
KIT-MIN Power Flow
OriginalKMO PSS-Intertia Gain
![Page 35: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/35.jpg)
34
Figure KIT1: Sensitivity with respect to Kittimat Load Composition- Original: 90% constant impedance, 10% motors with Driven Load D=2- Conservative: 80% constant current, 20% motors with Driven Load
D=0
10 12 14 16 18 200.85
0.9
0.95
1
1.05
1.1
Time (sec)
Vol
tage
(kV
)MIN-287-kV Voltage
OriginalMore Conservative
10 12 14 16 18 20200
250
300
350
400
450
500
550
600
Time (sec)
Pow
er (
MW
)
KIT-MIN Power Flow
OriginalMore Conservative
![Page 36: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/36.jpg)
35
Figure E1: Impact of extreme generation drop
0 10 20 30 40 50 60 70 8059.5
59.6
59.7
59.8
59.9
60
60.1
Time (sec)
Freq
uenc
y (H
z)Malin 500-kV Frequency
0 10 20 30 40 50 60 70 8059.5
59.6
59.7
59.8
59.9
60
60.1
Time (sec)
Freq
uenc
y (H
z)
Coronado 500-kV Frequency
May 16 as was4,000 MW RAS Gendrop
May 16 as was4,000 MW RAS Gendrop
![Page 37: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/37.jpg)
36
Figure E2: Impact of extreme generation drop
0 10 20 30 40 50 60 70 8059.5
59.6
59.7
59.8
59.9
60
60.1
Time (sec)
Freq
uenc
y (H
z)Williston 500-kV Frequency
0 10 20 30 40 50 60 70 8059.5
59.6
59.7
59.8
59.9
60
60.1
Time (sec)
Freq
uenc
y (H
z)
Langdon 500-kV Frequency
May 16 as was4,000 MW RAS Gendrop
May 16 as was4,000 MW RAS Gendrop
![Page 38: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/38.jpg)
37
Figure E3: Impact of extreme generation drop
5 10 15 20 250.8
0.9
1
1.1
Time (sec)
Vol
tage
(PU
))MIN 287-kV Voltage
May 16 as was4,000 MW RAS Gendrop
5 10 15 20 250.95
1
1.05
1.1
Time (sec)
Vol
tage
(PU
))
Langdon 500-kV Voltage
May 16 as was4,000 MW RAS Gendrop
5 10 15 20 251
1.01
1.02
1.03
1.04
1.05
Time (sec)
Vol
tage
(PU
))
Great Falls 230-kV Voltage
May 16 as was4,000 MW RAS Gendrop
![Page 39: Document name Model Validation Report for May 16, 2014 … Validation Report for May 16 2014 RAS Event.pdfplanning case, thereby greatly improving the development of a validation base](https://reader033.vdocuments.us/reader033/viewer/2022041506/5e2557e0331d54268b21218e/html5/thumbnails/39.jpg)
38
Figure E4: Impact of extreme generation drop
5 10 15 20 25-200
0
200
400
600
Time (sec)
Pow
er (
MW
)KIT-MIN Active Power
5 10 15 20 25-400
-200
0
200
400
600
Time (sec)
Pow
er (
MW
)
Langon-Cranbrook Active Power
5 10 15 20 25-100
0
100
200
300
Time (sec)
Pow
er (
MW
)
MATL Active Power
May 16 as was4,000 MW RAS Gendrop
May 16 as was4,000 MW RAS Gendrop
May 16 as was4,000 MW RAS Gendrop