document id: 0.7.522.352505 to: alejandro huerta · laura rodriguez principal planner ee logo --...

144
From: Laura Rodriguez <[email protected]> To: Alejandro Huerta <[email protected]>; Moosbrugger, Earl <[email protected]>; Kwan, Delon <[email protected]>; Jin Hwang <[email protected]> Cc: Stephanie Eyestone-Jones <[email protected]> Subject: Crossroads Project WSA Request Hello Please refer to email below – the check for the Crossroads Project WSA was hand-delivered today and provided to Julie Speocht. Please confirm receipt. Thank you Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles, California 90045 T (424) 207-5333 F (424) 207-5349 DIRECT (424) 207-5339 EMAIL [email protected] Date: Fri Apr 15 2016 14:59:30 PDT Attachments: image001.jpg Bcc: Document ID: 0.7.522.352505 Page 2 of 279

Upload: others

Post on 30-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Laura Rodriguez <[email protected]>To: Alejandro Huerta <[email protected]>; Moosbrugger, Earl <[email protected]>; Kwan, Delon <[email protected]>; Jin Hwang <[email protected]>Cc: Stephanie Eyestone-Jones <[email protected]>

Subject: Crossroads Project WSA Request

Hello

Please refer to email below – the check for the Crossroads Project WSA was hand-delivered today andprovided to Julie Speocht. Please confirm receipt.

Thank you

Laura RodriguezPrincipal Planner

EE logo -- horizontal stack (RGB, screen-res, 3

6701 Center Drive West, Suite 900

Los Angeles, California 90045

T (424) 207-5333

F (424) 207-5349

DIRECT (424) 207-5339

EMAIL [email protected]

Date: Fri Apr 15 2016 14:59:30 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.352505

Page 2 of 279

Page 2: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Myers Gmail [mailto:[email protected]]Sent: Friday, April 15, 2016 2:55 PMTo: Laura RodriguezCc: Kyndra Joy Casper; Stephanie Eyestone-Jones; Madonna Marcelo; Brad WoomerSubject: Re: Crossroads List of 1st Screencheck Batches_4 15 2016.docx

I hand-delivered it to 1455 and gave it to Julie Speocht. I gave her my phone and email. I told her itwas for a WSA and for the Crossroads project. She knew the project and understood what it was forand said she would give it to Martin.

Sent from my iPhone

Page 3 of 279

Page 3: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Laura Rodriguez <[email protected]>; Alejandro Huerta <[email protected]>; Moosbrugger, Earl <[email protected]>; Hwang, Jin <[email protected]>Cc: Stephanie Eyestone-Jones <[email protected]>

Subject: RE: Crossroads Project WSA Request

Hi Laura,

We received it.

Thanks,Delon Kwan, P.E.LADWP - Water Resources Development111 N. Hope Street, Room 1460Los Angeles, CA 90012(213) 367-2166<tel:%28213%29%20367-2166>(213) 367-1131<tel:%28213%29%20367-1131> [email protected]<mailto:[email protected]>

From: Laura Rodriguez [mailto:[email protected]]Sent: Friday, April 15, 2016 3:00 PMTo: Alejandro Huerta; Moosbrugger, Earl; Kwan, Delon; Hwang, JinCc: Stephanie Eyestone-JonesSubject: Crossroads Project WSA Request

Hello

Please refer to email below – the check for the Crossroads Project WSA was hand-delivered today andprovided to Julie Speocht. Please confirm receipt.

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Date: Fri Apr 15 2016 15:00:26 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.586093

Page 4 of 279

Page 4: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Myers Gmail [mailto:[email protected]]Sent: Friday, April 15, 2016 2:55 PMTo: Laura RodriguezCc: Kyndra Joy Casper; Stephanie Eyestone-Jones; Madonna Marcelo; Brad WoomerSubject: Re: Crossroads List of 1st Screencheck Batches_4 15 2016.docx

I hand-delivered it to 1455 and gave it to Julie Speocht. I gave her my phone and email. I told her itwas for a WSA and for the Crossroads project. She knew the project and understood what it was forand said she would give it to Martin.

Sent from my iPhone

Page 5 of 279

Page 5: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Laura Rodriguez <[email protected]>; Alejandro Huerta <[email protected]>; Moosbrugger, Earl <[email protected]>; Hwang, Jin <[email protected]>Cc: Stephanie Eyestone-Jones <[email protected]>

Subject: RE: Crossroads Project WSA Request

Hi Laura,

We received it.

Thanks,Delon Kwan, P.E.LADWP - Water Resources Development111 N. Hope Street, Room 1460Los Angeles, CA 90012(213) 367-2166<tel:%28213%29%20367-2166>(213) 367-1131<tel:%28213%29%20367-1131> [email protected]<mailto:[email protected]>

From: Laura Rodriguez [mailto:[email protected]]Sent: Friday, April 15, 2016 3:00 PMTo: Alejandro Huerta; Moosbrugger, Earl; Kwan, Delon; Hwang, JinCc: Stephanie Eyestone-JonesSubject: Crossroads Project WSA Request

Hello

Please refer to email below – the check for the Crossroads Project WSA was hand-delivered today andprovided to Julie Speocht. Please confirm receipt.

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Date: Fri Apr 15 2016 15:00:26 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.352508

Page 6 of 279

Page 6: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Myers Gmail [mailto:[email protected]]Sent: Friday, April 15, 2016 2:55 PMTo: Laura RodriguezCc: Kyndra Joy Casper; Stephanie Eyestone-Jones; Madonna Marcelo; Brad WoomerSubject: Re: Crossroads List of 1st Screencheck Batches_4 15 2016.docx

I hand-delivered it to 1455 and gave it to Julie Speocht. I gave her my phone and email. I told her itwas for a WSA and for the Crossroads project. She knew the project and understood what it was forand said she would give it to Martin.

Sent from my iPhone

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 7 of 279

Page 7: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Alejandro Huerta <[email protected]>To: Kwan, Delon <[email protected]>Cc: Laura Rodriguez <[email protected]>; Moosbrugger, Earl <[email protected]>; Hwang, Jin <[email protected]>; Stephanie Eyestone-Jones <[email protected]>

Subject: Re: Crossroads Project WSA Request

Thanks all,

Alejandro A. HuertaEnvironmental Analysis • Major Projects

(213) 978-1454

On Fri, Apr 15, 2016 at 3:00 PM, Kwan, Delon <[email protected]> wrote:

Hi Laura,

We received it.

Thanks,

Delon Kwan, P.E.

LADWP - Water Resources Development

111 N. Hope Street, Room 1460

Los Angeles, CA 90012

(213) 367-2166

(213) 367-1131 Fax

[email protected]

Date: Fri Apr 15 2016 15:01:15 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.352511

Page 8 of 279

Page 8: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Laura Rodriguez [mailto:[email protected]]Sent: Friday, April 15, 2016 3:00 PMTo: Alejandro Huerta; Moosbrugger, Earl; Kwan, Delon; Hwang, JinCc: Stephanie Eyestone-JonesSubject: Crossroads Project WSA Request

Hello

Please refer to email below – the check for the Crossroads Project WSA was hand-delivered today andprovided to Julie Speocht. Please confirm receipt.

Thank you

Laura RodriguezPrincipal Planner

EE logo -- horizontal stack (RGB, screen-res, 3

6701 Center Drive West, Suite 900

Los Angeles, California 90045

T (424) 207-5333

F (424) 207-5349

DIRECT (424) 207-5339

EMAIL [email protected]

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

Page 9 of 279

Page 9: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

P Please consider the environment before printing this email.

From: Myers Gmail [mailto:[email protected]]Sent: Friday, April 15, 2016 2:55 PMTo: Laura RodriguezCc: Kyndra Joy Casper; Stephanie Eyestone-Jones; Madonna Marcelo; Brad WoomerSubject: Re: Crossroads List of 1st Screencheck Batches_4 15 2016.docx

I hand-delivered it to 1455 and gave it to Julie Speocht. I gave her my phone and email. I told her itwas for a WSA and for the Crossroads project. She knew the project and understood what it was forand said she would give it to Martin.

Sent from my iPhone

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 10 of 279

Page 10: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Repp, Chris <[email protected]>To: [email protected] <[email protected]>Cc:

Subject: Hollywood/crossroads Project

I did not use a personal electronic device or personal email account to send or receive communicationsor documents related to this project.

Sent from my iPhone

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Date: Thu Mar 30 2017 18:02:23 PDTAttachments:

Bcc:

Document ID: 0.7.522.845486

Page 11 of 279

Page 11: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: FW: Crossroads WSA Request Letter

Earl,

Have we received the WSA request letter for the Crossroads Project?

From: Laura Rodriguez [mailto:[email protected]]Sent: Tuesday, April 12, 2016 3:31 PMTo: Hwang, Jin; Kwan, DelonSubject: Crossroads WSA Request Letter

Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Date: Wed Apr 13 2016 06:24:34 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.584042

Page 12 of 279

Page 12: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Aghakhani, Ryan <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Q/A WSA board meeting

Earl,

For your review. Left a copy of your notes on your desk and copy of my edits.

From: Moosbrugger, EarlSent: Wednesday, September 14, 2016 1:05 PMTo: Aghakhani, RyanSubject: FW: Q/A WSA board meeting

Ryan,

Please update.

This is priority for now.

I didn't read through, so not sure how much change needed.

Please let me know when complete.

Thanks

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Date: Wed Sep 14 2016 17:06:12 PDTAttachments: WSA Board Questions September 20 2016 - fact sheet.docx

Bcc:

Document ID: 0.7.522.745026

Page 13 of 279

Page 13: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Thanks.

Page 14 of 279

Page 14: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Aghakhani, Ryan <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: 3700 Wilshire Project WSA

Updated. I decided to eliminate that one paragraph about WSAP allocation. Everything in it ismentioned in that previous paragraph. There is no need for it when talking about water conservation forthe state through.

I'm heading to lunch, we can discuss after if we need to.

-Ryan

From: Aghakhani, RyanSent: Thursday, September 15, 2016 7:54 AMTo: Moosbrugger, EarlSubject: FW: 3700 Wilshire Project WSA

Excellent, received this. I'm starting to review the plans and info, looks concise upon first glance.

From: Jena Choi [mailto:[email protected]]Sent: Wednesday, September 14, 2016 6:50 PMTo: Aghakhani, RyanCc: [email protected]<mailto:[email protected]>; 'Garrett Lee';[email protected]<mailto:[email protected]>; 'MattDzurec'; 'Seth Wulkan'; 'Brendan Bettwy'; 'Jerry Lam'; 'Chris Joseph'; 'Robert Lisauskas'; [email protected]<mailto:[email protected]>; [email protected]<mailto:[email protected]>Subject: 3700 Wilshire Project WSA

Hi Ryan,

Attached please find the conservation commitment draft letter and answers to your questions for 3700Wilshire's WSA.

Also, we updated the attached WSA request letter with the latest project information since it was lastsubmitted for reference.

Proposed project plans can be downloaded here: https://www.dropbox.com/s/9t2rpah0qlok9y7/3700%20Wilshire%20-%20Case%20Filing%206-27-16.pdf?dl=0

Existing project plans can be downloaded here: https://www.dropbox.com/s/sr2cw6pu580deh2/3700_existing%20architectural%20dwg%20scan.zip?dl=0

Lastly, we sent the fee check out today, to the following address:

Date: Thu Sep 15 2016 11:58:51 PDTAttachments: WSA Board Questions September 20 2016 - fact sheet (9-15-16).docx

Bcc:

Document ID: 0.7.522.745391

Page 15 of 279

Page 15: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Los Angeles Department of Water and PowerMartin L. AdamsSenior Assistant General Manager - Water System111 North Hope Street, Room 1455Los Angeles, California 90012Please let us know if you have any questions.

Thanks,Jena

Jena ChoiJamison Properties, LP / 3470 Wilshire Boulevard, Suite 700 / Los Angeles, California 90010Direct: 213 788 3307 / Main: 213 365 5000 / [email protected]<mailto:[email protected]>

Page 16 of 279

Page 16: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Aghakhani, Ryan <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: 3700 Wilshire Project WSA

Final

From: Aghakhani, RyanSent: Thursday, September 15, 2016 11:59 AMTo: Moosbrugger, EarlSubject: RE: 3700 Wilshire Project WSA

Updated. I decided to eliminate that one paragraph about WSAP allocation. Everything in it ismentioned in that previous paragraph. There is no need for it when talking about water conservation forthe state through.

I'm heading to lunch, we can discuss after if we need to.

-Ryan

From: Aghakhani, RyanSent: Thursday, September 15, 2016 7:54 AMTo: Moosbrugger, EarlSubject: FW: 3700 Wilshire Project WSA

Excellent, received this. I'm starting to review the plans and info, looks concise upon first glance.

From: Jena Choi [mailto:[email protected]]Sent: Wednesday, September 14, 2016 6:50 PMTo: Aghakhani, RyanCc: [email protected]<mailto:[email protected]>; 'Garrett Lee';[email protected]<mailto:[email protected]>; 'MattDzurec'; 'Seth Wulkan'; 'Brendan Bettwy'; 'Jerry Lam'; 'Chris Joseph'; 'Robert Lisauskas'; [email protected]<mailto:[email protected]>; [email protected]<mailto:[email protected]>Subject: 3700 Wilshire Project WSA

Hi Ryan,

Attached please find the conservation commitment draft letter and answers to your questions for 3700Wilshire's WSA.

Also, we updated the attached WSA request letter with the latest project information since it was lastsubmitted for reference.

Date: Thu Sep 15 2016 14:28:41 PDTAttachments: WSA Board Questions September 20 2016 - fact sheet (9-15-16) FINAL.docx

Bcc:

Document ID: 0.7.522.745395

Page 17 of 279

Page 17: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Proposed project plans can be downloaded here: https://www.dropbox.com/s/9t2rpah0qlok9y7/3700%20Wilshire%20-%20Case%20Filing%206-27-16.pdf?dl=0

Existing project plans can be downloaded here: https://www.dropbox.com/s/sr2cw6pu580deh2/3700_existing%20architectural%20dwg%20scan.zip?dl=0

Lastly, we sent the fee check out today, to the following address:Los Angeles Department of Water and PowerMartin L. AdamsSenior Assistant General Manager - Water System111 North Hope Street, Room 1455Los Angeles, California 90012Please let us know if you have any questions.

Thanks,Jena

Jena ChoiJamison Properties, LP / 3470 Wilshire Boulevard, Suite 700 / Los Angeles, California 90010Direct: 213 788 3307 / Main: 213 365 5000 / [email protected]<mailto:[email protected]>

Page 18 of 279

Page 18: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Aghakhani, Ryan <[email protected]>Cc:

Subject: RE: 3700 Wilshire Project WSA

I made a few additions/edits.

Please remove comments but keep in track changes mode and send to Delon with C.C. to me.

Also, please delete everything in title after last parenthesis.

Thanks

From: Aghakhani, RyanSent: Thursday, September 15, 2016 2:29 PMTo: Moosbrugger, EarlSubject: RE: 3700 Wilshire Project WSA

Final

From: Aghakhani, RyanSent: Thursday, September 15, 2016 11:59 AMTo: Moosbrugger, EarlSubject: RE: 3700 Wilshire Project WSA

Updated. I decided to eliminate that one paragraph about WSAP allocation. Everything in it ismentioned in that previous paragraph. There is no need for it when talking about water conservation forthe state through.

I'm heading to lunch, we can discuss after if we need to.

-Ryan

From: Aghakhani, RyanSent: Thursday, September 15, 2016 7:54 AMTo: Moosbrugger, EarlSubject: FW: 3700 Wilshire Project WSA

Excellent, received this. I'm starting to review the plans and info, looks concise upon first glance.

From: Jena Choi [mailto:[email protected]]Sent: Wednesday, September 14, 2016 6:50 PM

Date: Thu Sep 15 2016 15:20:28 PDTAttachments: WSA Board Questions September 20 2016 - fact sheet (9-15-16) FINAL edm 1.docx

Bcc:

Document ID: 0.7.522.745415

Page 19 of 279

Page 19: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

To: Aghakhani, RyanCc: [email protected]<mailto:[email protected]>; 'Garrett Lee';[email protected]<mailto:[email protected]>; 'MattDzurec'; 'Seth Wulkan'; 'Brendan Bettwy'; 'Jerry Lam'; 'Chris Joseph'; 'Robert Lisauskas'; [email protected]<mailto:[email protected]>; [email protected]<mailto:[email protected]>Subject: 3700 Wilshire Project WSA

Hi Ryan,

Attached please find the conservation commitment draft letter and answers to your questions for 3700Wilshire's WSA.

Also, we updated the attached WSA request letter with the latest project information since it was lastsubmitted for reference.

Proposed project plans can be downloaded here: https://www.dropbox.com/s/9t2rpah0qlok9y7/3700%20Wilshire%20-%20Case%20Filing%206-27-16.pdf?dl=0

Existing project plans can be downloaded here: https://www.dropbox.com/s/sr2cw6pu580deh2/3700_existing%20architectural%20dwg%20scan.zip?dl=0

Lastly, we sent the fee check out today, to the following address:Los Angeles Department of Water and PowerMartin L. AdamsSenior Assistant General Manager - Water System111 North Hope Street, Room 1455Los Angeles, California 90012Please let us know if you have any questions.

Thanks,Jena

Jena ChoiJamison Properties, LP / 3470 Wilshire Boulevard, Suite 700 / Los Angeles, California 90010Direct: 213 788 3307 / Main: 213 365 5000 / [email protected]<mailto:[email protected]>

Page 20 of 279

Page 20: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Aghakhani, Ryan <[email protected]>Cc:

Subject: FW: Q/A WSA board meeting

Ryan,

Please update.

This is priority for now.

I didn't read through, so not sure how much change needed.

Please let me know when complete.

Thanks

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Date: Wed Sep 14 2016 13:04:46 PDTAttachments: WSA Board Questions August 2, 2016 - fact sheet.docx

Bcc:

Document ID: 0.7.522.744725

Page 21 of 279

Page 21: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Aghakhani, Ryan <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Q/A WSA board meeting

Only one project specific item changed

From: Moosbrugger, EarlSent: Wednesday, September 14, 2016 1:05 PMTo: Aghakhani, RyanSubject: FW: Q/A WSA board meeting

Ryan,

Please update.

This is priority for now.

I didn't read through, so not sure how much change needed.

Please let me know when complete.

Thanks

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Date: Wed Sep 14 2016 14:04:14 PDTAttachments: WSA Board Questions September 20 2016 - fact sheet.docx

Bcc:

Document ID: 0.7.522.744759

Page 22 of 279

Page 22: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: RE: LADWP Board Agenda for 11-15-16

Here is updated; I put all three WSAs on same sheet for convenience.

Staff reviewed highlighted updated after I completed (quickest way).

Would you like a print out of final on your desk?

From: Kwan, DelonSent: Monday, November 14, 2016 9:05 AMTo: Moosbrugger, EarlSubject: Re: LADWP Board Agenda for 11-15-16

its a separate Q&A to address board's prior questions at meetings

________________________________From: Moosbrugger, EarlSent: Monday, November 14, 2016 7:35 AMTo: Kwan, DelonSubject: RE: LADWP Board Agenda for 11-15-16

Are you talking about the Q&A section of the fact sheets?

From: Kwan, DelonSent: Monday, November 14, 2016 7:32 AMTo: Moosbrugger, EarlSubject: Re: LADWP Board Agenda for 11-15-16

for tomorrow's board meeting, can you /staff also update and send me the water supply Q&As sheet.

________________________________From: Kwan, DelonSent: Monday, November 14, 2016 6:55 AMTo: Moosbrugger, EarlSubject: Fw: LADWP Board Agenda for 11-15-16

Date: Mon Nov 14 2016 11:07:27 PSTAttachments: WSA Board Questions Responses for November 15, 2016 - v1.docx

Bcc:

Document ID: 0.7.522.691008

Page 23 of 279

Page 23: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

________________________________From: Flores, VivianSent: Monday, November 14, 2016 6:53 AMTo: Hobson, Cristal; Kwan, Delon; Pettijohn, DavidSubject: FW: LADWP Board Agenda for 11-15-16

From: Flores, VivianSent: Monday, November 14, 2016 6:49 AMTo: Gastelum, Albert; Grime, Karyn; Harasick, Richard; Mejia, Nelson; Pettijohn, David; Rowghani,Susan; Session, Keith (Manager); Spacht, Julie; Dooley, Delilah; Gonzalez, Lupe; Kay, Maria; Rayas-glen, Yvonne; Rodriguez, Arlene; Yu, JennifferSubject: LADWP Board Agenda for 11-15-16

Attached is tomorrow’s agenda. Meeting starts at 10a.

Please forward as needed.

Thank you,

Vivian Flores(213) 367-1016Utility Executive Secretary for Richard F. HarasickLos Angeles Department of Water and Power

From: Moschos, BarbaraSent: Thursday, November 10, 2016 4:17 PMSubject: LADWP Board Agenda for 11-15-16

FYI – LADWP Board agenda for Tuesday, November 15, 2016.

NOTE: Regular Board meetings now start at 10:00 a.m.

Barbara E. MoschosBoard Secretary(213) 367-1351

Page 24 of 279

Page 24: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: FW: Q/A WSA board meeting - 698 New Hampshire

I took a second look; it does show all substantive changes

From: Aghakhani, RyanSent: Thursday, September 15, 2016 3:42 PMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Q/A WSA board meeting - 698 New Hampshire

Delon,

Updated for the New Hampshire Project. Track changes mode is reflective of latest revision betweenEarl and me.

-Ryan

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Date: Fri Sep 16 2016 07:45:20 PDTAttachments: WSA Board Questions September 20 2016 - fact sheet (9-15-16).docx

Bcc:

Document ID: 0.7.522.615055

Page 25 of 279

Page 25: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Aghakhani, Ryan <[email protected]>To: Kwan, Delon <[email protected]>Cc: Moosbrugger, Earl <[email protected]>

Subject: Q/A WSA board meeting - 698 New Hampshire

Delon,

Updated for the New Hampshire Project. Track changes mode is reflective of latest revision betweenEarl and me.

-Ryan

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Date: Thu Sep 15 2016 15:42:27 PDTAttachments: WSA Board Questions September 20 2016 - fact sheet (9-15-16).docx

Bcc:

Document ID: 0.7.522.614864

Page 26 of 279

Page 26: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Date: Wed Sep 14 2016 07:30:20 PDTAttachments: WSA Board Questions August 2, 2016 - fact sheet.docx

Bcc:

Document ID: 0.7.522.611265

Page 27 of 279

Page 27: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: RE: Q/A WSA board meeting

Attached has new additions under Submetering section.

Thanks

From: Moosbrugger, EarlSent: Monday, August 01, 2016 11:22 AMTo: Kwan, DelonSubject: FW: Q/A WSA board meeting

Actually, I need to add a couple more items to the sheet that I sent, regarding submetering.

From: Moosbrugger, EarlSent: Monday, August 01, 2016 11:19 AMTo: Kwan, DelonSubject: RE: Q/A WSA board meeting

Here is code, but not specifically for commercial:

99.05.303.1.1. New Buildings or Additions in Excess of 50,000 Square Feet.Separate submeters or meters shall be installed as follows:1. For each individual leased, rented, or other tenant space within thebuilding projected to consume more than 100 gallons per day (380 Llday).2. Where potable water is used for industrial/process uses, for watersupplied to the following subsystems:a. Makeup water for cooling towers where flow through isgreater than 500 gpm (30 Us).b. Makeup water for evaporative coolers greater than 6 gpm(0.04 Lis).c. Steam and hot-water boilers with energy input more than500,000 Btu/h (147 kW).3. For each building that uses more than 100 gallons per day on aparcel containing multiple buildings.

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Kwan, Delon

Date: Mon Aug 01 2016 11:27:59 PDTAttachments: WSA Board Questions August 2 2016 - fact sheet - EDM 160801 v2.docx

Bcc:

Document ID: 0.7.522.521575

Page 28 of 279

Page 28: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Sent: Monday, August 01, 2016 11:08 AMTo: Moosbrugger, EarlSubject: RE: Q/A WSA board meeting

Thanks.

I just remembered on submetering for commericial, there are requirements if estimated demand meetscertain conditions?

From: Moosbrugger, EarlSent: Monday, August 01, 2016 11:03 AMTo: Kwan, DelonSubject: RE: Q/A WSA board meeting

Here you go.

Thanks

From: Kwan, DelonSent: Monday, August 01, 2016 10:13 AMTo: Moosbrugger, Earl; Hwang, JinSubject: RE: Q/A WSA board meeting

I would like to give to Dave shortly since board meeting is tomorrow, if you can let me know if you haveany further edits by 11 am today.

Thanks.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Page 29 of 279

Page 29: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: RE: Q/A WSA board meeting

Here you go.

Thanks

From: Kwan, DelonSent: Monday, August 01, 2016 10:13 AMTo: Moosbrugger, Earl; Hwang, JinSubject: RE: Q/A WSA board meeting

I would like to give to Dave shortly since board meeting is tomorrow, if you can let me know if you haveany further edits by 11 am today.

Thanks.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Date: Mon Aug 01 2016 11:02:34 PDTAttachments: WSA Board Questions August 2 2016 - fact sheet - EDM 160801.docx

Bcc:

Document ID: 0.7.522.521297

Page 30 of 279

Page 30: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Moosbrugger, Earl <[email protected]>; Hwang, Jin <[email protected]>Cc:

Subject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Date: Mon Aug 01 2016 08:00:09 PDTAttachments: WSA Board Questions August 2, 2016 - fact sheet.docx

Bcc:

Document ID: 0.7.522.520477

Page 31 of 279

Page 31: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Tcharssov, Andrei <[email protected]>; Hwang, Jin <[email protected]>; Aghakhani, Ryan <[email protected]>Cc:

Subject: PLease Review Highlighted Figures Only Before Lunch

Please review highlighted figures and let me know if they are okay before lunch.

thanks

Date: Mon Nov 14 2016 10:50:12 PSTAttachments: WSA Board Questions Responses for November 15, 2016 - v1.docx

Bcc:

Document ID: 0.7.522.286148

Page 32 of 279

Page 32: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

I can’t tell from vague responses how much of template and for Crossroad project updates remainingstill required. I took a brief look at link and still require updates in several sections from what I can tell.Also, Did Greg Reed’s group look at update to GW section?

Assume you have better handle on it regarding when might be completed?

From: Hwang, JinSent: Thursday, June 09, 2016 11:38 AMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

both

From: Kwan, DelonSent: Thursday, June 09, 2016 11:37 AMTo: Hwang, JinCc: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Are you talking about updates to template and/or Crossroads project, or both?

From: Hwang, JinSent: Thursday, June 09, 2016 11:33 AMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Crossroads Hollywood Project WSA

Delon,

I’m still working on updating the WSA, but here is the link to the latest copy.Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood WSA at 6-9-16 JH.docx<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20WSA%20at%206-9-16%20JH.docx>

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and Power

Date: Fri Jun 10 2016 08:19:35 PDTAttachments:

Bcc:

Document ID: 0.7.522.440359

Page 33 of 279

Page 33: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Water Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

Page 34 of 279

Page 34: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Hwang, Jin <[email protected]>Cc: Moosbrugger, Earl <[email protected]>

Subject: RE: Crossroads Hollywood Project WSA

Are you talking about updates to template and/or Crossroads project, or both?

From: Hwang, JinSent: Thursday, June 09, 2016 11:33 AMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Crossroads Hollywood Project WSA

Delon,

I’m still working on updating the WSA, but here is the link to the latest copy.Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood WSA at 6-9-16 JH.docx<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20WSA%20at%206-9-16%20JH.docx>

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

Date: Thu Jun 09 2016 11:36:32 PDTAttachments:

Bcc:

Document ID: 0.7.522.438280

Page 35 of 279

Page 35: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Q/A WSA board meeting - 698 New Hampshire

You sure this is the updated one, it still describes the Crossroads project, etc. or am I looking at wrongtrack changes settings?

From: Moosbrugger, EarlSent: Friday, September 16, 2016 7:45 AMTo: Kwan, DelonSubject: FW: Q/A WSA board meeting - 698 New Hampshire

I took a second look; it does show all substantive changes

From: Aghakhani, RyanSent: Thursday, September 15, 2016 3:42 PMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Q/A WSA board meeting - 698 New Hampshire

Delon,

Updated for the New Hampshire Project. Track changes mode is reflective of latest revision betweenEarl and me.

-Ryan

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, Jin

Date: Mon Sep 19 2016 07:20:09 PDTAttachments:

Bcc:

Document ID: 0.7.522.616183

Page 36 of 279

Page 36: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Subject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Page 37 of 279

Page 37: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy Casper

Date: Thu Jul 14 2016 15:24:16 PDTAttachments: CEQA_handbook.pdf image001.jpg

Bcc:

Document ID: 0.7.522.630424

Page 38 of 279

Page 38: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Subject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Page 39 of 279

Page 39: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045

Page 40 of 279

Page 40: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Page 41 of 279

Page 41: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 42 of 279

Page 42: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Aghakhani, Ryan <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: Monitoring Spreadsheet

Hi Jin,

I'm filling out the Monitoring Spreadsheet for my 698 New Hampshire WSA Project. Looking at AA57for your Crossroads project, where do you get the 1,432,500sf from? I notice 1,191,339sf is for garageand 31,506sf is for landscaping in the formula. It seems like 1,432,500sf is all the building but some ofthe sf is in dwelling units instead because of the calculation. Did you grab the 1,432,500 from what thecontractor gave you? Do you have that specific number somewhere? I just want to be consistent andknow what number to use for my project there. Call me if I sound confusing, thanks!

Ryan AghakhaniResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2022

Date: Thu Sep 01 2016 17:00:09 PDTAttachments:

Bcc:

Document ID: 0.7.522.652175

Page 43 of 279

Page 43: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads WSA Request Letter

No

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Wednesday, April 13, 2016 6:25 AMTo: Moosbrugger, EarlSubject: FW: Crossroads WSA Request Letter

Earl,

Have we received the WSA request letter for the Crossroads Project?

From: Laura Rodriguez [mailto:[email protected]]Sent: Tuesday, April 12, 2016 3:31 PMTo: Hwang, Jin; Kwan, DelonSubject: Crossroads WSA Request Letter

Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Date: Wed Apr 13 2016 06:50:57 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.584066

Page 46 of 279

Page 44: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 47 of 279

Page 45: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Delon ,

I deal with this daily, and I had bi-weekly meeting with staff yesterday focusing on four points we agreedupon for improvement; one covers the issue below about reporting on tasks and projects.

Regarding GW, yes, Greg responded on 5/13 and we incorporated his input.

I think detail in weekly summary sent a few minutes ago gives best explanation of where we stand, butbottom line is that I need to check calcs again (final check), complete MWD review (Andrei’s commentsand fact checking which I accomplished a lot of yesterday) and follow up on remaining updates Idescribed in weekly summary. As you suggested, and what I had assumed, we might need to updatefor Conservation Group based on UWMP and other sources of info.

It is just a matter of working through all of this now (lots of interruptions), and I will utilize other staff ifneeded.

Thanks!

From: Kwan, DelonSent: Friday, June 10, 2016 8:20 AMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

I can’t tell from vague responses how much of template and for Crossroad project updates remainingstill required. I took a brief look at link and still require updates in several sections from what I can tell.Also, Did Greg Reed’s group look at update to GW section?

Assume you have better handle on it regarding when might be completed?

From: Hwang, JinSent: Thursday, June 09, 2016 11:38 AMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

both

From: Kwan, DelonSent: Thursday, June 09, 2016 11:37 AMTo: Hwang, JinCc: Moosbrugger, Earl

Date: Fri Jun 10 2016 08:25:44 PDTAttachments:

Bcc:

Document ID: 0.7.522.440363

Page 48 of 279

Page 46: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Subject: RE: Crossroads Hollywood Project WSA

Are you talking about updates to template and/or Crossroads project, or both?

From: Hwang, JinSent: Thursday, June 09, 2016 11:33 AMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Crossroads Hollywood Project WSA

Delon,

I’m still working on updating the WSA, but here is the link to the latest copy.Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood WSA at 6-9-16 JH.docx<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20WSA%20at%206-9-16%20JH.docx>

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

Page 49 of 279

Page 47: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: Fwd: Crossroads WSA Request Letter

I've not seen request

________________________________From: "Laura Rodriguez" <[email protected]>Subject: Crossroads WSA Request LetterDate: 12 April 2016 15:31To: "Hwang, Jin" <[email protected]>, "Kwan, Delon" <[email protected]>Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Date: Tue Apr 12 2016 16:19:57 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.344569

Page 51 of 279

Page 48: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Laura Rodriguez <[email protected]>To: Hwang, Jin <[email protected]>; Kwan, Delon <[email protected]>Cc:

Subject: Crossroads WSA Request Letter

Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

EE logo -- horizontal stack (RGB, screen-res, 3

6701 Center Drive West, Suite 900

Los Angeles, California 90045

T (424) 207-5333

F (424) 207-5349

DIRECT (424) 207-5339

EMAIL [email protected]

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This

Date: Tue Apr 12 2016 15:31:06 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.344457

Page 52 of 279

Page 49: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

transmission is sent in trust, for the sole purpose of delivery to the intended recipient. If you havereceived this transmission in error, any use, reproduction or dissemination of this transmission is strictlyprohibited. If you are not the intended recipient, please immediately notify the sender by reply e-mail orphone and delete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 53 of 279

Page 50: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Aghakhani, Ryan <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Monitoring Spreadsheet

Nevermind realized today was your ASDO and I found the number in the request letter!

From: Aghakhani, RyanSent: Thursday, September 01, 2016 5:00 PMTo: Hwang, JinSubject: Monitoring Spreadsheet

Hi Jin,

I'm filling out the Monitoring Spreadsheet for my 698 New Hampshire WSA Project. Looking at AA57for your Crossroads project, where do you get the 1,432,500sf from? I notice 1,191,339sf is for garageand 31,506sf is for landscaping in the formula. It seems like 1,432,500sf is all the building but some ofthe sf is in dwelling units instead because of the calculation. Did you grab the 1,432,500 from what thecontractor gave you? Do you have that specific number somewhere? I just want to be consistent andknow what number to use for my project there. Call me if I sound confusing, thanks!

Ryan AghakhaniResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2022

Date: Fri Sep 02 2016 08:07:06 PDTAttachments:

Bcc:

Document ID: 0.7.522.652198

Page 59 of 279

Page 51: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Kwan, Delon <[email protected]>Cc: Moosbrugger, Earl <[email protected]>

Subject: RE: Crossroads Hollywood Project WSA

both

From: Kwan, DelonSent: Thursday, June 09, 2016 11:37 AMTo: Hwang, JinCc: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Are you talking about updates to template and/or Crossroads project, or both?

From: Hwang, JinSent: Thursday, June 09, 2016 11:33 AMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Crossroads Hollywood Project WSA

Delon,

I’m still working on updating the WSA, but here is the link to the latest copy.Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood WSA at 6-9-16 JH.docx<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20WSA%20at%206-9-16%20JH.docx>

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

Date: Thu Jun 09 2016 11:37:48 PDTAttachments:

Bcc:

Document ID: 0.7.522.438283

Page 60 of 279

Page 52: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads WSA Request Letter

Do you want me to reply that we have not received it and ask her to send us an electronic copy?

From: Moosbrugger, EarlSent: Wednesday, April 13, 2016 6:51 AMTo: Hwang, JinSubject: RE: Crossroads WSA Request Letter

No

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Wednesday, April 13, 2016 6:25 AMTo: Moosbrugger, EarlSubject: FW: Crossroads WSA Request Letter

Earl,

Have we received the WSA request letter for the Crossroads Project?

From: Laura Rodriguez [mailto:[email protected]]Sent: Tuesday, April 12, 2016 3:31 PMTo: Hwang, Jin; Kwan, DelonSubject: Crossroads WSA Request Letter

Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

Date: Wed Apr 13 2016 06:53:15 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.584068

Page 61 of 279

Page 53: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 62 of 279

Page 54: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads WSA Request Letter

Try to find out who the contact is in City Planning and tell that person that we have not received theletter.

Thanks!

From: Hwang, JinSent: Wednesday, April 13, 2016 6:53 AMTo: Moosbrugger, EarlSubject: RE: Crossroads WSA Request Letter

Do you want me to reply that we have not received it and ask her to send us an electronic copy?

From: Moosbrugger, EarlSent: Wednesday, April 13, 2016 6:51 AMTo: Hwang, JinSubject: RE: Crossroads WSA Request Letter

No

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Wednesday, April 13, 2016 6:25 AMTo: Moosbrugger, EarlSubject: FW: Crossroads WSA Request Letter

Earl,

Have we received the WSA request letter for the Crossroads Project?

From: Laura Rodriguez [mailto:[email protected]]Sent: Tuesday, April 12, 2016 3:31 PMTo: Hwang, Jin; Kwan, DelonSubject: Crossroads WSA Request Letter

Hi Jin and Delon,

Date: Wed Apr 13 2016 08:04:47 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.584077

Page 63 of 279

Page 55: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 64 of 279

Page 56: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads WSA Request Letter

Thanks!

Please let me know either way by the end of today.

From: Hwang, JinSent: Wednesday, April 13, 2016 8:21 AMTo: Moosbrugger, EarlSubject: RE: Crossroads WSA Request Letter

Alejandro, the planner at City Planning, thought he sent the request letter by email to me and Delon on3/9/16, but he cannot find a record of it. He'll find out and let me know.

From: Moosbrugger, EarlSent: Wednesday, April 13, 2016 8:05 AMTo: Hwang, JinSubject: RE: Crossroads WSA Request Letter

Try to find out who the contact is in City Planning and tell that person that we have not received theletter.

Thanks!

From: Hwang, JinSent: Wednesday, April 13, 2016 6:53 AMTo: Moosbrugger, EarlSubject: RE: Crossroads WSA Request Letter

Do you want me to reply that we have not received it and ask her to send us an electronic copy?

From: Moosbrugger, EarlSent: Wednesday, April 13, 2016 6:51 AMTo: Hwang, JinSubject: RE: Crossroads WSA Request Letter

No

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450

Date: Wed Apr 13 2016 08:43:02 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.584084

Page 65 of 279

Page 57: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Wednesday, April 13, 2016 6:25 AMTo: Moosbrugger, EarlSubject: FW: Crossroads WSA Request Letter

Earl,

Have we received the WSA request letter for the Crossroads Project?

From: Laura Rodriguez [mailto:[email protected]]Sent: Tuesday, April 12, 2016 3:31 PMTo: Hwang, Jin; Kwan, DelonSubject: Crossroads WSA Request Letter

Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 66 of 279

Page 58: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads WSA Request Letter

Alejandro, the planner at City Planning, thought he sent the request letter by email to me and Delon on3/9/16, but he cannot find a record of it. He'll find out and let me know.

From: Moosbrugger, EarlSent: Wednesday, April 13, 2016 8:05 AMTo: Hwang, JinSubject: RE: Crossroads WSA Request Letter

Try to find out who the contact is in City Planning and tell that person that we have not received theletter.

Thanks!

From: Hwang, JinSent: Wednesday, April 13, 2016 6:53 AMTo: Moosbrugger, EarlSubject: RE: Crossroads WSA Request Letter

Do you want me to reply that we have not received it and ask her to send us an electronic copy?

From: Moosbrugger, EarlSent: Wednesday, April 13, 2016 6:51 AMTo: Hwang, JinSubject: RE: Crossroads WSA Request Letter

No

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Wednesday, April 13, 2016 6:25 AMTo: Moosbrugger, EarlSubject: FW: Crossroads WSA Request Letter

Earl,

Date: Wed Apr 13 2016 08:21:28 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.584082

Page 67 of 279

Page 59: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Have we received the WSA request letter for the Crossroads Project?

From: Laura Rodriguez [mailto:[email protected]]Sent: Tuesday, April 12, 2016 3:31 PMTo: Hwang, Jin; Kwan, DelonSubject: Crossroads WSA Request Letter

Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 68 of 279

Page 60: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Here are my notes / comments to the latest draft WSA template sent by staff as of last week at linkbelow.

Let me know if you want to go over any of the comments.

Thanks.

From: Moosbrugger, EarlSent: Friday, June 10, 2016 8:26 AMTo: Kwan, DelonSubject: RE: Crossroads Hollywood Project WSA

Delon ,

I deal with this daily, and I had bi-weekly meeting with staff yesterday focusing on four points we agreedupon for improvement; one covers the issue below about reporting on tasks and projects.

Regarding GW, yes, Greg responded on 5/13 and we incorporated his input.

I think detail in weekly summary sent a few minutes ago gives best explanation of where we stand, butbottom line is that I need to check calcs again (final check), complete MWD review (Andrei’s commentsand fact checking which I accomplished a lot of yesterday) and follow up on remaining updates Idescribed in weekly summary. As you suggested, and what I had assumed, we might need to updatefor Conservation Group based on UWMP and other sources of info.

It is just a matter of working through all of this now (lots of interruptions), and I will utilize other staff ifneeded.

Thanks!

From: Kwan, DelonSent: Friday, June 10, 2016 8:20 AMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

I can’t tell from vague responses how much of template and for Crossroad project updates remainingstill required. I took a brief look at link and still require updates in several sections from what I can tell.Also, Did Greg Reed’s group look at update to GW section?

Assume you have better handle on it regarding when might be completed?

Date: Tue Jun 14 2016 08:43:28 PDTAttachments: Crossroads Hollywood WSA at 6-9-16 JH - delon edits 06-14-16.docx

Bcc:

Document ID: 0.7.522.444765

Page 69 of 279

Page 61: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, JinSent: Thursday, June 09, 2016 11:38 AMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

both

From: Kwan, DelonSent: Thursday, June 09, 2016 11:37 AMTo: Hwang, JinCc: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Are you talking about updates to template and/or Crossroads project, or both?

From: Hwang, JinSent: Thursday, June 09, 2016 11:33 AMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Crossroads Hollywood Project WSA

Delon,

I’m still working on updating the WSA, but here is the link to the latest copy.Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood WSA at 6-9-16 JH.docx<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20WSA%20at%206-9-16%20JH.docx>

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

Page 70 of 279

Page 62: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Aghakhani, Ryan <[email protected]>Cc:

Subject: RE: Monitoring Spreadsheet

Okay. :)

From: Aghakhani, RyanSent: Friday, September 02, 2016 8:07 AMTo: Hwang, JinSubject: RE: Monitoring Spreadsheet

Nevermind realized today was your ASDO and I found the number in the request letter!

From: Aghakhani, RyanSent: Thursday, September 01, 2016 5:00 PMTo: Hwang, JinSubject: Monitoring Spreadsheet

Hi Jin,

I'm filling out the Monitoring Spreadsheet for my 698 New Hampshire WSA Project. Looking at AA57for your Crossroads project, where do you get the 1,432,500sf from? I notice 1,191,339sf is for garageand 31,506sf is for landscaping in the formula. It seems like 1,432,500sf is all the building but some ofthe sf is in dwelling units instead because of the calculation. Did you grab the 1,432,500 from what thecontractor gave you? Do you have that specific number somewhere? I just want to be consistent andknow what number to use for my project there. Call me if I sound confusing, thanks!

Ryan AghakhaniResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2022

Date: Tue Sep 06 2016 06:45:07 PDTAttachments:

Bcc:

Document ID: 0.7.522.652489

Page 73 of 279

Page 63: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Kwan, Delon <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Q/A WSA board meeting - 698 New Hampshire

Did WSA have update on stress test results from state? Include in Q/A section following MWD endingallocation.

From: Kwan, DelonSent: Monday, September 19, 2016 7:20 AMTo: Moosbrugger, EarlSubject: RE: Q/A WSA board meeting - 698 New Hampshire

You sure this is the updated one, it still describes the Crossroads project, etc. or am I looking at wrongtrack changes settings?

From: Moosbrugger, EarlSent: Friday, September 16, 2016 7:45 AMTo: Kwan, DelonSubject: FW: Q/A WSA board meeting - 698 New Hampshire

I took a second look; it does show all substantive changes

From: Aghakhani, RyanSent: Thursday, September 15, 2016 3:42 PMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Q/A WSA board meeting - 698 New Hampshire

Delon,

Updated for the New Hampshire Project. Track changes mode is reflective of latest revision betweenEarl and me.

-Ryan

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

Date: Mon Sep 19 2016 07:53:41 PDTAttachments:

Bcc:

Document ID: 0.7.522.616296

Page 74 of 279

Page 64: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Page 75 of 279

Page 65: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: RE: Q/A WSA board meeting - 698 New Hampshire

I missed that word, but still updated version.

I will read through once more and re-send.

Thanks

From: Kwan, DelonSent: Monday, September 19, 2016 7:20 AMTo: Moosbrugger, EarlSubject: RE: Q/A WSA board meeting - 698 New Hampshire

You sure this is the updated one, it still describes the Crossroads project, etc. or am I looking at wrongtrack changes settings?

From: Moosbrugger, EarlSent: Friday, September 16, 2016 7:45 AMTo: Kwan, DelonSubject: FW: Q/A WSA board meeting - 698 New Hampshire

I took a second look; it does show all substantive changes

From: Aghakhani, RyanSent: Thursday, September 15, 2016 3:42 PMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Q/A WSA board meeting - 698 New Hampshire

Delon,

Updated for the New Hampshire Project. Track changes mode is reflective of latest revision betweenEarl and me.

-Ryan

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

Date: Mon Sep 19 2016 07:52:31 PDTAttachments:

Bcc:

Document ID: 0.7.522.616297

Page 76 of 279

Page 66: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Page 77 of 279

Page 67: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: RE: Crossroads WSA Request Letter

The only record I have is that we send instructions on 3/9/16.

From: Kwan, DelonSent: Tuesday, April 12, 2016 4:20 PMTo: Moosbrugger, EarlSubject: Fwd: Crossroads WSA Request Letter

I've not seen request

________________________________From: "Laura Rodriguez" <[email protected]<mailto:[email protected]>>Subject: Crossroads WSA Request LetterDate: 12 April 2016 15:31To: "Hwang, Jin" <[email protected]<mailto:[email protected]>>, "Kwan, Delon" <[email protected]<mailto:[email protected]>>Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly

Date: Tue Apr 12 2016 16:22:58 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.344523

Page 79 of 279

Page 68: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

prohibited. If you are not the intended recipient, please immediately notify the sender by reply e-mail orphone and delete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 80 of 279

Page 69: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: RE: Q/A WSA board meeting - 698 New Hampshire

The preceding paragraph had a sentence with "three-year supply" mentioned; that was how weaddressed it.

I will re-work it and re-submit.

Thanks

From: Kwan, DelonSent: Monday, September 19, 2016 7:54 AMTo: Moosbrugger, EarlSubject: RE: Q/A WSA board meeting - 698 New Hampshire

Did WSA have update on stress test results from state? Include in Q/A section following MWD endingallocation.

From: Kwan, DelonSent: Monday, September 19, 2016 7:20 AMTo: Moosbrugger, EarlSubject: RE: Q/A WSA board meeting - 698 New Hampshire

You sure this is the updated one, it still describes the Crossroads project, etc. or am I looking at wrongtrack changes settings?

From: Moosbrugger, EarlSent: Friday, September 16, 2016 7:45 AMTo: Kwan, DelonSubject: FW: Q/A WSA board meeting - 698 New Hampshire

I took a second look; it does show all substantive changes

From: Aghakhani, RyanSent: Thursday, September 15, 2016 3:42 PMTo: Kwan, DelonCc: Moosbrugger, EarlSubject: Q/A WSA board meeting - 698 New Hampshire

Delon,

Date: Mon Sep 19 2016 08:01:26 PDTAttachments:

Bcc:

Document ID: 0.7.522.616302

Page 83 of 279

Page 70: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Updated for the New Hampshire Project. Track changes mode is reflective of latest revision betweenEarl and me.

-Ryan

From: Kwan, DelonSent: Wednesday, September 14, 2016 7:30 AMTo: Moosbrugger, EarlSubject: Q/A WSA board meeting

I sent you before Q&A fact sheet in prep for WSAs at board meeting (at last WSA Crossroads), needyou / Ryan to review and update if any for 698 new Hampshire WSA at next week's 9/20 meeting.

When updated, send back to me for review and I can provide to Dave.

See me if you have any questions.

From: Kwan, DelonSent: Monday, August 01, 2016 8:00 AMTo: Moosbrugger, Earl; Hwang, JinSubject: Q/A WSA board meeting

I've prepared additional Q&A document (see enclosed)for WSA board meeting, please review and letme know if info is accurate.

Thanks.

Page 84 of 279

Page 71: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Kwan, Delon <[email protected]>Cc:

Subject: RE: Crossroads WSA Request Letter

Delon,

Jin tracked it down; it was mailed to Marty's office on 3/31 (I saw Fed Ex receipt).

It is probably in Vivian's in-box, and she will check at her first opportunity.

She is bottle-necked at this time.

Thanks

From: Kwan, DelonSent: Wednesday, April 13, 2016 6:39 AMTo: Moosbrugger, EarlSubject: RE: Crossroads WSA Request Letter

I didn't hear from staff. Can you follow up.

If nothing, let Planning know we didn't receive and if they can send another copy so we can process.

From: Moosbrugger, EarlSent: Tuesday, April 12, 2016 4:23 PMTo: Kwan, DelonSubject: RE: Crossroads WSA Request Letter

The only record I have is that we send instructions on 3/9/16.

From: Kwan, DelonSent: Tuesday, April 12, 2016 4:20 PMTo: Moosbrugger, EarlSubject: Fwd: Crossroads WSA Request Letter

I've not seen request

________________________________From: "Laura Rodriguez" <[email protected]<mailto:[email protected]>>Subject: Crossroads WSA Request LetterDate: 12 April 2016 15:31To: "Hwang, Jin" <[email protected]<mailto:[email protected]>>, "Kwan, Delon" <[email protected]<mailto:[email protected]>>

Date: Wed Apr 13 2016 10:49:19 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.347239

Page 85 of 279

Page 72: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Hi Jin and Delon,

We are working with the City on the Crossroads Project. The City mailed you a WSA request letter acouple weeks ago. Have you received it?

Thank you

Laura RodriguezPrincipal Planner

[EE logo -- horizontal stack (RGB, screen-res, 3]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5333F (424) 207-5349

DIRECT (424) 207-5339EMAIL [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 86 of 279

Page 73: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Jin,

Here are comments/edits to one of the questions from v2:

How are the changes to prior approved WSAs handled by DWP? Are there any other previouslyapproved WSAs that had a scope change after the WSA was approved?A4: If the project scope changes after the WSA is approved, the CEQA Lead Agency will ask DWPwhether a new WSA will be required.

LADWP makes the determination on whether a new WSA will be required based on thecombination of the changes in scope and use as well as the resulting change in water demand.LADWP works with the lead agency to come to this conclusion on a case-by-case basis.

Bixel and Lucas: Approved on 11/18/08, but LADWP was notified that the residential scope wasreduced on 12/29/11. Since the scope was reduced, no new WSA was needed.

Village at Westfield Topanga: Approved on 6/16/09, but LADWP was notified of scope reduction on10/25/10. WSA was not amended.

NBC Universal Evolution Plan: Approved on 5/4/10, but Final EIR was made available on 7/16/12, andAlternative 10: No Residential Alternative was analyzed and identified as the environmentally superioralternative. The City water demand was reduced and the County water demand was increased due toscope change. However, decision was made not to amend the WSA since the overall Project waterdemand decreased due to the scope change.

NBCU's change in Gross Proposed Potable Demand (Net Add'l+ Demolition) was less than significant.No new WSA required.

Boyle Heights Mixed-Use Community Project: Approved on 11/20/09, but on 11/16/10, Planninginformed LADWP that the developer wants to change their water conservation commitment to useartificial turf to natural turf on the plaza level and rooftop. Use of RW in place of artificial turf wasproposed. LADWP replied to Planning that a no new WSA will be required if the Planning Dept does notconsider the potential change in scope to be significant.

LAX Northside Plan Update Project: WSA for Los Angeles World Airports Master Plan Alternative "D"approved on 7/1/03, and LAX Northside Plan Update Project was approved on 8/27/13.The 20 year historical City's water supply shows variation of approximately 26%.LAX Northside Plan Update Project's change in dev't [what is this, "development" (i.e. scope) or waterdemand, or both? Need to statet specifically.] sf was significant. New WSA required.

Earl Moosbrugger, PEResources Development and Supply Assessment Group

Date: Mon Jul 18 2016 13:26:08 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.631675

Page 182 of 279

Page 74: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Water System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:36 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood Project Summary FactSheet 2016 07 14 v2.doc<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20Project%20Summary%20Fact%20Sheet%202016%2007%2014%20v2.doc>

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:34 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Please see Delon tomorrow to discuss and focus on completing the fact sheet.

Thnaks!

From: Hwang, JinSent: Thursday, July 14, 2016 3:29 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

I did not mention that we used the word "is" in the scope confirmation.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:28 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

But they are aware of the difference, so either they missed it or there is another explanation.

Did you mention that we used the work "is" in the scope confirmation?

From: Hwang, JinSent: Thursday, July 14, 2016 3:27 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

We wrote it, and they just confirmed it. They did not write the statement.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:26 PMTo: Hwang, Jin

Page 183 of 279

Page 75: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Subject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Page 184 of 279

Page 76: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This

Page 185 of 279

Page 77: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

transmission is sent in trust, for the sole purpose of delivery to the intended recipient. If you havereceived this transmission in error, any use, reproduction or dissemination of this transmission is strictlyprohibited. If you are not the intended recipient, please immediately notify the sender by reply e-mail orphone and delete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta (alejandro.

Page 186 of 279

Page 78: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

[email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:

Page 187 of 279

Page 79: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

Page 188 of 279

Page 80: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 189 of 279

Page 81: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450

Date: Thu Jul 14 2016 15:25:05 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.630431

Page 190 of 279

Page 82: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PM

Page 191 of 279

Page 83: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

To: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attached

Page 192 of 279

Page 84: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

and let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water Supply

Page 193 of 279

Page 85: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Assessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 194 of 279

Page 86: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Date: Thu Jul 14 2016 15:25:36 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.630676

Page 195 of 279

Page 87: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

Page 196 of 279

Page 88: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Page 197 of 279

Page 89: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTS

Page 198 of 279

Page 90: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

SEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Water

Page 199 of 279

Page 91: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

and Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 200 of 279

Page 92: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Date: Thu Jul 14 2016 15:26:01 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.630677

Page 201 of 279

Page 93: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

Page 202 of 279

Page 94: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

Page 203 of 279

Page 95: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta (alejandro.

Page 204 of 279

Page 96: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

[email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<

Page 205 of 279

Page 97: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 206 of 279

Page 98: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

We wrote it, and they just confirmed it. They did not write the statement.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Date: Thu Jul 14 2016 15:26:45 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.630683

Page 207 of 279

Page 99: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Page 208 of 279

Page 100: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)

Page 209 of 279

Page 101: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

Page 210 of 279

Page 102: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Water

Page 211 of 279

Page 103: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

and Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 212 of 279

Page 104: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

But they are aware of the difference, so either they missed it or there is another explanation.

Did you mention that we used the work "is" in the scope confirmation?

From: Hwang, JinSent: Thursday, July 14, 2016 3:27 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

We wrote it, and they just confirmed it. They did not write the statement.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PE

Date: Thu Jul 14 2016 15:27:41 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.630688

Page 213 of 279

Page 105: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Resources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Page 214 of 279

Page 106: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin Hwang

Page 215 of 279

Page 107: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Civil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349

Page 216 of 279

Page 108: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering Associate

Page 217 of 279

Page 109: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Los Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 218 of 279

Page 110: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

I did not mention that we used the word "is" in the scope confirmation.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:28 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

But they are aware of the difference, so either they missed it or there is another explanation.

Did you mention that we used the work "is" in the scope confirmation?

From: Hwang, JinSent: Thursday, July 14, 2016 3:27 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

We wrote it, and they just confirmed it. They did not write the statement.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, Earl

Date: Thu Jul 14 2016 15:28:46 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.630691

Page 219 of 279

Page 111: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Sent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

Page 220 of 279

Page 112: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Page 221 of 279

Page 113: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

Page 222 of 279

Page 114: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Page 223 of 279

Page 115: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 224 of 279

Page 116: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Please see Delon tomorrow to discuss and focus on completing the fact sheet.

Thnaks!

From: Hwang, JinSent: Thursday, July 14, 2016 3:29 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

I did not mention that we used the word "is" in the scope confirmation.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:28 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

But they are aware of the difference, so either they missed it or there is another explanation.

Did you mention that we used the work "is" in the scope confirmation?

From: Hwang, JinSent: Thursday, July 14, 2016 3:27 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

We wrote it, and they just confirmed it. They did not write the statement.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012

Date: Thu Jul 14 2016 15:34:23 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.630693

Page 225 of 279

Page 117: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power

Page 226 of 279

Page 118: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]

Page 227 of 279

Page 119: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) that

Page 228 of 279

Page 120: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

we are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Page 229 of 279

Page 121: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 230 of 279

Page 122: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood Project Summary FactSheet 2016 07 14 v2.doc<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20Project%20Summary%20Fact%20Sheet%202016%2007%2014%20v2.doc>

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:34 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Please see Delon tomorrow to discuss and focus on completing the fact sheet.

Thnaks!

From: Hwang, JinSent: Thursday, July 14, 2016 3:29 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

I did not mention that we used the word "is" in the scope confirmation.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:28 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

But they are aware of the difference, so either they missed it or there is another explanation.

Did you mention that we used the work "is" in the scope confirmation?

From: Hwang, JinSent: Thursday, July 14, 2016 3:27 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

We wrote it, and they just confirmed it. They did not write the statement.

From: Moosbrugger, Earl

Date: Thu Jul 14 2016 15:35:36 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.630708

Page 231 of 279

Page 123: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Sent: Thursday, July 14, 2016 3:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Page 232 of 279

Page 124: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Page 233 of 279

Page 125: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna Marcelo

Page 234 of 279

Page 126: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Sent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

Page 235 of 279

Page 127: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid and

Page 236 of 279

Page 128: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Coml_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 237 of 279

Page 129: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Moosbrugger, Earl <[email protected]>To: Hwang, Jin <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Please see other edits/comments, below:

Q11: Considering recent measures such as Mayor's Sustainable City pLAn, (Issued April 2015, reducegpcd by 20% by 2017, 22.5% by 2025, and 25% by 2035; reduce purchases from MWD 50% by 2025;expand local resources to reach 50% of total supply by 2035), and Governor's Executive Directive B-29-15 (Issued 4/1/15, 25% statewide reduction - 16% for DWP but no longer mandatory - in potable urbanwater use by 2/28/16 compared to 2013), what conservation measures has applicant agreed to thatwould contribute to the related conservation goals?

Delon's Comments Needing Follow up on:

* What happened with discussion on current version of Hollywood Community Plan basis for thisproject, link to 2012, will be or is consistent, etc.?

o I think we already discussed the need to add this item.

* A14: maybe instead of stating that 2015 UWMP is not precise, highlight the % range in demandsgiven hydrology, I think +/- 10%, verify with Simon. This range would cover any differences brought onby 2016 forecast being slightly higher than 2012 forecast.

o We already discussed this one too.

From: Moosbrugger, EarlSent: Monday, July 18, 2016 1:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Here are comments/edits to one of the questions from v2:

How are the changes to prior approved WSAs handled by DWP? Are there any other previouslyapproved WSAs that had a scope change after the WSA was approved?A4: If the project scope changes after the WSA is approved, the CEQA Lead Agency will ask DWPwhether a new WSA will be required.

LADWP makes the determination on whether a new WSA will be required based on thecombination of the changes in scope and use as well as the resulting change in water demand.LADWP works with the lead agency to come to this conclusion on a case-by-case basis.

Bixel and Lucas: Approved on 11/18/08, but LADWP was notified that the residential scope wasreduced on 12/29/11. Since the scope was reduced, no new WSA was needed.

Date: Mon Jul 18 2016 13:38:03 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.631681

Page 244 of 279

Page 130: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Village at Westfield Topanga: Approved on 6/16/09, but LADWP was notified of scope reduction on10/25/10. WSA was not amended.

NBC Universal Evolution Plan: Approved on 5/4/10, but Final EIR was made available on 7/16/12, andAlternative 10: No Residential Alternative was analyzed and identified as the environmentally superioralternative. The City water demand was reduced and the County water demand was increased due toscope change. However, decision was made not to amend the WSA since the overall Project waterdemand decreased due to the scope change.

NBCU's change in Gross Proposed Potable Demand (Net Add'l+ Demolition) was less than significant.No new WSA required.

Boyle Heights Mixed-Use Community Project: Approved on 11/20/09, but on 11/16/10, Planninginformed LADWP that the developer wants to change their water conservation commitment to useartificial turf to natural turf on the plaza level and rooftop. Use of RW in place of artificial turf wasproposed. LADWP replied to Planning that a no new WSA will be required if the Planning Dept does notconsider the potential change in scope to be significant.

LAX Northside Plan Update Project: WSA for Los Angeles World Airports Master Plan Alternative "D"approved on 7/1/03, and LAX Northside Plan Update Project was approved on 8/27/13.The 20 year historical City's water supply shows variation of approximately 26%.LAX Northside Plan Update Project's change in dev't [what is this, "development" (i.e. scope) or waterdemand, or both? Need to statet specifically.] sf was significant. New WSA required.

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:36 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood Project Summary FactSheet 2016 07 14 v2.doc<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20Project%20Summary%20Fact%20Sheet%202016%2007%2014%20v2.doc>

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:34 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Please see Delon tomorrow to discuss and focus on completing the fact sheet.

Thnaks!

Page 245 of 279

Page 131: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, JinSent: Thursday, July 14, 2016 3:29 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

I did not mention that we used the word "is" in the scope confirmation.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:28 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

But they are aware of the difference, so either they missed it or there is another explanation.

Did you mention that we used the work "is" in the scope confirmation?

From: Hwang, JinSent: Thursday, July 14, 2016 3:27 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

We wrote it, and they just confirmed it. They did not write the statement.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment Group

Page 246 of 279

Page 132: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Water System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PMTo: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Page 247 of 279

Page 133: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering Associate

Page 248 of 279

Page 134: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Los Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Page 249 of 279

Page 135: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and Power

Page 250 of 279

Page 136: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Water Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 251 of 279

Page 137: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

From: Hwang, Jin <[email protected]>To: Moosbrugger, Earl <[email protected]>Cc:

Subject: RE: Crossroads Hollywood Project WSA

Please see the revised. Z:\Water Resources Development\Projects & Tasks\Water SupplyAssessments\WSA Projects\Crossroads Hollywood Project\Board Package\Crossroads HollywoodProject Summary Fact Sheet 2016 07 18 v3.doc<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%20Project%20Summary%20Fact%20Sheet%202016%2007%2018%20v3.doc>

From: Moosbrugger, EarlSent: Monday, July 18, 2016 1:38 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Please see other edits/comments, below:

Q11: Considering recent measures such as Mayor's Sustainable City pLAn, (Issued April 2015, reducegpcd by 20% by 2017, 22.5% by 2025, and 25% by 2035; reduce purchases from MWD 50% by 2025;expand local resources to reach 50% of total supply by 2035), and Governor's Executive Directive B-29-15 (Issued 4/1/15, 25% statewide reduction - 16% for DWP but no longer mandatory - in potable urbanwater use by 2/28/16 compared to 2013), what conservation measures has applicant agreed to thatwould contribute to the related conservation goals?

Delon's Comments Needing Follow up on:

* What happened with discussion on current version of Hollywood Community Plan basis for thisproject, link to 2012, will be or is consistent, etc.?

o I think we already discussed the need to add this item.

* A14: maybe instead of stating that 2015 UWMP is not precise, highlight the % range in demandsgiven hydrology, I think +/- 10%, verify with Simon. This range would cover any differences brought onby 2016 forecast being slightly higher than 2012 forecast.

o We already discussed this one too.

From: Moosbrugger, EarlSent: Monday, July 18, 2016 1:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Here are comments/edits to one of the questions from v2:

Date: Mon Jul 18 2016 14:35:51 PDTAttachments: image001.jpg

Bcc:

Document ID: 0.7.522.631698

Page 252 of 279

Page 138: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

How are the changes to prior approved WSAs handled by DWP? Are there any other previouslyapproved WSAs that had a scope change after the WSA was approved?A4: If the project scope changes after the WSA is approved, the CEQA Lead Agency will ask DWPwhether a new WSA will be required.

LADWP makes the determination on whether a new WSA will be required based on thecombination of the changes in scope and use as well as the resulting change in water demand.LADWP works with the lead agency to come to this conclusion on a case-by-case basis.

Bixel and Lucas: Approved on 11/18/08, but LADWP was notified that the residential scope wasreduced on 12/29/11. Since the scope was reduced, no new WSA was needed.

Village at Westfield Topanga: Approved on 6/16/09, but LADWP was notified of scope reduction on10/25/10. WSA was not amended.

NBC Universal Evolution Plan: Approved on 5/4/10, but Final EIR was made available on 7/16/12, andAlternative 10: No Residential Alternative was analyzed and identified as the environmentally superioralternative. The City water demand was reduced and the County water demand was increased due toscope change. However, decision was made not to amend the WSA since the overall Project waterdemand decreased due to the scope change.

NBCU's change in Gross Proposed Potable Demand (Net Add'l+ Demolition) was less than significant.No new WSA required.

Boyle Heights Mixed-Use Community Project: Approved on 11/20/09, but on 11/16/10, Planninginformed LADWP that the developer wants to change their water conservation commitment to useartificial turf to natural turf on the plaza level and rooftop. Use of RW in place of artificial turf wasproposed. LADWP replied to Planning that a no new WSA will be required if the Planning Dept does notconsider the potential change in scope to be significant.

LAX Northside Plan Update Project: WSA for Los Angeles World Airports Master Plan Alternative "D"approved on 7/1/03, and LAX Northside Plan Update Project was approved on 8/27/13.The 20 year historical City's water supply shows variation of approximately 26%.LAX Northside Plan Update Project's change in dev't [what is this, "development" (i.e. scope) or waterdemand, or both? Need to statet specifically.] sf was significant. New WSA required.

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:36 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Z:\Water Resources Development\Projects & Tasks\Water Supply Assessments\WSAProjects\Crossroads Hollywood Project\Board Package\Crossroads Hollywood Project Summary FactSheet 2016 07 14 v2.doc<file:///\\Galaxy\Water%20Resources\Water%20Resources%20Development\Projects%20&%20Tasks\Water%20Supply%20Assessments\WSA%20Projects\Crossroads%20Hollywood%20Project\Board%20Package\Crossroads%20Hollywood%

Page 253 of 279

Page 139: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

20Project%20Summary%20Fact%20Sheet%202016%2007%2014%20v2.doc>

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:34 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Please see Delon tomorrow to discuss and focus on completing the fact sheet.

Thnaks!

From: Hwang, JinSent: Thursday, July 14, 2016 3:29 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

I did not mention that we used the word "is" in the scope confirmation.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:28 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

But they are aware of the difference, so either they missed it or there is another explanation.

Did you mention that we used the work "is" in the scope confirmation?

From: Hwang, JinSent: Thursday, July 14, 2016 3:27 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

We wrote it, and they just confirmed it. They did not write the statement.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:26 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Then why are they using "is" in the scope confirmation?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:26 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Page 254 of 279

Page 140: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

No. We're in Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 3:25 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

So are we in the entitlement process now?

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 3:24 PMTo: Moosbrugger, EarlSubject: RE: Crossroads Hollywood Project WSA

Alejandro Huerta from Planning informed me over the phone that during the Environmental Reviewperiod, Planning uses the word "would" to state that the project is consistent with the RTP because it isconditional. However, during the Entitlement process, Planning uses the word "is" to state that theproposed project is consistent with the RTP. For the Crossroads project, the WSA request letter pages5 and 6 list the approvals required such as zone variation, vesting tentative tract map, etc.

Based on the attached document pg. 13, Entitlement process happens after Environmental Review.

From: Moosbrugger, EarlSent: Thursday, July 14, 2016 1:56 PMTo: Hwang, JinSubject: RE: Crossroads Hollywood Project WSA

Jin,

Scope confirmation e-mail states project "is" consistent with 2012 RTP while the attachment you sentstates "would be."

Would you please give Planning a quick call to confirm that they have already determined consistencyand that the term "is" is correct.

Thanks

Earl Moosbrugger, PEResources Development and Supply Assessment GroupWater System Executive Office / Water Resources SectionLos Angeles Department of Water and Power111 N. Hope Street, Room 1450Los Angeles, CA 90012(213) 367-2527

From: Hwang, JinSent: Thursday, July 14, 2016 1:43 PM

Page 255 of 279

Page 141: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

To: Moosbrugger, EarlSubject: FW: Crossroads Hollywood Project WSA

From: Madonna Marcelo [mailto:[email protected]]Sent: Friday, May 13, 2016 4:23 PMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are our additional responses to your comments and questions regarding our originalresponses.

Given where we are in the design process, this is the level of specificity we can provide at the moment.We would appreciate it very much if your team can make conservative and reasonable assumptions forthose Project components for which we currently do not have more specific information.

We will have the Draft Water Conservation Commitment Letter to you shortly.

Thank you so much for your and your team's responsiveness to our request!

Madonna

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: Hwang, Jin [mailto:[email protected]]Sent: Monday, May 09, 2016 2:46 PMTo: Madonna Marcelo; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Page 256 of 279

Page 142: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Hello Madonna,

Please see our comments/questions in track changes in the attached file.

Also, as requested at the April 26, 2016 Water Conservation Meeting, please submit a DRAFT WaterConservation Commitment Letter by e-mail.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

From: Madonna Marcelo [mailto:[email protected]]Sent: Thursday, May 05, 2016 11:14 AMTo: Hwang, Jin; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are the updated versions of our responses to the WSA scope questions and the attachments(including Attachment B) that I sent you yesterday.

If you need anything else, please let us know.

Thank you!

Madonna

From: Madonna MarceloSent: Wednesday, May 04, 2016 5:16 PMTo: 'Hwang, Jin'; Kwan, Delon; Moosbrugger, Earl; Estrada, Robert; Alejandro Huerta ([email protected]<mailto:[email protected]>)Cc: Stephanie Eyestone-Jones; Laura Rodriguez; Kyndra Joy CasperSubject: RE: Crossroads Hollywood Project WSA

Hi Jin,

Attached are most of our responses to the WSA scope questions and a pdf of the attachmentsreferenced in the responses.

Please note there are a couple of outstanding questions (related to amenities and cooling towers) thatwe are still working on. We will have those to you shortly. In the meantime, please review the attachedand let us know if you need anything else.

Thank you!

Madonna

Page 257 of 279

Page 143: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

Madonna MarceloPrincipal Planner

[cid:[email protected]]

6701 Center Drive West, Suite 900Los Angeles, California 90045T (424) 207-5337F (424) 207-5349Email [email protected]<mailto:[email protected]>

Statement of Confidentiality. The contents of this e-mail message and any attachments are confidentialand are intended solely for addressee. The information may also be legally privileged. This transmissionis sent in trust, for the sole purpose of delivery to the intended recipient. If you have received thistransmission in error, any use, reproduction or dissemination of this transmission is strictly prohibited. Ifyou are not the intended recipient, please immediately notify the sender by reply e-mail or phone anddelete this message and its attachments, if any.

P Please consider the environment before printing this email.

From: "Hwang, Jin" <[email protected]<mailto:[email protected]>>To: "Kwan, Delon" <[email protected]<mailto:[email protected]>>, "Moosbrugger, Earl"<[email protected]<mailto:[email protected]>>, "Estrada, Robert" <[email protected]<mailto:[email protected]>>, "Alejandro Huerta ([email protected]<mailto:[email protected]>)" <[email protected]<mailto:[email protected]>>, "Stephanie Eyestone-Jones" <[email protected]<mailto:[email protected]>>, "Laura Rodriguez" <[email protected]<mailto:[email protected]>>, "Kyndra Joy Casper" <[email protected]<mailto:[email protected]>>Cc: "Masis Mesropian" <[email protected]<mailto:[email protected]>>, "'JodiMensen'" <[email protected]<mailto:[email protected]>>, "Deering Volkmann"<[email protected]<mailto:[email protected]>>Subject: Crossroads Hollywood Project WSA

UPDATED:ADDED 1 MORE DOCUMENT. THERE ARE 7 ATTACHMENTS TOTAL.

UPDATED:ADDED 3 MORE DOCUMENTSSEE https://cityclerk.lacity.org/lacityclerkconnect/index.cfm?fa=ccfi.viewrecord&cfnumber=15-0458FOR NEW ORDINANCE PENDING APPROVAL 5/2/16.

Hi all,

Please attend the Water Conservation Meeting for the Crossroads Hollywood Project Water SupplyAssessment.

Meeting Number: 993 261 062Meeting Password: Not requiredPhone Number(s): (213) 367-0100, (818) 771-3100, (661) 294-3300, (310) 522-1400

Page 258 of 279

Page 144: Document ID: 0.7.522.352505 To: Alejandro Huerta · Laura Rodriguez Principal Planner EE logo -- horizontal stack (RGB, screen-res, 3 6701 Center Drive West, Suite 900 Los Angeles,

I'm attaching some handouts for the meeting below. I may send you an updated meeting notice withmore handouts later.

Thank you.

Jin HwangCivil Engineering AssociateLos Angeles Department of Water and PowerWater Executive / Water Resources111 N. Hope St. Room 1468Los Angeles, CA 90012213-367-4845

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.<< File: Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00001.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00002.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00003.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00004.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00005.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00006.htm >> << File:Crossroads Hollywood WSA Request Letter_3-31-16.pdf >> << File: ATT00007.htm >> << File:Crossroads Hollywood Project WSA - Scope questions .eml >> << File: ATT00008.htm >> << File:Crossroads Hollywood Project - Water Conservation Mtg Agenda.doc >> << File: ATT00009.htm >> <<File: Water Conservation for New Construction March 2014.xls >> << File: ATT00010.htm >> << File:Sample Conservation Commitment Letter.doc >> << File: ATT00011.htm >> << File: 2016 WtrEfficiency Req Ordinance - PENDING APPROVAL.pdf >> << File: ATT00012.htm >> << File: Resid andComl_CALGreen_Plumbing_Tips_1_21_2016.pdf >> << File: ATT00013.htm >> << File: ATT00014.htm>>

-------------------------Confidentiality Notice--------------------------This electronic message transmission contains information from the Los Angeles Department of Waterand Power, which may be confidential. If you are not the intended recipient, be aware that anydisclosure, copying, distribution or use of the content of this information is prohibited. If you havereceived this communication in error, please notify us immediately by e-mail and delete the originalmessage and any attachment without reading or saving in any manner.

Page 259 of 279