document 525 pre-implementation report chapter: … · president zachary mueller...
TRANSCRIPT
Document 525
PRE-IMPLEMENTATION REPORT
CHAPTER: University of Texas at San Antonio
COUNTRY: Peru
COMMUNITY: Viña Vieja
PROJECT: Viña Vieja Water System
PREPARED BY
Francisco Balandrano
Timothy Hayes
Diego A. Gonzalez
Steven Byers
Jessica George
Adam Bazar
Zach Mueller
John Joseph, Ph. D.
Dustin Vasquez
Rodrigo Zertuche
May 20th
, 2012
ENGINEERS WITHOUT BORDERS-USA
www.ewb-usa.org
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
© 2005 Engineers Without Borders - USA. All Rights Reserved. Page 1 of 58
Table of Contents Part 1 – Administrative Information ....................................................................................... 2-9
Part 2 – Technical Information ............................................................................................ 10-26
Appendix ................................................................................................................................. 27-57
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 2 of 58
Pre-Implementation Report Part 1 – Administrative
Information
1.0 Contact Information
Project Title Name Email Phone Organization
Name
Project Lead Francisco
Balandrano
(210) 425-
9263
EWB-
UTSA
President Zachary
Mueller
(210) 595-
0070
EWB-
UTSA
Mentor #1 Dr John
Joseph
[email protected] (210) 843-
2378
EWB-
UTSA
Mentor #2 Dr AnnMarie
Spexet
[email protected] (404) 863-
0836
EWB-
USA
Faculty Advisor Dr Heather
Shipley
[email protected] (210) 458-
7926
EWB-
UTSA
Health and Safety
Officer
Steven Byers [email protected] (210) 725-
5715
EWB-
UTSA
Health and Safety
Officer
Dustin
Vasquez
[email protected] (281) 684-
6015
EWB-
UTSA
NGO Contact Iliana Diaz [email protected]
(210) 834-
0477
Texas Partners
of the
Americas
2.0 Travel History
Dates of Travel Assessment or
Implementation Description of Trip
July 6-13, 2010 Assessment Initial contact with the community. Assessed the
community needs. March 12-20, 2012 Assessment Assessed the need for a water distribution
system. Conducted household surveys, carried
out water tests, took elevations surveys, obtained
GPS data, signed MOU with the community,
located supplies, and met with local officials.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 3 of 58
3.0 Travel Team (Should be 8 or fewer):
# Name E-mail Phone Chapter Student or
Professional
1 Dr John Joseph [email protected] (210) 843-
2378
EWB-
UTSA
Professional
2 Dr AnnMarie
Spexet
[email protected] (404) 863-
0836
EWB-
USA
Professional
3 Francisco
Balandrano
(210) 425-
9263
EWB-
UTSA
Student
4 Steven Byers [email protected]
(210) 725-
5715
EWB-
UTSA
Student
5 Dustin Vasquez [email protected] (281) 684-
6015
EWB-
UTSA
Student
6 Timothy Hayes [email protected] (210) 380-
1175
EWB-
UTSA
Student
7 Diego A.
Gonzalez
[email protected] (210) 844-
9360
EWB-
UTSA
Student
8 Adam Bazar [email protected] (210) 383-
3954
EWB-
UTSA
Student
4.0 Health and Safety
The travel team will follow the site-specific HASP that has been prepared for this
implementation trip and has been submitted as a standalone document along with this pre-trip
report.
5.0 Budget
5.1 Project Budget
Project City/Region and Country: Viña Vieja, Ica, Peru
EWB-USA Chapter: University of Texas at San Antonio
Year: 2012
Trips Planned: 1
Planned Month for Trip: August
Trip type: I= Implementation
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 4 of 58
Direct Costs Project Budget Total Budget
Travel
Airfare $1250 * 8 Tickets $10,000
Gas $28.50 * 22 Days $650
Rental Vehicle $0
Driver $57.00 * 22 Days $1250
Misc. $0
Sub-Total $0 $11,900
Travel Logistics
Exit Fees/ Visas $0
Inoculations $300 * 4 people $1,200
Insurance $2.50/day/person $285
Licenses & Fees $0
Medical Exams $0
Passport Issuance $200 per passport $600
Misc. $0
Sub-Total $0 $2,085
Food & Lodging
Lodging $0
Food & Beverage (Non-alcoholic) $8/person/day $1,056
Misc. $0
Sub-Total $0 $1,056
Labor
In-Country logistical support $0
Local Skilled labor $0
Misc. $0
Sub-Total $0 $0
EWB-USA
Program QA/QC(1) $1,000 $1,000
Sub-Total $1,000 $1,000
Project Materials & Equipment
Piping 5.5 km (2”, 3”) $9,860
Foundations Contractor $2,500
Pumps 2 cent, 1 sub $1,000
Valves 20 $170
Tanks 4 $11,120
Sub-Total $0 $24,650
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 5 of 58
Misc.
Report Preparation $0
Advertising & Marketing $0
Postage & Delivery $0
Misc. $0
Sub-Total $0 $0
TOTAL $0 $40,691
EWB-USA National office use:
Indirect Costs
EWB-USA
Program Infrastructure(1) $0 $0
Sub-Total $0 $0
TOTAL $0 $0
Note (1): These rows are calculated automatically based on type of trip.
Non-Budget Items:
Additional Contributions to Project Costs
Community
Labor $0
Materials $0
Logistics $0
Cash $0
Other $0
Sub-Total $0 $0
EWB-USA Professional Service In-Kind
Professional Service Hours 360 hours
Hours converted to $$(1) $100 $36,000
Sub-Total $0 $36,000
GRAND TOTAL (Project cost) $0 $76,691
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 6 of 58
Funds Raised for Project by Source
Actual Raised to Date
Source and Amount
Engineering Societies $0
Corporations $0
University $3,200
Rotary $0
Grants - Government $0
Grants - Foundation/Trusts $500
Grants - EWB-USA program $0
Other Nonprofits $0
Individuals $750
Special Events $450
Misc. $0
$0
Total $0 $4,900
5.1 Donors and Funding
Donor Name Type Account Kept
at EWB-USA?
Amount
UTSA College of
Engineering
Institute No $3,200
UTSA Family Association
and Parent Council
Association No $500
Jessica George, Timothy
Hayes & Adam Bazar
In-Kind No $750
EWB UTSA - Fundraising
Events
Organization No $450
Total Amount Raised: $4900
6.0 Project Discipline(s):
Water Supply
____ Source Development
√ Water Storage
√ Water Distribution
√ Water Treatment
√ Water Pump
Civil Works
____ Roads
____ Drainage
____ Dams
Energy
____ Fuel
____ Electricity
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 7 of 58
Sanitation
____ Latrine
____ Gray Water System
____ Black Water System
Structures
____ Bridge
____ Building
Agriculture
____ Irrigation Pump
____ Irrigation Line
____ Water Storage
____ Soil Improvement
____ Fish Farm
____ Crop Processing Equipment
Information Systems
____ Computer Service
7.0 Project Location Longitude: 13
°28
' 52
'' S
Latitude: 76°0
' 55
'' W
8.0 Project Impact
Number of persons directly affected: 500
Number of persons indirectly affected: 500
9.0 Professional Mentor Resume
John F. Joseph, P.E., Ph.D.
(210) 843-2378
Primary Career Goal:
Provide expertise to communities who may be egregiously affected by environmental
injustice, when such communities want such support. The support is to include an
exchange of perspectives, in which I gain understanding of the community’s viewpoints
and the community gains understanding of my technical knowledge.
Education:
Ph.D. Environmental Science and Engineering, University of Texas at San Antonio,
2011. Dissertation, Preliminaries to Watershed Instrumentation System Design, provides
a basis for proving and predicting the movement of contaminants through watersheds of
communities that may be affected, particularly the Ecuadoran Cofan community, whom I
visited while developing the dissertation proposal.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 8 of 58
M.S. Environmental Engineering, University of North Carolina at Chapel Hill, 1990.
Thesis, Queuing Theory Applied to Standpost Design, develops and applies Markovian
matrices to determine expected waiting line lengths for drawing water in rural and peri-
urban areas of the developing world, and to recommend revisions to the World Health
Organization standards for standpost design. Thesis won first place in a national
competition to receive the James M. Montgomery/Association of Environmental
Engineering Professors Master’s Thesis Award.
B.S. Civil Engineering, University of Texas at Austin, 1985.
Recipient of Kenneth Howard Academic Excellence scholarship. Graduated with
Honors.
M.A. Pastoral Ministry, Oblate School of Theology in San Antonio, Texas, 2000.
This degree helped me to appreciate various cultures, and to communicate within various
cultural contexts.
Teaching Experience:
Instructor, Fall ’11, EGR 2323 Applied Engineering Analysis I, University of Texas at San
Antonio.
Instructor, Fall ’09 and Spring ’09, CE 2633 Introduction to Environmental Engineering,
University of Texas at San Antonio.
Instructor/Education Skills Specialist II, 1998-2004, various remedial math courses, Alamo
Community College District, San Antonio, Texas.
Instructor, Spring ’92 and Spring ’93, CE 4643 Air Pollution and Industrial Hygiene, University
of Texas at San Antonio.
Relevant Research Experience:
Research Assistant, August ’85 – Dec ’86, University of North Carolina at Chapel Hill. Work
included statistical analysis of demographic, hygiene, and sanitation data in rural Malawi. Work
also included an examination of water use patterns in peri-urban Tegucigalpa, Honduras, with a
two-week field visit.
Relevant Work Experience
Engineer-in-Training, Aug. ’87 – Aug. ’90, Wright-Pierce Engineers, Topsham, Maine.
Reviewed shop drawings for compliance with specifications; design of pumps, piping, and
chemical feed systems for 4 million gallon per day water treatment facility, subject to
approval/modification by project engineer; distribution system modeling for water utility master
plans.
District Area Engineer, July ‘05 – June ’08, BexarMet Water District, San Antonio, Texas.
Actually, I was in training for the first few months of this time period, and did not become a
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 9 of 58
District Area Engineer until later in ’05. Responsible for up to approximately 20 projects
simultaneously, mostly water main projects, but also storage tanks, pumping stations, well
capacity testing, and treatment facilities, and other projects.
Publications:
Joseph, J., and H. Sharif, 2009. Preliminaries to Assessing the Quality of SWAT Parameter
Confidence Intervals, 2009 International SWAT Conference Proceedings, Texas Water Resource
Institute Technical Report No. 356, 116-123.
Joseph, J. and H. Sharif, et al, 2011. Synthesis of Hydrologic and Hydraulic Impacts, Technical
Report TxDOT Project 0-6671, Texas Department of Transportation.
Several articles now under review by a variety of peer-reviewed journals.
Miscellaneous:
Excellence in Teaching Nominee, 2011, University of Texas at San Antonio.
University Teaching Fellow, 2009-2010 Academic Year, University of Texas at San Antonio.
The 2010 Outstanding Graduate Student for the College of Engineering, University of Texas at
San Antonio.
Licensed civil engineer since 1990.
One year (1995-1996) of living in rural Oaxaca, Mexico, has proven helpful in developing
appreciation for other cultures.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 10 of 58
Pre-Implementation Report Part 2 – Technical Information
1.0 INTRODUCTION
The purpose of this document is to present the design for a ground water storage and distribution
system to be built for Viña Vieja, Peru by EWB-UTSA members. This system aims to improve
the lifestyle of the community members through better access to clean drinking water. The
construction of this system is only the first step in a multiyear commitment by EWB-UTSA with
the overall goal of sustainably improving the lives of the members of the Viña Vieja community.
After two assessment trips and conducting an analysis of alternative solutions, the team has
found a ground water based system to be the most appropriate solution. This solution calls for
the installation of a submersible pump in a well located easily accessible by the community and
to which the community members have contractual rights. The submersible pump will feed water
into three 10,000L storage tanks near the well and a booster pump will pump some water further
uphill, to two additional 10,000 L water tank. When the booster pump is off, water pressure will
be achieved through gravity for homes above the well's evaluation; gravity will provide water
pressure at all times for homes at lower elevations than the well and three primary storage tanks.
There are to be approximately 5.5 kilometers of piping in the proposed system, with larger main
pipelines running along the length of the community and a few branching pipelines intended to
provide for small subsections not located on the main road. The system will provide water to
each home through individual taps. Most homes are currently provided with its own tap, thus our
system is designed to match that level of convenience; however, the water quality from the
current system is poor and water access from those taps is unreliable and controlled by
individuals outside of the community. Further detail of this design and its analysis is provided
later in this report.
2.0 PROGRAM BACKGROUND
Viña Vieja is a small rural community, home to around ninety families, in the southwest region
of Peru. In 2007, two consecutive earthquakes struck Viña Vieja and caused severe structural
damage in the community. Since that same year, Texas Partners of the Americas, a non-
governmental organization based in San Antonio, has supported the community in areas from
education to health and safety by reconstructing the school, reopening the health clinic, and
building a communal kitchen. The EWB-UTSA student chapter was approached by Texas
Partners of the Americas in 2010 to assist with the water situation.
Currently, there is no central water supply in Viña Vieja; therefore families obtain their water
from different unreliable sources which have shown traces of water contamination. During the
first assessment trip, the EWB-UTSA team was able to initiate a relationship with the
community and gather significant information about a particular agricultural well ceded to the
community for a period of one year. The members of the community were very friendly with the
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 11 of 58
team and expressed their support for the project. The travel team was able to collect maps and
GPS coordinates during the trip as well. Unfortunately, the contract of the previously analyzed
well was not renewed and the community lost the rights to use that specific well.
After the previous contract expired, a new agreement of use for a different well was issued to the
community for a length of ten years starting in May 2011. The well agreement includes a
possibility of renewal at the end of the determined period; also, as established in the Peruvian
laws, after five years of constant use the water well will automatically belong to the community.
Having the property rights of the well resolved, EWB-UTSA plans to use this well, called “Pozo
de Manuel”, located in a suitable area of Viña Vieja, to provide continuous and sustainable water
to the community.
The team made a more recent assessment trip to Viña Vieja in March 2012. On this trip, the team
was able to collect all the necessary water data from the new well, as well as inspect key areas
the team expects to use for the implementation of the water distribution system. Another
important accomplishment from this trip was the discussion with the community members. The
team was able to sit down with many of the community members to discuss what their greatest
needs are, what options we see available to solving their water needs, EWB-UTSA's continued
commitment to their community, and even expected costs to them for ongoing use and
maintenance of the expected system.
Since the team's return, the team looked through all of their notes, pictures, and data from the
assessment trip and debated between various alternative systems. A rainwater system was
deemed improbable due to the low amount of rainfall throughout the year in the community. A
surface water system was determined to be also unreliable because of the large differences in
water levels of the Matagente River between wet and dry seasons, as well as the lower
cleanliness of water from the river. The team ultimately landed upon a ground water sourced
system, provided by the contracted well, for its convenience, water quality, ease of access, and
moderate cost. For the chosen solution, as well as for many of the other alternatives discussed,
maintenance and operation system will easily be localized based on the observed skills of some
of the community members; this is important, as sustainability is a highly valued aspect of our
design process.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 12 of 58
3.0 FACILITY DESIGN
The proposed solution, discussed below, consists of one submersible and two booster pumps;
five 10,000L water tanks, with three near the source water well and the other two uphill from the
community; over 5 kilometers of PVC pipe, with various diameters; and individual taps available
at nearly every individual home. The design and analysis is discussed in detail below.
3.1 Description of the Proposed Facilities
3.1.1 Water Well A. Well Site, Structure and Capacity
The proposed water source is a pre-existing well that was drilled in the 1960s and lies in the
center of the community just off of the main road. The site available for well pump
appurtenances, storage tanks, and booster pumps is approximately 0.25 acres and is bounded by
the edge of a cotton farm, a dirt road, and an irrigation ditch. The soil around the well is loose
and, in some spots, higher than the top of the well casing. Fortunately, there is an adequate
elevation drop from the top of the casing to the edge of cotton field and the irrigation ditch,
allowing for the earth to be cut lower than the top of the casing and then sloped away from the
well. Animal feces were near the well at the time of our visit, emphasizing the importance of
enclosing the site with a chain link fence.
Little documentation regarding the structure of the well has been found. We measured the steel
casing diameter to be approximately 18 inches, and the casing thickness to be 0.5 inches. The
owner of the property on which the well sits, and with whom the village has a contract to use the
well, stated that the depth of the well is 45 meters. We measured the water level to be 7.1 meters
below the top of the casing, but the dry season water level may be several meters lower. Since
the well has been out of use for decades, there was no knowledge among the people as to how
much the water level may vary by season. Interviews with residents who use shallower wells
closer to the Matagente River and under greater influence of surface water suggest that the water
level in those wells may fluctuate by approximately 5 meters between the wet season from
January to May and the dry season, June to December. Before installing the well pump, the well
water level will be re-measured during the dry season on several occasions, and the pump will be
set several meters below that water level.
Water quality assessment required disinfecting and flushing the well. This flushing also served
as an opportunity to assess the well capacity. Priming a gas-powered, locally owned pump was
particularly challenging because the depth of the water level was just barely high enough for
formation of adequate suction pressure. When flow was finally delivered, the flow rate was fairly
stable at approximately 4 liters/second for 2 hours, and then the pump stopped due to exhausting
its fuel supply. A water infrastructure map stamped by a licensed Peruvian engineer in December
2006 indicates that the flow capacity of this well is 22 liters/second, which is beyond the
capacity of the pump used for flushing. We suspect that the flow capacity of the well is
substantially greater than the 4 liters/second delivered during well flushing.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 13 of 58
B. Well Water Quality
Prior to testing the water quality, approximately a half liter of Chlorox was poured into it to add
a few mg/L of chlorine to its water, in an effort to disinfect it. This concentration is far below the
chlorine concentrations stated in well disinfection standards such as those of the American Water
Works Association. However, resources were limited, and the team wished to avoid disposal of
highly chlorinated flushing discharge. The chlorine was allowed to set in the water for
approximately 12 hours. The following morning, after nearly two hours of flushing, samples
were grabbed. Conductivity, pH, turbidity, and microbes were tested a few hours later that day in
Viña Vieja. All other items shown in Appendix C were measured after the team’s return to the
University of Texas at San Antonio (UTSA).
The microbes were measured using Petrifilm plates. To each of three such plates, 1.0 mL of
sample was added. Within two days, colonies emerged. For the water from the proposed well,
the colony count for the total of 3.0 mL was zero for non-coliforms, zero for coliforms, and zero
for E. coli. At the time of grabbing the sample, as would be shown by later testing in the lab at
UTSA, the concentration of total chlorine was 0.05 mg/L.
Water quality testing confirmed the Viña Vieja community’s confidence that the well is an
appropriate source for potable water. As shown in Appendix C, none of the constituents
exceeded the maximum contaminant levels listed as U.S. Environmental Protection Agency
standards. The arsenic level is only slightly less than the EPA maximum contaminant level of 10
parts per billion, and therefore will be monitored. We anticipate no need for water treatment, but
space is provided at the well site for the addition of treatment processes, such as chlorination and
the removal of arsenic or other metals by a small, packaged water treatment system.
The water quality was also tested from a material compatibility perspective. The Langelier
Index was determined to be -0.135, which is neither scale forming nor significantly corrosive.
3.1.2 Water Demand During the assessment trip, a survey of the community revealed ninety households with an
average of approximately 5 persons per household. Thirty of these households lie west and uphill
from the well, and are in what we designate as Pressure Zone A, while the remaining 60 homes
lie east and at a lower elevation than the well, are in what we designate as Pressure Zone B. The
water consumption survey indicates that the average daily consumption for households having a
tap in the front yard (the scenario which matches are design condition) is approximately 9
gallons per capita per day (gpcd). Households who have to walk a significant distance for water
use less water in their homes, and may wash laundry and bathe at a spring, irrigation canal, or the
Matagente River.
Most households with taps have no flow at the tap from 5:00 p.m. to midnight, and on some
occasions have no flow for a few consecutive days. Water demand at these households is likely
to increase beyond the average of 9 gpcd once the proposed system is installed due to more
consistent availability. However, upon consulting with our in-house veteran expert (Dr. Louis
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 14 of 58
Manz, who has been involved with dozens of community water supply efforts in Honduras),
providing more than 15 gpcd may lead to ponding of excess water and wastewater, becoming a
health concern. We believe that allowing for 15 gpcd is safe, particularly in this dry climate, but
the Committee will be instructed regarding the need to monitor and educate against such a
potential health problem. Control of the well and booster pumps will provide leverage for
preventing such complications, if necessary.
With 30 households in Zone A and 60 households in Zone B, our design demand is 2,250
gallons/day (8,500 liters/day) for Zone A and 4,500 gallons/day (17,000 liters/day) for Zone B.
While the average daily demand is helpful in establishing required storage capacity, the peak
hourly demand is needed to estimate maximum velocities and frictional losses for Zone B, and,
depending on the pump/system curve relationship, perhaps for Zone A as well. We have selected
a peak hourly demand to average daily demand ratio of 4. This is approximately the ratio used by
the Texas Commission on Environmental Quality and others for community water supply
systems. The ratio may increase for communities smaller than Viña Vieja. We believe that the
ratio of 4 is conservative because the proposed system will have only one tap per household and
many homes store water on site.
The population is not expected to grow substantially. Essentially all land is presently occupied
by houses or agriculture, and the main source of employment is agriculture. Even if we assume
an increase in demand of 50%, the proposed system discussed below can adequately
accommodate the increase. The water well is capable of meeting such a future demand many
times over, the well pump and booster pumps can easily be run for 50% more time per day and
still have substantial down time, the site for storage tanks has room for additional tanks, and the
conservatively sized pipe diameters can accommodate such an increase without substantial
increase in energy losses.
3.2 Description of Design and Design Calculations
3.2.1 Piping A. Pipe Sizing
Our community covers approximately seven kilometers from one end to the other. The well lies
near the center of the community, at the convergence of Zones A and B. All flow will be by
gravity except for that delivered from a proposed booster pump at the well site pumping water to
the water tank at the highest elevation 1,300 meters away in Zone A. This line will serve as the
main trunk line for Zone A. For Zone B, the main trunk line will extend from tanks B-1 through
B-4 near the well to the village’s elementary school approximately 3,500 meters away.
Pipe sizing is based primarily on the peak flow rate. Our design peak hourly demands are 6.25
gallons/minute (gpm) for Zone A, and 12.5 gpm for Zone B. For Zone B, where flow is strictly
by gravity, this peak hourly demand is also the peak flow rate in the main trunk line. For Zone A,
the peak hourly demand must be compared with the booster pump operating point, and the
greater of the two is to be the peak flow rate in the main trunk line. The trunk lines for both
zones lie along the main road, which passes through the full length of the village and leads to
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 15 of 58
neighboring El Carmen. Several significant branches serve clusters of houses near to or some
distance from the main road, as shown in Appendix F, Maps.
Compared to the cost and effort of trenching, laying and piecing together pipe, and filling the
trench, a one inch increase in pipe diameter is not very significant. Pipes were therefore sized
such that frictional losses (see Appendix A, Frictional Head Losses) and minor losses (Appendix
A, Minor Losses) are very low even at the peak flow rate. The resulting energy grade lines are
shown in Appendix B, for each of the lines shown in Grade line Zone A and Grade line Zone B.
We do not anticipate build up of particulates in the pipeline due to low velocities because the
well water is of naturally low turbidity. The relatively large pipe sizes accommodate an increase
in future demand of 50% without a substantial change in the energy grade lines even if the
conservative peaking factor of 4 is maintained. Also, for the main trunk line of Zone A, which is
a force main, the relatively low peak velocity provided by the large pipe size allows for easier
control of surges, and less likely pipe failure should surge control measures fail.
B. Pipe Material
The water is non-corrosive or only mildly corrosive based on the calculation of the Langelier
Index (Appendix A, corrosivity). Therefore, from a corrosivity or scaling perspective, virtually
any pipe material is acceptable. Because of cost limitations, we anticipate providing no more
than approximately 1.5 ft of cover over the top of the pipe, and the question arises as to whether
the pipes will be adequately protected against the stresses exerted by traffic, especially if the
least expensive material, PVC, is to be used. Nearly all the vehicles that travel the road are light-
weight motorcycle “dirt bikes”, but occasionally a farm tractor or a cement truck may travel the
road. Therefore, we assume the heavy truck traffic of H-20 wheel loading as specified by the
American Association of State Highway and Transportation Officials (AASHTO). Based on the
deflection equation (Appendix A, Deflection Equation), Class 10 PVC (which is nearly
equivalent to Schedule 40 PVC) is adequate for such loading. We note that the high stiffness of
the 3” and smaller Class 10 pipe sizes enable the pipes to withstand such loading.
As shown in the drawings, the water lines must cross irrigation canals or other obstacles which
prevent the provision of earthen cover. The exposure of PVC to ultraviolet radiation from the sun
causes it to become brittle and to fail. Also, PVC can easily be damaged when struck by heavy
objects. For these reasons, galvanized steel casing of 1.5” diameter or larger (depending on the
diameter of the PVC pipe) will be provided for such crossings, as shown in Appendix B, crossing
detail.
At one location, where a concrete bridge passes over a stream, it would be impossible to prevent
PVC from being exposed near the edges of the casing. Therefore, the piping itself is to be
galvanized steel. The transition from PVC to galvanized steel occurs in the trench line, and is
accomplished with transition couplings. See Appendix B, bridge crossing.
C. Joint Restraints and Thrust Blocks
Static pressure, pressure surges, and changes in flow direction at bends and tees all create forces
towards separating pipe at its joints. The sum of these forces is known as the thrust force. The
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 16 of 58
total thrust force must be calculated. Joint restraints or thrust blocks or both must be used to
ensure that the thrust force does not push the piping apart, particularly at bends, tees, and dead
ends.
The anticipated force due to static pressure is based on the maximum possible static pressure in
the system, and is calculated by Appendix A, static pressure. The force due to a pressure surge
occurs in Zone A only, where there are booster pumps, and is based on the assumption that surge
controls fail. This force is calculated by Appendix A, Surge. Finally, the force due to a change in
flow direction at a bend is relatively small, and is calculated by force due to change in
momentum, Appendix A. The thrust force, the sum of these three forces, dictates the restraint
design requirements. In Zone A this force is at its maximum at bends in the trunk line near the
booster pumps. In Zone B this force is at its maximum at the point of lowest elevation in Zone
B.
Both thrust blocks and restraints at the joints may be used for restraint design. Thrust blocks,
made by pouring concrete at the pipe fitting, offer the advantage of never corroding, but tend to
cover the fitting in concrete if not poured carefully. If a leak occurs at or near the fitting,
repairing the leak will become greatly complicated. Also, if not carefully poured, the block may
sink with time, dragging the fitting and piping with it, ultimately rupturing the piping.
Joint restraints are applied where segments of pipe are connected, or where fitting or valves join
pipe segments. If made from inadequate materials, or if not protected against corrosion, the
fittings may fail with time.
Joint restraints and thrust blocks are relatively inexpensive and will be used for this project to
better ensure adequate restraint for decades to come, with thrust blocks to be carefully poured
and the possibility of joint restraint corrosion being carefully considered. Redundancy is
achieved by designing the thrust blocks as if there were to be no joint restraints and the joint
restraints as if there were to be no thrust blocks. For thrust block design, the back surface area of
the thrust block is based on the soil bearing strength and the thrust force, as shown in Appendix
A, Thrust Blocks.
For joint restraint design, the length of piping which must be restrained at the joints is calculated
based on frictional forces between the soil and the pipe that act against the thrust force. The
longer the length over which the piping is restrained at the joints, the greater the thrust force that
would be needed to separate it. In Appendix A, Restraints, the equations are used for calculating
the length over which the joints must be restrained. In cases where solvent weld PVC is to be
used, the solvent welding serves as the joint restraint.
The water in this pipe is fed by a booster pump when Tank A is filling and gravity fed when the
tank is full. The major loss in the pipe was accounted for based on the Hazen-Williams equation,
Appendix A. The minor loss in the pipe was accounted for using the equation in Appendix A,
Minor Losses. These figures contributed to choosing a diameter of 2 inches in order to decrease
the major and minor energy losses as well as maintain demand in this zone. Zone B is located
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 17 of 58
west of the well and decreases in elevation 17.68 meters. The pipe in this zone will be gravity fed
from Tank B. This zone will provide water to 60 households. The major and minor losses in this
zone were higher than Zone A and designed for using the major and minor losses as in Zone A.
The diameter of the mainline was increased to 3 inches based on the increased demand and
energy losses. The main lines will service the majority of the community; however there are
households that lie off the main road. In order to provide water to these families, the main line
will have 4 branch lines. Zone A will have one branch line in order to service households that lie
south of Tank A. Zone B will have three branch lines, with one going south of Tank B, one going
west of the end of mainline B, and one north of the end of mainline B. The design of these pipes
called for a diameter of 1.5 inch because of decreased demand. The demand was very minimal;
however, an increased diameter was chosen in order to account for future growth.
Each household will be serviced by an individual tap located on the outside of their home. These
taps will all be serviced by a tap line of 0.5 inch diameter. The pipelines for this project will be
underground except on bridge crossings. The pipeline will be buried approximately sixty
centimeters deep and dug using machinery donated by a nearby farmer/landowner. The bottom
of the trench will be lined with sand in order to provide a level surface for the pipe to sit on. The
bridge crossing will be done using galvanized steel pipeline in order to provide the necessary
strength to cross the span.
Thrust blocks were designed for the critical points in our pipeline. These critical points were at
the southernmost point of Mainline A as well the southernmost point of Mainline B. Mainline B
had a static pressure of 4206.5 lb/ft2 as calculated using the Static Pressure equation, Appendix
A. Mainline A had a static force of 3178.5 lb/ft2 and a surge pressure was accounted for based on
the worst cases scenario that the valve on Tank A closed and the pump did not stop pumping
water. This surge force was calculated as 57 ft H2O using the Surge equation in Appendix A. The
thrust block was then designed based on the worst case scenario in Zone B, coming out to an
area of 0.11 in2. Even though this was the critical point, thrust blocks will also be added at the
ends of the branch lines and 90 degree turns in order to provide added protection against pipe
separation. As an additional precaution, restraints will be added to the pipe system. These
restraints will be used on all 90 and 45 degree bends, as well as t-joints and dead ends. The
design of these restraints was done using restraint calculations as seen in Appendix A. On T
joints the design calls for the pipe to be restrained 1.7 ft on the branch and 2 feet on the runs. On
the 90 degree bends 2.10 feet of restraint is called for. The 45 degree bends call for 0.86 feet of
restraint and the dead ends require 2.5 feet.
3.2.2 Water Tanks The size of the tanks was designed to provide proper support for the community as well as the
ability to serve increased demand in the future. In order to provide satisfactory capacity for the
community, four 10,000 L tanks will be used as storage. The topography of the area requires that
three of the tanks be placed at the location of the well. The remaining tank will be placed in Zone
A at the top of the hill. This tank will be fed by a booster pump until it is full. Once it is full the
tank will be able to supply the households in Zone A by gravity.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 18 of 58
3.2.3 Pumps In order to draw water from the well, a submersible pump is chosen because the water level
below the top of casing would provide inadequate suction pressure for above-ground impellers.
The demand of the community as well as the total dynamic head at various flow rates were
plotted against the pump operating points. The intersection point yielded the operating flow rate
of the pump. The most efficient pump, using the numbers from these graphs, was a Pedrollo 45k
submersible pump. This pump will be able to provide sufficient water to fill the tanks located by
the well.
A centrifugal-type booster pump was needed in order provide water to Zone A. This pump was
found using the same general methods described in choosing the submersible pump. The pump
that best fit the system’s needs was the Pedrollo 3CPm80E. Designing for sustainability, two
booster pumps will be installed in order to decrease continuous use of each pump, and to allow
time for repair without disruption of service. The pumps will rotate each day and need to be
turned on manually, but turned off automatically based on the height of water in the zone A
tanks. The manual start is designed to require a community member to visit the area around the
well each day and perform visual inspection. As the community matures in its understanding of
the system, it may choose to implement greater automation.
3.2.4 Automatic Shut Off of Booster Pumps An altitude control valve will be needed on the storage Tanks A serving pressure Zone A. This
valve will close when the water level in the tank reaches full capacity, but will close slowly to
minimize surges. As it closes, the pressure at the booster pump will increase, causing a pressure
switch at the pump discharge end to shut down the pump. The booster pump will need to be
restarted manually (most likely the following day). After the pump stops, the pressure in the
force main from the booster pump to Tank A will drop, causing the altitude valve to re-open so
that water may flow by gravity from it to community members in Zone A.
The slow closure of the altitude control valve is essential to minimizing surges. The critical time
for the surge was calculated to be 4.9 seconds based on the Critical Time Equation in Appendix
A. This is the time for the surge to travel from the pump to the valve and back to the pump. The
surge pressure is not only positive, but also, in its wake, leaves a pressure reduction, equal in
magnitude. A closure any less than 4.9 seconds will not reduce the maximum surge pressure
exerted on the system, or the minimum pressure occurring in the wake. For our system, the
primary concern is that the minimum pressure does not dip below the vapor pressure of water
(which is 0.2 psia, or approximately -14.5 psig), so that column separation does not occur. To
maintain a minimum pressure of no less than -5 psig, the valve closure should occur over a time
span of no less than 15 seconds, by application of the time critical equation in Appendix A,
surge.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 19 of 58
4.0 PROJECT OWNERSHIP
The Viña Vieja Water Committee will take ownership of the financial obligations and
maintenance of the facilities implemented for the project, which includes but is not limited to
four tanks, two centrifugal water pumps, one submersible pump, and all the necessary piping.
The committee will consist of a president (community leader, Javier Ortiz Espino), who makes
sure the water distribution system works properly; a treasurer (Mayor Francisco Cartagena)
responsible of collecting the fees; a maintenance man, in charge of all of the operation and
maintenance; and a secretary, to do the bookkeeping. All of the committee members will be
selected before our arrival and the whole community is aware of the maintenance and operational
fees involved in the system. The land that the water well, pumps, and three of the tanks sit on is
owned by C.A.U. Manco Capac Ltda. with a transfer of use agreement (see Appendix D,
Contracts) in place for the community lasting at least ten years.
5.0 CONSTRUCTION PLAN
The foundation needs to be created and cured and the trench for the pipe already cleared so that
the project can be completed during the implementation trip. The community has access to a
trench digger, through La Calera, a local agriculture company, that can complete the trenching in
less than seven days. The community has agreed that they will have this completed before we
arrive in Viña Vieja on the 8th
of August. We will be hiring a contractor to lay the foundation for
the tanks and pumps in July while Texas Partners of the Americas, the local NGO, is in Viña
Vieja so they can facilitate the process. This needs to be done before we arrive in Viña Vieja
because the time needed for the concrete to cure is 28 days.
At our arrival in August, we will lay PVC pipe in the cleared out trenches over the full five and a
half kilometers. The different connections and fittings will be attached on an as needed basis.
The galvanized steel casing will be installed in the crossing and the pipes fed through these
casings. Once we do a test run with the water and verify that all the pipes were connected
properly and no pipes are leaking, we can go and fill the trench with the back dirt. The next step
is to install the pumps in the proper position and attach the pipes to the pump. The pump needs
to be connected to the power grid, which is about one hundred meters away from the pump site.
Once this is completed, the tanks can be anchored to the foundation and pipe connections
completed. Since we are using four plastic tanks, a connection between all of the storage tanks is
crucial but it is also essential we design something that will not fail when one tank cracks and
can no longer be used until replaced. This connection between the tanks will be installed and
then we will be ready to turn the pump on and make sure all of our connections have been
completed properly.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 20 of 58
The foundations done by a contractor will include clearing ground for the foundation, the form
reinforcement, pouring concrete for the foundation, concrete cure time, and anchoring. The
piping installations include laying the pipe, installing the connections, and fill in the trenches.
The storage tanks installation include connecting the pumps and pipes to the tanks and the
connections between the four storage tanks pumping installations.
6.0 SUSTAINABILITY
6.1 Background Since the beginning, this design aimed to improve living conditions for the people Viña Vieja.
Thus, the feasibility of maintaining and repairing the project lies with the resources available to
the region. All of the hardware stores from which we will be getting supplies, are in Chincha
Alta, a one hour drive from Viña Vieja. Many residents from Viña Vieja are workers in Chincha
Alta, making transportation and communication between the two continuous and reliable. The
plastic tanks that we will be using are from Rotoplas. These tanks have a lifetime warranty so
long as they are not subject to misuse or abuse, making any unexpected issue manageable at a
reduced cost or no cost at all. Through the MOU it has been agreed that the people of Viña Vieja
will pay an affordable monthly tax, which will be used for the maintenance and replacement
parts. The initial maintenance will be done by members of EWB-UTSA, who will later train the
elected officials of Viña Vieja. All of these factors have been considered in order to ensure the
sustainability of the design.
6.2 Operation and Maintenance All operations and maintenance activities for the water pump systems and tanks are identified
below.
Centrifugal Pump:
There will be two interchangeable pumps, each running every other day. A two pump system
allows reduced strain on each individual pump and allows interruption free maintenance on an
individual pump. Routine inspections of the pump will take place daily. One should look for any
of the following: if there is any unusual noise or vibration, something inside the pump may be
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 21 of 58
loose; if water is detected around connections, then there may be leaks. Problems with the
centrifugal pumps will be addressed by the appointed member of the water committee.
Submersible Pump:
The submersible pump is made with the capability of going unattended for long periods of time.
It has control systems that will, in many occurrences, handle any mishaps. System controls for
the pump can only handle stable conditions; hence if the conditions of the well change to an
extreme, the pump may not be able to handle the changes and will most likely cease functioning.
Short scheduled maintenance sessions should decrease the chance of the submergible pump
failing. In these sessions one should look for alarms in the control panel, excessive noise and any
sign of overheating and should be done every two to four weeks.
Pipes:
Pipes should be checked weekly for leaks or whenever the community deems necessary.
Inspections will be organized and documented by the water committee. In case of any damage or
aging, PVC pipes can be bought from any of the three providers in Chincha Alta. Time needed to
maintain the pipe’s is estimated to be approximately 40-50 minutes per week.
Water Tanks:
Tanks must be cleaned and disinfected annually and should be checked for leaks monthly. One
should not enter the tank while cleaning. In order to clean, first drain the tank and close the tap.
Wash the inside surfaces of the tank with water and then drain the freshwater and sediment from
the bottom by opening the spigot. Chlorination and bleach can be used to disinfect it but both
include mixing with water (5 mL of bleach per liter of water), which would be difficult. In using
chlorine and bleach, the solution needs to sit for 2-5 hours and then let drain until the smell of
chlorine disappears. The spigot should be tightly closed and secured after every use. Estimated
time for cleaning and inspecting tanks is 4 to 6 hours per year.
Water System Committee:
During our assessment trip, we visited the neighboring community of Punta de la Isla. After
analyzing their water system, we proceeded to discuss our findings with leader of the community
of Viña Vieja, Javier Ortiz Espino. It was decided that, like Punta de la Isla, there will be a
charge of 5 soles per month per household. Additionally, it was concluded that the creation of a
committee, who will take charge of the project, was needed which will be later know as The
Water System Committee. The Water System Committee is composed of four officials, elected
annually, and a group of representatives. The four officials consist of a President, Treasurer,
Secretary and Maintenance official. The President will deal with the community and will
mobilize the workforce in order to keep the project running. The Treasurer will collect fees and
evaluate the need of funds on maintenance. The Secretary will keep a log of meetings, a history
of water quality tests and update the community representatives on any upcoming meetings. The
Maintenance officer will check the equipment to be in good working condition as well as let the
President and the Treasurer know of any work needed to be done. The representatives consist of
people who will represent each cluster of households, such that no group is neglected and the
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 22 of 58
whole community is involved. These representatives are not necessarily elected by the
community as a whole, they are chosen by the members of each cluster so that everyone is
represented and involved.
Finance:
As stated in the MOU the community members will be paying a monthly fee of 5 soles per
household in order for the maintenance of project to be assured. It is recommended for the
community Treasurer and Secretary to keep a record of any expense made on the project, as well
as a record of water quality tests. Prices of any replacement parts will be approximately equal to
the costs of individual parts in our cost estimate (see Appendix E for pricing information).
General View:
In general, inspections for the water pump system will take 60-90 minutes every week. The tank
will also need cleaning every year, which will require 4-6 hours. Supplies can be acquired in a
neighboring city which has good relations with Viña Vieja. If anything happens to the tanks there
is a lifetime warranty that can be validated through the distributor. At the end of the tanks’
lifetime, approximately 35 years, replacement tanks may be procured from the distributors at
Chincha Alta. Water pressure is an important factor for reducing time spent on inspections. If
water pressure decreases in any section and only in that section it is most likely that only that
particular area has the issue. Hence the area being checked is reduced to a small area instead of
the entire distribution system.
6.3 Education The community of Viña Vieja has skilled workers who have prior experience with the
maintenance of pipes and tanks. This will reduce mechanical education on the O&M of the
design. What we want to focus on in our education committee meetings, lead by our mentor Dr.
Joseph, are the “why’s”. Why are we checking for leaks? Why is it a hazard to leave leaks alone?
Why only small and precise amounts of bleach should be used? Are prices for the maintenance
going to increase and why? These questions are only a few of the many we plan to discuss. Our
aim is to clarify and give them an understanding of why it is important to follow the O&M.
Additionally, we will give them instructions for the equipment we will be providing them such
as; Petrifilm for the monitoring of E. Coli and water quality tests to check the level of arsenic in
the water.
EWB-UTSA is still in the process of forming an Operations and Maintenance Manual for the
system as a whole to be provided to the committee upon completion of the system. This manual
will cover all operations and maintenance points mentioned above and include EWB-UTSA’s
recommendations on fund collection.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 23 of 58
7.0 MONITORING
7.1 Monitoring plan for current project
The project will be monitored on three different aspects to ensure the success and sustainability
of the project.
The first aspect of the monitoring plan regards with the construction and operation of the water
distribution system. The system will be monitored to work under the expected conditions in
terms of water pressure, ease of access by households, tank maintenance, and pipeline integrity.
The previous parameters will be monitored in monthly conversations with the community and
visually inspected during every visit.
The second aspect is about the continuation and effectiveness of the community committee in
charge of the operation and maintenance of the system. The functionality of the committee will
be based on its dedication to the system, fulfilling their responsibilities of following a
maintenance program, assessing all fees, and holding committee elections periodically. As well
as the previous monitoring aspect, the committee will be evaluated in monthly conversations and
during the monitoring trips to the community.
The third aspect deals with the community’s education and behaviors regarding health and
hygiene. It will be based on the community’s understanding and practices about proper disposal
of wastewater, health issues related to drinking contaminated water and potential contamination
risks in stored drinking water. During the implementation trip proper and improper water storing
techniques will be displayed and consequences explained. Techniques in water storage and
disposal can be inspected visually during future trips and maintained as needed.
The education and training about the maintenance of the water distribution system and sanitation
will be given by EWB-UTSA to the community committee. The committee will be responsible
for educating the rest of the community and monitoring their sanitation behaviors continuously.
7.2 Monitoring of past-implemented projects
There are no previously implemented projects to monitor.
8.0 COMMUNITY AGREEMENT
The Memorandum of Understanding (MOU) represents the commitment of the three parties
involved in the water distribution project of Viña Vieja. The first version of the MOU was
written by the team in San Antonio before the assessment trip. On the third day in Viña Vieja,
the MOU was discussed with the community leaders; they valued our commitment to the project
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 24 of 58
and only demanded a few modifications to it. On the next day, the required modifications were
made and the MOU was read, discussed, and signed during the community meeting.
The MOU expresses the commitment to the project by the community, the NGO, and the EWB-
UTSA chapter. In summary, the residents of Viña Vieja agreed to allow EWB-UTSA to work on
the project, they will create a local committee in charge of the operation and maintenance of the
system, and each family will pay a monthly fee to cover the operational expenses. The NGO,
Texas Partners of the Americas, will also support the project and provide transportation,
communication, and translators to EWB-UTSA if necessary. EWB-UTSA is committed to
design the project, to teach the community on how to properly maintain the system, and to
provide the in-built drawings to Viña Vieja after the project completion.
The MOU was signed by the lieutenant governor of Viña Vieja, Francisco Cartagena, by the
president of Texas Partners of the Americas, Iliana Diaz, and by the professional mentor of
EWB-UTSA, Dr John F. Joseph. A re-evaluation of the MOU will be made during each trip and
any adjustments agreed upon by all parties will be added as an addendum. A copy of the signed
MOU in Spanish and its translation in English is shown in Appendix D, Contracts.
9.0 COST ESTIMATE
Item Unit Unit Cost (S/.) Quantity Total (S/.) Total ($)
Pipe
1" Class 10 3m 7.06 541 3,822.11 $1,433.67
1.5" Class 10 3m 8.08 975 7,876.03 $2,954.30
2" Class 10 3m 8.80 432 3,800.65 $1,425.62
3" Class 10 3m 15.54 695 10,802.23 $4,051.92
Subtotal $9,865.51
Foundation
Concrete 1 yd^3 186.62 12.8 2,388.74 $896
Base 1 yd^3 57.00 7.2 410.40 $154
Corner bars n/a 60.00 16 960.00 $360
Tie Downs 1 strap 120.00 2 240.00 $90
Rebar 20ft 300.00 4 1,200.00 $450
Stirrups n/a 440.00 1 440.00 $165
Subtotal $2,115
Water Tanks
10,000 L Tank n/a 7,411.50 4 29,646.00 $11,120
Subtotal $11,120
Pumps
Pump n/a 675.00 3 2,025.00 $760
Subtotal $760
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 25 of 58
Valves
1/2" Valve n/a 3.50 60 210.00 $78.77
1" Valve n/a 7.00 9 63.00 $23.63
2" Valve n/a 17.20 11 189.15 $70.95
Subtotal $173.35
Transportation
Transport Water Tanks 1 trip 100.00 4 400.00 $150.04
Transport Pipe 1 trip 100.00 4 400.00 $150.04
Subtotal $300.08
Grand total
$24,333.98
Maintenance (per year)
Electricity 1 pump 450.00 2 900.00 $337.59
Water testing 1 test 200.00 1 200.00 $75.02
Pump repair n/a 200.00 1 200.00 $75.02
Pipe repair n/a 150.00 1 150.00 $56.27
Yearly Maintenance Total $543.90
10.0 SITE ASSESSMENT ACTIVITIES
The site assessment component of this trip includes considerations of wastewater needs once the
water system is in place. The amount of water provided to each house may necessitate a
wastewater consolidation plan in order to avoid groundwater contamination and excess erosion.
As a portion of our community engagement, we'll introduce waste water considerations to the
people of Viña Vieja and gauge interest in a future waste water plan. EWB-UTSA will attempt to
locate possible sites for pipe and septic tanks for future additions to this community's total water
solution.
11.0 PROFESSIONAL MENTOR ASSESSMENT
11.1 Professional Mentor Name John F. Joseph, Ph.D.
11.2 Professional Mentor/Technical Lead Assessment
All those listed on the front page of this report contributed significant time to its development.
At least one student thoroughly understands each of the many equations listed for hydraulics and
for foundation design. Students consulted me for guidance regarding hydraulics, piping material,
pumps, system operation and thrust restraint, and water quality. They also consulted Dr. Heather
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 26 of 58
Shipley for water quality and water quality testing. UTSA faculty member Dr. Manuel Diaz, a
structural engineer and native of Peru, provided guidance on foundation design. AnnMarie
Spexet provided helpful insights for important general guidance.
In the earlier stages of the report preparation, many of the students were caught in the business of
the last weeks of the semester – working on major reports, preparing for finals, etc., and much of
the work done depended on who had time and energy to invest in the project. But as the
semester closed, a chart was created by the students, in which they tasks were assigned to each.
11.3 Professional Mentor Affirmation I, John F. Joseph, have been involved in this design development phase, and accept responsibility
for the course that this project is taking.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 27 of 58
APPENDIX
Appendix A – Calculations Equations Frictional Head Loss (Hazen-Williams Equation)
L=Length (ft.)
Q=Flow rate (gpm)
C=Roughness Coefficient
d=inner diameter (in.)
Minor Loss
K= minor loss coefficient
V=Velocity (ft/s)
g=acceleration due to gravity (32.2 ft/s2)
Surge
a=elastic wave speed (ft/sec), calculated below
∆v=change in water velocity due to pump kicking on or off and valve closing (ft/sec)
g= gravity (32.2 ft/s2)
Wave Speed (a)
K=bulk modulus of elasticity of water (lb/ft
2)
=density of water (slugs/ft3)
E=modulus of elasticity of pipe material (lbs/ft3)
C=correction factor for pipe constraining, and depends on pipe material. We'll assume
pipe is constrained against axial movement. (See Pumping Station Design, 3rd ed,
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 28 of 58
Chapter 6, for details.) This leaves us with C = 1-0.45^2=0.80 for PVC
D=inner diameter of pipe (ft)
e= pipe wall thickness (ft)
Time Critical
L=length (ft)
a= wave speed (ft/sec)
Force due to change in momentum
Fx=force exerted on bend in x-direction (ft*lb)
=density of water (slug/ft3)
velocity of water in the x-direction before the bend is reached (ft/s)
= velocity of water in the x-direction after it passes the bend
Q=volumetric flow rate (ft3/s)
Force on bend after booster pump
Static Pressure
γ = specific weight of water (lb/ft
3)
h=height (ft)
Static pressure at bottom of Zone A
Static pressure at bottom of Zone B
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 29 of 58
Pipe Deflection
∆ = deflection (%)
DL= deflection lag factor
K=Bedding Constant
= Prism Load (lb/in2)
PS = pipe stiffness (lb/in2)
E1=soil modulus (lb/in
2)
Corrosivity
pH=pH
pHs=(9.3+a+b) - (c+d)
b=13.12(log10(C+273)) + 34.55
c=log10(Ca2+
as CaCO3) - 0.4
d=log10(alkalinity as CaCO3)
-0.135 is between 0 and -0.5, therefore the water is non-corrosive and has no tendency to scale
Frictional Resistance
Ap=area based on half the pipe circumference in contact with soil (ft
2/ft)
Fc=cohesion modifier coefficient
c=cohesion of the soil (lb/ft2)
D=outside diameter of pipe (ft)
We=normal force due to vertical prism load of soil (lb/ft)
Wp=normal force due to the weight of the pipe (lb/ft)
Ww=normal force due to the weight of the water in the pipe (lb/ft)
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 30 of 58
Zone A
Zone B
Fittings
Horizontal bends
Sf=Safety Factor 1
P=internal pressure (lb/in2)
A=cross sectional area of pipe (in2)
Fs=frictional resistance acting on pipeline, acting on half the pipe diameter (lb/ft)
=bend angle in degrees
Kn=trench compaction modifier
horizontal passive soil pressure (lb/ft2)
=soil density (lb/ft
2)
Hc=mean depth from surface to pipe center line (ft)
c=cohesion of soil (lb/ft2)
Kp=Rankin passive pressure coefficient
=internal friction angle of soil (degrees)
90 degree bend
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 31 of 58
45 Degree Bend
Tees
Ab=cross sectional area of the branch of the tee (in
2)
Lr=minimum restrained length on each side of the run of a tee (ft)
Fsb=frictional resistance acting on the pipeline (acting on the full pipe diameter)
(Ap)b=area based on full pipe circumference in contact with soil (ft
2/ft)
D=outside diameter of pipe (ft)
3 inch
tan(0.6*29)=164.67
Dead End
3 Inch
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 32 of 58
Thrust Blocks
T=Thrust force (lb)
qallow=soil bearing pressure (lb/in2)
Zone B
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 33 of 58
Foundation Calculations (three pages)
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 34 of 58
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 35 of 58
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 36 of 58
Appendix B – Drawings
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 37 of 58
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 38 of 58
Foundation
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 39 of 58
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 40 of 58
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 41 of 58
Grade line Zone A
Grade line Zone B
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 42 of 58
Appendix C – Water Quality
March 2012 Viña Vieja Water Testing Results (Pozo de Manuel)
After-Pump Water EPA Requirement
Water Tests: Reading Units Secondary Guideline
pH 7.46 6.5-8.5
Conductivity 445.0 μS/cm
TDS 225.0 mg/L 500 mg/L
DO 7.00 mg/L O2
Turbidity 1.06 NTU N/A
Coliform Present Zero to One per Month
Alkalinity 125.0 mg/L CaCO3 N/A
Total Hardness 197.6 mg/L CaCO3 N/A
EPA Requirement (MCLG or MCL)
Testing Metals: Concentration Unit MCLG
MCL (or Secondary Guideline)
Ni 1.432 μg/L Ni+2
Cu 0.326 μg/L Cu+2 1.3 1.3; TT mg/L
Zn 0.302 μg/L Zn+2 5 mg/L
As 6.088 μg/L As(III) 0 0.01 mg/L
Ag 0.042 μg/L Ag+1 0.1 mg/L
Cd 0.062 μg/L Cd+2 0.005 0.005 mg/L
Pb 0.008 μg/L Pb+4 0 0.015 mg/L
Mg 13.173 mg/L Mg+2
Ca 40.951 mg/L Ca+2
Na 1.806 mg/L Na+1
Fe 0.170 mg/L Fe 0.3 mg/L
Phosphate 0.150 mg/L PO4-3
Chlorine 0.05 mg/L Cl2 4.0 4.0 mg/L
Corrosivity -0.135 (Noncorrosive) Noncorrosive
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 43 of 58
Appendix D - Contracts
Copy of the “Pozo de Manuel” contract (three pages).
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 44 of 58
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 45 of 58
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 46 of 58
Translation of the “Pozo de Manuel” contract.
TRANSFER OF USE AGREEMENT SIGNED BY THE C.A.U. MANCO CAPAC LTDA.
AND GENTLEMEN CIRILO ORTIZ MARCOS AND JAVIER ORLANDO ORTIZ
ESPINO.
BY MUTUAL CONSENT BETWEEN THE INTERESTED PARTIES MEANING THE
COOPERATIVA AGRARIA DE USUARIOS MANCO CAPAC LTDA. AND MR. CIRILO
ORTIZ MARCOS AND MR. JAVIER ORLANDO ORTIZ ESPINO, PRESIDENT OF
CENTRO POBLADO VIÑA VIEJA AND PRESIDENT OF THE EXECUTIVE GROUP OF
CENTRO POBLADO VIÑA VIEJA RESPECTIVELY, AGREE TO CONCLUDE THIS
TRANSFER OF USE AGREEMENT UNDER THE FOLLOWING TERMS AND
CONDITIONS:
1.-
The C.A.U. MANCO CAPAC LTDA. duly represented by its General Manager Mr. Pedro Pablo
CASTILLA CARPIO, and its Chairman of the Board Mr. Luis Enrique MINA ORTIZ, and Mr.
CIRILO ORTIZ MARCOS with ID Nº 21826848 AND JAVIER ORTIZ ESPINO with ID Nº
21828542, both farmers, married, with legal addresses in Fundo Viña Vieja, District of El
Carmen, Province of Chincha, Ica region. Agree to grant in TRANSFER OF USE for a period of
TEN (10) YEARS, A TUBULAR WELL IDENTIFIED WITH IRHS Nº 212, called
"MANUEL" and situated 219.41 meters above sea level. It is located in Viña Vieja, District of El
Carmen, Province of Chincha, Ica region and it is property of C.A.U. MANCO CAPAC Ltda.
2.-
This TRANSFER OF USE is done based on the agreement of this administration, which
determined to TEMPORARILY CEDE this well, without tools and equipment. In order to be
used by the applicant to obtain water and supply Viña Vieja, District of El Carmen with this vital
element.
3.-
The gentlemen CIRILO ORTIZ MARCOS AND JAVIER ORTIZ ESPINO, may recover, clean
up, and employ the previously mentioned tubular well as long as the TRANSFER OF USE
agreement is in effect.
4.-
The company WILL NOT CHARGE ANY MONETARY FEE for the use of this tubular well
during the agreed time period.
5.-
Mr. CIRILO ORTIZ MARCOS and Mr. JAVIER ORTIZ ESPINO commit to maintain the rights
of the tubular well, given to them by this transfer of use agreement.
6.-
LENGTH OF TRANSFER OF USE AGREEMENT
THE LENGTH OF THE CURRENT TRANFER OF USE AGREEMENT WILL BE FOR (10)
YEARS, WILL TAKE EFFECT AT THE MOMENT OF SIGINING THIS DOCUMENT.
7.-
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 47 of 58
The C.A.U. MANCO CAPAC Ltda. will be able to renew the transfer of use agreement if the
applicants wish to do so, by communicating to this company a month prior to the expiration of
the current transfer of use agreement.
8.-
The TUBULAR WELL, matter of TRANSFER OF USE, by being PROPERTY OF
COOPERATIVA AGRARIA DE USUARIOS MANCO CAPAC Ltda. CAN NOT BE
AWARDED, TITLED, SOLD, OR TRANSFERRED without the company authorization
because it is an intangible patrimony asset of this Cooperative.
9.
Obligations of Cirilo Ortiz Marcos and Javier Ortiz Espino
9.1
Receive the goods, take care of them and used them for what they are meant for.
9.2
Communicate to CAU. Manco Capac LTDA. of any usurpation, disturbance or imposition
against the goods.
9.3
They should not make irresponsible use of the goods or against the law.
9.4
Return the goods to CAU. Manco Capac LTDA. After the cession** reach the deadline of the
contract.
9.5
Cirilo Ortiz Marcos and Javier Ortiz Espino are not allowed to rent the water well which is under
cession. If they brake this rule without a special permit of the corporation, the cession will be
automatically terminated.
10.
Any modification that Cirilo Ortiz Marcos and Javier Ortiz Espino make to the water well will
be to full benefit of CAU. Manco Capac LTDA. without any cost.
11.
Jurisdiction
11.1
the parts specifically resign to the law of their addresses and to be put under the judges and
courts of Chincha Alta.
12.
The deadline of this cession will be on July 1st 2021.
This document was signed by C.A.U. Manco Capac LTDA, Cirilo Ortiz Marcos and Javier Ortiz
Espino. On July 1st 2011 at Viña Vieja, district of El Carmen, province of Chincha and Region
Ica.
Cession- The act of Cession, or to cede, is the assignment of property to another entity. In
international law it commonly refers to land transferred by treaty.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 48 of 58
Signed Memorandum of Understanding (Spanish version; two pages).
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 49 of 58
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 50 of 58
Memorandum of Understanding (English version; two pages) MOU for EWB UTSA/Viña Vieja Water Supply Project
Engineers Without Borders-University of Texas at San Antonio chapter (EWB-UTSA) believes that in order to
ensure that projects are put in the best position to succeed it is vital that communities are strongly committed to
collaborating with its chapters. Therefore, it asks that communities provide some sort of support for the
requested project. This can take many forms, from providing money or labor during implementation to housing
for volunteers or providing materials for the project.
This contract is between Viña Vieja, Texas Partners of the Americas (TPA) and EWB-UTSA for the purpose
of setting guidelines for the Viña Vieja water supply project.
The residents of Viña Vieja agree to the following:
Viña Vieja residents agree to allow EWB-UTSA to work on the water supply project.
Viña Vieja residents agree to participate in the work of constructing the system.
Viña Vieja residents agree to conserve water and maintain their system.
Viña Vieja will work to obtain support from the local government with respect to labor and materials.
Viña Vieja residents agree that the goal of water supply project is to improve the health of everyone in
the village, not just those who can afford to pay a tax/fee. Therefore, Viña Vieja residents will strive to
find ways to provide clean water to everyone.
Viña Vieja will hold annual elections for water board positions.
Viña Vieja residents agree to pay a household tax/fee of 5 Soles per household per month to be used
for maintenance and repairs of the water system, the amount can vary each year depending on the
community judgment.
More as determined by project…
Texas Partners of the Americas agrees to the following:
TPA will work with Viña Vieja to establish continuing support of the system.
TPA will provide contacts for ongoing maintenance, if the community is not directly responsible for
this.
TPA will provide local transportation for the travel members of EWB-UTSA.
TPA will provide translators and trainers for the EWB-UTSA.
More as determined by project…
EWB-UTSA agrees to the following:
EWB-UTSA will work with Viña Vieja to design and develop improvements to their water system.
EWB-UTSA will work to obtain implementation approval from EWB-USA.
EWB-UTSA will provide materials not obtained by the community for construction of the project.
EWB-UTSA will teach community members to maintain their system.
EWB-UTSA will seek input from community members during the design phase, but will not submit
plans for approval by a third party.
EWB-UTSA will provide as-built drawings to Viña Vieja after project completion.
More as determined by project…
Sanctions - EWB-UTSA reserves the right at any time to stop funding any or all aspects of the project.
If at any time, EWB-UTSA determines that a problem has arisen that jeopardizes the successful
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 51 of 58
implementation of the work, all parties will be notified in a first effort to reconcile the problem. If this
fails to resolve the issue to the mutual satisfaction of EWB-UTSA and Viña Vieja, EWB-UTSA will
take successive steps to escalate the issue until it is resolved or no measurable progress is achieved
and project success is deemed very unlikely:
1. Project suspension until corrective actions are completed and there is agreement to
continue; then
2. Non-binding mediation, conducted by a mutually acceptable third party selected by
EWB-UTSA and Viña Vieja at the start of the project; then
3. Cessation of project implementation should mediation prove unacceptable to either
or both parties.
Rewards – EWB-UTSA and Viña Vieja enter this MOU with the objective of building a foundation
for long-term relationships through an initial project success. Follow-on projects are the planned
reward for achieving this mutual objective.
Adjustment to the MOU This MOU will be re-evaluated as necessary and any adjustments can be added as an addendum to the MOU if
agreed by all parties.
On behalf of, and acting with the authority of the residents of Viña Vieja, the NGO, Texas Partners of the
Americas and Engineers Without Borders-University of Texas at San Antonio chapter, the under-signed agree
to abide by the above conditions.
Viña Vieja Representative Date
Texas Partners of the Americas Representative Date
Engineers Without Borders University Date
of Texas at San Antonio Representative
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 52 of 58
Appendix E - Pricing Electricity Bill from a household of Viña Vieja
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 53 of 58
Prices of Materials - Chincha Alta, Peru
Sodimac Chincha
Rocio Construcciones S.A.C. Chincha
Contact: Laura Aguirre Tasayco
Contact: N/A
Nextel: 113*9368 / Cellphone: (056) 599 700
Nextel: 828*9792 / Cellphone: (965) 722 343
Address: Calle Leopoldo Carrillo s/n Mz. C Lt. 3
Address: Av Victor A. Belaunde Nº 619
Product Description Price (Soles)
Product Description Price (Soles)
Rebar 3/8" AA x 9 meters S/. 14.57
Rebar 3/8" x 9 meters S/. 15.20
Rebar 1/2" AA x 9 meters S/. 26.00
Rebar 1/2" x 9 meters S/. 26.50
Rebar 6 mm x 9 meters S/. 5.79
Rebar 1/4" x 9 meters S/. 6.20
Cement Sol 42.5 KGS S/. 17.90
Cement Sol 42.5 KGS S/. 18.00
Drain Pipe 2" x 3 meters PV. S/. 8.70
Pipe 2" C/R Posco S/. 60.00
Drain Pipe 3" x 3 meters PV. S/. 15.40
Pipe 2" Embone Posco S/. 45.00
Drain Pipe 4" x 3 meters TF. S/. 12.90
Pipe 3" Embone x 6 meters S/. 78.00
Centrifug. Pump Humboldt 1 HP S/. 289.90
Pipe 4" Embone x 6 meters S/. 125.00
Pump Pedrollo CPM 650 1.5 hp S/. 1,249.90
Pump Rotobomba 0.5 hp S/. 240.00
Pump Pedrollo CPM 660 2 hp S/. 1,329.90
Tank ROTOPLAS. 1100 L S/. 395.00
PE Tank 10,000 L ROTOPLAS. S/. 7,337.90
Wire KG Nº 16 & 8 S/. 4.00
PE Tank 10,000 L ETERNIT BLACK S/. 6,499.90
Multiples Cuva S.A.C Chincha
Contact: Elmer Cuba Nextel: 422*2104 / Cellphone: (956) 596 191 [email protected]
Address: Jr. Lima Nº 345, Pueblo Nuevo
Product Description Price (Soles) Rebar 3/8" Fe x meters S/. 16.00 Rebar 1/2" Fe x meters S/. 26.50 Cement Sol 42.5 KGS S/. 18.00 Pipe 2" PVC SAP - C10 x 5 meters S/. 39.00 Pipe 3" PVC SAP - C10 x 5 meters S/. 85.00 Pipe 4" PVC SAP - C10 x 5 meters S/. 120.00 Wire Black KG Nº 16 & 8 S/. 4.30 Nail KG 2", 2.5", 3", 4" S/. 4.30
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 54 of 58
Appendix F – Maps GIS map of Viña Vieja
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 55 of 58
Geological map, legend on bottom
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 56 of 58
Topographic map of Viña Vieja.
Document 525 - Pre-Implementation Report Rev. 05-2012
EWB - University of Texas at San Antonio
Viña Vieja, Peru
Viña Vieja Water System
Page 57 of 58
Conceptual system design map