document 00 00 11 addendum no. 1 thursday june 22, … · 16. drawing m106: add a second rpz...

47
Addendum No. 1 SIOUX 142164 00 00 11 - 1 DOCUMENT 00 00 11 ADDENDUM NO. 1 Thursday June 22, 2017 Foundation Park Lift Station, LS 243 City of Sioux Falls, SD Sealed bids shall be received by Engineering, 2 nd Floor, City Hall, 224 W. 9 th St., P.O. Box 7402, Sioux Falls, SD 57117-7402, not later than 2:00 PM, Thursday, June 29, 2017. Bid Request No. 17-1032 CIP No. 23029 SRF No. C461232-37 SEH No. SIOUX 142164 From: Short Elliott Hendrickson Inc. 3535 Vadnais Center Drive Saint Paul, MN 55110-5196 To: Document Holders DOCUMENT HOLDERS on the above-named project are hereby notified that this document shall be appended to, take precedence over and become part of the original bidding documents for this work. Bids submitted for the construction of this work shall conform to this document. This addendum consists of 47 page(s) including attached Pre-Bid Conference Minutes and Pre-Bid Conference Sign In Sheet. General 1. ADD Pre-Bid Conference Minutes with questions, responses, and sign in sheet, in Attachment 1 hereto. Changes to Specifications: 2. REPLACE Wage Decision SD170034 MOD 2 Revised 4/21/2017 with Wage Decision SD170034 Dated 6/9/2017, in Attachment 2 hereto. 3. ADD the following Approved Substitution Requests (in accordance with Spec Section 01 25 13), in Attachment 3 hereto: a. KSB – Sump Pumps b. Sweeney Controls – System Integrator c. W R Meadows – Moisture Barrier 4. ADD the following to Spec Section 01 11 00, Paragraph 1.04 C: The Foundation Park sanitary sewer collection system is being constructed by Metro Construction Inc. Also, coordinate with the Marion Road (from I-90 north) paving contractor, Asphalt Surfacing Co. 5. Spec Section 01 23 00, Paragraph 1.01 B. 1: CHANGE “Instructions to Bidders: Section 15” to “Instructions to Bidders: Sections 8 and 9”. 6. ADD the following to Spec Section 01 77 00, Paragraph 1.02 B. 3. a: “Note that the project is located outside of the city limits of Sioux Falls. Therefore, the Contractor shall obtain all required county building permits and inspections. The City of Sioux Falls will perform all applicable building inspections as well.” 7. Spec Section 22 11 16, Paragraph 3.11 A. 2. D: CHANGE “24 hours” to “16 hours”. 8. DELETE Spec Section 23 09 93, Paragraphs 1.07 F. 1. and 1.07 F. 2. Combustible Gas Detectors shall be MSA X 5000 Series Gas Monitors as specified in Spec Section 40 90 00, Paragraph 2.12.

Upload: vukhanh

Post on 13-May-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Addendum No. 1 SIOUX 142164 00 00 11 - 1

DOCUMENT 00 00 11

ADDENDUM NO. 1 Thursday June 22, 2017

Foundation Park Lift Station, LS 243

City of Sioux Falls, SD

Sealed bids shall be received by Engineering, 2nd Floor, City Hall, 224 W. 9th St., P.O. Box 7402, Sioux Falls, SD 57117-7402, not later than 2:00 PM, Thursday, June 29, 2017.

Bid Request No. 17-1032

CIP No. 23029 SRF No. C461232-37

SEH No. SIOUX 142164 From: Short Elliott Hendrickson Inc.

3535 Vadnais Center Drive Saint Paul, MN 55110-5196

To: Document Holders DOCUMENT HOLDERS on the above-named project are hereby notified that this document shall be appended to, take precedence over and become part of the original bidding documents for this work. Bids submitted for the construction of this work shall conform to this document.

This addendum consists of 47 page(s) including attached Pre-Bid Conference Minutes and Pre-Bid Conference Sign In Sheet.

General

1. ADD Pre-Bid Conference Minutes with questions, responses, and sign in sheet, in Attachment 1 hereto.

Changes to Specifications:

2. REPLACE Wage Decision SD170034 MOD 2 Revised 4/21/2017 with Wage Decision SD170034 Dated 6/9/2017, in Attachment 2 hereto.

3. ADD the following Approved Substitution Requests (in accordance with Spec Section 01 25 13), in Attachment 3 hereto:

a. KSB – Sump Pumps

b. Sweeney Controls – System Integrator

c. W R Meadows – Moisture Barrier

4. ADD the following to Spec Section 01 11 00, Paragraph 1.04 C: The Foundation Park sanitary sewer collection system is being constructed by Metro Construction Inc. Also, coordinate with the Marion Road (from I-90 north) paving contractor, Asphalt Surfacing Co.

5. Spec Section 01 23 00, Paragraph 1.01 B. 1: CHANGE “Instructions to Bidders: Section 15” to “Instructions to Bidders: Sections 8 and 9”.

6. ADD the following to Spec Section 01 77 00, Paragraph 1.02 B. 3. a: “Note that the project is located outside of the city limits of Sioux Falls. Therefore, the Contractor shall obtain all required county building permits and inspections. The City of Sioux Falls will perform all applicable building inspections as well.”

7. Spec Section 22 11 16, Paragraph 3.11 A. 2. D: CHANGE “24 hours” to “16 hours”.

8. DELETE Spec Section 23 09 93, Paragraphs 1.07 F. 1. and 1.07 F. 2. Combustible Gas Detectors shall be MSA X 5000 Series Gas Monitors as specified in Spec Section 40 90 00, Paragraph 2.12.

Addendum No. 1 00 00 11 - 2 SIOUX 142164

9. Spec Section 26 05 33: ADD Paragraph 2.04 J: All Electrical Boxes, Enclosures, and Cabinets located in the Wet Wells, Pump Room, and Service Area shall be 316 stainless steel.

10. Spec Section 35 20 20, Schedule 1: CHANGE all sluice gate materials of construction from “cast iron” to “stainless steel” as specified in Section 35 20 20.

11. Spec Section 40 23 40: DELETE Paragraph 2.01 C. ADD new Paragraph 2.01 C. as follows: “Pipe hangers and supports shall be fabricated from 316 stainless steel”.

12. Spec Section 40 90 00:

a. Paragraph 2.04 A: REPLACE “Allen-Bradley Panelview+ 6 Compact 2711PC-T12W21D8S” with “Allen-Bradley Panelview+ 2711P-T12W21D8S”.

b. Paragraph 2.04 A. 1: REPLACE “10-inch” with “12-inch”.

c. ADD Paragraph 2.04 A. 4. As follows: “Provide Pump Room OIT with NEMA 4X stainless steel enclosure.”

d. Paragraph 2.06 B: REPLACE “600V RMS, 55 amp rating.” with “Rated as required for each individual application. Provide SPDT relays on terminal blocks as required for isolation”.

e. Appendix C, PLC Input/Output List, Page 40 90 00-22: MOVE Combustible Gas Detectors CGD-1-1,-2 from the “PLC Discrete Inputs” list to the “PLC Analog Inputs” list.

f. Appendix C, PLC Input/Output List, Page 40 90 00-22: ADD analog signals from wet well level transmitters (LIT-1-3-1,-2,-3) to the “PLC Analog Inputs” list.

Changes to Drawings:

13. Drawing M100, General Mechanical Note 5, CHANGE “Minnesota” to “South Dakota”.

14. Drawing M101, Key Note 1: CHANGE “304 stainless steel” to “316 stainless steel”.

15. Drawing M102, Key Note 1: CHANGE “304 stainless steel” to “316 stainless steel”.

16. Drawing M106: ADD a second RPZ backflow preventer, 1-1/2” BFP-2 on potable water line to potable use points. Provide isolation ball valves (upstream and downstream), strainer, and drain line for each backflow preventer as shown on Detail 1, Sheet M107.

17. Drawing M109, Ground Level Water Riser Diagram: ADD a second RPZ backflow preventer, 1-1/2” BFP-2 on potable water line to potable use points. Provide isolation ball valves (upstream and downstream), strainer, and drain line for each backflow preventer as shown on Detail 1, Sheet M107.

18. Drawing E103: ADD Key Note 7, pointing at Fiber Panel: "Provide dedicated receptacle in Fiber Panel. Provide 3/4" conduit, 2#12, #12G circuit from panel LVP. See panel schedule on sheet E104."

19. Drawing E104: ADD a 20A/120V circuit breaker to panel "LVP" to provide power for Fiber Panel receptacle. Make circuit #18. On the Electrical One-Line Diagram, ADD 3/4" conduit, 2#14 circuit running from each disconnect to each VFD, for all three 100 HP Raw Wastewater Pumps. Connect as shown per schematics.

20. Drawing E105:

a. PLC One-Line Diagram: ADD analog signals from wet well level transmitters (LIT-1-3-1,-2,-3) to Main PLC Control Panel.

b. Network Diagram: ADD to Main PLC Control Panel Modbus Communications modules to accept Modbus signals from emergency generator and automatic transfer switch. Provide Prosoft Model No. PLX31-EIP-MBS EtherNet/IP to Modbus Serial communication gateways OR Prosoft Model No. PLX31-EIP-MBTCP EtherNet/IP to Modbus TCP/IP communication gateways, as appropriate.

21. Drawing E106, Detail 1 (P-1-5-1 Pump Schematic): CHANGE “18-pulse” VFD to “6-pulse VFD with passive harmonic filter”.

Addendum No. 1 SIOUX 142164 00 00 11 - 3

22. Drawing I101, Wiring Interface 2: CHANGE wiring of analog signals from wet well level transmitters (LIT-1-3-1,-2,-3) to Main PLC Control Panel, instead of to individual Pump VFD’s (VFD-1-5-1,-2,-3).

Note: Receipt of this Addendum No. 1 (dated Thursday June 22, 2017) shall be acknowledged on the PROPOSAL FORM. Failure to do so may subject Bidder to disqualification.

END OF ADDENDUM

ATTACHMENT 1 PRE-BID CONFERENCE

MINUTES AND SIGN-IN SHEET

Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-5196

SEH is an equal opportunity employer | www.sehinc.com | 651.490.2000 | 800.325.2055 | 651.490.2150 fax

PRE-BID CONFERENCE MINUTES

Re: Foundation Park Lift Station, LS No. 243 Date of Meeting: June 19, 2017 Sioux Falls, South Dakota Project Mgr.: Al Bush, PE Time of Meeting: 10:30 am SEH No.: SIOUX 142164 Location of Meeting: Water Reclamation Facility

Administration Building

I. Please Sign In – See Attendance List

The purpose of the meeting is to introduce the project and also provide an opportunity to view the site. General questions will be entertained but detailed design questions should be submitted in writing to the Engineer and will be answered by addendum.

II. Introductions - Project Personnel Al Bush, PE, SEH Project Manager

Al Murra, PE, SEH Civil Designer

Brad Ludens, PE, City of Sioux Falls Principal Engineer

Ryan Johnson, PE, City of Sioux Falls Principal Engineer

Paul Faris, City of Sioux Falls Sewer Collection Supervisor

Joe Van Schepen, City of Sioux Falls Controls Technician

III. Bid Date/Time The bid time and date is set for 2:00 p.m. Thursday, June 29, 2017.

IV. Permits A. A Building permit is required.

B. Contractor to secure other permits that may apply.

V. Construction Schedule (Proposal Form)

The bidder will substantially complete all base bid work required such that the Lift Station is operable by August 31, 2018. Bidder further agrees to pay as liquidated damages the amount specified in the City of Sioux Falls’ current edition of the General Conditions for Public Improvements, Section 8.10, for each working day thereafter all base bid work that remains uncompleted beyond the substantial completion date. All remaining work not required to be completed by the substantial completion date and punchlist items will be completed by the final completion date of October 31, 2018. Bidder further agrees to pay as liquidated damages the amount specified in the City of Sioux Falls’ current edition of the General Conditions for Public Improvements, Section 8.10, for each working day all remaining work is uncompleted beyond the final completion date.

Pre-Bid Conference MINUTES Page 2

VI. Instructions to Bidders & City of Sioux Falls current edition of General Conditions

Bidder to review General Conditions along with Instruction to Bidders.

VII. Proposal Form Base Bid – Foundation Park Lift Station Deduct Alternate No. 1 Bid - Raw Wastewater Pump No. 3. Deduct Raw Wastewater Pump No. 3 and associated piping, valves, VFD, instrumentation, and wiring.

VIII. Additional Forms to be submitted with Bid Form A. Submit the following with the Bid:

1. Bid Bond or Certified Check 2. Bidder’s Activity Report (BAR) 3. DBE Subcontractor Solicitation Information (DBE – 6) 4. DBE Form A or Form B 5. Debar-2 form 6. American Iron and Steel Certification (AIS-21 and AIS-22)

B. Within 10 calendar days of the bid opening submit:

1. DBE Subcontractor Performance Form (EPA Form 6100-3) 2. DBE Subcontractor Utilization Form (EPA Form 6100-4)

C. Within 10 calendar days after bid award, the successful general Contractor shall submit:

1. DBE Notification of Intent to Sub-contract (Form A-1) 2. Contractor and Subcontractor Activity Report (Form H) 3. DOL Notification Form (EEO-7)

IX. Funding A. This project will be partially funded by the State Revolving Fund and will be subject to the

requirements of such, including: Executive Order 11246 (Equal Employment Opportunity) as amended, Executive Order 11518 and 11625 as amended, and Executive Order 12138, MBE/WBE requirements, & Elimination of Segregated Facilities Certification.

B. MBE/WBE – Certification of payments due 30 days following completion of project.

C. Wage determination: Davis Bacon and Related Acts apply to this project. All provisions relative to those acts must be met.

D. SRF American Iron and Steel requirements apply.

X. Project Review

Summary of Work (Section 01 11 00):

A. Description of the Project: Foundation Park Lift Station, LS No. 243, 47196 260th Street, Sioux Falls, SD 57107.

B. Concurrent Work: City will award separate construction contracts for lift station force mains (bids in July), Foundation Park sanitary sewer collection system and other utilities (Metro Construction Co.). Also, coordinate with the Marion Road Paving Contractor, Asphalt Surfacing Co.

Pre-Bid Conference MINUTES Page 3 XI. Testing During Construction

A. Owner is responsible for hiring an independent testing laboratory to perform tests called for in specification (Section 01 45 10), except as otherwise noted.

B. Piping pressure testing by Contractor (Section 40 23 50).

XII. Contractor Questions

A. Questions during Pre-Bid Conference:

Question: Regarding American Iron and Steel (AIS) Certification, are waivers required to be submitted before the bid?

Answer: According to Page AIS-21 of the AIS Certification Form, documentation regarding any non-American made iron or steel proposed for the project must be submitted with the bid. The waiver process for any non-American made iron or steel must be initiated prior to the bid, as stated in Paragraph 5. b. of the form. Waivers that have not been initiated before the bid date and submitted with the bids will not be considered. Refer to Pages AIS-1 through AIS-20 of the SRF General Conditions for more detailed information.

Question: Will a backflow preventer be required on the building potable water supply, as well as the non-potable water supply?

Answer: Yes, to be addressed as a part of Addendum No. 1.

Question: Should piping supports and hangers be zinc plated or stainless steel?

Answer: Stainless steel.

Question: Who will be installing the Foundation Park sanitary sewer collection system?

Answer: Metro Construction Inc. Also, coordinate with the Marion Road Paving Contractor, Asphalt Surfacing Co.

B. Questions after Pre-Bid Conference:

Question: Is there retainage and if so how much?

Answer: The City of Sioux Falls does not withhold any retainage from construction progress payments.

Question: On the Bidder’s Activity Report are you wanting the subcontractors/suppliers that we are using in our bid on that form or everyone that bids us?

Answer: Regarding the Bidder's Activity Report, according to 49 CFR Part 26.11(c)(2): ""You must obtain the following information about DBE and non-DBE contractors and sub contractors who seek to work on your Federally-assisted contracts”.

Question: Are there any specific bid bond forms that the City of Sioux Falls prefers?

Answer: The City of Sioux Falls does not have a standard bid bond form. Provide bid security in accordance with Paragraph 4 of the Instructions to Bidders.

Pre-Bid Conference MINUTES Page 4

Question: Is the fiber cable being brought to the building by someone else or where does this come from? If so, will it be left long enough to go from the handhole to the fiber panel. If so, will they also handle the terminations?

Answer: In accordance with Drawing C106, all fiber optic cable will be provided by others (meaning the force main contractor, which will bid in July). The intent is for enough fiber optic to reach the lift station electrical room plus 50 feet of slack, which will be coiled in a junction box at the contract interface point where indicated. The Lift Station contractor will pull the coiled fiber optic cable provided by others to the lift station electrical room and make terminations as shown on the Network Diagram on Drawing E105.

Question: According to drawing E105, the fiber panel will also house the fiber to Ethernet switch. Will we also need a 120V receptacle in or near the panel for switch power?

Answer: Yes, provide need a receptacle inside the panel to feed a power strip.

Question: On the disconnect switches for the 100 HP VFD Raw Wastewater Pumps 1, 2, and 3 do you want auxillary switches installed in them to prevent VFD start while disconnect is in the off position. If so, will these wire back to the VFD or to the PLC panel?

Answer: Contacts are shown on Drawing E106 – Detail 1 (P-1-5-1 Pump Schematic). Provide wiring from disconnects back to VFD’s. This will be addressed as a part of Addendum No. 1.

Question: Can cables shown on the electrical one-line and PLC one-line diagrams be combined or do you want a conduit for each as detailed on E104 and E105? For example, the Ethernet cable from VFD to PLC shows a 1” conduit for each, but all 3 would fit in one 1” conduit piped from PLC and jumpered between each VFD?

Answer: Circuits can be combined, but need to keep each type separate (power, digital, analog, ect), If you are adding the Ethernet cables together, this conduit should be increased to 1-1/2" at a minimum. Still need to follow fill requirement for Ethernet cables.

XIII. Site Investigation

In accordance with the project specifications and City of Sioux Falls General Conditions, the Bidder is allowed, and encouraged, to investigate the site prior to bidding.

ATTACHMENT 2 WAGE DECISION SD170034

DATED 6/9/2017

General Decision Number: SD170034 06/09/2017 SD34

Superseded General Decision Number: SD20160034

State: South Dakota

Construction Type: Building

County: Minnehaha County in South Dakota.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017 1 01/27/2017 2 02/10/2017 3 04/21/2017 4 06/02/2017 5 06/09/2017

* BRSD0001-004 05/01/2017

Rates Fringes

BRICKLAYER.......................$ 35.83 2.52 ---------------------------------------------------------------- CARP0587-002 06/01/2016

Rates Fringes

CARPENTER (Drywall Finishing/Taping, Drywall Hanging and Metal Stud Installation Only)...............$ 28.48 9.91 ---------------------------------------------------------------- ELEC0426-002 06/01/2017

Rates Fringes

ELECTRICIAN......................$ 27.94 1.5%+11.26 ---------------------------------------------------------------- ELEV0033-004 01/01/2017

Rates Fringes

ELEVATOR MECHANIC................$ 42.13 31.585

FOOTNOTES: 8 Paid Holidays: New Year's Day; Memorial Day;Independence Day; Labor Day; Veteran's Day; Thanksgiving Day; the Day after Thanksgiving & Christmas

Page 1 of 5

6/9/2017https://www.wdol.gov/wdol/scafiles/davisbacon/SD34.dvb?v=5

Day.

---------------------------------------------------------------- PLUM0300-015 05/01/2016

Rates Fringes

PIPEFITTER.......................$ 27.26 12.90 ---------------------------------------------------------------- SUSD2012-025 08/21/2014

Rates Fringes

CARPENTER (Excludes Drywall Finishing/Taping, Drywall Hanging and Metal Stud Installation)....................$ 17.61 8.53

CEMENT MASON/CONCRETE FINISHER...$ 17.54 2.65

INSULATOR - MECHANICAL (Duct, Pipe & Mechanical System Insulation)...............$ 15.20 0.00

IRONWORKER, STRUCTURAL...........$ 23.91 12.05

LABORER: Common or General......$ 16.21 2.21

LABORER: Mason Tender - Brick...$ 20.96 0.00

OPERATOR: Backhoe/Excavator/Trackhoe.......$ 17.90 0.00

PAINTER (Brush, Roller and Spray), Excludes Drywall Finishing/Taping.................$ 23.61 17.90

PLUMBER..........................$ 21.12 9.00

ROOFER...........................$ 13.82 1.34

SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 19.28 7.63

TRUCK DRIVER: Dump Truck........$ 15.06 1.10 ----------------------------------------------------------------

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

================================================================

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic

Page 2 of 5

6/9/2017https://www.wdol.gov/wdol/scafiles/davisbacon/SD34.dvb?v=5

violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

----------------------------------------------------------------

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those

Page 3 of 5

6/9/2017https://www.wdol.gov/wdol/scafiles/davisbacon/SD34.dvb?v=5

classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

----------------------------------------------------------------

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination * a survey underlying a wage determination * a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

Page 4 of 5

6/9/2017https://www.wdol.gov/wdol/scafiles/davisbacon/SD34.dvb?v=5

U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

================================================================

END OF GENERAL DECISION

Page 5 of 5

6/9/2017https://www.wdol.gov/wdol/scafiles/davisbacon/SD34.dvb?v=5

ATTACHMENT 3 APPROVED SUBSTITUTION REQUESTS

 

 

WR MEADOWS ALTERNATE REQUEST

Project: Foundation Park Lift Station

To: Alan Bush Date: 6/13/2017 Short Elliot Hendrickson

Re: Alternate Approval:

AIR-SHIELD™ LSR Specification Title: Liquid Membrane Air/Vapor and Liquid Moisture Barrier

Section: 072700 Page: 4 Section: E

SPECIFICED PRODUCTS PROPOSED SUBSTITUTION. Name of Product: AIR-SHIELD™ LSR Manufacture: W.R. MEADOWS, INC.  

The Undersigned certifies: Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product. Same maintenance service and source of replacement parts, as applicable, is available. Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule. Proposed substitution does not affect dimensions and functional clearances.  

Firm: W.R. MEADOWS Submitted by: Taylor Wodzinski / Mike Krulas Address: 300 Industrial Dr. E-mail: [email protected] Hampshire, IL Telephone: 847-214-2100 / 612-704-0145

60140-0338

Substitution approved - Make submittals in accordance with Specification Section 01 25 00 Substitution Procedures. Substitution approved as noted - Make submittals in accordance with Specification Section 01 25 00 Substitution Procedures. Substitution rejected - Use specified materials. Substitution Request received too late - Use specified materials.

Signed by: Date: 6/13/2017

 

   

As noted above, Product submitted for consideration shall be considered as APPROVED as equal or 

better material compared to specified product.  Pursuant to specifications, provide  shop drawing 

submittal  for approval. 

T. Schuette, Architectural Technician    2017.06.13        

DESCRIPTION AIR-SHIELD LSR (liquid synthetic rubber) is an asphalt-free, single-component, synthetic rubber based liquid air/vapor and liquid moisture barrier. AIR-SHIELD LSR cures to form a tough, seamless, elastomeric membrane, which exhibits excellent resistance to air and moisture transmission.

USES AIR-SHIELD LSR has been specifically formulated to act as an air/vapor and liquid moisture barrier within the building envelope. It may be applied to most common surfaces and integrated into various wall systems. AIR-SHIELD LSR is suitable for both new construction and restoration.

FEATURES/BENEFITS • Non-asphaltic – designed to meet stringent fire code

requirements. • Low permeability - prevents the transmission of air and

inhibits moisture and vapor from passing through porous building materials.

• Highly flexible - bridges cracks, which may form in the substrate.

• Environmentally compatible - AIR-SHIELD LSR is non-toxic.

• User friendly – single-component, water-based technology allows for simple, safe application and easy cleanup.

• Liquid applied - simplifies detailing and assures a monolithic, seamless membrane when applied to a rough or smooth surface.

• Sprayable - with appropriately configured airless spray equipment - low application costs.

• Excellent adhesion - remains firmly bonded to the substrate, even when applied over damp surfaces.

• Low VOC content (<100 g/L). Produces no harmful odors.

• Compatible with asphalt-based emulsion products. • UV resistant – membrane can be left exposed up to four

months.

PACKAGING 5 Gallon (18.93 L) Pails 55 Gallon (208.20 L) Drums

COVERAGE Application Rate 17 - 22 ft.2/gal. (1.59 – 2.05 m2/3.8 L) Wet Film Thickness 75 mils

Cured Film Thickness 40 mils (1 mm) Coverage dependant on substrate type, weather, and application conditions. SHELF LIFE When stored indoors in original, unopened containers at temperatures between 40° - 90° F (4° - 32° C), optimum performance and best use is obtained within one year of date of manufacture. SPECIFICATIONS • ASTM E 84, Class A • Exceeds ABAA maximum material air permeance requirements

when tested in accordance with ASTM E2178. • Complies with all current federal, state, and local maximum

allowable VOC requirements, including U.S. EPA, LADCO, SCAQMD, and OTC.

TECHNICAL DATA Solids Content, %: 56

VOC Content, g/L 56 Color: Sprays Pink

Dries to Desert Tan Flexibility @ -26° C (-15° F),

PASS (ASTM C 836): Tensile Strength (ASTM D 412), PSI 250

Elongation (ASTM D 412), %: 700 Water Vapor Permeance

0.1 (ASTM E 96, Procedure B) Perms:

Service Temperature: Not to exceed 175° F (80° C)

Nail Sealability (ASTM D 1970): Pass Storage Temperature of AIR-SHIELD LSR 40° - 90° F (4° - 32° C) Air/Substrate Temperature (At Time of Application): >20° F (-6.7° C)

NO. 724-C MAY 2015 (Supersedes February 2014)

CONTINUED ON REVERSE SIDE…

AIR-SHIELD TM LSR Liquid Membrane Air/Vapor and Liquid Moisture Barrier

MasterFormat: 07 27 26

Air Leakage Test Method ASTM E 2178-01 ASTM E 2357 Pressure: 75 Pa (1.57 lb/ft.2) 75 Pa (1.57 lb/ft.²) ABAA Requirements, maximum:

0.004 cfm/ft.2 (0.02 L/S/M2)

0.04 cfm/ft.² (0.2 L/S/M²)

AIR-SHIELD LSR Results:

<0.004 cfm/ft.2

(<0.02 L/S/M2) <0.04 cfm/ft.² (<0.2 L/S/M²)

*Independent test available upon request AIR-SHIELD LSR may be used in NFPA 285 complying wall assemblies. Contact W. R. MEADOWS for further information. APPLICATION Surface Preparation … All surfaces must be clean (free of all coatings and curing compounds), structurally sound, frost-free, and relatively smooth. Prepare substrate per manufacturer’s instruction prior to application of membrane. Exterior Sheathing Panels … Exterior sheathing panels are to be installed and fastened per manufacturer’s recommendation. For detailed application information, see INSTALLATION INSTRUCTIONS: JOINT TREATMENT OF EXTERIOR SHEATHING PANELS available at www.wrmeadows.com. Rough Openings and Protrusions … Refer to AIR-SHIELD ROUGH OPENINGS INSTALLATION GUIDELINES document available at www.wrmeadows.com for recommendations on protrusions and rough openings. Concrete Masonry Units … Before applying AIR-SHIELD LSR to CMU surfaces, patch all cracks, protrusions, small voids, offsets, details, irregularities, and small deformities with MEADOW-PATCH® 5 or MEADOW-PATCH 20 from W. R. MEADOWS at least two hours before application.

Application Method … AIR-SHIELD LSR may be applied by spraying or a 3/4" (19.1 mm) minimum nap roller. (For recommendations on spray equipment, consult W. R. MEADOWS technical staff.) AIR-SHIELD LSR may be sprayed on at the minimum coverage rate of approximately 17 - 22 ft.2/gal. (0.42 - 0.54 m2/L) (75 mils wet) (40 mils dry). Note: For roller applications or during periods of extremely hot weather, two coats may be necessary if the material begins to slump. Apply second coat after first coat has completely dried, approximately one to two hours after first coat. Frequently inspect surface area with a wet mil gauge to ensure consistent thickness. Work material well into any fluted rib forming indentations. Porous masonry block walls may require additional coats to obtain desired thickness. Curing and Drying ... Allow material to dry at air and surface temperatures of 20° F (-6.7° C) or higher. Curing times will be affected by relative humidity, temperature and airflow. The following times are given for average conditions

and standard thicknesses. Actual times may differ, depending on specific conditions present on job at time of application. It is recommended that AIR-SHIELD LSR be allowed to air dry to a tack-free film before application of specified insulation. Maximum exposure time for AIR-SHIELD LSR is four months. Tack-free film: 2 hours Full cure: 48 hours

Cleanup … Uncured AIR-SHIELD LSR cleans up easily while wet with water. Cured material is best removed by xylene or by mechanical means.

PRECAUTIONS AIR-SHIELD LSR is not designed to perform as a permanently exposed membrane. Maximum UV exposure period for membrane is four months. Keep containers tightly sealed. KEEP FROM FREEZING. Do not apply AIR-SHIELD LSR if rainfall or snow is forecast within 12 hours.

TECHNICAL ASSISTANCE Please contact W. R. MEADOWS for specific details and/or data not outlined in this literature. Technical assistance, from design to product application, is available upon request. LEED INFORMATION May help contribute to LEED credits: EA Credit 1: Optimize Energy Performance IEQ Credit 3.1: Construction Indoor Air

Quality Management Plan - During Construction

IEQ Credit 7.1: Thermal Comfort - Design MR Credit 2: Construction Waste

Management MR Credit 5: Regional Materials For most recent data sheet, further LEED information, and MSDS, visit www.wrmeadows.com.

PAGE 2 … AIR-SHIELD LSR #724-C … MAY 2015

© W. R. MEADOWS 2002 7/07-4M

© W. R. MEADOWS 2015 04/15-1M

X

X

Control Systems for the Water and Wastewater IndustriesDESIGN | IMPLEMENTATION | INTEGRATION | MAINTENANCE

Our Commitment to ExcellenceAs an automation control systems integrator, we have been overcoming the challenges of water and wastewater facilities for more than 60 years. As your partner, we work with you to design, implement and integrate innovative solutions that meet your unique needs. Our commitment is to deliver cost effective, results based solutions that give you operational efficiency, reliability, ease of use and peace of mind. We appreciate the value of long-term business relationships, and have earned the trust of an extensive list of repeat customers who recognize the value of our service and quality workmanship.

QUALITY. INNOVATION. SERVICE.What We Bring

• More than 60 years experience in designing, implementing, integrating and maintaining control systems.

• Specialized knowledge in control systems for water treatment and distribution, and wastewater collection and treatment facilities.

• Personal attention backed by industry experience, through every stage of your project.

• Quality control panel design that’s second to none; manufactured and tested in our certified facility, our systems meet the strictest quality standards for material and workmanship.

• Accurate and thorough documentation for each system, including electrical drawings, physical layouts and operation manuals.

• Qualified service technicians, available 24 hours a day – 7 days a week.

FACILITY OPERATION EXPERTISE• Water Treatment Plants

• Waste Water Treatment Plants

• Storm Water Lift Stations

• Sanitary Lift Stations

• Rural Water Systems

• Water Tower Level Controls

• Pressure Booster Stations

• Water Irrigation

• Golf Course Pump Stations

Control Automation

Project

Specifications &

Requirements

System Design

Training, Technical Support

Start-Up and Commissioning

Panel, Equipment

Design & Fabrication

“I have the utmost confidence in Sweeney Controls Company to supply the expertise it takes to make a user friendly product for years of reliable service.”

- Eric Hanson, City of West Fargo ND

HELPING YOU CONTROL YOUR BUSINESSWhether you are designing a new facility, expanding for additional demands, or upgrading existing systems — Sweeney Controls Company can help you automate it to your unique needs.

Gain Visibility to All Operations Levels, pressure, influent flow, effluent flow, alarms, load factors, costs and demand – you have a lot to think about. We help you gain access to the information you need to monitor the flow of your operations through system automation and monitoring that is designed specifically to meet your needs.

Manage Remote StationsWith limited staff and time, it can be challenging to monitor your entire operation. Through reliable communication methods, your water towers, lift stations and booster stations can be monitored via a central control system. Now, you can optimize your facilities and save time with accurate information.

Minimize Downtime and Maintain Quality of Water Supply You need to quickly diagnose concerns and get fast response times. We give you the tools and information you need to adjust processes as needed.

Manage Regulatory ComplianceGenerate state and custom reports automatically. Manage ever-changing water treatment requirements. Flexible report solutions help you analyze your operations with ease.

Ease of Maintenance and SupportProper documentation for the control system and detailed drawings allow you to quickly troubleshoot, plan for maintenance needs and train staff.

MAKING IT ALL WORK TOGETHERWorking with you every step of the way, our professional project managers, systems architects, control system specialists and field service technicians provide custom engineered solutions that meet your unique needs and exceed your expectations.

CAPABILITIESProgrammable Logic Controls (PLC) ProgrammingThe PLC is the heart of the automation. Rest assured we are well-equipped to keep your systems processes flowing smoothly. Our staff is fluent in the following hardware.

• Rockwell Automation/Allen-Bradley

• General Electric

• Koyo/Automation Direct

• Mitsubishi

• Schneider/Modicon/Telemecanique

Supervisory Control and Data Acquisition (SCADA)SCADA is the art of gathering and displaying information from disparate systems over various networks. Our integration services allow you to monitor trends, manage alarms and track process data remotely.

Communication SystemsA reliable communication network brings the process information directly to your control room. We’ll help you choose the right network for your needs:

• Licensed & Spread spectrum Radio

• Phone Line

• Ethernet

• DeviceNet

• ControlNet

• Profibus

• HART

Human Machine Interface (HMI) Software ConfigurationUsing HMI technology, we provide graphical, animated views of process data, alarm management, data logging and trending via platforms including:

• Rockwell Software (Allen Bradley) – FactoryTalk View

• Wonderware – InTouch

• General Electric – Proficy

• Intellution – Fix

• C-more

MISSION

Provide innovative control systems and integration solutions for our clients with honesty,

integrity and superior customer service.

OUR COMPANY PROFILE

Founded in 1952, Sweeney Controls Company began as a control panel builder.

Today we offer comprehensive design, fabrication, integration, commissioning and

maintenance service for products ranging from relay based panels to completely

integrated control systems. A stable, growing company, we provide integration

services for water, wastewater, food, beverage and material handling uses.

We are committed to understanding our customers’ needs to develop a solution that

meets and exceeds their expectations. With a staff of field service technicians, control

systems specialist and project managers, our services include consulting, project

management, PLC programming, HMI programming, control panel construction and

on-site system commissioning. Sweeney Controls Company’s manufacturing facility

is UL 508A and UL 698A certified.

Overcoming unique customer challenges for over 60 years, we have implemented

innovative solutions using our knowledge and expertise to provide our customers

with the cost-effective, results based solutions they are looking for. Looking to

the future, we offer the promise of advancement in technologies, innovation and

continued excellence in customer service.

Contact UsWe would love the opportunity to discuss your next control system project or become part of your support team. Feel free to contact us for more information about our services.

234 28th St. S., Fargo, ND 58103701-232-3644 | 800-743-6536 | Fax: 701-232-3635

[email protected]

Affiliates System Integrators For

“My experience with Sweeney Controls started about 25 years ago, as we use their controls in our lift stations and water treatment plant. They provide high quality panels and control equipment and the service they provide is second to none. Their techs are very good at what they do. I would recommend Sweeney Controls for all your needs.” - Ken Sanstead, Utilities Supervisor City, Hoffman MN

Sweeney Controls Company Profile

Founded in 1952, Sweeney Controls Company is a privately owned company and began as a control panel builder. Today, we have grown to provide full automation controls system integration services including comprehensive design, fabrication, integration, commissioning, and maintenance services for products ranging from relay based panels to completely integrated control systems. A stable, growing company, we provide integration services for municipal water, wastewater, and other process industries.

As a control systems integrator, we are committed to understanding our customers’ needs to develop a custom solution that meets and exceeds their expectations. With a staff of field service technicians, control systems architects, control system specialists and project managers, we are able to offer consulting, project management, design, programming for PLC, SCADA, and HMI systems, panel construction, communication systems, on-site system commissioning and training.

Solving Industry Challenges Our specialized knowledge in control systems for water and wastewater facilities has been gained by delivering over 500 projects to municipality and rural water systems across a five state region.

Our commitment is to deliver cost effective, results based solutions that give clients the reliability, ease of use and operational efficiency they need.

Facility Experience

• Water Treatment Plants • Wastewater Treatment Plants • Storm Water Lift Stations • Sanitary Lift Stations • Rural Water Systems

• Water Tower Level Controls • Pressure Booster Stations • Water Irrigation • Pump Station

Industry Memberships We are a proud member of several industry associations, together we can share, learn and solve the challenges facing the industry

OUR MISSION

Provide innovative control systems and

integration solutions for our clients with

honesty, integrity and superior

customer service.

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

What We Bring Personal attention through every stage of your project.

• Proven project methodology that ensures adequate planning, monitoring, proactive communication and progress reviews to ensure project success

• Our clients receive a custom solution that solves their unique needs, we achieve that through working together to define and design a solution.

• Accurate and thorough documentation for each system, including electrical drawings, physical layouts and operation manuals

• Quality control panel design that’s second to none; manufactured and tested in our certified facility, our systems meet the strictest quality standards for material and workmanship

Locations Sweeney Controls has a staff of 24 team members, our headquarters is in Fargo ND along with a field service office in Sioux Falls, SD.

Customer Satisfaction We appreciate the value of long-term business relationships, and have earned the trust of an extensive list of repeat clients who recognize the value of our service and quality workmanship.

Testing & Field Service We provide factory acceptance testing (FAT) in-house before hardware is shipped to client. Field start up assistance is provided to ensure successful on-site commissioning of your system.

Warranties Our clients receive warranties as quoted and our commitment to service.

Technical Support Rely on our 24/7 or on-site technical support service to ensure that your system is operational at all times. This requires no special contract and is a service we provide to all of our clients. Thanks to our friendly, knowledgeable staff and remote diagnostics capabilities, a phone call is usually all it takes to get your system up and running. Training With our on-site training and detailed Operation Manuals, our trained professionals ensure your complete understanding of your system and its capabilities.

Specifications &

Requirements

System Design

Panel Equipment Design &

Fabrication

Start-Up and Commissioning

Training, Technical Support Services Control

Automation Project

234 28th Street S Fargo ND 58103

T. 701-232-3644 F. 701-232-3635

www.sweeneycontrols.com

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com Page 1 of 1

Certification proves that your integrator has met or exceeded CSIA Best Practices in nine key areas:

General Management Supporting Activities

Project Management Quality Assurance Management

Financial Management Service and Support

Human Resources Management System Development Lifecycle

Marketing, Business Development, and Sales Management

 

234 28th Street S  Fargo ND 58103  |  T.  701.232.3644  |  F. 701.232.3635  |  www.sweeneycontrols.com 

Project:WaterTreatmentPlantSCADASystemDetroit Lakes, MN 

Contact:Mr. Mike Lahlum 

(218) 846‐7102 

EngineerofRecord: Mr. Jon Pratt 

Ulteig 

(218) 847‐5607 

ProjectComplete:October, 2010 

NotesofInterest: System consists of Water Treatment Plant, four wells and one water tower 

4.3 MGD gravity filtration facility 

Gravity filter control system by Sweeney Controls 

Fiber optic communication to wells and water tower 

Designing, manufacturing and programming done by Sweeney Controls Company 

SystemComponents:PLC  Allen Bradley CompactlLogix & MicroLogix Operator Interface  Automation Direct C‐More HMI Software  Rockwell Automation FactoryTalk View SE Alarm Dialing Software  Specter Instruments WIN‐911 Motor Control Centers  Square D Variable Frequency Drives  Square D Altivar 61 Flow Meters  Rosemount 8700 Series 

 

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Project: Wastewater Treatment Plant SCADA System Brookings, SD

Contact: Mr. Scott Minor

(605) 693-3287

Engineer of Record: Mr. DelRon Peters

HDR Engineering – Sioux Falls

(605) 977-7745

Project Complete: April, 2016

Notes of Interest: System consists of a pretreatment area, primary clarifiers, aeration basin, final clarifiers, digesters,

tertiary filters, UV disinfection area and remote office monitoring location

10 MGD Wastewater Treatment Facility

Sludge source to destination transfer from Primary Clarifiers to Digesters

Multiple PID loops for multiple level and flow processes

Fiber redundant ring network with 6 PLC’s and managed Allen Bradley network switches

Designing, manufacturing and programming done by Sweeney Controls Company

System Components: PLC Allen Bradley CompactLogix Operator Interface Allen Bradley Panelview Plus HMI Software FactoryTalk View SE Variable Frequency Drives Square D and Allen Bradley Flow Meters Rosemount and FloDar

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Project: Wastewater Treatment Plant SCADA System Milbank, SD

Contact: Mr. Dick Poppen

(605) 692-6342

Engineer of Record: Mr. Dan Johnson

Banner Associates

(605) 692-6342

Project Complete: March, 2004

April, 2009 – Facility Improvements

November, 2012 – Facility

Improvements

Notes of Interest: System consists of a pretreatment area, bio filter, aeration basin, digesters, disinfection area and remote

office monitoring location

4 MGD Wastewater Treatment Facility

PID loop for maintaining dissolved oxygen content

Designing, manufacturing and programming done by Sweeney Controls Company

System Components: PLC Allen Bradley SLC 5/05 Operator Interface Allen Bradley Panelview Plus HMI Software FactoryTalk View SE Variable Frequency Drives General Electric Flow Meters Endress & Hauser

 

234 28th Street S  Fargo ND 58103  |  T.  701.232.3644  |  F. 701.232.3635  |  www.sweeneycontrols.com 

Project:EffluentReuseFacilitySCADASystemFargo, ND 

Contact:Mr. Jeff Hoff 

(701) 241‐1454 

EngineerofRecord: Mr. Kent Ritterman 

Moore Engineering 

(701) 282‐4692 

ProjectComplete:May, 2009 

NotesofInterest: System consists of  RO Skids, Memcor CP filtration system, CIP system, chemical system, generator and 

one reservoir 

1.7 MGD Reverse Osmosis facility 

Treats Effluent from the Wastewater Treatment Plant and is pumped to an Ethanol plant 30 miles away 

in Casselton, ND 

Integration of control system with Siemens/US Filter Reverse Osmosis and CP systems 

Integration into Allen Bradley DeviceNet Intellicenter 

Designing, manufacturing, programming and FCC licensing done by Sweeney Controls Company 

SystemComponents:PLC  Allen Bradley ControlLogix Operator Interface  Advantech 17” Industrial Touchscreen HMI Software  Wonderware InTouch Radio Modems  Microwave Data Systems MDS4710 Motor Control Centers  Allen Bradley IntelliCenter Variable Frequency Drives  Allen Bradley PowerFlex 700 Flow Meters  Rosemount 8700 Series 

 

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Project: Water Treatment Plant SCADA System Madison, SD

Contact: Mr. Rick Nighbert (605) 256-7527

Engineer of Record: Mr. Dave Odens Banner Associates (605) 692-6342

Project Complete: June, 2010

Notes of Interest: System consists of Water Treatment Plant, high service pump station, eleven wells and two water

towers 4.0 MGD lime and gravity filtration facility Gravity filter and slaker control system by Sweeney Controls Ethernet radio system that can be used for remote access Designing, manufacturing, and programming done by Sweeney Controls Company

System Components: PLC Allen Bradley CompactLogix, SLC 500 & MicroLogix Operator Interface Allen Bradley PanelView Plus HMI Software Rockwell Automation FactoryTalk View SE Radio Modems Microwave Data Systems iNet 900 Motor Control Centers Square D Variable Frequency Drives Square D Altivar 61 Flow Meters Rosemount 8700 Series

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Project: Potable, Sanitary and Storm Water SCADA System West Fargo, ND

Contact: Mr. Ryan James

(701) 433-5400

Engineer of Record: Mr. Kevin Bucholz

Moore Engineering

(701) 282-4692

Project Complete: Started 1998 and frequently expanded

Notes of Interest: System currently consists of thirty-five sanitary lift stations, thirty-two storm lift stations, eight well sites,

four water towers and two master sites. System is continuously being expanding

Intricate potable well alternation system to best preserve to aquifer

Sweeney Controls is the Control Systems Integrator for the City of West Fargo

Designing, manufacturing, programming and FCC licensing done by Sweeney Controls Company

System Components: PLC Allen Bradley ControlLogix, SLC 500 & MicroLogix Operator Interface Allen Bradley PanelView Plus HMI Software Rockwell Automation FactoryTalk View SE Distributed Radio Modems Microwave Data Systems MDS4710 & SD04 Motor Control Centers Allen Bradley Variable Frequency Drives Allen Bradley Flow Meters Rosemount 8700 Series

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Joe Sweeney - President

Joe has 21 years of experience dedicated to automation and control system integration. He attended North Dakota State University for three and a half years where he studied Electrical Engineering. Joe began his career at Sweeney Controls Company as a control panel technician, progressed to control engineer and to senior project manager. Joe now serves as the president of Sweeney Controls Company and provides leadership and direction for the Company's vision, growth and long term goals.

Joe enjoys spending his free time with his wife and three children, working on cars, riding off-road and street motorcycles. He also likes to spend time riding snowmobiles in the mountains and waterskiing on Minnesota lakes. PLC Programming Experience With:

• Rockwell Automation/Allen Bradley • General Electric • Koyo Series/Automation Direct

• Modicon/Telemacanique/Schneider Electric

• Mitsubishi

HMI Software Programming Experience With:

• Rockwell Automation Software • C-more/Automation Direct

• Iconics • Wonder Ware InTouch

Communication Network Experience With:

• Wireless Telemetry Systems • Phone Line Telemetry Systems • Ethernet Systems

• DeviceNet™ • DH+ Network • DH-485 Network

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Steven Crumby - PMP Project Manager

Steven brings 8 years of project management skills and knowledge with him to ensure efficiency and success for every team member and project he works with. Steven has a Bachelor of Science in Information Technology from the University of Mary in Bismarck, ND. He spent 6 years in the Air Force as an Avionics Technician and currently holds a PMP certification through PMI. As a Project Manager, Steven is responsible for project contract review, project specification review, project scheduling and execution. Steven spends his free time fishing the lakes of Minnesota, watching sporting events and relaxing with his family.

Professional Experience: • 6.5 years Fire Alarm, Security, Access Control, Nurse Call, Intercom projects • Management of large fire alarm, security card access, CCTV, nurse call and intrusion detection

systems projects • 6 years United States Air Force Active Duty Avionics Technician • C-130 Avionics Flight Line Technician, Ramstein, AFB Germany • KC-135 Avionics Flight Line Technician, Grand Forks, AFB Grand Forks, ND. • 18 months in Healthcare IT projects as the Red River Valley Technology Expansion Project

Director

Education:

• Bachelor of Science, Management Information Systems, Information Technology – University of Mary

• Associates of Science, Electronics/Avionics - Community College of the Air Force

Professional Certifications:

• PMP Certification #1681634

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Josh Schoenberg – P.E. Systems Architect

Josh has 10 years’ experience in designing and implementing control systems for Sweeney Controls Company. He graduated in Electrical Engineering from North Dakota State University and continued his education receiving his professional engineering license.

As a System Architect, Josh is responsible for engineering functions that include system design and functional description as well as mentoring control system specialists.

As the son of a family owned construction business in Minot, ND, Josh learned early on his strong work ethics and family values. An area of special interest is process control systems.

PLC Programming Experience With:

• Rockwell Automation/Allen Bradley • Koyo Series/Automation Direct • Schneider Electric

HMI Software Programming Experience With:

• Automation Direct C-more • GE Proficy • Rockwell Software

• Schneider Electric Citect SCADA • Wonderware InTouch

Network Communication Experience With:

• Wireless telemetry systems • Phone line telemetry systems • Ethernet • DeviceNet™ • ControlNet™

• DH-485 Network • DH+ Network • Profibus • Modbus RTU & TCP

Education

• B.S. Electrical Engineering, North Dakota State University – Fargo ND • Professional Engineer – ND PE-6877

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Adam Lawler - P.E. Control Systems Specialist

Adam has over 7 years of experience working with controls and HMI systems. He attended North Dakota State University and is a graduate in Electrical Engineering. Adam pursued and obtained his Professional Engineering license from the state of North Dakota. As a Control Systems Specialist for Sweeney Controls, Adam is responsible for project engineering functions that include programming PLC, HMI, and reporting systems.

Adam spends his free time golfing, hunting, gaming and enjoys time back home on his family’s farm.

PLC Programming Experience With:

• Rockwell Automation/Allen Bradley Logix, MicroLogix & SLC series • Koyo 05 Series/Automation Direct

HMI Software Programming Experience With:

• Automation Direct C-more • Rockwell Software RSView Studio

• Rockwell Software RSView 32 • Wonderware InTouch

Network Communication Experience With:

• Radio telemetry systems • Ethernet • DeviceNet™ • DH-485 Network • DH+ Network

Education

• B.S. Electrical Engineering, North Dakota State University – Fargo ND • Professional Engineer – ND PE-8412

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Bau Tran - Control Systems Specialist

Bau has over 21 years of experience working with controls and HMI systems. He attended North Dakota State University and is a graduate of the Masters Program in Electrical & Electronics Engineering. As a Control System Specialist for Sweeney Controls Company Bau is responsible for project engineering functions that include programming PLC, HMI, and reporting systems.

Bau likes to spend his free time with family as well as reading. PLC Programming Experience With:

• General Electric • Allen Bradley • Horner

• VBA • Maple Systems

HMI Software Experience With:

• Rockwell Automation • General Electric

Further Experience With:

• DC/AC Motors and Drives • Electro-mechanical motion control systems • Troubleshooting, calibrating and PID tuning • SCADA system design

Education:

• Master of Science: Electrical & Electronics Engineering, North Dakota State University o Thesis- Robust Stability of a Set of Parameters of Discrete-Time Systems

• B.S. Electrical & Electronics Engineering, North Dakota State University – Fargo, ND

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Ted Schlepuetz - Technical Database Developer

Ted brings 11 years of Information Systems and Software Development to the organization. Having worked for a large food manufacturer, he has an extensive background in analyzing business processes and developing reporting needs based on data captured through automation. Ted also has achieved a SIX SIGMA black belt certification. He and his family live on a farm near Jamestown ND and enjoy the outdoors.

Professional Experience: • 11 years of experience in Systems Support and

Development, and Information Systems

Computer software programming experience with:

• VBA

• T-SQL

• Microsoft SQL Server

• Microsoft Visual Basic Studio

• Factory Talk View SE V7, V8

• Factory Talk View ME

• OISSoft PI Historian

• Rockwell Historian

• InfinityQS – Statistical Process Control

Communication Network and Hardware Experience:

• Wireless telemetry systems • Ethernet

• Cisco RV042 • Cat 6 Networking Cables

Education:

• Bachelor of Arts – Computer Science, University of Jamestown – Jamestown ND

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Jason Stewart - Field Service Technician

Jason has 4 years’ experience working with control systems and is a graduate in Construction Electricity from Minnesota State Community and Technical College. Jason started his career troubleshooting and repairing electrical, mechanical and hydraulic systems on automated machines in the oil fields of North Dakota. Jason started as a Control Panel Technician for Sweeney Controls Company and was responsible for the fabrication and construction of control panels. He was promoted to Field Service Technician and is now responsible for the interfacing, testing, startup and training for process control systems.

When Jason isn’t spending time with his wife and four daughters, he enjoys home remodeling projects and training with Brazilian Jiu Jitsu. Panel manufacturing experience with:

• Fabrication and assembling of Panels • Interpreting electrical schematics

• Factory Acceptance Tests

PLC programming experience with:

• Allen Bradley MicroLogix series • Allen Bradley SLC series

• Koyo • IDEC MicroSmart

Education

• Construction Electricity Degree, Minnesota State Community and Technical College, Moorhead MN

234 28th Street S Fargo ND 58103 | T. 701.232.3644 | F. 701.232.3635 | www.sweeneycontrols.com

Berny Berndt - CAD Technician

Berny has 10 years of experience with control system building and design. He has a degree in Electronics Technology from the North Dakota State College of Science. Berny started his career as a control panel technician where he excelled and then progressed to a CAD Technician. He is responsible for project drawings, interfacing, testing, startup and training for various control systems.

In his free time Berny enjoy spending time with his wife and two children, fishing and running half-marathons in local events.

PLC Programming Experience With:

• Rockwell Automation/Allen Bradley

HMI Software Programming Experience With:

• Rockwell Software

Design and Engineering Software Experience With:

• Bentley promis•e • Bentley MicroStation • AutoCAD®

Communication System Experience With:

• Phone line telemetry systems • Ethernet

Education

• Electronics Technology Degree, North Dakota State College of Science, Wahpeton, ND