dn63pedn100 dn63pe dn6pe - pages - home - …mrwa.com.au/documents/standards/mrwawsa03/300...
TRANSCRIPT
![Page 1: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/1.jpg)
MRWA WATER SUPPLY STANDARDS
VERSION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEW
YVW
DATENAME APPROVED:
CWW
SEW
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
R. JAGGERR. JAGGER
B. VANOSC. PAXMANJ.TOMASI
R. CARRUTHERS
D. ERREYFIRST DRAFT1 CP / JT / RJ D. O'DONOVAN
01/09/1601/09/1601/09/16
01/09/1601/09/1601/09/16
01/05/16
2016
MRWA-W-300A2
SHUT OFF BLOCK DESIGNAPPERTUNANCE PLACEMENT
CWW, SEW or YVW 200m120m200m
WATERAGENCY
RESIDENTIAL COMMERCIALINDUSTRIAL
TABLE 300-C: MAXIMUM HYDRANT SPACINGS
50m
HIGH DENSITYURBAN
500m
RURAL
CFA
MFB CWWSEW or YVW 120m
120m90m
PROCESS STEP DESCRIPTIONSTEP
AB
CDE
F
J
K
TABLE 300-A: RETICULATION SHUT OFF BLOCK (SOB) DESIGN PROCESS
Identify where the distance between neighboring hydrants is excessive.Place as few additional hydrants as possible in the SOB to ensure that thedistance between hydrants is not excessive.
· additional hydrants not required for DW network where dual water.· locate adjacent to valve(s) where practical as a first priority.· ensure the distance between hydrants is approximately equi-distant
as a second priority.· all of these hydrants shall be designated "Council Owned".
Identify all SOBs containing too many property service connections.Place as few valves as possible in these SOBs to meet this requirement,locating valves:· to create SOBs of approximately equal size.· at un-valved offtakes (if present).· at high points where practicable, especially where there is a significant
elevation change in the SOB (ie: > 2m).
Valve the smaller main (if > DN100) adjacent to tapers / reducers
Valve all offtakes from > DN300 mains at the tee
KEYREFERENCESSECTION 8.2.7.2
TABLE 300-C
TABLE 300-B
Valve all offtakes from < DN280 mains at the splay.CWW & SEW do not require valves on DN100 offtakes from DN100 mains
SECTION 8.2.7.3
SECTION 8.2.7.5
Designate the ownership of these hydrants:· where a hydrant could be removed and the maximum spacing
distance still be met, this hydrant shall be marked as "Water Agencyowned".
· all other hydrants shall be marked as "Council Owned".
< DN150 25 (YVW), 40 (CWW & SEW)100N/A
WATER MAINSIZE (DN)
NUMBER OF PROPERTIESCONNECTED
TABLE 300-B: MAXIMUM SOB SIZES
750m
MAXIMUMVALVE SPACING
6
MAX NUMBERVALVES OF SOB
200-300375
300 / 500m *
1000m450
N/A1500m525 / 600
675 / 750
1150m
1900mN/A> 750 5000m #
N/AN/A
* 300 in urban areas, 500 in rural areas.# Valve spacing for larger mains shall be decided in consultation with the Water Agency.
Identify all SOBs containing a length between valves in excess of the limit.Place additional valves as required to reduce the distance to < the maximum.Identify all SOBs containing too many shut off valves.Place additional valves centrally as required to reduce the number of shut offvalves.
TABLE 300-B
TABLE 300-B
G
Place a hydrant adjacent to a valve in each SOB (typically the highest valveunless the SOB includes a dead end hydrant).Placement at the highest valve is especially important where there is asignificant rise in the SOB.(ie: >2m difference in elevation).
H
Place a hydrant at the lowest point in the SOB where the SOB has adifference in elevation >5m
NOTES Regarding FIGURE 300-A to C:1. Example is suitable for:
· DW only networks, and· NDW networks, however· For DW network of a dual water system, all hydrants installed as
part of step "L" shall not be installed.2. Colours denote unique SOB areas.3. Uncoloured lots are part of SOBs which extend off the example area
and so are incomplete.4. Letter markings next to valves and hydrants correspond to the Step ID
in Table 300-A.5. Detailed placement of hydrants (ie: offset / inline etc) shall be as per
MRWA-W-304.6. All connections within a court bowl should be counted in with
connections on the adjacent network main, (ie: where practical, courtbowl SOBs shall include some network main).
8
10
Valve just after transition to sub-mainsValve offtakes to court bowls where there are more than 10 connectionsbetween the intersection and the valve inserted as part of Step D
L
M
NDW ORDW ONLY
DW OF DUALWATER
MRWA-W-108
I Place a hydrant at the end of DN100 mains in court bowls and dead ends.Ensure fire fighting hydrant is within 60m of the furthest kerb of a dead end rd.
MRWA-W-108
Will bemostlyCouncilOwned
Will probablyall be WaterAgencyOwned
The front of every property shall be no more than the maximum hydrant spacing / 2 from the nearest hydrant.
FIGURE 300-A: SOB DESIGN EXAMPLE - RELEVANT TO CWW (RESIDENTIAL MFB AREAS)(40 lot SOB and max 120m between hydrants shown)
RESERVE
RESERVE
RESERVE
DN30
0DN
375
DN150A
A
C
B
B
B
B
B
B
D
D
D
C
D
60
59
58
57
56
55
54
53
5251
61
5049
B
B
SCALE: 1mm = 2m at A3
II & J
E
DN10
0< D
N6PE
DN100
DN10
0DN
100
DN10
0
DN100
DN10
0
D N 1 0 0
< DN63PE
< DN63PE
< DN63PE
< DN63PE
< DN6PE
DN100
DN100
DN100DN150
DN100
DN10
0
DN100
DN10
0
DN10
0
RESERVE
K
J FF
K
J
J
FJ
F
F
FI & J
F
JJ
H
L
L
L
LL
L
I & J
L
L
L
2 PUBLISHED FIRST ISSUE 1/12/16 CP / JT / RJ
![Page 2: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/2.jpg)
FIGURE 300-C: SOB DESIGN EXAMPLE - RELEVANT TO ALL YVW RESIDENTIAL AREAS(25 lot SOB and max 200m between hydrants shown)
RESERVE
RESERVE
RESERVE
DN30
0DN
375
DN150A
A
C
B
B
B
B
B
D
D
D
C
D
60
59
58
57
56
55
54
53
5251
61
5049
B
B
SCALE: 1mm = 2m at A3
II & J
E
DN10
0< D
N6PE
DN100
DN10
0DN
100
DN10
0
DN100
DN10
0
D N 1 0 0
< DN63PE
< DN63PE
< DN63PE
< DN63PE
< DN63PE
DN100
DN100
DN100DN150
DN100
DN10
0
DN100
MRWA WATER SUPPLY STANDARDS
VERSION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEW
YVW
DATENAME APPROVED:
CWW
SEW
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
R. JAGGERB. VANOS
B. VANOSC. PAXMANJ.TOMASI
R. CARRUTHERS
D. ERREYFIRST DRAFT1 CP / JT / RJ D. O'DONOVAN
01/09/1601/09/1601/09/16
01/09/1601/09/1601/09/16
01/05/16
2016
MRWA-W-300B2
SHUT OFF BLOCK DESIGN EXAMPLESAPPERTUNANCE PLACEMENT
DN10
0
DN10
0
RESERVE
L J
KF
F
FJ
K
J
J
F
FJ
L
FFFI & J
F
I & J
F
J F & HJ
I & J
FIGURE 300-B: SOB DESIGN EXAMPLE - RELEVANT TO CWW (RESIDENTIAL CFA AREAS) AND ALLSEW RESIDENTIAL AREAS (40 lot SOB and max 200m between hydrants shown)
RESERVE
RESERVE
RESERVE
DN30
0DN
375
DN150
60
59
58
57
56
55
54
53
5251
61
5049
DN10
0< D
N6PE
DN100
DN10
0DN
100
DN10
0
DN100
DN10
0
DN 1 0 0
< DN63PE
< DN63PE
< DN63PE
< DN63PE
< DN63PE
DN100
DN100
DN100DN150
DN100
DN10
0
DN100
DN10
0
DN10
0
RESERVE
A
A
C
B
B
B
B
B
D
D
D
C
D
B
B
II & J
E
K
J FF
K
J
J
FJ
F
F
FI & J
F
JJ
H
L
L
I & J
This standard should beread in conjunction with
MRWA-S-300A.
I
B BI
I
2 PUBLISHED FIRST ISSUE 1/12/16 CP / JT / RJ
![Page 3: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/3.jpg)
K E R B L I N E
K E R B L I N E
K E R B L I N E
P R O P E R T Y L I N E
K E R B L I N E
K E R B L I N E
K E R B L I N E
VALVE OR HYDRANT
FENCE
1800±500
ROAD CL
MAIN
MAIN
MAIN
HYDRANTCATS EYE
FOOTPATH
HYDRANT PATCH
100 to 150DEVELOPEDPROPERTY
FOOTPATH
FIGURE 300-A: OPEN RESERVES OR ROADS WITHOUT KERBS
FIGURE 300-B: PAVED ROAD (ABUTTED BY URBAN PRIVATE PROPERTY)
FIGURE 300-C: PAVED ROAD (ABUTTED BY PUBLIC OPEN SPACE OR RURAL LAND)
GENERAL NOTES:1. Valves shall be marked differently according to whether they are deemed to part of a "valve cluster" as defined in Table 300-A.2. All hydrants (whether temporary, DW, NDW) require the same marking as indicated in this drawing unless the hydrant is on an irrigation only or less reliable supply.3. When temporary end of line hydrants are removed, all markings shall be removed concurrently.4. When a main is renewed or decommissioned, all redundant markings shall be completed removed.5. 40mm washouts shall be marked as valves.6. Type, location, fixture arrangements and orientation of markers to be in accordance with MRWA-W-301.7. Refer to water agency product catalogues for details of marking products.8. Locate marker posts at right angles to the main with post facing towards the valve or hydrant.9. Where there is a valve cluster of the same network (DW or NDW) only one marker post is required at the valve cluster.10. Where there is a valve cluster containing both NDW and DW valves, a single DW and a single NDW post will be required.11. The construction contractor is to install these markings.
FIGURE 300-D: TYPICAL POSITIONING OF VALVE AND HYDRANT MARKERS
DEVELOPED AREA
NDW WATER MAIN
NON-
DRIN
KING
(NDW
) WAT
ER
DRIN
KING
(W)
WAT
ER M
AIN
DRINKING (W)WATER MAIN
DEVELOPED AREARURAL AREA
RURALAREA URBAN P R O P E R T Y L I N E
LEGEND: HYDRANT MARKER POSTVALVE MARKER POSTHYDRANT MARKING CATS EYE
HYDRANT MARKING REFLECTIVE PATCHVALVE MARKING DISC
VALVE MARKER DISC (WHEN NO KERB)REFER NOTE 4.
ROAD CL
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-300NOT TO SCALE
2012 3
VALVE AND HYDRANT MARKINGARRANGEMENTS
MARKER POST(TRIANGLE AT TOP TO
POINT TOWARDSFITTING)
KERB VALVEMARKER DISC
HYDRANTCATS EYE
100 to 150KERB VALVEMARKER DISC
MARKER POST (TRIANGLEAT TOP TO POINTTOWARDS FITTING)
200±100
URBAN PROPERTY LINEPO
ST
ROAD
PAT
CH
HYDRANT NOT CLUSTEREDVALVES (PER VALVE)
OPEN RESERVES OR ROADSWITHOUT KERBS
PAVED ROAD (ABUTTED BY URBANPRIVATE PROPERTY)
PAVED ROAD (ABUTTING PUBLIC OPENSPACE OR RURAL PRIVATE PROPERTY)
Valve Cluster Definition:More than 2 valves in close proximity, ie:· 3 valves within a 6m diameter circle· 4 valves within a 8m diameter circle· 5 valves within a 10m diameter circle, etc or,· As directed by the water agency(this is irrespective of whether valves are DW or NDW)
A G E A C BRELEVANT MRWA -W-301 FIGURE
ROAD
CAT
S EY
E(B
LUE)
KERB
DIS
C
TABLE 300-A: HYDRANT & VALVE MARKING REQUIREMENTS
COVE
R /
SURR
OUND
DIS
C
CLUSTEREDVALVES
A C B
C
B
A
RELE
VANT
MRW
A-W
-300
FIG
URE
POST
POST
(1 P
OST
FOR
EACH
DW
/ND
W C
LUST
ER)
COVE
R / S
URRO
UND
DISC
(1 P
ER V
ALVE
)
COLO
URED
PAT
CH(1
PER
VAL
VE)
COLO
URED
PATC
H
C
MAIN
HYDRANTOR VALVE
HYDRANT PATCH
MAIN
HYDRANTOR VALVE
![Page 4: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/4.jpg)
FIGURE 301-D: MARKER INSTALLATIONS EXAMPLES (PLAN VIEW)
REFERFIG 301-H
BACK
OF
KERB
FACE
OF
KERB
LIP O
F KE
RB
MARKERPOST
HYDRANT
100 to 150
1300
± 20
0 (RE
SERV
ES &
RUR
AL)
350 ±
50>5
0
>250
FIGURE 301-A: MARKER POST INSTALLATION (SECTION VIEW)
H (FOR HYDRANT) or V (FOR VALVE)POINT THE POST TRIANGLE TO THESURFACE FITTING AND ROAD
· BLACK (FOR OPERATIONALHYDRANTS)
· RED (FOR FIRE FIGHTINGHYDRANTS) or
· DARK BLUE (FOR VALVE)
REFLECTOR DISC (BLUE)
WHITE (FOR DW) orPURPLE (FOR NDW)
POST AS PER WATER AGENCYPRODUCT CATALOGUE
BOLT OR PIN
CEMENTSTABILIZEDSOIL (5%)
DISC EXAMPLE: NONDRINKING WATER
BYPASS VALVE
DISC EXAMPLE: DRINKING WATERCROSS CONNECTION VALVE
LETTER(S) VALVE TYPEDIVIDE VALVE (FOR USE IN MAINS > DN375)OFFTAKE OR RETICULATION VALVESCOUR CONTROL VALVEHYDRANT CONTROL VALVEAIR VALVE CONTROL VALVE
BYPASS VALVECROSS CONNECTION VALVEXC
BP
AVHV
SCVV
DV
WO WASHOUT
TABLE 301-C: VALVE DISC LETTERING
FIGURE 301-H: ROAD PAVEMENT HYDRANT REFLECTIVE PATCHNOTES on Figure 301-H:A. Use preformed thermoplastic road marking product,
white in colour as per AS4049.2 or as per wateragency products catalogue.A.A. Use wire brush to thoroughly clean surface
before application.A.B. Bond using gas torch until well adhered.
Apply as per manufacturers instructions.
B. Patch may be applied using vicroads approved markingpaint.
C. Point triangle to hydrant (if hydrant in road, pointtriangle towards road center).
D. Patches are not required at Acceptance of Works.E. Patches are required at End of Defects.
250 ±
20
450 ± 50
NOTES Regarding Figure 301-B:A. Colour patch to be preformed
thermoplastic road marking product as perAS4049.2.
B. The substrate shall be thoroughly cleanedor roughened and chemically treated asrequired to achieve a strong bond betweenthe marking and substrate.
C. Ensure divide line between colours isorientated correctly to indicate the size /status of the main on either side of thevalve.
FIGURE 301-G: SPINDLE CAP FOR VALVESNOTES on Figure 301-G:1. Required for normally shut valves (red)2. Required for dialysis patient valves (blue).
All dialysis shut off block valves shall be capped and havean attached waterproof label with the customer's address.
150
Ø75
PAINTED AREA
REFERFIG 301-A
REFER FIG 301-E
KERB
4.8mm OD,50mm LONG
PIN WITH KINK
CONCRETE
REFERFIG 301-F
FIGURE 301-F: CATS EYE
CATS EYEBOND
NOTES on Figure 301-E:1. Attach to ground using hotmelt marker adhesive
(bituminous) or two pack epoxy adhesive as perAS1906.3.
2. Apply as per manufacturers instructions.Roughen surface with cold chisel & use wire brushto thoroughly clean surface before application.
3. Cats eyes are not required at Acceptance of Works.4. Cats eyes are required at End of Defects.
CENT
RE O
F RO
AD
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-301NOT TO SCALE
2012 3
VALVE AND HYDRANT MARKING DETAILS(CWW and SEW ONLY)
VALVEMARKERDISC
WHITE
FOOT
PATH
200 ± 100
WATER
VALVE
1. For fastening into concrete (kerb or surround): use 316 SSconcrete pins, pre-drilled with 5mm min masonry bit.
2. For fastening to ductile iron, drill hole, tap thread and fasten withpan head M6, 25mm (1 inch) long 316 SS metal thread screws.
3. For fastening to plastic covers or surrounds, grind off plasticprotrusions in area to which disc is to be fitted, drill through coverand attach disc with 316 SS, M6, 60mm long cup head bolts &316 SS nuts and washers.
CONCRETE FASTENING PIN DETAIL
KERB FASTENING POSITION
XCW
W
BPTRAFFICABLE VALVE SURROUNDS
PLASTIC VALVE SURROUNDS
ROAD
PAV
EMEN
T
BACK
OF
KERB
FACE
OF
KERB
LIP O
F KE
RB
CENT
RE O
F RO
AD
FOOT
PATH
FACETRIANGLEPATCHTOWARDSHYDRANT
100 to 150
LIP OF KERB
CONCRETESURROUND
VALVEMARKER
DISC
WATER
VALVE
FOR LONE VALVES WHERE THERE IS A KERB
NON TRAFFICABLE VALVES IN CLUSTERS OR WHEN NO KERB
FOR TRAFFICABLE VALVES IN CLUSTERS OR WHEN NO KERB
TRAFFICABLE VALVES INNATURE STRIPS
TRAFFICABLE VALVES INPAVED AREAS (NO SURROUND)
VALVEMARKER DISC
FIGURE 301-E: VALVE MARKER DISCS
BACK
OF
KERB
FACE
OF
KERB
LIP O
F KE
RB
FOOT
PATH
VALVE WITHCOLOUREDPATCH (REFERFIG 301-B)
HYDRANT IN URBAN ROADWAYHYDRANT
VALVE IN ROADWAYABUTTING OPEN SPACE
MARKERPOST
REFER FIG301-A
200 ± 100
HYDRANT IN ROADWAYABUTTING OPEN SPACE
FIRE SERVICEOFFTAKE
NORMALLY OPENVALVE ON > DN250MAIN
NORMALLYCLOSED VALVE
DIALYSISSOB VALVE
SYSTEMCONNECTED TO< DN250 MAINPLAIN (NO COLOUR)
LILAC LID
TABLE 301-B: HYDRANT / FLUSHING BOX COLOURS
DW
NDWRED TOP
LILAC BELOW RED TOP
LEVEL
NDW
DWBELOW GROUND
BELOW GROUNDABOVE GROUND
ABOVE GROUND
CONNECTED TO>DN250 MAIN
YELLOW
12 LILAC & 12 YELLOWBLACK TOP
LILAC BELOW BLACK TOP
ROAD PAVEMENT
FIGURE 301-B: VALVE SURROUND COLOURING
ABOVE GROUND HYDRANTS TO BE MARKED AS PER FIGURE 305-C.
FV FROG MOUTH CONTROL VALVE
NOTES Regarding Fastening Arrangements:
Ø40mm andMIN 2mmTHICK 316 SS
Ø6.5mm
Lettering to bestamped oretched at least0.03mm deep
DO NOT FIT DISCS TO BLUE STONE
EXTENT OFMARKING
Where necessary, recycled water may beindicated with a separate dedicated disc.
DRINKINGWATERVALVES
NORMALLY OPEN< DN250 VALVE OFF> DN250 MAIN
NORMALLY OPENVALVE ON > DN250MAIN
NORMALLYCLOSED VALVE
NON-DRINKINGWATERVALVES
NORMALLY OPEN< DN250 VALVE OFF> DN250 MAIN
NORMALLYOPEN VALVE ON< DN250 MAIN
OTHERVALVES
NORMALLYOPEN VALVE ON< DN250 MAIN
70
Lilac (if NDW)
Plain (nocolour)
FIGURE 301-C: HYDRANT / FLUSHING BOX COLOURS
Hydrantconnected
to main< DN250
DW Hydrant onmain < DN250
DW Hydrant on /off main >DN250
NDW Hydrant onmain < DN250
NDW Hydrant onmain >DN250
70
Hydrantconnected
to main>DN250
ABOVE GROUND HYDRANTS BELOW GROUND HYDRANTS
If RectangularCover
THESE MARKINGS TO BEINSTALLED BY CONSTRUCTIONCONTRACTOR
Hydrants offset from >DN250mains or located on valve bypasspipework shall be marked Black
![Page 5: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/5.jpg)
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-302
NOT TO SCALE
2012 3
VALVE SURFACE ARRANGEMENTSTRAFFICABLE & NON-TRAFFICABLE AREAS
R. JAGGER 04/04/2011D. TOLENTINO 04/04/2011
X C. RIVETTE 04/04/12X C.PAXMAN 04/04/12X K.DAWSON 04/04/12
X R.CARRUTHERS 04/04/12X G.REYNOLDS 04/04/12X A.COSHAM 04/04/12
1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 R.JAGGER
2 PUBLISHED FIRST ISSUE 04/04/12 R.JAGGER
3 NEW FIGURE 302-C 1/12/16 CP / JT / RJ
FSL
DIRECTION OF TRAFFIC
HINGE
PAVEMENT
GRADE
> 400
GRADE
SV
WATER
VALVE
> 400
S.V
Valve markingsrefer MRWA-W-301
Plasticsurround
Valve markingsrefer MRWA-W-301
2 of 300 x 300 x 50Approved hardwood, recycledplastic or concrete support
Valve markingsrefer MRWA-W-301
TRAFFICABLE
5030
>50>30
Minimum covercompacted crushedrock over lip of cover
Minimum cover of naturestrip top soil
Minimum covercompacted crushedrock over lip of cover
Minimum cover of naturestrip top soil
NOTES on Valves in Nature Strips & Open Reserves:A. Where the main is aligned close to the kerb such that non trafficable covers (which are larger)
would clash with the kerb, trafficable covers shall be used (which are substantially smaller).B. Non trafficable covers shall not be cut down in size.C. Trafficable covers with concrete surrounds shall be used in nature strips where vehicles are
likely to regularly mount the kerb (Refer Figure 302-C). This includes :C.A. All valves within industrial or commercial driveways,C.B. All valves within 5m of any road intersections.C.C. All valves within 2m of residential driveways.
D. Elevate cover up to 75 above finished surface level and grade soil away to reduce waterentry into the shroud.
E. Hinge covers to close in the direction of fall of land.F. When the valve is part of a valve cluster or there is no kerb, the valve surround shall be fitted
with an identification disc. Refer MRWA-W-300 & 301 for details.
NOTES on Valves in Road Pavement:a. All surface box covers and frames to be in accordance with AS 3996: class D loading -
trafficable and the water agency product catalogue.b. Hinge covers to close in the direction of traffic.c. When the valve is part of a valve cluster or there is no kerb, the valve cover shall be
fitted with an identification disc. Refer MRWA-W-300 & 301 for details.d. No surround is required for valve covers in road pavement.
GENERAL NOTES:1. Provide a level compacted crushed rock foundation for all covers, surrounds and shrouds
(as shown) to the embedment material.Crushed rock to be in accordance with MRWA-W-201.
2. A gap is required between the cover and shroud. The shroud shall be cut at 90 degrees.The shroud shall not contact the cover & be kept > 20 mm clear.
3. Install cover, frame, spindle sleeve, shroud and shroud support so that no loading istransmitted to the valve or pipe.
4. Install an extension spindle where distance from the surface to valve spindle exceeds 350.Fix false spindle to the valve spindle using supplied grub screw where practical.
5. Refer to MRWA-W-205A for stop valve installation details.6. For non-drinking water valves, the words / letters: "non-drinking water" or "NDW" or "RW"
shall be cast / stamped/ embossed or engraved into the cover or lid.7. For drinking water valves, the words / letters: "Water" or "W" or "Drinking Water" shall be
cast / stamped/ embossed or engraved into the cover or lid.8. For valve marking arrangements refer to MRWA-W-300 & 301.9. Refer to water agency products catalogue for authorized materials.
150 / 225 DWV whitePVC SN4 pipe shroud
100 to 350
FSL
PAVEMENTValve markingsrefer MRWA-W-301
150 / 225 DWV whitePVC SN4 pipe shroud
100 to 350
FIGURE 302- A: TYPE A TRAFFICABLEVALVE SURFACE ARRANGEMENT
Concrete surround (ifrequired). Refer Note C.
150 / 225 DWV whitePVC SN4 pipe shroud
150 / 225 DWV whitePVC SN4 pipe shroud
WATER
VALVEValve markingsrefer MRWA-W-301
Valve disc marker( if required)
100 to 350
100 to 350
Shroud must beclear of surfacefitting
Shroud must beclear of surfacefitting
Shroud must beclear of surfacefitting
Valve disc marker( if required)
Valve disc marker( if required)
Compacted crushed rock asper MRWA-W-201(Type R in road pavement)(Type F in nature strip).
Compacted crushed rock as perMRWA-W-201 (Type F).
Compacted crushed rock as perMRWA-W-201 (Type F).
VALVE DISC MARKER( IF REQUIRED)
VALVE DISCMARKER ( IFREQUIRED)
WAT
ERVA
LVE
FIGURE 302- B: TYPE B TRAFFICABLE VALVE SURFACE ARRANGEMENT
FIGURE 302-D: DRINKING WATER NON TRAFFICABLEVALVE SURFACE ARRANGEMENT
FIGURE 302-E: NON-DRINKING WATER NONTRAFFICABLE VALVE SURFACE ARRANGEMENT
2 m
RESIDENTIALDRIVEWAY
5 m2 m
TRAFFICABLECOVERS REQUIREDIN THESE PARTS OFTHE NATURE STRIP
5 m
KERB
KERB
TRAFFICABLE COVERS REQUIRED IN INDUSTRIAL AREAS
KERB
FIGURE 302-C: TRAFFICABLE VALVE COVERSIN NON TRAFFICABLE AREAS
NON TRAFFICABLE
NOT FOR USE IN YARRA VALLEY WATER AREA
Compacted crushed rockas per MRWA-W-201(Type R in road pavement)(Type F in nature strip).
2 cups cementspread over surfaceof compactedcrushed rock
Plasticsurround
Shroud must beclear of surface fitting
2 cups cementspread over surfaceof compactedcrushed rock
FOOTPATH
Valve disc marker( if required)
2 of 300 x 300 x 50Approved hardwood, recycledplastic or concrete support
![Page 6: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/6.jpg)
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-303
NOT TO SCALE
2012 3
HYDRANT & WASHOUTSURFACE ARRANGEMENTS
R. JAGGER 04/04/2011D. TOLENTINO 04/04/2011
X C. RIVETTE 04/04/12X C.PAXMAN 04/04/12X K.DAWSON 04/04/12
X R.CARRUTHERS 04/04/12X G.REYNOLDS 04/04/12X A.COSHAM 04/04/12
1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 R.JAGGER
2 PUBLISHED FIRST ISSUE 04/04/12 R.JAGGER
3 REMOVE OLD DETAIL A. NEW FIG 303-C 1/12/16 RJ / CP / JT
FSL
BOLT AND MAIN ALIGNMENT
Hydrant head orientationunder the cover
GRADEFSLFSL GRADE
> 300
FIGURE 303-A: NON TRAFFICABLE NON-DRINKING WATER HYDRANT COVERS
FIGURE 303-B: TRAFFICABLE AREA HYDRANT COVERS
PAVEMENT
Compacted crush rockas per MRWA-W-201
(Type F trafficable area)
>50
>30
Minimum cover compactedcrushed rock over lip of cover
Minimum cover of naturestrip top soil
225 DWV white PVCSN4 pipe shroud
FIGURE 303-D: NON TRAFFICABLE COVERS FORALL IN ONE VALVE CONTROLLED HYDRANTS OR FLUSHING BOXES
100 to 250
Minimum cover ofnature strip top soil
>50
FSL
FIGURE 303- F: DRIVEWAY, PARKING BAY & FOOTPATH COVERS FORALL IN ONE VALVE CONTROLLED HYDRANTS OR FLUSHING BOXES
100 to 250
> 400
CONCRETE
Hinged heavy cover (ie:large fitzroy box)
PE non trafficableflushing box with cover &top lip removed
All in One Hydrant Controlled Valve & Flushing Box Fittings:· Covers and frames for all in one valve controlled hydrants, washouts and below ground
domestic meters can be constructed in this way.· Cover must be appropriately labeled as "hydrant" or "washout" / "flushing box" or "meter".· Only SEW allow the use of all in one valve controlled hydrants.
FSL
600 reinforced concreteor MC shaft and coverarrangement as per Fig306-C(i) from seweragestandards
100 to 250
Purple if NDW
Hydrant marking if NDWrefer MRWA-W-301
600 standard ClassD heavy cover
FIGURE 303-E: TRAFFICABLE COVER FOR ROADS FORALL IN ONE VALVE CONTROLLED HYDRANTS OR FLUSHING BOXES
100 to 250
Hydrant marking if NDWrefer MRWA-W-301
Hydrant marking ifNDW.Refer MRWA-W-01
> 100
Concrete surround. ReferNote c (if required).
NOTES on Hydrants in Nature Strips & Open Reserves:a. Where the main is aligned close to the kerb such that non trafficable covers
(which are larger) would clash with the kerb, trafficable covers shall be used(which are substantially smaller).
b. Non trafficable covers shall not be cut down in size.c. Trafficable covers with concrete surrounds shall be used in nature strips where
vehicles are likely to regularly mount the kerb (Ref Figure 303-C). This includes:c.a. All hydrants in industrial areas,c.b. All hydrants within 5m of any road intersections,c.c. All hydrants within 2m of residential driveways.
d. Elevate cover up to 75 above finished surface level and grade soil away toprevent water entry.
NOTES on Hydrants in Road Pavement:A. Hinge covers to close in the direction of the adjacent road lane traffic.B. In trafficable areas a hardwood, recycled plastic or concrete bearer is
required to support the surface fitting.C. No surround is required for trafficable hydrant covers.
PAVEMENT
PE flushingbox & lid
4 of 300 X 300 X 50Approved hardwood, recycled
plastic or concrete supports,one each side of shaft.
Shroud must be clear ofsurface fitting
Compacted Crushed Rock as perMRWA-W-201 (Type R trafficable area)
Compacted crushed rock asper MRWA-W-201 (Type Ftrafficable area)
GENERAL NOTES:1. Provide a level compacted crushed rock foundation for all covers, surrounds and shrouds (as shown) to the embedment material.
Crushed rock to be in accordance with the trafficable section of MRWA-W-201.2. A gap is required between the cover and shroud. The shroud shall be cut at 90 degrees.
The shroud shall not contact the cover & be kept > 20 mm clear.3. Install cover, surround, spindle sleeve, shroud and shroud support so that no loading is transmitted to the valve or pipe.4. For non-drinking water hydrants & washouts, the words / letters: "Non-Drinking Water" or "NDW" or "RW" shall be cast / stamped/
embossed or engraved into the cover or lid.5. For drinking water hydrants & washouts, the words / letters: "Water" or "W" or "Drinking Water" shall be cast / stamped/ embossed or
engraved into the cover or lid.6. For hydrant marking arrangements refer to MRWA-W-300 & 301.7. Refer to water agency products catalogue for authorized materials.
All in one valve controlled hydrant shown.Same arrangement for flushing boxes.
100 - 250
2 m
RESIDENTIALDRIVEWAY
5 m2 m
5 m
KERB
KERB
FIGURE 303-C: TRAFFICABLE HYDRANTCOVERS IN NON TRAFFICABLE AREAS
Hydrant marking if NDW.Refer MRWA-W-301
ROUND (IF NDW) AND SQUARE (IF DW)
ROUND (NDW) SHOWN
2 cups cementspread over surfaceof compactedcrushed rock
TRAFFICABLE HYDRANT REQUIRED IN INDUSTRIAL AREAS
KERB
TRAFFICABLECOVERS REQUIREDIN THESE PARTS OFTHE NATURE STRIP
FOOTPATH
Only SEW allow use of all inone valve controlled hydrant
Flushing box shown.Same arrangement for allin one valve controlledhydrant (SEW only) .
Flushing box shown.Same arrangement for all in one
valve controlled hydrant (SEW only).
Compacted crushed rock asper MRWA-W-201(Type R in road pavement)(Type F in nature strip).
2 of 300 x 300 x 50Approved hardwood, recycledplastic or concrete support
Compacted Crushed Rock as perMRWA-W-201 (Type R trafficable area)
![Page 7: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/7.jpg)
FIGURE 304-ii: SECTION VIEW. TYPICAL OFFSET ARRANGEMENTS
ROAD PAVEMENT
Main connectiondetail as per FIG
305: I, J of K
Surface fittingdetail as per
FIG 305: A, D,E or F
BACK
OF
KERB
Surface fittingdetail as perFIG 305- A,B, C or D
Main connectiondetail as per FIG
305-G or H
FSL
FIGURE 304-i: SECTION VIEW.
IN LINE ARRANGEMENT
FALL
DN100
GENERAL NOTES:1. For definitions of trafficable and non-trafficable refer to MRWA-W-201.2. Require an air egress fitting between any two valves to facilitate charging of the water mains.3. Hydrants shall be located adjacent to valves wherever possible (as per Figure 205-K).
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-304
NOT TO SCALE
2012 3
HYDRANT AND AIR VALVEARRANGEMENTS
R. JAGGER 20/02/2011D. TOLENTINO 20/02/2011
X C. RIVETTE 04/04/12X C.PAXMAN 04/04/12X K.DAWSON 04/04/12
X R.CARRUTHERS 04/04/12X G.REYNOLDS 04/04/12X A.COSHAM 04/04/12
1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 R.JAGGER
2 PUBLISHED FIRST ISSUE 04/04/12 R.JAGGER
3 CLARIFIED PREFERENCES 1/12/16 RJ / CP / JT
If FIG 304:iv.Vertical bend
If FIG 304:iiiHorizontal bend
followed byvertical bend at
end of line.
Valve requiredwhere "offtakevalve" indicated inTable 304-A.
TABLE 304-A: HYDRANT AND AIR VALVE SELECTION AND ARRANGEMENTS NOTES Regarding Table 304-A:1. Hydrants typically used alone between DN250 to <=DN375 unless the main has a significant rise or fall or the main
is pumped or has a PRV (in which case an air valve will likely be required).All air valves shall be combination (dual action) air valves.Air valves plus hydrants are typically required on mains >DN375.The designer shall undertake hydraulic and air handling analysis to confirm the optimum fitting type, size andlocation of air fittings.Air valve requirements should be determined using water agency approved air valve supplier software (and softwaresettings used by the water agency) and an appropriate surge analysis.
2. Options nominated first are preferred if practical.3. Offsetting the fitting may be impracticable if there is no space in the non trafficable area and there is no reasonable
opportunity to make enough space by altering the location of other assets.4. Locating the air valve below ground may be impracticable if:
A- the surface cannot be raised to above the 1 in 100 year flood level, orB- there is inadequate cover over the main to locate the surface fitting below ground and it is unreasonable to lower the main to accommodate the surface fitting below ground, orC- there is inadequate clearance from other buried assets and those assets cannot be reasonably moved.
5. YVW air valves must be Offset and Above Ground. If this is not possible, contact YVW.6. Locate hydrant away from areas where vehicles will likely park.
Locate hydrants >3m from kerb and in front of driveways or within 10m of an intersection.7. Above ground in line air valves are not acceptable as above ground fittings must have a valve at the offtake (in case
they get knocked over)).8. Select iii or iv according to where the surface fitting could be best located.
Require min 2m offset of above ground fitting from offtake valve.Require 800 separation of below ground air fitting and offtake valve.
9. In line hydrants connected to >DN250 trafficable mains would only be acceptable if there was no alternative.10. There is no other option than for air valves connected to trafficable mains to be offset and located in a non trafficable
location.11. For above ground air valves, they should be located as far from the road pavement as practical and in such a way
as to minimise the chance of accidental collision.
MAIN
FOOTWAY RESERVE ORMEDIAN STRIP
BACK OF KERB
FIGURE 304-iv: STANDARD OFFSET ARRANGEMENT (PLAN)
VALVE (IFREQUIRED)
FOOTWAY RESERVE ORMEDIAN STRIP
BACK OF KERB
FIGURE 304-iii: DOUBLE OFFSET ARRANGEMENT (PLAN)
ROAD PAVEMENT
FIG 305-A,D, E or F
AIR VALVEOR
HYDRANT
VALVE
For hydrants and < DN100air valves, DN100 pipework.For >DN100 air valves,DN150 pipework.
>200>200
>800
>800 (if below ground), or>2m (if above ground A.V)
>800
>DN250 MAIN
Valve requiredwhere "offtakevalve" indicated inTable 304-A.
Valve requiredwhere "offtakevalve" indicatedin Table 304-A.
FIG 305-A,D, E or F
AIR VALVEOR
HYDRANT
FIG 305-AHYDRANT (IF
WITH AIRVALVE)
>200
>800 (if below ground), or>2m (if above ground A.V & YVW)>5m (if above ground A.V & CWW or SEW)
FIG 305-AHYDRANT (IF
WITH AIRVALVE)
ROAD PAVEMENTVALVE (IFREQUIRED)
MAINMAIN
VALVE
FIG 305-A,D, E or F
AIR VALVEOR
HYDRANT
>800
DN100 pipework. Requirea DN150 to DN100 taperwhere A.V is >DN100.
>DN250 MAIN
![Page 8: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/8.jpg)
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-304B
NOT TO SCALE
2016 2
HYDRANT AND AIR VALVEARRANGEMENT EXAMPLES
R. JAGGER 1/02/2016R. JAGGER 1/02/2016
X B. VANOS 1/10/2016X C. PAXMAN 1/10/2016X J. TOMASI 1/10/2016
X R.CARRUTHERS 1/12/2016X D. O'DONOVAN 1/12/2016X D. ERREY 1/12/2016
1 PRE PUBLISHED DRAFT FOR COMMENT 12/03/16 RJ / CP / JT
2 PUBLISHED FIRST ISSUE 01/12/16 RJ / CP / JT
FRONT BOUNDARY
KERB
< DN250 MAIN
FRONT BOUNDARY
KERB
> DN250 MAIN
FIGURE 304B-A: CWW-SEW-YVW NON TRAFFICABLEMAIN < DN250· IN LINE STANDARD HYDRANT
FIGURE 304B-B: SEW NON TRAFFICABLE HYDRANTSON MAINS >DN250IN LINE ALL IN ONE VALVED HYDRANT
FRONT BOUNDARY
KERB
> DN250 MAIN
FIGURE 304B-C: NON TRAFFICABLE MAIN >DN250· CWW or YVW- OFFSET VALVE CONTROLLED HYDRANT OR AIR VALVE· SEW- OFFSET VALVE CONTROLLED AIR VALVE· YVW AIR VALVE TO BE ABOVE GROUND· ALL OTHER FITTINGS TO BE BELOW GROUND
FRONT BOUNDARY
KERB
> DN250 MAIN
FIGURE 304B-D: CWW-SEW- YVW NON TRAFFICABLEMAIN >DN250
· IN LINE VALVED RISER PLUS AIR FITTING.· WHEN FIG 304B-C CANNOT BE INSTALLED DUE TO SITE CONSTRAINTS.· CWW or YVW IN LINE HYDRANTS or· CWW or SEW BELOW GROUND AIR VALVES.
FRONT BOUNDARY
KERB
FRONT BOUNDARY
KERB> 3m
FIGURE 304B-F: SEW TRAFFICABLE MAIN < DN250IN LINE STANDARD BELOW GROUND HYDRANT FIGURE 304B-H: CWW-YVW TRAFFICABLE MAIN < DN250
· IN LINE STANDARD BELOW GROUND HYDRANT WHERE IT ISIMPRACTICAL TO OFFSET
· LOCATE HYDRANT IN FRONT OF DRIVEWAY OR WITHIN 10m OFINTERSECTION, and
· OFFSET >3m FROM BACK OF KERB WHERE PRACTICAL.
FRONT BOUNDARY
KERB< 10m
FIGURE 304B-G: CWW-YVW TRAFFICABLE MAIN < DN250OFFSET STANDARD BELOW GROUND HYDRANT
FRONT BOUNDARY
KERB> DN250 MAIN
FIGURE 304B-J: CWW-SEW-YVW TRAFFICABLE MAIN >DN250· VALVE CONTROLLED OFFSET BELOW GROUND HYDRANT OR AIR VALVE· YVW AIR VALVE TO BE ABOVE GROUND· ALL OTHER FITTINGS TO BE BELOW GROUND
FRONT BOUNDARY
KERB
FIGURE 304B-L: CWW-SEW-YVW TRAFFICABLE MAIN > DN450· OFFSET VALVE CONTROLLED AIR VALVE PLUS HYDRANT· YVW AIR VALVE TO BE ABOVE GROUND· ALL OTHER FITTINGS TO BE BELOW GROUND
HYDRANT (FIG 305-A)
HYDRANT OR AIR VALVE (FIG 305-A, D, E or F)
ALL IN ONE VALVED HYDRANT (FIG 305-B)
VALVED RISER PLUS HYDRANT OR AIR VALVE (FIG 305-C or D)
FRONT BOUNDARY
KERB
FIGURE 304B-M: CWW-SEW-YVW DIVIDE VALVE ONMAIN > DN450· OFFSET BYPASS WITH HYDRANT AND AIR VALVE.· AIR VALVE LIKELY REQUIRED WHERE THIS IS AT A DISTINCT
HIGH POINT
AIR VALVE (FIG 305-D, E or F)
LEGEND
<DN2
50 M
AIN
Locate valves andhydrants in the naturestrip as close to the
splay corner as practical
Underground fittingsmay be single offset
where practical.
Above ground fittingsshall be double offset
where practical.
> DN450 MAIN > DN450 MAIN
NOTE: ALWAYS LOCATENATURE STRIP VALVESAND HYDRANTS ASCLOSE AS PRACTICAL TOTHE SPLAY CORNER
TRAFFICABLE MAINS < DN250 NON TRAFFICABLE
< DN250 MAIN < DN250 MAIN< DN250 MAIN
TRAFFICABLE MAINS >DN250
FRONT BOUNDARY
KERB> 3m
> DN250 MAIN
FIGURE 304B-K: CWW-SEW-YVW TRAFFICABLE MAIN >DN250· in line below ground valved hydrants or air valves where it is impractical to offset· locate hydrant or air valve in front of driveway or within 10m of intersection, and· offset main >3m from back of kerb.
< 10mSEW Shown CWW / YVW Shown
NONTRAFFICABLEAREA
ROAD PAVEMENT
> DN250 MAIN
FIGURE 304B-I: CWW-SEW ABOVE GROUND AIR VALVES· WHERE BELOW GROUND AIR VALVE IMPRACTICABLE.· LOCATE ABOVE GROUND AIR VALVES IN NON TRAFFICABLE
AREAS > 5m FROM ROAD PAVEMENT.· MAIN MAY BE LOCATED IN A NON TRAFFICABLE OR TRAFFICABLE
AREA.
> 5m> DN450 MAIN
> DN250 MAIN> DN450 MAIN
FRONT BOUNDARY
KERB
> DN450 MAIN
FIGURE 304B-E: NON TRAFFICABLE MAIN > DN450· OFFSET VALVE CONTROLLED AIR VALVE + HYDRANT· YVW AIR VALVE SHALL BE ABOVE GROUND· CWW - SEW AIR VALVE SHALL BE BELOW GROUND
KERB
![Page 9: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/9.jpg)
FSL
Di riser length tosuitDN
100
· This is the standard for retic pipelines.· Only spring hydrants permitted.
· Trafficable or non-trafficable.· Refer to MRWA-W-303 for details.
· Only for SEW for mains >DN250· Non-trafficable where practical.· Not to be offset from main.
· Only spring hydrants permitted.· Refer to MRWA-W-303 for
details.
FSL
FSL
FIGURE 305-D: BELOW GROUND AIR VALVE WITH ISOLATION VALVE1. Only for CWW & SEW air valves in non trafficable areas where the air valve is short and
would not protrude above ground.2. Not preferred by YVW.3. Approved polymeric or concrete shaft may be used as per gravity sewerage standards.4. 40mm diameter holes to be cut into cover (or use grated cover) equal in area to 1.5 x the
air valve orifice area.The cover, once holed, is no longer capable of withstanding the traffic loads.
5. Cover should lie 25mm above the surrounding natural surface level (not to protrudeexcessively above ground).Surface level shall be above the 1 in 100 year flood level.
6. Valve not required at the offtake where the in line arrangement is used.
FIGURE 305-F: ABOVE GROUND SMALL AIRVALVES1. Use where not SEW and:
1.1. The required air valve is small enough to fit within thecover, and
1.2. For YVW air valves, or1.3. For CWW air valves when the air valve is well back from
the road (ie: >5m).2. 40mm diameter holes to be drilled into cover equivalent in
area to at least 1.5 x the air valve orifice area.
d
h
D
FIGURE 305-G: STANDARD INLINE CONNECTION
FIGURE 305-I: OFFSET HYDRANTCONNECTION TO MAINS < DN150· Only for use in conjunction with Figure 305-A.· A valve is usually not fitted between the
hydrant / air valve and the offtake tee.
FIGURE 305-J: INVERTED SCOUR TEECONNECTION FOR MAINS > DN225· Only for use in conjunction with Figures 305-A,
D, E or F.· Fit valve directly to the offtake tee.
FIGURE 305-H: IN LINE AIR VALVECONNECTION TO MAINS > DN375· Only for use in conjunction with Figure
305-D.· Only possible where the water main is
unusually deep (> 1300mm) &/or an aboveground air valve is to be constructed.
· 'd' and 'h' should be > 0.5 x 'D'
AIR VALVE DETAILS
d
h
D
FIGURE 305-K: OFFSET AIR VALVE CONNECTION TO MAINS > DN375· Only for use in conjunction with Figures 305-D, E or F.· Only usually possible where the water main is unusually deep (> 1300mm) &/or an above
ground air valve is to be constructed.· 'd' and 'h' should be > 0.5 x 'D'· Place special flanged bend directly on tee to initiate a horizontal alignment.
HYDRANT SURFACE DETAILS
600 CLASS D COVER (if 600 shaft)750 CLASS D COVER (if 1070 shaft)
Connect to nearbydrain if practical
NOTES Regarding Air Valves:1. All options posed here are non trafficable.
Air valves shall not be located in trafficable locations.2. Air valve and riser pipe (from main) should be sized
according to the orifice cross sectional area(s), not thebore area of the air valve.
3. Where an air valve > DN200 is calculated as required,multiple smaller valves shall be installed on a manifoldinstead (ie. 2 x DN200 should be used instead of a singleDN300) and the shaft designed accordingly.
4. Air valve marking arrangements only required where Ltype hydrant covers are used.
NOTES on Figures 305-A, B & C:1. Refer to MRWA-W-303 for surface
cover arrangements for hydrants.2. Refer Table 301-B for hydrant marking
arrangements.3. Hydrants are not to be used in low
pressure applications (< 20 m),eg: some irrigation only NDW systems.
4. Spring hydrants are not automatic andrequire manual opening to allow airingress and egress.
DN10
0
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-305NOT TO SCALE
2012 3
HYDRANT AND AIR VALVEFITTING DETAILS
100 to 250
OFFSET
IN LINEIN LINE ONLY
IN LINE OROFFSET
Concretesurround
OFFSET ONLY
20mm bleedwith 316 ssball valve
FSL
Ball or butterfly valve.Required only if in linemain connection.
5mm thick aluminum checker plate lid withstiffening spacers
100 to 250
OFFSET ONLY
20mm bleedwith 316 ss
ball valve
1. Isolation valve must be operable from surface if 600Ø shaft is used to house the air valve.2. Approved 600Ø sewer maintenance shaft and cover preferred for air valves less than 300Ø.3. Approved 1070Ø sewer access shaft shall be used for air valves greater than 300 in width.
600 neck shall be located over clear ground (not over the air valve).
4. Minimise pit depth, step irons required for 1070Ø shaft > 1000 deep.5. Lay shaft and supports on compacted 20mm single sized crushed rock (self draining) to 95%
rd density.This crushed rock should extent to the embedment layer, extend the full width of the trenchand to a distance of 1m from fitting in both directions.
> 300 & > 13SHAFT HEIGHT
MAIN CONNECTION DETAILS
FIGURE 305-E: ABOVE GROUND LARGER AIR VALVES1. Use only concrete shaft.2. Use sufficient 316SS fastened or welded aluminum stiffening angle to support cover to
ensure <10mm deflection with a centered 100 kg load.3. Locate shaft well back from roadway (ie: >5m) if CWW or SEW.
Loose locatingbrackets at 10 and 2
o'clock
NOTES Regarding Details D & E:
PERSPECTIVE VIEW OF TOP OF SHAFT ARRANGEMENT
6mm thick, 60mm wide316ss strap
M12, 316ss bolts
PADLOCK
Install markings as perMRWA-W-301
Install markings as perMRWA-W-301
70
Black
Lilac (if NDW)
Compacted 20mmsingle sized
crushed rock
FSL
Standard 600 shaft(concrete or PP).
If PP, install as perFig 306C(i) from
sewerage standards
600 CLASS B/D COVER
APPROVED BALL ORBUTTERFLY VALVE
IN LINE ONLY
1. Use for CWW or YVW where:· Main is >DN250 .· An offset hydrant would normally be required but this requirement cannot
practically be accommodated due to site constraints, ie: other assets too close.2. Non-trafficable where practical.
3. Only use spring hydrants.4. All such hydrants are to be Water Agency owned and not included as part of fire
fighting spacing (as cannot be accessed by fire fighters).5. Approved polymeric (non-trafficable) or concrete (trafficable) shaft may be used.
FIGURE 305-C: BELOW GROUND IN LINE HYDRANT WITH ISOLATION VALVE
Install markings as perMRWA-W-301
100 to 250
FIGURE 305-A: BELOW GROUND HYDRANT FIGURE 305-B: BELOW GROUND ALL IN 1 VALVED HYDRANT
Only for use in conjunction with Figures305-A, B, C or D.
500 to1000
FSL shall be above the 1in 100 year flood level
Compacted crushed rock asper MRWA-W-201 (Type F)
SPACER
Standard 600 or 1070 shaft(concrete or PP).If 600PP, install as per Fig306C(i) from seweragestandards
<600 ifPractical
>100 >300<600 if
Practical
>100 >300
<600 ifPractical
>100 >300
300 x 300 x 50 (4 No.) approvedrecycled plastic or concrete support
300 x 300 x 50 (4 No.) approvedrecycled plastic or concrete support
2 cups cementspread oversurface
Compacted crushed rock asper MRWA-W-201 (Type F)
Compacted crushed rock as perMRWA-W-201 (Type F / R)
![Page 10: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/10.jpg)
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-306ANOT TO SCALE
2012 3
FLANGE ARRANGEMENTS
Fill gap between raised flange faceswith primer or mastic
FBEcoatedflange
Gasket
SS bolt, nut& washers
SS backingring
PRIMER
ACCEPTABLEPIPE COATING
GASKET
FIGURE 306A-A: CORROSION PROTECTION OF 2 x DI or 2 x MS UNCOATED FLANGES
GENERAL NOTES:A. All flanges are to be raised face type.B. Steel flanges shall be welded in an ISO9001 accredited workshop.
No on site welding of steel flanges is permitted.C. For flange, gasket and fastening details, refer to MRWA-W-306B.D. Corrosion protection is not required for concrete encased puddle
flanges.E. Any FBE coated fittings which are damaged to the point where bare
metal is exposed shall be repaired with a repair product approved by themanufacturer.Otherwise it shall be quarantined and not installed.
Overlap primerover pipe coating
by min 200
UNCOATED MSCL OR DI FLANGE
FBE COATED DI FITTING
Fill gap between raised flangefaces with primer or mastic
MASTICFILLER
CEMENT MORTAR REINSTATEMENT
FIGURE 306A-B: CORROSION PROTECTION OF AN UNCOATED FLANGE CONNECTED TO A COATED FITTING
Overlap primer overpipe coating by min
200
PRIMEROverlap protectivetape over primer
by min 150
Insulation top hat(if required- seenote B)
WASHER
2 x MS, or2 x DIflanges
WASHER
NOTES on Corrosion Protection:A. Embedment shall be scalloped under the flanges to enable tape to be wound underneath.B. Insert nylon or acetyl copolymer thermoplastic based insulation top hats with fasteners into all flange holes when
mating flange materials are dissimilar, ie: if both flanges are DI or both flanges are steel, no fastener insulation isrequired.Where flange insulation is required, test flange insulation in accordance with CORR-24.
C. FBE coated flange holes shall not be drilled out to make them larger for top hat insertion.Greater than 0.5mm thick sleeving and insulating washers or top hats thin enough to be inserted into flange holesshall be used. This is usually required for M16 & M24 bolt holes.
D. Corrosion protection described here is required for all steel or ductile iron flange surfaces which do not have a highintegrity coating consisting of one of the following:
D.A. Heat applied MDPE PE coating to AS4321.D.B. Fusion bonded epoxy coating to AS/NZS 4158.
D.C. Ductile iron pipe with zinc coating to 200 mg/m² to BS/EN 545.D.D. Ductile iron pipe with polyurethane coating to EN 545 or ISO 2531.
E. Bare, bitumen coated or painted surfaces are not acceptable coatings. These surfaces will be referred to as uncoated.F. All corrosion protection products shall be as per the water agency product catalogue.G. Products from a single manufacturer shall be used to ensure compatibility of products. All products shall be applied as
per the manufacturers instructions.H. Step 1: Surface Preparation- All surfaces to be primed shall be prepared to a finish of ST2.5 according to AS 1627.2
class SA2.5.Power wire brush remove all scale, loose rust and old flaking coating. Chisel off all weld splatter and slag.
I. Step 2: Primer- Shall be applied by brush or spray to all uncoated surfaces to a distance of 200mm past coated pipe /fittings. The entire area to be wrapped shall be primed, including all flanges and bolts.
J. Step 3: Mastic- Apply mastic to create a gradual and smooth transition from the pipe to the outer diameter of theflange. Application around bolt heads only is not acceptable. Apply mastic by hand, ensuring no significant voids arepresent.
K. Step 4: Protective Tape- Apply petrolatum, butyl or bitumen tape system continuously with 55% overlap, stretchingand moulding the tape to limit creases and prevent gaps.
L. Step 5: Overwrapping Plastic Tape- Provide physical and mechanical protection of the corrosion protective tape usinga PVC overwrapping tape. Apply with 55% overlap, stretching tape to limit creases and prevent gaps.Where DI pipe and fittings are PE sleeved (after step 4), over wrapping tape is not required.
M. Step 6: Coating Defect (holiday)Testing. Carry out holiday testing to determine the quality of coatings as per note J ofdrawing MRWA-W-400.
Corrosion protectiontape
MASTICFILLER
1. The PE puddle flange shall conform to the dimensions described in in Table 306A-A.2. Puddle flanges cast as part of a thrust fitting (thrust connectors) or welded on puddle flanges are preferred to bolted on
mechanical puddle flanges and shall be used where practicable.3. PE puddle flanges shall be extrusion welded to PE mains.4. Extrusion welding shall be undertaken in a clean and dry workshop.5. The extrusion welder shall be qualified to the competency PMBWELD309 or PMBWELD309A or PMBWELD309B.6. All welds shall be stamped with the welder's name or identification number.
FIGURE 306A-D: CORROSION PROTECTION FOR GALVANISED BOLTS WITH COATED FLANGES
PEstubflange
NOTES Regarding Galvanised Fastener Protection & Corrosive Ground Conditions:· Caps and sleeving as shown above are not required where Figure 306A-A or B apply.· Stainless steel fasteners in corrosive ground (ie: chlorides > 1000 ppm) shall be protected as shown in Figure 306A-D.· CWW does not accept the use of buried galvanised steel fasteners.· Either approved mastic or gel plus plastic caps may be used to encapsulate the galvanised fasteners.
Over wrappingtape
MASTICFILLER
MASTICFILLER
Overlap protective tape overprimer by min 150
Corrosion protectiontape
OVER WRAPPINGTAPE
2 x MS, or2 x DIflanges
Anticorrosion gelor mastic
Plastic sealing cap(optional)
PVC heavy duty"duct tape"
Double thickness of lowdensity PE sleeve
MASTIC
5 mm
NOTES Regarding Fused PE Puddle Flanges:
GASKET
FIGURE 306A-C: PE STUB FLANGE WITH SS FASTENERS
Fbe coated difittings
Choose one of Masticor Cap plus mastic / gel
PVC heavyduty "ducttape"
NOTES Regarding Sleeving:A. All Fasteners (gal or SS) shall be sleeve wrapped to prevent contact with soil.B. Gal fasteners in the open air (not buried) do not require additional corrosion protection.C. Triple wind PVC heavy duty "duct tape" to be min 0.18mm thick and 50mm in diameter around the sleeve to prevent
water / air ingress under the sleeve.D. Use low density polyethylene sleeve in accordance with AS 3680. Wrap so that any seem is located at top of the pipe.E. Ensure that all sleeving between the duct tape on one side and that on the other is not perforated in any way.F. Ensure flanges and bolts are clean and free of dirt of contaminants prior to being sleeved.
PIPE PE MAIN OUTSIDE DIAMETER< DN280> DN315
FLANGE THICKNESS (mm)3040FLANGE OD (mm)
< DN500> DN560
PIPE OD +100PIPE OD + (2 x PIPE WALL THICKNESS)
TABLE 306A-A: PE PUDDLE FLANGE DIMENSIONS FOR PE MAINS
PE pipe
FIGURE 306A-E: PE PUDDLE FLANGES
Puddle Flange Thickness
Puddle FlangeOutside Diameter
Extrusion Weld (fullcircumference on both sides)
PIPE PE MAIN OUTSIDE DIAMETER
![Page 11: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/11.jpg)
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-306B
NOT TO SCALE
2012 3
FLANGE DETAILS ANDFLANGE FASTENING REQUIREMENTS
K. DAWSON 11/03/2011R. JAGGER 11/03/2011
X R.JAGGER 04/04/12X C.PAXMAN 04/04/12X S. TAN 04/04/12
X R.CARRUTHERS 04/04/12X G.REYNOLDS 04/04/12X A.COSHAM 04/04/12
1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 K.DAWSON
2 PUBLISHED FIRST ISSUE 04/04/12 K.DAWSON
3 PE PUDDLE FLANGES. TORQUE AMENDMENTS 01/12/16 RJ / CP / JT
PIPE NOMINAL SIZEFLANGE OUTSIDE DIAMETERPITCH CIRCLE DIAMETERGASKET INTERNAL DIAMETERNUMBER OF HOLES / BOLTSDIAMETER OF HOLESBOLT SIZELENGTH OF BOLTS (mm)BOLT TENSION (kN)TORQUE (LIGHTLY OILED GAL)- NmTORQUE (WELL LUBRICATED)TORQUE (PTFE or INSULATED)- NmDI FLANGE THICKNESS (mm)STEEL FLANGE THICKNESS (mm)
100215178108418M1675207050402011
150280235161818M1675207050402311
225370324241818M1675259060502415
3004554063251222M2010035160110803023
3755504954061226M24100502701801453330
4506405844851226M24120552902001603330
6008257566411630M27130704202902304248
7509959277962033M30130805303802904748
TABLE 306B- A: CLASS 16 (PN16) FLANGE & FASTENING DATA
NOTES Regarding Gasket and Fastener Material Requirements:a. CWW only permits 316 stainless steel fasteners in buried applications.
Galvanized fasteners are allowed where the fasteners are exposed to the open air rather than soil.b. Class 16 flange gaskets shall be full face, solid 3mm thick EPDM rubber (seal-16).c. Class 16 galvanised steel studs (bolts), nuts and washers shall be grade 4.6.d. Class 16 stainless steel studs (bolts), nuts (ptfe coated) and washers shall be 316 stainless steel (A4), class 50.e. Class 35 flange gaskets shall be full face, 1.5mm thick compressed fibre, Teadit style na1000, which contains Aramid fibres, woven wire mesh
reinforcement, a nitre rubber matrix and graphited surface on both sides.f. Class 35 galvanised steel studs (bolts), nuts and washers shall be grade 8.8.g. Class 35 stainless steel studs (bolts), nuts (ptfe coated) and washers shall be 316 stainless steel (A4), class 70 .h. Flange gaskets shall conform to WSAA industry standard WSA 109, which includes compliance to AS4020 for potable water contact.i. All stainless steel fasteners shall include the use of PTFE (teflon) or Molybdenum Sulphide (MoS
2) coated nuts to reduce seizing, galling and thetightening friction of the nut on the washer (thus reducing the tightening torque required).
NOTES on Tables 306B- A & B:A. The flange and fastening details provided in these tables are based on AS/NZS 4087:2011 and WSAA standard WSA 109-2011.
In AS/NZS 4087, figure B5 covers PN16 and figure B6 covers PN35.B. All flanges shall be raised face type.C. "lightly oiled" refers to the application of a good quality lubricating oil and is the usual as received condition of fasteners.
A torque K factor of 0.22 has been used to calculate the torque values in Tables 306B- A & B in this case.D. "well lubricated" refers to the application of molybdenum disulfide grease, or equivalent antiseize compound, eg: nickel graphite lubricant such as loctite 771.
A torque K factor of 0.15 has been used to calculate the torque values in tables 1 & 2 in this case.Unless proven to be otherwise, assume grey coated nuts fall under "well lubricated".
E. "PTFE / Insulated" refers to the application of a PTFE coating or the use of insulating polymeric top hats or washers / with well lubricated fasteners.A torque K factor of 0.12 has been used to calculate the torque values in tables 1 & 2 in this case.
F. Torques quoted are minimums.Maximum torque allowable shall be 1.5 x the minimum.
G. The bolt lengths described assume Di to Di flanges. Insulated flanges may require longer bolts.H. The nominated gasket internal diameter is the inside diameter of flange class ductile iron pipe, excluding the cement lining.
While PN35 class Di pipe has a larger ID than flange class, the nominated gasket inside diameters are larger than pipe cement lining inside diameters (ie:the gasket will not protrude into water flow of any Di pipe).
PIPE NOMINAL SIZEFLANGE OUTSIDE DIAMETERPITCH CIRCLE DIAMETERGASKET INTERNAL DIAMETERNUMBER OF HOLES / BOLTSDIAMETER OF HOLESBOLT SIZELENGTH OF BOLTS (mm)BOLT TENSION (kN)TORQUE (LIGHTLY OILED GAL)- NmTORQUE (WELL LUBRICATED)TORQUE (PTFE or INSULATED)- NmDI FLANGE THICKNESS (mm)STEEL FLANGE THICKNESS (mm)
100230191108818M169050180120962224
1503052601611222M2090803502401902731
2254053562411226M241201156104203303438
3004904383251626M241201156104203303838
3755805214061626M241301509006104304248
4506756104852033M3015018011908105204658
6008507816412436M33180230167011407455468
75010159407962836M331802301670114083059-
TABLE 306B- B: CLASS 35 (PN35) FLANGE & FASTENING DATA
112
5
3
79 2
11
4
810
6
1
5
3
7 2
6
8
41
3 2
4
4 BOLTS 8 BOLTS 12 BOLTS
112 5
37
9
211
4
8
106
16 BOLTS
13
14
15
16
GENERAL NOTES:· Where test pressures are < 1600 kPa, class 16 flanges and gaskets are typically screwed onto flange class pipe (which is typically thicker than
class 35 ductile iron pipe).· Where there are more than 16 bolts, the same principle as applied in the 16 bolt flange pattern should be utilised.
NOTES Regarding Mechanical Flange Attachment:· Mechanical puddle flanges shall not be applied to PVC pipe.· Clean mechanical puddle flanges (ie: bolted) fixed to metallic pipe shall be fitted to a clean pipe with
a 2 pack epoxy resin liberally applied to the pipe and puddle flange mating surfaces.· Install as per manufacturer's instructions. Where fastening torque is not specified:· Firmly fasten the puddle flange bolts to a torque equivalent to that specified for lightly oiled
galvanised flange bolts in Table 306B-A (PN16) or Table 306B- B (PN35).
Flanged Joint Installation Guidelines:1. Do not allowed gasket materials to be exposed to temperatures above 50 deg C or exposed to
contaminants.2. Thoroughly clean the flange faces to be jointed, ensuring there is no dirt, particles of foreign matter,
protrusions or coating build-up on the mating surfaces.Use a scraper or wire brush to remove any irregularities.
3. Ensure that the mating threads of all nuts and bolts are clean and in good condition.4. If galvanised fasteners are to be used, evenly apply a suitable lubricant (eg: molybdenum sulphide)
to all mating threads, including the nut load bearing face.5. Align the flanges to be joined and ensure that the components are satisfactorily supported to avoid
bending stress on the flanged joint during and after assembly.6. Insert four bolts i(with insulators if required) In locations 1 to 4 as indicated in Figure 306B- A,
positioning the gasket in between the flange mating faces.Take care not to damage the gasket surfaces.
7. Tighten the nuts to finger tight and check the alignment of the flange faces and gasket.8. Insert the remaining bolts (with insulators if required) and tighten nuts to finger tight.9. Determine the correct tightening torque from the above tables.10. Tighten nuts to 30% of this torque using the star pattern detailed in the figure below.10. Tighten nuts to 60% of this torque using the star pattern detailed in the figure below.10. Tighten nuts to 100% of this torque using the star pattern detailed in the figure below.11. Finish with one final pass, torquing in a clockwise direction.12. Re-torque fasteners 30 minutes after the initial tightening sequence (to cater for relaxation of the
gasket).13. If galvanised fasteners are to be used, apply corrosion protection measures as detailed in
MRWA-W-306A.Torque wrenches used must provide torques to an accuracy of + - 25%, which is typical.In critical applications where torques are substantial (ie: > 200 nm), a more accurate hydraulic tensionershall be used.
NOM DIFITTING SIZE100150225
300 #375450
PE STUBSIZE125180225
315SPECIAL ORDER STUB FLANGE + BACKING RING + ADAPTOR REQUIRED450
OD215280
455
640
PCD178235
406
584
PEADAPTOR
NOT REQUIRED225 to 280, or 225 to 315
315 to 355, or 315 to 400
PE EQUIVALENTDNPE SIZE(S) ^125180280 or 315
355 or 400400 or 500560 or 630
TABLE 306B-C: PE MAIN CONNECTION TO CLASS 16 FLANGES (PN16)
450 to 560, or 450 to 630
SPECIAL ORDER
NOT REQUIRED
PE BACKING RINGSIZE110180
315
450
ID128195
345
480
FLANGE
250 * 280 405 356 NOT REQUIRED N/A280 300
Notes Regarding Table 306B-C:^ Equivalent size means that these sizes have the most similar hydraulic capacity.* Flange size 250 is included to enable DN280 PE mains to directly connect to DN250 valves / hydrant tees etc (ie: no adaptor would
be required). Socket spigot mains shall not be constructed in DN250 size.# If preferred, DN315PE pipe may directly connect to a DN300 valve for convenience (no adaptor would be required), although the
valve in this case would be larger than required. Refer to Figure 306B- B.· all PE adaptors shall be moulded fittings and butt weld fused to pipes / stubs.
370 324
DN300VALVE 325 256
DN315PE STUBFLANGE,BACKING RINGAND PIPE
315DN225 VALVE 241 205
DN225PE STUB FLANGE
225
UNLESS PROVEN TO BE OTHERWISE, ASSUME GREY COATED NUTS FALL UNDER "WELL LUBRICATED".TORQUES QUOTED ARE MINIMUMS. MAXIMUM TORQUE ALLOWABLE SHALL BE 1.5 x THE MINIMUM.
Apply torque according to the size of thevalve flange (Refer Tables 306B-A & B)
FIGURE 306B- A: BOLT TIGHTENING SEQUENCE
DN315PE TODN225PEREDUCER
315 DN315PEPIPE
SPECIAL ORDER BACKING RING
FIGURE 306B-C: ALTERNATIVE DN315PE VALVE ARRANGEMENTS
FIGURE 306B-B: MECHANICAL PUDDLE FLANGE CONNECTION
Ductile iron orPE pipe
Bolted on mechanicalpuddle flange
![Page 12: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/12.jpg)
FSL
DISCHARGE PIPE ON FALLING GRADE
2 to 5m FROM OUTLET STRUCTURE
FIGURE 307-C: DISCHARGE TO WETLANDS OR WATERWAYS
FIGURE 307-A: SCOUR CONNECTION
GENERAL NOTES:A. Scour valve and pipework to provide required main drainage time (refer table 8.3 of WSA 03- MRWA edition).B. Discharge to drains and water ways is preferred for drinking water.C. Discharge to a pit or tanker connection point is required for non drinking water. Locate discharge pits nearby > DN300 sewerage main maintenance structures if practical.D. Downstream valves at the end of the scour line are only required when the discharge cannot be seen or heard at the distribution main's offtake valve which is typically
when the drain, pit or waterway is more than 20m away. For tanker connection points, the butterfly valve below the connection coupling provides satisfactory dischargecontrol.
E. Unreinforced concrete to be N20 and reinforced concrete N25.F. Connections into drains shall be undertaken as per the requirements of the relevant drainage authority.G. Discharge to wetlands, creeks and drains only permitted for drinking water and treated storm water.H. Scours are typically sized as per bypass valves, although drainage time and scour flow velocity should also be taken into account (refer to Table 105-A for details).
GATE VALVE
Valve surface arrangementsas per MRWA-W-302
NOTES Regarding Discharge Pits:1. To be used on NDW mains only. Locate nearby > DN300 sewerage main maintenance structures if practical.2. Pump out pits may only be used on DW mains in cases where there the water main is constructed ahead of drainage.
DW Pump out pits shall be decommissioned and replaced with properly constructed drainage system scour connections when drainagebecomes available.
3. Use minimum 1050 manhole design. Consider larger manholes for larger mains.4. Construct pit in accordance with WSA 02- cast in situ manholes.5. Designers must produce a feasible scour water removal plan and adjust the scour pit design to suit.
The plan should take into account: the grade of the main, the volume of water in the main, the volume of the pit, the feasibility of pumping pitcontents to a sewer, or the number of eductor truck loads required to empty the main.
6. Pit storage shall be no less than 150 of the water main shutoff volume being removed unless the pit is within 50m of a nearby > DN300 sewer.7. Water main shutoff volume must be < 300m³.
FIGURE 307-B: DISCHARGE PIT DETAIL
Non-returnflap
> 150
Design and construct pit asa Maintenance Hole inaccordance with MRWASewerage standards
FSL
>
DN300 MAINS
FSL
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-307NOT TO SCALE
2012 3
SCOUR ARRANGEMENTS FOR
Spindle extension tosurface arrangementas per MRWA-W-302
> 2m
Valve surface detailsas per MRWA-W-302
Valve surface details(refer MRWA-W-302)
FSL
50 to 150
20mm bleedwith 316 SSball valve
Ball or butterflydischarge controlvalve.
4 of 300 x 300 x 50Approved hardwood, recycledplastic or concrete support
FIGURE 307-D: TANKER CONNECTION POINT
Hole in handle toenable connection
of operating rod
Downstream manualdischarge control valve(if required. Ref note D)
1. This arrangement is an alternative to Figure 307-B.It is preferred when the scour water removal plan indicates a single tanker truckcould empty the isolated section of main with in the required time (refer to table 8.3of WSA03).
2. Locate the pit in a non trafficable location if possible.3. Cover shall be Class D and the shaft shall be reinforced concrete if the pit is
located in a trafficable location.4. Approved polymeric or concrete shaft may be used in non trafficable locations.
5. Cover should lie 25mm above the surrounding natural surface level (not toprotrude excessively above ground) in non trafficable locations.
6. System to be operated as follows; 1) sit on edge of opening, with legs in pit, 2)couple truck hose to quick connector, 3) open discharge control valve & fill tanker,4) close valve, 5) disconnect hose from quick connector or truck. The shaft shall besized and dimensioned to enable this.
7. Quick connector is a Bauer couplings for CWW.
NOTES Regarding Tanker Connection Points:
Roughen pipeand seal withepoxy mortar
STORAGEVOLUME
REFER TO SEWERAGE STANDARDFIGURES MRWA-S-404-D to H FOROUTLET DESIGN DETAILS
Tee restraint not requiredwhere discharge main isrestrained.
Lugged wafer check valve required if discharging to aTanker Connection Point (ref Fig 307-C) or a StormWater drain or pit (ie: discharges to waterways anddischarge pits have a flap gate valve at the outletalready).
<600 ifPractical
>100 >400
CompactedEmbedment
~30
Finishmortarflush withpit wall
<30
Flap gate
30°
1 to 5 mDownstream manualdischarge control valve(if required. Ref noteD)
ReferMRWA-W-204and 205
ReferMRWA-W-204and 205
600 CLASS D COVER (if 600 shaft)750 CLASS D COVER (if 1070 shaft)
Standard 600 shaft (concrete or PP).If PP, install as per Fig 306C(i) from
sewerage standards
![Page 13: DN63PEDN100 DN63PE DN6PE - Pages - Home - …mrwa.com.au/Documents/Standards/MRWAWSA03/300 Series.pdfIdentify where the distance between neighboring hydrants is excessive. Place as](https://reader030.vdocuments.us/reader030/viewer/2022020108/5b00605f7f8b9a256b8feada/html5/thumbnails/13.jpg)
MRWA WATER SUPPLY STANDARDS
REVISION NO.ISSUED
MELBOURNE RETAIL WATER AGENCIES
DATE:
DATE:
CHECKED:DRAWN:DESIGNED:
1 2 6 7 8 9 10 12113 4 5
H H
CWW
SEWL
YVW
DATENAME APPROVED:
CWW
SEWL
YVW
DATENAME
APPROVEDDATEDESCRIPTIONREV
A
1 2 63 4 5
B
C
D
A
E
F
G
1 2 6 7 8 9 10 12113 5
A
B
C
D
E
F
G
H
MRWA-W-308
NOT TO SCALE
2012 3
SWABBING, CHLORINATION AND EXTENDING MAINS
R. JAGGER 20/01/2011R. JAGGER 20/01/2011
X C. RIVETTE 04/04/12X C.PAXMAN 04/04/12X K.DAWSON 04/04/12
X R.CARRUTHERS 04/04/12X G.REYNOLDS 04/04/12X A.COSHAM 04/04/12
1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 R. JAGGER
2 PUBLISHED FIRST ISSUE 04/04/12 R. JAGGER
3 ADD TEMPORARY END OF LINE ARRANGEMENT 1/12/16 RJ / CP / JT
FIGURE 308-D: EXAMPLE COMPLETED CONNECTION
PE pipe, bolted or butt welded.Flexible lay flat PE sleeve /hose may be acceptable for< DN150 mains where safe todo so.
FIGURE 308-E: END OF LINE WITH PERMANENT VALVEAND SWAB DISCHARGE CONTROL ARRANGEMENT
a. Permanent valve(s) are generally required at temporarydead ends as per Option ii) to v).This is to ensure that the minimum number of customersare affected when later works are completed.If practicable, <10 existing connections shall be designedinto a SOB which is to be completed at a later date (asindicated in Option i).
b. When swabbing downhill is to occur, permanent valves arerequired at the down hill end of the mains to control theswab and keep the main full once swabbing is complete.
c. With respect to Option i), the undisturbed ground behindthe washout shall not be disturbed for a distance of atleast 2 meters.
d. Where washouts on new mains are to be placed hard upagainst a blank plate at the end of a previous stage(Options ii, iii & iv), multiple blocks will make it easier toremove the temporary washout, and in the case of Optionsii & iii, the increased separation will make it easier toattach the standpipes without them clashing.
SWAB BEINGDISCHARGED
TABLE 308-A: SWABBING REQUIREMENTS
FIGURE 308-A: END OF PRIORSTAGE ARRANGEMENTS
FIGURE 308-B: TEMPORARYCHARGING CONNECTIONS FIGURE 308-C: PERMANENT CONNECTIONS
Acceptable where a valve is betterset back from the end of the main(ie: at a splay corner) and there are< 10 connections in between.
<10 CONNECTIONS
Preferred where there are >10 connectionsbetween the next valve back and the end of line.Maintain FL-FL piece to keep distance fromanchor.
Preferred where a hydrant is alsorequired for on going operationalor fire fighting reasons.
Preferred where a hydrant is also required foron going operational or fire fighting reasons.
Preferred where a larger connection is requiredto facilitate swabbing at 0.5 to 1.0 m/s. ReferFigure 308-E and accompanying notes.
(REFER FIGURE 308-E)
(REFER FIG 308-D)
(REFER FIGURE 308-F)
> 2m
TIMBER / RECYCLED BLOCKS
i)
ii)
iii)
v)
iv)
BLANKPLATES
> VALUE IN TABLE 308-A
DISCHARGECONTROL UNITLENGTH (mm)
100 OR 125PE
MAIN SIZE(DN)
150 OR 18OPE225 OR 280PE300 OR 355PE375 OR 450PE450 OR 560PE600750
SWABDIAMETER(mm)
SWABLENGTH(mm)
200250300400475550750900
3003504005005506509001050
NOT REQUIRED
16001800200026003200
NOT REQUIRED1500
HYDRANT1 FLOW(l/s)
51020201826
201826
1826
HYDRANT2 FLOW(l/s)
HYDRANT3 FLOW(l/s)
SITE SPECIFIC PLAN REQUIREDSITE SPECIFIC PLAN REQUIRED
FLOW REQUIRED TO ACHIEVE ASWABBING VELOCITY OF 0.5 m/s
LATTERCONSTRUCTION
Limit of prior construction.Ground must be left undisturbed to
this point when extensionconstruction begins.
STANDPIPES
Pressuretest point
Isolation valve (forpressure testing)
Connectinghose
TEMPORARY ARRANGEMENT NOT REQUIRED
Testable singledetector checkvalve (or better)
METER
Chlorineinjectiontapping
FIGURE 308-F: PERMANENT END OF LINE ASSEMBLY CWW & YVW- DN225 & DN280PE mains SEW- DN225, DN300 or DN375 mains with all in one valve controlled hydrants
NOTES Regarding Large Main End of Line Arrangements:
KEY REFERENCES:· Chlorination and water quality compliance as
per WSA 03-2010 / MRWA Specification 04-02.· Concrete thrust restraints as per MRWA-W-204
and 205A or 205B.· Surface covers as per MRWA-W-302 & 303.
NOTES Regarding Swabbing:A. All mains > DN100 > 15m long shall be
swabbed unless the main contains butterflydivide valves.
B. Swabbing is to be undertaken in accordancewith the swabbing plan (authorised by thesuperintendent) to a velocity of 0.5 to 1.0 m/s.
C. Swabs are single use only, manufactured frompolyurethane foam to AS2281 & AS4020.
D. Swabs are to be marked with the entry pointproperty address using a permanent marker.This is to aid swab reconciliation.
E. Single swabs are acceptable for < DN200mains. (DN100 & 150 swabs are under review)Two swabs are required for each swabbing runon mains > DN200.
F. Swab discharge drinking water may only bedischarged to open land where it will pond, to atanker truck or to a storm water system whichhas adequate silt containment andenvironmental controls.
· For > DN300 and in lower pressure (static P < 400 KPa)DN225 mains, a temporary hose connection between thehydrants will be unable to push the swab with adequatevelocity.
· In such cases, swabbing flows will need to be delivered thoughthe operation of an in line valve.
· This valve (and any bypass valve) shall successfully pass apressure test to the new system test pressure prior toinstallation (to ensure it does not leak super chlorinated waterback into the in service main).
· Install these valves closed and do not operate them until the
downstream system successfully passes its pressure test.· Where the distance back to the last permanent divide valve on
the main is close to the maximum spacing (ie: > 2/3rds of themaximum spacing in Table 300-B), the end of line valve andhydrant arrangement shall be permanent (refer Figure 308-Fand Figure 308-H).
· Where the distance back to the last permanent divide valve onthe main is substantially less than the maximum spacing, theend of line valve and hydrant arrangement shall be temporary(refer Figure 308-G).
· Temporary end of line assemblies shall be sized as per Table106-D.
BLANKPLATES
BLANK PLATE
End of prior stage arrangements Temporary chlorination arrangement
NOTES Regarding Fig 308-H:· Components shown in red are temporary.· Connect chlorination hose & fittings (as
indicated in Figure 308-F) between thepermanent and temporary hydrants tofacilitate charging and chlorination.
· Refer to MRWA-W-105 for assembly details.· Where valves cannot be offset, refer to
MRWA-W-304A & B for details.
SWAB
TEMPORARY CONSTRUCTION(installed with prior construction)
PRIORCONSTRUCTION
START OF LATTERCONSTRUCTION
FIGURE 308-G: TEMPORARY END OF LINE ASSEMBLY ON > DN225 MAINS(known as "CHLORINATION ASSEMBLY")
FIGURE 308-H: PERMANENT END OF LINE ASSEMBLYCWW & YVW- > DN300 MAINS. SEW- > DN450 MAINS
Permanent arrangement
NOTES Regarding Valve & Hydrant Requirements:
DUCKFOOT BEND &HYDRANT
(Joints and pipe information not shown for clarity)
Swab. Inserted just priorto recommencement oflatter construction