djb+nangloi+water+project term+sheet+ bidders 06092011+pg

13
Draft for Discussion Page 1 of 13 PROJECT RESUME – Key Contractual Parameters PARAMETER PARTICULARS Title of the Project Improvement & Revamping of Existing Water Supply, Transmission and Distribution Network under the Command area of Nangloi Water Treatment Plant, Delhi Basic Objective To renovate the Raw Water Main, WTP, connect the entire project area with piped network, migrate from intermittent and tanker supply to continuous system within a defined period, and achieve marked improvement in service and operational efficiency by reducing both Technical and Commercial Losses to predefined targets. Project Components and basic details Existing Situation WTP Capacity – 40 MGD Bulk Water to WTP is being supplied from Bawana Intake Works. Raw Water Feeder Main from Bawana intake works to Nangloi WTP (Approx Length 12‐14km) is included in the Operator’s scope. The WTP to be rehabilitated / upgraded; and construction of recycling plant. Present Output at Nangloi WTP: 34 MGD( Project Area – 22.33 MGD and outside Project Area – 11.67 MGD) Supply to outside project area (11.67 MGD) includes: Supply to Bodella UGR Supply to CT‐2 Dwarka Supply to BPS at Uttam Nagar Losses at WTP: Approx. 19.5% observed during the period (May 2011 – July 2011) Supply to the project Area from Other Sources: Haiderpur WTP: 5.12 MGD (will be discontinued after commissioning of Dwarka WTP (by 2016)) Khyala UGR: 0.3 MGD (shall be discontinued after 6 month from Initial Handover Date) Bodella UGR: 0.28 MGD (shall be discontinued after 6 month from Initial Handover Date) Tube wells & Tanker Supply: 2.27 MGD

Upload: deyprasen

Post on 27-Nov-2015

10 views

Category:

Documents


0 download

DESCRIPTION

mnnn

TRANSCRIPT

Page 1: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 1 of 13

PROJECT RESUME – Key Contractual Parameters    

PARAMETER  PARTICULARS 

Title of the Project Improvement & Revamping of Existing Water Supply, Transmission and Distribution Network under the Command area of Nangloi Water Treatment Plant, Delhi 

Basic Objective 

To renovate  the Raw Water Main, WTP, connect  the entire project area with piped network, migrate  from  intermittent  and  tanker supply  to  continuous  system  within  a  defined  period,  and  achieve marked  improvement  in  service  and  operational  efficiency  by reducing both Technical and Commercial Losses to predefined targets.   

Project Components and basic details ­ Existing Situation 

 • WTP Capacity – 40 MGD  

   

• Bulk Water to WTP is being supplied from Bawana Intake Works. Raw Water Feeder Main from Bawana intake works to Nangloi WTP (Approx Length 12‐14km) is included in the Operator’s scope. 

• The WTP to be rehabilitated / upgraded; and construction of recycling plant. • Present Output at Nangloi WTP: 34 MGD( Project Area – 22.33 MGD and outside Project Area – 11.67 MGD) 

 • Supply to outside project area (11.67 MGD) includes: 

Supply to Bodella UGR  Supply to CT‐2 Dwarka  Supply to BPS at Uttam Nagar 

 

• Losses at WTP: Approx. 19.5% observed during the period (May 2011 – July 2011)   

• Supply to the project Area from Other Sources: 

Haiderpur WTP: 5.12 MGD (will be discontinued after commissioning of Dwarka WTP (by 2016))   Khyala UGR: 0.3 MGD (shall be discontinued after 6 month from Initial Handover Date)  Bodella UGR: 0.28 MGD (shall be discontinued after 6 month from Initial Handover Date)   Tube wells & Tanker Supply: 2.27 MGD 

 

Page 2: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 2 of 13

PARAMETER  PARTICULARS 

Total: 7.97 MGD  

 • Supply to Bodella UGR from Nangloi WTP will be shifted to Haiderpur WTP from Initial handover Date. 

 • Supply to CT‐2 Dwarka, Ujwa and Daulatpur UGRs will be as Bulk Supply from Nangloi WTP till Dwarka WTP is commissioned 

fully.  

• Project Area: Nangloi WTP Command with an approx. built‐up area – 65 Sq Kms. (excluding Ujwa and Daulatpur)  • Present Network Coverage: (Planned – 99.3%, UA Reg – 100%, UA TBR – 49.3%, UA – 32.2%, Villages – 99.1%)  • Proposed Network Coverage‐ (Planned – 100%, UA Reg – 100%, UA TBR – 100%, UA – 100%, VILLAGES – 100). The cost of 

proposed Network is included in the Capex however, the implementation of the same shall be done priority‐wise depending upon the availability of water  

 • Population in project area:  

Existing – Approx. 10,72,000 (excluding Ujwa and Daulatpur) Projected in Yr (2027) – Approx. 16,16,000 (excluding Ujwa and Daulatpur)  

• No of Consumer connections:  Existing ‐ 80,724 (including Ujwa and Daulatpur)  

• Existing UGRs/ BPS with Capacities & Yr of commissioning:  Nangloi               – 9.2 MG  commissioned in 2008 Najafgarh           – 2.2 MG commissioned in 1992 Mohan Garden – 1.0 MG commissioned in July 2009 Ujwa                    – 1.2 MG commissioned in 2009 Daulatpur          – 1.1 MG Commissioned in 2009  

• Existing OHSRs with Capacities & Yr of commissioning:  Nangloi  ‐ 3 Lakh Gallon  

• Proposed UGRs with Capacities:  Najafgarh – 8.0 MG (In Operator’s scope) Mundka – 6. 5 MG (Not in Operator’s scope) 

Page 3: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 3 of 13

PARAMETER  PARTICULARS  

• Length of transmission system : Approx. 31 kms   • Length of distribution system: Approx. 1127 kms                          

The material‐wise distribution is as follows: 

Pipe Material  Length in km AC    (75mm to 500mm)  105.7 PVC  (75mm to 150mm)  34.7 CI/DI (75mm to 1000mm)  973.9 MS    (100mm to 1500mm)  4.8 PSC  (600mm to 900mm)  8.0 GI      (100mm)  0.024 

 • No of borewells: Nos: 126, Output – 1.55 MGD 

 • Per capita Supply at present in Project Area:   150 LPCD with the existing network coverage 

Average LPCD for the Project Area (including  unauthorised + Colonies and villages not under network)– 65 LPCD  

• Tanker supply: in 2010  Najafgarh UGR  Nangloi OHT   Paschim Vihar OHT Nos.: 59  Nos.: 21  Nos.: 22 Trips: 410  Trips: 137  Trips: 66 Volume supplied: 0.49 MGD  Volume supplied: 0.16 MGD  Volume supplied: 0.07 MGD  

• NRW % : 78%  

Broad Project Scope  

Capex • Rehabilitation of Raw water Feeder Main from Bawana Intake works to Nangloi WTP. • Rehabilitation and automation of Nangloi Water Treatment Plant including construction of recycling Treatment unit. 

 • Repair, Rehabilitation and Construction of Underground reservoirs (UGRs)/ BPS/ Tube wells  • Installation, replacement, Rehabilitation, Automation of Transmission & Distribution system in the Service Area; • Replacement of existing service connections and meters for all categories of consumers. •  

Operation and Maintenance • Operation and Maintenance of Raw Water Feeder Main from Bawana Raw Water Pump House to Nangloi WTP. 

Page 4: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 4 of 13

PARAMETER  PARTICULARS • Operation and Maintenance of Nangloi Water Treatment Plant and Transmission and peripheral mains.  • Operation and Maintenance of UGRs/Tube wells and distribution network • Fixing of  system leakages with the aim of reducing Technical Losses from the system Billing, & Collection of water charges 

from Consumers in the Service Area and depositing into the Project Escrow account; • Meter Replacement to be undertaken as and when required. • Management, Operation & Maintenance of the Project Components during the project period.  • Customer Service and Grievance Redressal • Energy and water Audit  It is envisaged that implementation of the entire Rehabilitation & Development works envisaged in DPR provided by DJB, will spread over 3 yrs.  

Bid Variable for selection of Operator 

Option 1: Gross Operator Rate ‐ Rs. Per kl of water Billed in the Project Area Gross Operator Rate is inclusive of Operator’s all O&M expenses, cost of Bulk Water, Electricity charges, and also factors in recovery of Operator’s capital investment.  Option 2: Net Operator Rate ‐ Rs. Per kl of water Billed in the Project Area with Power Guarantees. Net Operator Rate is inclusive of Operator’s all O&M expenses and factors in recovery of Operator’s capital investment.  

 Key Contract Provisions PARAMETERS  PARTICULARS 

Implementation Format PPP – Concession  

Funding 

• Project Cost (excluding Road  Repairs) to be undertaken in the 3 yrs o DJB: 50% of actual project cost, as Grant, subject to a ceiling of 50% of capital cost estimated in DJB’s DPR & RFP.  o Operator: Balance 50% of the actual project cost, and cost incurred beyond the capital cost estimated in DJB’s DPR & 

RFP   

• DJB’s Contribution to be released through Escrow mechanism, as described later.  

Page 5: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 5 of 13

PARAMETERS  PARTICULARS 

Contract Period  The water demand and  supply  scenario was discussed and  it was decided  that  the Project Period will  be of 15 years  including 6 months for Due Diligence and 2.5 years for Construction (COD) described in this document as COD.  

 

PARAMETERS  PARTICULARS Project Facilities  Will include 

• All Existing Assets of DJB in the Project Area handed over to the Operator • All Assets Rehabilitated /Repaired by the Operator during the Term of the Concession • All new Assets installed by the Operator/DJB during the Term of the Concession 

Ownership  of  Project Facilities 

• Entirely remains with DJB, including all new assets built/installed by the Operator.   

Scope of Work / Operator’s  Obligations during  different  phases of the Concession 

Mobilisation / Compliance Period  

• Project mobilisation, Establishment of SPC’s office(s) in the project area, deployment of key staff & equipment on site, • Comprehensive assessment of the water supply system in the service area and establishing the baseline of existing service levels, 

connections, billing and revenue collection position. • Review of DPR provided by DJB as part of the RFP and preparation of Operator’s own Implementation Plan.  

o The  plan  should  cover  all findings  related  to  baseline  conditions;  Consumer  survey  and  demand  assessment,  details  of  hydraulic  model; Engineering  Designs;  Project  Cost  /  investment  required;  Funding  and  execution  plan  /  methodology;  Financial Management Plan  and  a  specific O&M Plan  laying  down  the  practices  proposed by  the Operator  for  achieving  the targeted KPIs.  

• Obtaining  approval  of  DJB on the Implementation Plan and MIS Plan 

• Getting  the  Existing  Assets (All assets or only visible structures like WTP, UGRs, BPS, etc.?) valued jointly by DJB and Operator with the assistance of third party approved valuers (for the purpose of Insurance). Cost of valuation exercise to be shared equally1. 

• Achieve Financial  Closure   Rehabilitation & Development Period 

                                                            1 DJB to check and inform accordingly. 

Page 6: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 6 of 13

PARAMETERS  PARTICULARS • Take over responsibility of the management and O&M of water supply facilities including monthly billing & revenue collection in 

the project area,  • Adherence to specifications and standards (CPWD Manual and Standards) • Replacement of all the existing meters and house connections and installation of new meters  • The meter installation work to commence after 6 months from the Initial Handover Date.  • Replacement of all AC and 

PVC Pipes in the project Area. • Replacement of CI and DI 

Pipes in the project Area to the extent required. • Formation of  DMZs of 10,000 connection during initial 3 years which then will be converted into DMA of 1,500 connections by 

the end of 10th year. • Energy  and  water  Audit  to  be  undertaken  by  Operator  on  yearly  basis.  The  operator  should  inform DJB  about  significant 

problems and its remedial measures including anticipated fresh investment through an Annual Plan in advance to DJB so as to allow DJB to make necessary Budget provisions.  

• Adopt  the computerized Billing or Revenue Management System of DJB  for  the Project Area,  if necessary, and ensure  that are installed and functioning properly 

• Operationalise  the  Escrow  Account  ‐  Generate  &  Issue  Bills  to  Consumers  on  behalf  of  DJB,  Collect  and  Deposit  consumer payments into escrow account  

• Undertake ‘Rehabilitation & Development Works’ in accordance with approved Implementation Plan,  o Operator  to ensure  that all DMZs  in  the distribution network are set up, all bulk & consumer meters and Pressure 

Data Loggers are installed, calibrated and functioning,  • Identify all illegal connections and take appropriate action as per instructions from DJB • Provide new connections with meters, replace old / defective meters, provide individual and group connections to consumers in 

urban poor area. • Arrange Security of project establishments like WTP and UGR/BPS, offices, etc.  • Take Insurance Cover for all existing, rehabilitated and new Project Assets  • Set up a Management Information System and provide information to DJB on technical and commercial aspects / performance of 

the project on daily basis as well as aggregate monthly, quarterly and annual basis.   • Set up and operate a Consumer service centre & helpline (24 x 7) 

                                                                                                                                                                                                                                                                                                                          2 Base Service charge shall include all expenses for operating and maintaining the facility as provided in the condition of contract for O&M, except for the cost covered by the other components and shall include without being limited to cost of staffing and personnel, administrative expenses, cost of routine maintenance, repairs and replacements.  

Page 7: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 7 of 13

PARAMETERS  PARTICULARS • To provide Rain Water Harvesting at all the DJB facilities within the project area. 

 By the end of 30 months from Initial Take Over Date, Operator should  achieve 

- Installation of meters for all existing Consumer connections and Bulk Meters - Commissioning and testing of WTP and distribution system in the Service Area as per Approved Implementation Plan  - Achievement of Baseline Service Levels post improvement, and KPI targets for O&M Period (jointly with DJB) - Computerised Billing System should be fully functioning  - Obtaining Completion Certificate from DJB for ‘Rehabilitation & Development Works’  

O&M period 

• Ensure  continuous  pressurized  water  supply  to  all  registered  consumers  at  prescribed  service  levels,  including  standby operations through Tankers.  

• Undertake calibration of meters as and when required during the Concession period • Replace water meters (bulk + consumer) and Service Connections as and when required during the Concession period • Ensure minimum basic supply to unauthorized colonies through tankers  as per DJB Policy, till area coverage is 100% • Undertake 2% of the existing network (not replaced in the CAPEX Period) replacement each year during the O&M period.  • Provide new service connections and prevent proliferation of unauthorised connections in the Project Area. • Generate & issue bills to consumers on behalf of DJB, collect and deposit consumer payments into escrow account  • Continuously strive to improve the levels of service to consumers and achieve the targeted KPIs   • Operate requisite number of Consumer service centre & helpline (an IVR system based on K nos. on MTNL pattern). Should also 

maintain mobile service centers.  • Handover  of  project  facility  to  DJB  at  the  end  of  Concession  Period  in  good  working  condition  (as  per  prescribed  handover 

requirements) • Management of Bulk Water Shortage  

o Operator & DJB to mutually work out strategies for meeting the service standards in project area o DJB (and Operator) to communicate to the Public about the shortage and its period of subsistence  o Operator will not be considered to  be in default during such period (and DJB compensating him through Idle/Base charges2 )  

 General Obligations during entire Concession Period • Submit  MIS  Reports  to  DJB  on  technical  and  commercial  aspects  /  performance  of  the  project  on  daily  basis  plus  monthly, 

quarterly and annual reports.   • Submit Audited Annual Reports to DJB and PMC  

Page 8: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 8 of 13

PARAMETERS  PARTICULARS • Meeting the Debt Service Obligations as per Financing Agreements • Indemnifying DJB against any claims that may arise on DJB on account of any default or inaction on the part of the Operator • Refrain from creation of encumbrances on project assets except to raise finance after permission from DJB. • An Escrow with 2 or more sub A/c s may be established: One for Construction and One for Revenue Collection • Enabling provision under Section 62 of Delhi Water Board Act, 1992 • Escrow Agent – Any Scheduled / Nationalised Bank acceptable to DJB  Construction Escrow • Funds from this account permitted to be spent till Rehabilitation and Development works (RDCD) • To  be  operationalised  on/before  the  Initial  Takeover  Date  and  continue  till  end  of  works  identified  under  Rehabilitation  & 

Development Works.  • Inflows to comprise the following: 

• Equity Contribution  by Operator ‐ To be deposited in tranches in accordance with Implementation Phasing Plan • Debt from Lenders in accordance with Implementation Phasing Plan. • Capital  Grant  from DJB  ‐  To  be  disbursed  in  tranches  after  the Concessionaire has expended the Equity, and shall be

disbursed proportionately along with the loan funds thereafter remaining to be disbursed by the Senior Lenders under the Financing Agreements. The Authority shall disburse each tranche of the Grant Support as and when due, but no later than 15 (fifteen) days of receiving a request from the Concessionaire along with necessary particulars.  

 • Outflows – priority of Charges 

• Statutory Dues & applicable Taxes; • Payment  to  Contractors  and  Suppliers  towards  Rehabilitation  and  Development  works  in  accordance  with 

Implementation Phasing Plan • Payments to be released by Escrow Agent only after the invoices have been certified by the PMC/TPA or DJB, within 30 

days of  submission of  Invoices   

Escrow Mechanism 

DJB Revenue Escrow • To be also operationalised on/before the Initial Takeover Date • Inflows to comprise the following: 

• Receipts from Consumers (including Arrears) to be deposited on daily basis;  • Authority’s contribution towards shortfall – in terms of Gross payment to Operator; 

 

Page 9: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 9 of 13

PARAMETERS  PARTICULARS • Outflows – Waterfall  

• Statutory dues, if any (separate sub a/c) • Payment of Electricity Dues, salaries of DJB Staff and Bulk Water Charges will be directly debited on instructions  from 

DJB. While  Sewerage Charges will  also be part  of  the billing,  but  they will  be  set  aside  /  credited  toDJB’s  sub‐account under the Escrow. 

• Operator’s Sub A/c (for Monthly Payments to Operator net of the above) • Balance, if any, to DJB sub account • A Reserve equivalent to Operator’s average net payment for two months will be kept aside by DJB.  • In case  the amount directed  to Operator’s  sub A/c after debiting Electricity Dues, salaries of DJB Staff and Bulk Water 

Charges is less than his net Fee entitlement, the shortfall will automatically flow in from the Reserve A/c which in turn will be topped up by DJB immediately.  

• Separate sub‐account for Retention Money during the Construction period. The Retention money will be deducted at the rate of 5% of  the gross amount of each  running bill. Any amount of  greater  than 5 Lakh  in  the Retention Money  sub‐account shall be given to the Operator against an equivalent amount of Bank Guarantee.  

• The amount in the Retention Money sub‐account shall be given to the Operator after 6 months of CoD.  

Operator’s Remuneration 

• No payment due for Compliance Period of 6 months.   During the Concession Period, Operator’s entitlement = Quoted Rate @Rs. ___Per kl of water  x  minimum guaranteed volume. There will be no escalation from Initial Take over Date till COD (COD period is envisaged of 30 months).  

o However if Operator is able to bill more than minimum guaranteed volume, it will paid on the basis of actual volume Billed by it. 

 OPTION 1: • Operator to be paid on the basis of Gross Operator Rate quoted by him ‐ Rs. Per kl of water Billed in the Project Area. • Gross Operator Rate will factor 

o O&M expenses to be incurred by the Operator,  o Cost of Bulk Water charges to be paid to DJB @ Rs. __ per kl.,  o Electricity charges to be paid by DJB,  o Recovery of Operator’s Investment 

OPTION 2: • Operator  to be paid on  the basis of Net 

Page 10: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 10 of 13

PARAMETERS  PARTICULARS Operator Rate quoted by him ‐ Rs. Per kl of water Billed in the Project Area. 

• Net Operator Rate will factor o O&M  expenses  to  be  incurred  by  the 

Operator,  o Recovery of Operator’s Investment 

 

• Operator’s entitlement = Quoted rate (Rs. Per kl of water billed)  x  Volume of Water Billed  x  Collection Efficiency   

• However, In case of Option 1, , Net Fee payable to Operator will be = [Quoted Gross rate (Rs. Per kl of water billed)  x  Volume of Water Billed  x  Collection Efficiency] – [ Payment of electricity charges, Bulk Water charges ] 

• Operator shall also get paid for the Bulk Water Supply to outside project Area as per the rate in the Concession Agreement. • Operator will also be entitled to reimbursement of Service Tax from DJB as applicable. Since there is generally a time lag between 

billing and collections, Monthly Payments to the Operator will be released in the same proportion of the payment made in the corresponding  month  of  the  previous  year  to  the  total  annual  payment  of  the  previous  year.  Reconciliations  against  actual achievements will be done on quarterly and annual basis. 

• The Operator will be entitled to Escalation in quoted Rates as per a Rebasing formula which will be factor in change in costs of the above input items year on year.  

Incentives & Penalties to Operator 

• Collection of Past Arrears (before Initial Takeover Date)of DJB: As ‐‐‐% of the Arrear collected, ‐ slabs based on age of the dues;  • However, if the past arrears are collected after announcement of some scheme by DJB then only ‐‐‐% (significantly lesser than the 

above) will be shared with the Operator • Optimisation  of  Energy  Costs:  There  could  be  set  certain  benchmarks  for  optimal  energy  consumption  over  the  life  of  the 

concession. If the Operator is able to save more energy, he automatically benefits, but if he exceeds the prescribed levels, DJB may consider whether to levy additional penalties. For this purpose, a set of benchmarks will be given in the RFP. Operator will also be  required  to  specify his  benchmarks  for optimal  energy  consumption  as part of his  Implementation Plan  after  studying  the project area, and whichever is lower, will be adopted as the target for his KPIs. 

• Failure by Operator to deposit Consumer payments into the designated Escrow A/c within 1 working days from date of receipt of payments ‐ Penalty levied @ Rs. 10,000 per day of delay for each bill.    

• Clearing of  construction debris:  removal  from service  area  all  surplus  construction machinery  and materials, waste materials (including  without  limitation,  hazardous  material  and  waste  water)  rubbish  and  other  debris  (including  without  limitation accident debris) – Rs 5,000  for each day of delay after  lapse of 3 Calender days  from  the day of  complaint  from Consumer or notice.  

Additional Capex,  • Possible Scope under Additional Capex 

Page 11: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 11 of 13

PARAMETERS  PARTICULARS Change of Scope, Change in Law items  

o Due  to  addition  of  Areas which  are  outside the Project Area but to be supplied water by the Operator. 

• DJB  to  select  a  third  party  contractor  for execution of the works through a transparent, competitive tendering process to determine the optimum cost for the works.  

• DJB to fund the entire capital investment. • DJB to fund replacement of pipes having dia 

more than 350 mm in the project Area. • Operator  to  supervise  the execution of  such 

works and is expected to include such supervision cost in his quoted rate.  

Payment Guarantee Mechanism 

• DJB to sign a escrow agreement before Initial take over date with Operator, Lender and a bank for setting up of Escrow account (agreement draft provided) 

• Initial  amount  from  DJB  into  the  account  should  be  equal  to  two  months  of  the  Operator  Remuneration  which  shall  be replenished regularly as per agreement conditions 

• Purpose and manner of utilization of amount deposited provided in Escrow agreement. • Further interest charges on delayed payment are applicable (delay in days and rate :______) 

 Standard  Operator’s Rate Adjustment 

Rebasing ‐ Every Financial year  Coefficients to be defined based on the factor of cost each year   As per the OPTION 1 for Operator Remuneration: Factors to be considered during rebasing are Bulk Water, Power and O&M Expenses.  As per the OPTION 2 for Operator Remuneration: Factors to be considered during rebasing are O&M Expenses (on WPI Index)  DJB to form a separate Committee for Rebasing and may include experts from outside DJB like academicians from IITs, Technical experts  in Water  field,  representative  of  DIPP  (which  undertakes WPI  indexing  activities),  CPHEEO  etc.  to  bring  in more objectivity and transparency in the process.  

 

Page 12: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 12 of 13

Key Performance Indicators

SLB target S. No.  KPI  SLB as per MoUD  2015  2016  2019  2024 

1  Coverage of water supply connections   100%  100% for areas covered in Phase I  

100% for areas covered in Phase II 

  ‐ 

2  Per capita supply of water  135 lpcd  Refer chapter 2 

3  Extent of metering of water connections*  100%  100% for areas covered in Phase I  

100% for areas covered in Phase II 

   

4  Extent of non‐revenue water (NRW)   20%  40%  33%  28%  15% 

5  Continuity of water supply   24 h  ‐  100% for areas covered in Phase I  

100% for areas covered in Phase II 

 

6  Quality of water supplied   100%  100%  100%  100%  100% 

7  Efficiency in redressal of customer complaints  80%  80%  80%  95%  95% 

8  Cost recovery in water supply services   100%  ‐  ‐  ‐  ‐ 

9  Efficiency in collection of water supply related charges  

90%  90% for areas covered in Phase I  

95% for areas covered in Phase I 

By 2018 ­ 95% for areas covered in 

 

Page 13: DJB+Nangloi+Water+Project Term+Sheet+ Bidders 06092011+PG

Draft for Discussion Page 13 of 13

SLB target S. No.  KPI  SLB as per MoUD  2015  2016  2019  2024 

90% for areas covered in Phase II 

Phase II  

  Additional KPI s not prescribed by the MoUD 

         

1  Water loss in the WTP   ‐  1.5% achievable in 2014 (at the end of construction period) 

1.5%  1.5%  1.5% 

2  Water loss in the transmission main  ‐  2%   2%  2%  2% 

3  Ph10 – District meter density (No./1000 service connections) (Number of district meters / number of service connections x 1000) Ph10  = C11 /C24 x 1000  C11  – District meters (No.)  C24  – Service connections (No.)  

‐  0.1 for areas covered in Phase I 

0.5 for areas covered in Phase I 0.1 for areas covered in Phase II 

By 2018 ­ 0.2 for areas covered in Phase II 

 

  * Note: 1. Phase I ‐ areas which have network coverage at the start of the project; Phase – II ‐ For the entire operator’s area except the colonies developed after award of  work to the operator 

                              2.  Meter installation will start 6 months after initial handover date.  Priority of installation will be – replacing non‐functional meters, metering un‐metered connections, and replacing functional meters, in that order.